SPNB successfully rehabilitates
abandoned projects 04/01/2008 The Sun By Yeong Ee-Wah
Syarikat Perumahan Negara Bhd (SPNB) has successfully completed an
abandoned project in Taman Kantan Permai, Kajang, which was awarded the
certificate of fitness (CF) on Dec 19, last year. |
Flat buyers left in the lurch
06/01/2008 NST By Malina Jeya Palan
Rosnah Ibrahim hopes the housing project will be completed soon PETALING
JAYA: More than 1,000 house buyers of an abandoned project in Shah Alam
have been waiting for seven years to move into their new homes.
|
Talam jangka siap 11,172 rumah,
apartmen
14/01/2008 Berita Harian
TALAM Corporation Bhd menjangka menyiapkan dan menyerahkan semua 11,172 unit
rumah dan apartmen bernilai RM825 juta yang dimajukannya, tetapi sebelum ini
tertangguh, dalam tempoh antara enam hingga 18 bulan.
|
Talam mahu fokus kepada
hartanah premium 16/01/2008 Utusan Malaysia
KUALA LUMPUR 16 Jan. – Talam Corporation Bhd. (Talam), yang sebelum ini
pernah digelar konglomerat hartanah tempatan, mahu memberi lebih fokus
sebagai pemaju hartanah premium apabila syarikat itu kembali pulih.
Pengarah Eksekutifnya, Chua Kim Lan berkata, pada masa ini, Talam
disenaraikan oleh Suruhanjaya Sekuriti (SC) sebagai syarikat berstatus
PN17. |
Bluestone sought after to
revive distressed projects
21/01/2008 The Star
A show unit of the Taragon Puteri Cheras K.H. SIM, dubbed the good
Samaritan for abandoned projects in Kuala Lumpur, sees his outfit, Bluestone
Group Malaysia, continuing to play a role to revive distressed projects.
|
Pembeli rumah kecewa
23/01/2008 Harian Metro Oleh Mary Victoria Dass
JOHOR BAHRU: Penantian 1,000 pembeli kediaman di Taman Cahaya Kota Putri,
Masai, bagi berpindah ke kediaman yang dibeli enam tahun lalu jelas
menghampakan apabila projek perumahan masih terbengkalai dan tidak
menunjukkan sebarang perkembangan positif.
|
Buyers want project revived
23/01/2008 New Straits Times
THE Cahaya Kota Putri House Buyers Pro-Tem Committee, which represents
more than 1,000 buyers, will hold a purchasers' general meeting at Permas
Jaya MBJB hall on Jan 27 to call for the revival of a project that had
been abandoned since October 2005.
|
Dilema pembeli pangsapuri
25/01/2008 Berita Harian Oleh Nor Azma Laila
Projek rumah kos sederhana, rendah terbengkalai sebabkan mereka tanggung
beban hutang dengan bank
PETALING JAYA: Selepas kira-kira empat tahun menunggu, hasrat 759 pembeli
rumah di Subang 2, Bandar Pinggiran Subang untuk menetap di kediaman
sendiri dan menghabiskan hari tua bersama anak cucu masih tidak kesampaian
kerana hartanah berkenaan sehingga kini gagal disiapkan.
|
Feared drowned at building site
28/01/2008 New Straits Times
PETALING JAYA: A 36-year-old lorry driver was feared drowned after a
fishing excursion went wrong on Saturday night. Sabahan Jerry Rambayan had
gone to catch fish at an abandoned building site opposite the Giant
hypermarket in USJ1, where water had collected. |
Buyers may see light at end of
tunnel 29/01/2008 The Star
Prime movers: Dr Loh (right) and Wong at the press conference. THE
seven-year wait for an apartment in the Taman Cemerlang project in Bandar
Baru Air Itam, Penang, may finally come to an end.
|
Body recovered from flooded car
park 30/01/2008 The Star
PETALING JAYA: The body of a 36-year-old lorry driver who went missing
while fishing at a water-filled basement car park of an uncompleted
building in Jalan USJ 1, Subang Jaya, on Saturday, has been recovered.
|
Ivory Properties bangun projek
terbengkalai di Tanjung Tokong
04/02/2008 Berita Harian
IVORY Properties Group akan membangunkan semula projek perumahan Fettes
Villa di Jalan Mount Erskine di Tanjung Tokong, Pulau Pinang yang
terbengkalai lebih 10 tahun lalu.
|
Anxious wait for housing project
to be revived 13/02/2008 The Star
I AM one of the victims of an abandoned housing project. Before it
happened to me, I had come across many stories of housing projects being
abandoned for years but I never imagined that I would be one of the
victims.
|
Three phases of stalled Palm
Springs Resort to be launched this year 15/02/2008 The Star By
Loong Tse Min
KUALA LUMPUR: Resorts operator and property developer Tanco Holdings Bhd
will, for the first time in 10 years, be launching this year three phases
of a previously stalled major project, Palm Springs Resort, in Port
Dickson.
|
Kesal rumah masih terbengkalai
15/02/2008 Utusan Malaysia
SAYA ingin meluahkan rasa hampa kerana rumah idaman yang saya beli tidak
dengar khabar berita sehingga kini.
|
'Syukur rumah siap’
16/02/2008 Harian Metro Oleh Mohamad Hussin
KAJANG: “Syukur alhamdulillah, penantian kami selama 17 tahun untuk mendiami
rumah sendiri akhirnya termakbul, walaupun terpaksa menderita selama
beberapa tahun lalu.
“Kami sekeluarga berasa lega selepas kerajaan sedia membantu membina semula
projek ini...kalau tak kami tidak tahu bagaimana nasib kami,” kata Rafidah
Ismail, 51, antara 792 pembeli rumah Taman Kantan Permai di sini, yang
terbengkalai sejak 17 tahun lalu. |
Buyers’ 18-year wait for
houses over at last 19/02/2008 The Star By Geetha
Krishnan
AFTER an 18-year delay, house buyers in Taman Kantan Permai, Kajang, finally
received the keys to their homes on Feb 14.
They signed the sales and purchase (S&P) agreement back in 1990 but the
project to build a total of 792 units of low-cost double-storey terrace
houses and medium-cost terrace houses came to a halt two years later. The
houses cost between RM25,000 to RM51,150. |
Dua projek perumahan terbengkalai di
NS dipulih 27/02/2008 Utusan Malaysia Oleh HUSSAINI AMRAN
SEREMBAN 26 Feb. - Projek perumahan Taman Senawang Jaya Fasa 1C di sini
yang terbengkalai sejak 24 tahun lalu berjaya dipulihkan oleh kerajaan
negeri dengan kerjasama Syarikat Perumahan Negara Berhad (SPNB) dan
dijangka siap Disember ini. |
2 Penang housing projects to be
revived 27/02/2008 New Straits Times By Lee Keng Fatt
GEORGE TOWN: Two abandoned housing projects in the state, one of them in
Kepala Batas, will be revived.
This follows the signing of a memorandum of understanding between UDA
Holdings Bhd's subsidiary, UDA Land (North) Sdn Bhd, and Koperasi
Serbaguna Jelutong Pulau Pinang Berhad (KSJPP) yesterday. |
Rumah tak siap 6 tahun
28/03/2008 Berita Harian Oleh Jaafar Mulup
Pembeli terpaksa tanggung beban pinjaman bank minta BPR siasat projek
terbengkalai TAMPIN: Pertemuan demi pertemuan sudah diadakan dengan pihak
bertanggungjawab, pelbagai saluran juga digunakan untuk menyuarakan
masalah dihadapi, tetapi nasib lebih 600 pembeli projek perumahan
terbengkalai di Bandar Utama Tampin, di sini masih tidak nampak jalan
penyelesaiannya.
|
Projek terbengkalai dibincang
28/03/2008 Berita Harian Oleh Azida Shaharuddin
Shahrir janji kemuka masalah Pacific Mall kepada jawatankuasa khas
JOHOR BAHRU: Ahli Parlimen Johor Bahru, Datuk Shahrir Samad berjanji akan
mengetengahkan masalah bangunan terbengkalai khususnya Pacific Mall di
tengah bandar raya ini kepada pihak berkuasa secepat mungkin.
|
Premis terbiar dibaik pulih
01/04/2008 Berita Harian Oleh Azida Shaharuddin
Kerajaan negeri usaha teruskan projek bangunan komersial terbengkalai
dengan bantuan pelabur tempatan
JOHOR BAHRU: Kerajaan Johor tekad untuk memulihkan kembali bangunan
komersial yang terbiar di sekitar bandar raya ini sekali gus menyediakan
ruang perniagaan runcit kepada pelabur di negeri ini.
|
Tangani
rumah terbengkalai 02/04/2008 Utusan
Malaysia
PERSATUAN Pengguna Pulau Pinang (CAP) memandang berat berhubung rekod
Kementerian Perumahan dan Kerajaan Tempatan yang menunjukkan bagaimana
keseluruhan projek terbengkalai bagi tempoh 1990 hingga 2005 begitu
bermasalah. |
Rumah terbengkalai aniaya
pembeli 06/04/2008 Berita Harian Oleh Azrul Affandi Sobry
Kerajaan wajar ambil tindakan drastik bela nasib rakyat perlukan kediaman
"ANIAYALAH kami macam ni.. bayar ansuran rumah tapi rumah tak siap-siap.
Sewa rumah pun kena bayar. Kalau selamanya begini, mana boleh hidup.
|
Kerajaan pinda akta kurangkan
masalah pembinaan 06/04/2008 Berita Harian
KEMENTERIAN Perumahan dan Kerajaan Tempatan sudah berjaya mengurangkan
masalah projek rumah terbengkalai sejak kementerian itu meminda Akta
Pemaju Perumahan (Kawalan dan Pelesenan) 1966 dan peraturan berkaitannya
pada Disember 2002.
|
Pendekatan konsep ‘bina dan
jual’ lebih adil 06/04/2008 Berita Harian
GABUNGAN Persekutuan Pengguna Malaysia (Fomca) tetap dengan pendirian
mereka mahu kerajaan meminda Akta Pemaju Perumahan dengan mewajibkan semua
pemaju melaksanakan konsep ‘bina dan jual’ bagi menangani masalah projek
terbengkalai yang mendatangkan masalah kepada pembeli selama ini.
|
Abandoned projects mar developed status 07/04/2008The Star By Elan
Perumal
THERE are more than 150 abandoned projects in Selangor and this does not
go well with the image of the state that has attained developed status. |
Taman Bidara Palma siap November ini 09/04/2008 Utusan Online
MELAKA 8 April – Projek perumahan Taman Bidara Palma Fasa Dua di Alor
Gajah di sini, yang terbengkalai sejak 10 tahun lalu akan siap menjelang
November depan. Pengerusi Jawatankuasa Perumahan & Pembangunan Pekan Kecil
dan Pemulihan Projek negeri, Datuk Abdul Ghaafar Atan berkata, jaminan itu
dinyatakan sendiri oleh pemaju yang berjanji akan menyambung semula projek
tersebut pada Jun depan. |
Pemulihan projek Pulau Melaka selesai tahun depan 11/04/2008
Utusan Online Oleh LUKMAN ISMAIL
MELAKA 10 April - Kerja-kerja pemulihan projek perumahan dan lot komersial
di Pulau Melaka di sini, yang terbengkalai sejak sekian lama dijangka
dapat diselesaikan tahun depan.
|
Liquidators given year-end
deadline 12/04/2008 The Star By Steven Daniel
MALACCA: The state government has instructed liquidators of the Pulau Melaka
reclamation project to complete work within 15 months. State Housing, Rural
Township Development and Revival of Abandoned Projects committee chairman
Datuk Abd Ghafar Atan said the state was serious in pushing for the
project’s completion following complaints by those who had purchased
property there. |
Pembeli
Lestari Permai bertegas 14/04/2008 Utusan Online Oleh A. JAILANI
ABDULLAH
PUCHONG 13 April – Para pembeli rumah Taman Lestari Permai di sini meminta
kerajaan negeri dan juga Pusat membantu menyelesaikan masalah mereka yang
telah menanti selama tiga tahun untuk melihat rumah disiapkan. |
Penjelasan isu
perumahan terbengkalai di Selangor
Posted on Saturday, April 19 @ 11:24:15 MYT by reformis
Oleh Iskandar Abdul Samad, EXCO Perumahan, Pengurusan Bangunan & Setinggan
Selangor
Pada 18 April 2008 telah dilaporkan oleh sebuah akhbar tempatan bahawa saya
telah memberitahu yang masalah projek perumahan terbengkalai di Selangor
akan diselesaikan di dalam sedikit masa lagi. |
TPPT pulih
74 projek rumah terbengkalai 06/05/2008 Utusan Online
KUALA LUMPUR 5 Mei - Tabung Projek Perumahan Terbengkalai (TPPT) yang
ditubuhkan pada 1990 berjaya membantu memulihkan 74 projek perumahan
terbengkalai di seluruh negara.
|
Angry housebuyers demand talks
06/05/2008 The Star
Taman Puncak Jalil Resident Association chairman S. Ayamani (right)
handing over a memorandum to Housing and Local Government Ministry deputy
director-general Dr G. Parameswaran to demand that the Ministry ensure
abandoned housing projects in the neighbourhood are revived. Some 100
other affected house-buyers are also present. |
Condo project
yet to take off after many years 06/05/2008 The Star By Christina
Low
THEY have invested their hard-earned savings as downpayments for their
dream homes, but after many years, all that the more than 60 distressed
and depressed apartment buyers can see is an empty piece of idle land.
They are the buyers of apartment units of the four-block Casa Gemilang
condominium project comprising 380 units in Taman Midah in Cheras, Kuala
Lumpur. |
Houseowners who can't move in 06/05/08 New Straits Times By Noel
Achariam
SUBANG JAYA: All we want is to move into our new houses. That is the plea
of some 200 house owners at the Taman Puncak Jalil Phase 10A housing
development at Bukit Jalil, Puchong, near here. They have been waiting for
the last four years to receive the certificate of fitness (CF) from their
developer. They claim they have written to the developer several times but
their request seemed to have fallen on deaf ears. |
Sampai
bila harus sabar? 07/05/2008 Utusan Online Oleh A. Jailani
Abdullah
HILANG SABAR... Pembeli rumah Lestari Permai di Puchong yang sudah
menunggu hampir empat tahun berkumpul di kawasan perumahan mereka yang
terbengkalai bagi menuntut pemaju menyiapkan rumah mereka, baru-baru ini.
|
Wrath of
house-buyers 07/05/08 New Straits Times Noel Achariam
KUALA LUMPUR: More than 2,000 house-buyers in Puchong have had enough with
developers. After waiting for more than three years for their houses, they
have demanded that the Ministry of Housing and Local Government act to solve
their problem. They have bought houses in Taman Lestari Permai, Taman
Lestari Puchong, Taman Saujana Puchong 9 and Taman Puncak Jalil Phase 10
which have all become abandoned projects. |
Pembeli
rumah minta kerajaan campur tangan 08/05/2008 Berita Harian
KUALA LUMPUR: Lebih 200 pembeli rumah terbengkalai yang dimajukan sebuah
syarikat hartanah, menghantar memorandum kepada Kementerian Perumahan dan
Kerajaan Tempatan memohon supaya kerajaan campur tangan dan mencari
penyelesaian kepada masalah kelewatan projek perumahan mereka yang sudah
berlarutan lebih lima tahun.
|
Precinct 11
housing project at a standstill 08/05/2008 The Star By Geetha
Krishnan
FAILED projects are the bane of any modern city and a planned enclave like
the nation’s administration centre Putrajaya has not been spared the
construction consternation. The fiasco of the stalled housing project at
Precinct 11 has been kept under wraps for two years to protect the Putrajaya
image but the disappointed and disgruntled buyers are not prepared to suffer
in silence. |
Pembeli rumah Talam mungkin dapat pampasan RM30,000 10/05/2008
Utusan Online
KUALA LUMPUR 9 Mei - Para pembeli rumah yang dimajukan oleh Talam
Corporation (Talam) di empat kawasan sekitar Puchong yang sehingga kini
masih belum dapat menduduki rumah mereka mungkin menerima sehingga RM30,000
sebagai pampasan di atas kelewatan itu. Menteri Perumahan dan Kerajaan
Tempatan, Datuk Seri Ong Ka Chuan berkata, pampasan itu diberikan kepada
pembeli yang layak melalui tribunal pengguna. |
Kesabaran
kami ada had - Pembeli 12/05/2008 Utusan
Online
KUALA LUMPUR 11 Mei - ''Sudah enam tahun kami menanti. Kami hanya mahu sijil
layak menduduki (CF) dengan segera,'' kata mereka. Begitulah rungutan 96
pembeli projek perumahan Fasa 10, Taman Puncak Jalil yang tidak dapat
memiliki rumah disebabkan keengganan pemaju memohon CF untuk mereka.
Rata-rata penduduk kecewa dengan tindakan pemaju yang enggan menyerahkan CF
tersebut walaupun rumah mereka telah siap dibina dan selamat untuk diduduki. |
Pembeli
merana rumah Nusa Mewah terbengkalai 13/05/2008 Utusan Online Oleh
PEMBELI MERANA, Selangor
SAYA adalah pembeli rumah Nusa Mewah Villa Kondominium di Bukit Pandan,
Pandan Indah, Cheras. Mengikut perjanjian, rumah itu siap pada bulan Julai
2005. Malangnya projek itu tertangguh. Pihak pemaju telah berjanji projek
itu diteruskan.
|
Projek Pondok
Kempas terbengkalai siap Ogos ini 13/05/2008 Utusan Online
JASIN 12 Mei - Pembinaan 22 unit rumah kos rendah fasa dua Pondok Kempas,
Selandar di sini yang terbengkalai sejak lapan tahun lalu telah disambung
semula. Pengerusi Jawatankuasa Perumahan, Pembangunan Pekan Kecil dan
Pemulihan Projek negeri, Datuk Abdul Ghafaar Atan berkata, projek tersebut
dijangka dapat disiapkan Ogos ini. |
Pemaju 3
projek diberi tempoh hingga akhir bulan 14/05/2008 Berita Harian
KUALA LUMPUR: Kementerian Perumahan dan Kerajaan Tempatan (KPKT) memberi
masa sehingga akhir bulan ini kepada pemaju projek perumahan terbengkalai di
Taman Lestari Permai, Taman Lestari Puchong dan Taman Saujana Puchong 9
untuk menyelesaikan isu itu selepas mencapai kata sepakat melalui mesyuarat
khas mengenainya kelmarin.
|
Tiada kompromi
pemaju 13 rumah kosong 14/05/2008 Utusan Online
SEREMBAN 13 Mei - Tiada lagi kompromi. Itu ditegaskan oleh Yang Dipertua
Majlis Perbandaran Seremban (MPS), Datuk Abd. Halim Abd. Latif mengenai
status 13 rumah teres dua tingkat yang terbengkalai di Taman Temiang Jaya di
sini. |
Rumah terbengkalai jadi sarang penagih 14/05/2008 Utusan Online Oleh
FARABI SHEIKH SAID AL JABRI
SEREMBAN 13 Mei - Rumah terbengkalai hampir 20 tahun di Taman Temiang Jaya
di sini digelar 'rumah hantu' kerana menjadi lokasi kaki botol, penagih
dadah dan penghidu gam melepaskan gian.
|
HDC to the rescue
20/05/08 New Straits Times by Zoe Phoon
At long last, there’s light at the end of the tunnel for those who bought
units in projects that were subsequently abandoned by their developers. This
hope, taking the form of a special purpose vehicle called the Housing
Development Corp (HDC), will be the long-term solution to replace the
current ad-hoc manner in which abandoned projects are revived. |
10 tahun menanti
Plaza Rakyat 21/05/2008 Utusan Online Oleh Farah Musa
KUALA LUMPUR 20 Mei - Kegawatan ekonomi pada 1997-1999 sememangnya
memberikan tamparan yang hebat kepada keadaan politik dan sosioekonomi
negara ini. |
Warga kota mahu
projek diteruskan 21/05/2008 Utusan Online
KUALA LUMPUR 20 Mei - Projek pembangunan Plaza Rakyat berhampiran Hentian
Pudu Raya di sini telah menimbulkan pelbagai persoalan kepada orang ramai
memandangkan ia terbengkalai sejak lebih 10 tahun. |
Changes to
housing policy to protect buyers’ rights 25/05/2008 The Star
KUALA LUMPUR: Major changes are in store for the housing industry once the
Government amends certain aspects of the National Housing Policy. Deputy
Housing and Local Government Minister Datuk Hamzah Zainudin said it would
focus on improving three areas. |
Policy revision
to curb abandoned projects 25/05/2008 New Straits Times
KUALA LUMPUR: The National Housing Policy will be revised in a bid to reduce
the number of abandoned housing projects.
Housing and Local Government Deputy Minister Datuk Hamzah Zainuddin said the
move was necessary to stop developers who defaulted on their projects. |
Dasar Perumahan
lindungi pembeli 25/05/2008 Utusan Online
KUALA LUMPUR 24 Mei - Masalah projek perumahan terbengkalai mungkin akan
menjadi suatu perkara lapuk tidak lama lagi apabila kerajaan memperkenal dan
melaksanakan Dasar Perumahan Negara khusus bagi menangani pelbagai masalah
dalam sektor perumahan. |
Kecewa rumah belum
siap 26/05/2008 Utusan Online
BANYAK projek sudah terbengkalai termasuk rumah yang saya beli iaitu La
Cottage di kawasan Puchong, Selangor. |
Ministry can only play the
role of mediator in disputes 26/05/2008 The Star
SINCE 1990, only 1% of the 2.3 million units of residential properties in
the country had not been completed.
|
Forging a win-win
deal 26/05/2008 The Star By Teh Eng Hock
TWO blocks of condominiums in a prime area sat abandoned for eight years
until the intervention of Housing and Local Government Ministry
Secretary-General Datuk Ahmad Fuad Ismail. Ahmad Fuad said the condominiums
in Taman Tun Dr Ismail were already 80% complete when the developer stopped
work. |
Abandoned housing projects
'not govt fault' 26/05/2008 New Straits Times
The new owners with Tan Sri Nor Mohamed Yakcop (left) yesterday.
BUTTERWORTH: Don't blame the government for abandoned housing projects,
Second Finance Minister Tan Sri Nor Mohamed Yakcop said yesterday.
He said most of these projects were privately managed. |
Plaza Rakyat tetap
diteruskan 26/05/2008 Utusan Online Oleh Siti Airunnisa Alaui
KUALA LUMPUR 25 Mei - Projek Plaza Rakyat yang terbengkalai sejak 10 tahun
lalu tetap akan diteruskan pembinaannya, kata Pengarah Hal Ehwal
Undang-Undang Dewan Bandaraya Kuala Lumpur (DBKL), Rohayah Karim. |
Abandoned projects to be
revived 27/05/2008 The Star By Elan Perumah, Lim Chia Ying and Salina Khalid at the
Selangor State Assembly in Shah Alam
ABANDONED projects in Selangor will be confiscated for redevelopment if a
proposal from the State housing committee gets the nod from the state
government.
State property, housing and maintenance committee chairman Iskandar Abdul
Samad said the move was aimed at salvaging the abandoned projects. |
Puchong township
littered with stalled or abandoned projects 29/05/2008 The Star By
Geetha Krishnan
IF there was an award for the area with the most number of stalled housing
projects in Selangor, Puchong would easily win the dubious honour. Puchong
is littered with stalled or abandoned projects, creating an eyesore for an
otherwise booming beautiful township. |
Malacca initiative saves 600
houses in five of 21 projects 06/06/2008 The Star By Chen Pelf Yeen
MALACCA: The state has revived more than 600 houses in five abandoned
housing projects here. Chief Minister Datuk Seri Mohd Ali Rustam said the
five projects were among 21 abandoned projects in the state, adding that
three other projects were being revived. |
Disgruntled purchasers want housing project revived
09/06/2008 The Star
KUALA LUMPUR: Newly-married IT engineer Kamal Manaf withdrew most of his
savings in 1998 to buy a house in Taman Kenanga, Bandar Baru Salak Tinggi,
and hoped to start a family. But the developer went bust in 2003, shattering
Kamal's dreams. Now, Kamal is paying hundreds of ringgit each month for a
loan he took for a house that does not exist. |
Melaka tekad pulih projek
terbengkalai 10/06/2008 Berita Harian Oleh Nasir Abd Wahab
Jawatankuasa khas dipengerusikan Adun Gedek tangani masalah MELAKA: Kerajaan
negeri pimpinan Datuk Seri Mohd Ali Rustam giat membantu memulihkan projek
pembangunan terbengkalai di seluruh Melaka bagi memastikan rakyat, khususnya,
pembeli menikmati semula pulangan setimpal selepas menanti dengan pelbagai
emosi sejak sekian lama. |
New contractor appointed to revive stalled project at PJS 9
14/06/2008 The Star By Lim Chia Ying
THE four uncompleted blocks of the Lagoon Perdana Apartments at PJS 9 are
being revived. Developer Tenaga Gagah Sdn Bhd has appointed IJM Construction
Sdn Bhd as principal contractor for the project since early 2007, as well as
two other sub-contractors to help with the revival. |
Tackling abandoned housing woes
17/06/2008 New Straits Times
Deputy Housing and Local Government Minister Datuk Hamzah Zainudin (centre)
assuring the disgruntled house buyers of abandoned projects yesterday.
|
Penduduk Lestari Permai
ucap terima kasih 17/06/2008 Utusan Online
PUCHONG 16 Jun - Jawatankuasa Pembeli Lestari Permai di sini bersyukur
apabila masalah rumah terbengkalai membabitkan lima fasa di sini berjaya
diselesaikan berikutan campur tangan kerajaan secara langsung. |
Woes of abandoned housing projects 19/06/2008 The Star Stories by
Salina Khalid
TO have a home of one’s own is every person’s dream. But, for thousands of
families in Selangor, their dreams have turned into nightmares after the
houses they bought using big long-term bank loans were left incomplete and
the developers disappeared. |
State in a bind over legal action on errant developers 19/06/2008
The Star
Iskandar: Under the Housing Developer Act (Enforcement and Licensing) 1966,
the minister could order the developer to get advice from a third party on
how to implement a project. THE Selangor government has no legal authority
to take enforcement action against errant developers in the state. |
New
contractor for abandoned Puchong schemes 20/06/2008 New
Straits Times
K.P Leong, who represents the house buyers of Taman Lestari Puchong, showing
diagrams of the abandoned housing project.
KUALA LUMPUR: House buyers of three abandoned housing schemes in Puchong are
relieved that a contractor has finally been appointed to revive their
projects. |
Perumahan
Kopetra terbengkalai
26/06/2008 Utusan Online
SIMPANG EMPAT 25 Jun - Isu rumah terbengkalai, kediaman tidak selesa dan
masalah kekurangan kemudahan awam di perumahan kos rendah dan projek
perumahan rakyat sering kali disiarkan di media massa. |
|
|