SPN ready to take over
construction of teachers' quarters
03/01/2002 BT
SYARIKAT Perumahan Negara (SPN) yesterday expressed its willingness to take
over the construction of 10,000 units of teachers' quarters which are facing
delays if asked to do so by the Government. SPN chairman Datuk Zahid Hamidi
said the company has the capacity and expertise to carry out the task based
on its current performance and its future and current projects.
-
Rumah guru: Kesatuan mahu
siasatan terperinci
04/01/2002 BH By Syuhada Choo Abdullah
KEMENTERIAN Pendidikan digesa menjalankan siasatan terperinci bagi mengenal
pasti punca kegagalan program penswastaan rumah guru yang hanya menyiapkan
2.1 peratus daripada sasaran pembinaan 19,000 unit kediaman di luar kawasan
sekolah dalam tempoh ditetapkan. Sambil meminta mengambil tindakan segera,
pertubuhan keguruan yang dihubungi Berita Harian rata-rata berasa kesal dan
menyifatkan kegagalan itu sebagai serius serta perlu ditangani sebaik
mungkin.
-
Buyers: Stalled
mall project yet to resume work
08/01/2002 The Star
PENANG: Shoplot buyers of the stalled Bayan World
Megamall are upset that work on the RM75mil project
has yet to resume after nearly four years.A
spokesman for the purchasers, Ang Thean Hock, said
the five-storey megamall project was only 60%
completed although the Penang Develop-ment
Corporation (PDC), which holds 30% stake in the
company, had set a new deadline for its completion
in December this year.
-
Pembeli tanggung masalah
pemaju
09/01/2002 HM By Hamid Karim
MEMILIKI rumah sendiri sebahagian daripada impian hidup kita. Ini kerana
rumah adalah antara keperluan asas yang sama pentingnya dengan pakaian dan
makanan dalam kehidupan seharian manusia. Namun, tidak semua impian memiliki
rumah sentiasa indah, kerana sejak bertahun-tahun lalu pembeli di negara
kita sering dihantui pelbagai kerenah dan masalah yang sekali gus menjadi
igauan yang menakutkan.
-
Usaha teruskan projek Plaza
Rakyat masih samar
10/01/2002 HM
KUALA LUMPUR: Plaza Rakyat bersebelahan Hentian Puduraya yang sepatutnya
siap tiga tahun lalu tidak akan dibiarkan menjadi projek terbengkalai yang
mencacatkan pemandangan ibu kota. Timbalan Menteri di Jabatan Perdana
Menteri, Datuk Seri Tengku Azlan Sultan Abu Bakar, berkata kerajaan tidak
akan membiarkan projek raksasa yang terhenti berikutan kegawatan ekonomi itu
terbiar begitu saja.
-
Usah jejas imej negara
11/01/2002 HM By Si Kalam
KALAM tidak dapat menerima hakikat projek Plaza Rakyat bersebelahan Hentian
Pudu Raya yang sepatutnya siap tiga tahun lalu masih terbiar. Anak buah
Kalam yang meninjau kawasan itu kelmarin mendapati pemandangan terbiar tapak
berkenaan boleh dilihat dengan jelas ketika menaiki LRT di Hentian Plaza
Rakyat.
-
Buyers not interested in reviving
abandoned projects
11/01/2002 MM
SOME buyers of abandoned housing projects have no interest in reviving them. This was what the government discovered after conducting in-depth studies into such projects. Of the 156 abandoned projects that were looked at, about 20 per cent of such projects in Peninsular Malaysia fell into this category. Most of the buyers who declined to have the projects revived had only paid the 10 per cent deposit. This is in contrast to those buyers who have paid up to 80 per cent of the purchase price. These buyers undoubtedly were keen on having the projects in question revived. The study also revealed that only 52 abandoned projects were still viable.
-
Ramai sokong kerja disambung
12/01/2002 HM
KUALA LUMPUR: Orang ramai bersetuju projek Plaza Rakyat yang terbengkalai
diteruskan bagi keselesaan kawasan berhampiran di masa hadapan. Projek yang
terbengkalai memberi gambaran buruk kepada orang ramai terutama pelancong
asing kerana ia terletak di pusat bandar raya.
-
PM mahu projek Plaza Rakyat
diteruskan 12/01/2002 HM
By Norlaila Hamima Jamaluddin
KUALA LUMPUR: Kerajaan akan berusaha bagi meneruskan projek Plaza Rakyat
yang tertangguh sejak tiga tahun lalu bagi mengelak ia menjadi projek "gajah
putih". Datuk Seri Dr Mahathir Mohamad, berkata beliau akan meminta semua
pihak yang terbabit dengan projek itu meneruskannya seberapa segera bagi
mengelak kos lebih tinggi.
-
UKM to revive RM60m hostel
28/01/2002 NST By Farrah Naz Karim
BANGI, Sun. - The RM60 million abandoned hostel project in Universiti
Kebangsaan Malaysia, which was previously awarded to UKM Alumni Organisation
and Pandan Mulia Development Sdn Bhd, will resume construction once a new
developer is identified. UKM vice-chancellor Prof Datuk Dr Anuwar Ali said
the university's administration was negotiating with Pengurusan Danaharta
Nasional Berhad on reviving the project and the undertaking would then be
open for tendering.
-
Penagih lepas gian di halaman
rumah
04/02/2002 HM
KUALA LUMPUR: Sebuah bangunan tiga tingkat yang terbengkalai di jalan Raja
Alang, dekat sini, dikesan menjadi `syurga' bagi beratus-ratus penagih dadah
melepaskan gian mereka. Harian Metro difahamkan, bangunan itu mula dibina
awal tahun 80-an. tetapi pembinaannya gagal disiapkan kontraktor.
-
Projek jadi belukar
14/02/2002 HM By Idris Musa
KAJANG: Lebih 100 unit rumah kos sederhana di Taman Kantan Permai, di sini,
yang tidak disiapkan pemaju kira-kira 10 tahun lalu kini ditumbuhi
semak-samun dan belukar, menjadi sarang binatang berbisa seperti ular.
Tinjauan Harian Metro, di kawasan itu semalam, mendapati projek rumah
tingkat itu dalam peringkat akhir untuk disiapkan. Angkara pemaju bermasalah,
projek itu terbengkalai, hingga keadaannya berubah wajah kepada belukar.
-
Projek perumahan terbengkalai
jadi kediaman 15/02/2002 HM
SUBANG: Pendatang Indonesia dan Bangladesh kini menjadikan projek perumahan
yang terbengkalai sebagai kediaman bagi mengelak diserbu pihak berkuasa
seperti yang dialami rakan mereka di rumah kongsi atau setinggan. Tinjauan
Harian Metro di Taman Subang Dua di Pinggiran Subang dekat sini mendapati
kedudukan lot kedai dan kawasan perumahan yang begitu terpencil memberi
peluang kepada mereka tinggal di situ tanpa diketahui.
-
Hotel site a mosquito breeding
ground
15/02/2002 NST
SEREMBAN, Thurs. - The uncompleted low-budget hotel facing the King George
Five school, abandoned almost four years ago, has become a mosquito breeding
ground besides being an eyesore. Pools of stagnant rainwater have collected
at the site and some of the structures have given way, posing a danger to
passers-by.
-
Woolley to revive abandoned
project
16/02/2002 NST-BUSS By Noor Adzman Baharuddin
WOOLLEY Development Sdn Bhd has big plans to develop more commercial
properties in Penang. For a start, it is rehabilitating the abandoned Raja
Tun Uda commercial district near Butterworth in mainland Penang.
-
Bangunan terbengkalai musnah
terbakar 17/02/2002 BM
KUALA LUMPUR: Dua menara bangunan di tapak projek pembangunan bercampur,
Sentul Raya, yang terbengkalai sejak kira-kira tujuh tahun lalu musnah dalam
kebakaran, malam semalam. Kejadian kira-kira jam 7.30 malam itu memusnahkan
binaan di bangunan separuh siap projek bernilai RM1.3 bilion di Jalan
Perhentian, Sentul dekat sini.
-
Persatuan ragui bangunan
terbakar angkara penagih
19/02/2002 BH
KUALA LUMPUR, Isnin - Persatuan Pembeli Hartanah Sentul Raya Kuala Lumpur (PPHSR),
meragui kebakaran bangunan terbengkalai, Villa Perhentian di Jalan
Perhentian, Sentul dekat sini dilakukan oleh penagih dadah dan meminta ia
disiasat. Presidennya, Moideen Kutty berkata, agak sukar mempercayai penagih
dadah terbabit dalam kebakaran itu kerana bangunan yang terbengkalai sejak
tujuh tahun lalu, berpagar dan dijaga rapi oleh pegawai keselamatan.
-
Housebuyers file suit against
new developer
22/02/2002 NST
MALACCA, Thurs. - Five housebuyers from Taman Bukit Tembakau in Umbai have
filed a suit in the High Court against housing developer Jejaka Megah Sdn
Bhd and government-owned Tabung Pemulihan Perumahan Terbengkalai Sdn Bhd (TPPT).
A. Chelvadurai, K. Arajunan, Mahfar Alwee, Redzuan Mohd Said and Hamidah Md
Noor, who is the widow of Ibrahim Amat, the original houseowner, filed the
writ through the firm of Mogan Karupiah and Co.
-
Problems facing 70 abandoned projects
27/02/2002
NST By A. Hafiz Yatim
MALACCA, Tues. - Problems have been encountered in reviving about 70
abandoned housing projects in the country. These include failure to attract
new developers, problem pertaining to the status of the affected land, and
house buyers who could not strike a deal with the new developers.
-
840 pembeli diminta beri peluang pemaju siapkan rumah
20/03/2002 BH By Hasnira Hassan
SUBANG, Selasa - Kira-kira 840 pembeli rumah di Seksyen 2, Bandar Pinggiran
Subang, Sungai Buloh, Shah Alam di sini diminta memberi peluang kedua kepada
pemaju, Unique Creation Sdn Bhd (Unique Creation) menyiapkan projek yang
terbengkalai. Pengerusi Jawatankuasa Tetap Pelancongan, Sains dan Teknologi
dan Pembangunan Organisasi negeri, Datuk Ir Lum Weng Keong, berkata pihaknya
yakin pemaju terbabit ingin menunaikan tanggungjawab menyiapkan projek.
-
Rumah tak siap, ansuran terus
bayar 20/03/2002 HM
SUBANG: Kira-kira 50 pembeli rumah teres Delima dan apartmen Orkid di
Seksyen 2, Bandar Pinggiran Subang, di sini, merungut kerana terpaksa
membayar ansuran pinjaman bank walaupun kediaman yang dibeli terbengkalai.
Projek perumahan yang mula dibina pada tahun 1997 dijangka siap pada tahun
lalu tetapi masih terbengkalai.
-
Malton unit to revive RM350m
project in Malacca
21/03/2002 BT
MALTON Bhd's subsidiary, Domain Resources Sdn Bhd, has been given the task
to revive the RM350 million Malaysia China Light Industrial City (MCLIC)
project in Malacca. Domain Resources has been appointed as the project
manager for the 162.8-ha MCLIC, said Malton executive director Philip Ho
during a media tour at the project site in Malacca yesterday.
-
Domain Resources pulih projek
terbengkalai 22/03/2002
BH By Daud Awang
DOMAIN Resources Sdn Bhd (Domain Resources) memperoleh hak memulihkan projek
perumahan dan bangunan komersial terbengkalai bernilai RM350 juta di Bandar
Industri Ringan Malaysia China (MCLIC) di Tanjung Minyak, Melaka. Berikutan
itu, Domain Resources, iaitu sebuah syarikat milik penuh Malton Bhd kini
bertanggungjawab sepenuhnya terhadap pembangunan projek di tapak seluas
162.8 hektar yang sudah terbengkalai sejak 1999 itu.
-
Pencen habis bayar rumah 25/03/2002 HM By Munir Ana'am Zuljadan
SEMENYIH: "Saya tidak merasa wang pencen sejak bersara pada 1995 kerana
semua habis untuk bayaran ansuran rumah terbengkalai," kata Mohd Zin
Abdullah, 62. Pesara kerani sekolah menengah di Jinjang itu mendakwa dia
terpaksa melunaskan ansuran RM262 sebulan sejak membeli rumah kos rendah
Taman Dalma, di sini, pada 1994.
-
SPN bela nasib pemilik rumah
25/03/2002 HM
SEMENYIH: Syarikat Perumahan Negara Berhad (SPN) memberi jaminan membela
nasib 106 pemilik rumah kos rendah Taman Dalma, di sini, sehingga mereka
dapat menduduki rumah masing-masing. Penolong Pengurus Besarnya, Mohd Amin
Mohd Salleh berkata, pemilik rumah Taman Dalma tidak perlu mengeluarkan
belanja kerana semuanya ditanggung SPN.
-
Taman Dalma project revived
after 7 years
03/04/2002 NST-CITY By L.H. Lim
AFTER a seven-year wait, 102 house buyers of Taman Dalma at Km2 Jalan Bangi,
Semenyih, Selangor will get their houses by September under a rescue scheme
by Syarikat Perumahan Negara Berhad. Beranang State Assemblyman Ahmad Kuris
Mohd Nor said under the RM2 million aid scheme by the national housing
company (SPNB) of the Housing and Local Government Ministry, the project
will be revived this month.
-
1,400 waiting for white
knight to come along
15/04/2002 The Star
About 1,400 purchasers of the stalled Taman Cemerlang housing scheme
are still waiting for a white knight to rescue the project in Bandar
Baru Air Itam. Housebuyers committee chairman Chang Yeong Shen
said most buyers were from the low income group and could not afford
to come up with additional money to take over the project
themselves.
-
Pembeli rayu kerajaan Johor segera siapkan rumah murah
16/04/2002 BH
SAYA mewakili pembeli rumah pangsa Taman
Desa Rakyat Perdana, Jalan Kong-Kong,
Pasir Gudang, Johor, bersebelahan
Politeknik Johor Bahru dan berdepan
Taman Kampung Kopok Baru merayu kerajaan
Johor memberi perhatian kepada masalah
kami yang tidak selesai sejak Mei 1998.
Projek ini dimiliki Kumpulan Prasarana
Rakyat Johor Sdn Bhd iaitu syarikat
Kerajaan Negeri Johor. Taman perumahan
ini sepatutnya siap pertengahan 2001,
seperti yang tertera pada papan tanda
projek.
-
YTL mahu jadi pemaju utama
17/04/2002 BH By Abdul Halim Yusoff
KUMPULAN YTL menjangka pembangunan hartanah bakal muncul sebagai penyumbang
utama pendapatannya dengan pelaksanaan projek pembangunan semula perbandaran
Sentul di Kuala Lumpur. YTL Land & Development Bhd (YTL Land), iaitu
syarikat hartanah Kumpulan YTL semalam membentangkan rancangannya untuk
menghidupkan semula projek pembangunan perbandaran itu yang sudah
terbengkalai sejak krisis kewangan Asia pada 1997,1998.
-
Lebih 26,000 rumah terbengkalai
dipulih
21/04/2002 BM By Ziauddin Sharuddin
SEREMBAN: Kementerian Perumahan dan Kerajaan Tempatan mengenal pasti 70
projek perumahan terbengkalai membabitkan 26,510 unit rumah di seluruh
negara untuk dipulihkan segera oleh Syarikat Perumahan Negara Bhd (SPNB).
Daripada keseluruhan projek bernilai RM3.2 bilion itu, 12 adalah di Selangor,
Pahang (10), Wilayah Persekutuan (9), Johor (7), Kelantan (7), Negeri
Sembilan (6), Perak (5), Kedah (4), Pulau Pinang (4), Melaka (3), Terengganu
(2) dan Perlis (1).
-
SPNB mahu
pulih 70 projek
21/04/2002 MA
SEREMBAN: Kementerian Perumahan dan Kerajaan Tempatan melalui Bahagian
Pengawasan dan Penguatkuasa mengenal pasti 70 projek perumahan terbengkalai
di seluruh negara untuk dipulihkan Syarikat Perumahan Negara Bhd (SPNB).
Penolong Pengurus Besar SPNB, Mohd Amin Mohd Salleh berkata, daripada 70
projek perumahan terbengkalai itu, 12 di Selangor, Pahang (10), Wilayah
Persekutuan (9), Johor (7), Kelantan (7), Negeri Sembilan (6), Perak (5),
Kedah (4), Pulau Pinang (4), Melaka (3), Terengganu (2) dan Perlis (1).
-
Firm to revive 70 failed projects
21/04/2002 Sunday
Star
SEREMBAN: Some 26,000 houses, with an
estimated value of RM3.23bil and left
incomplete more than five years ago,
are expected to be ready by next year.
Syarikat Perumahan Negara Berhad
assistant general manager (project
rehabilitation) Mohd Amin Mohd Salleh
said the company was targeting to
complete the abandoned projects by
next year.
-
Revival of abandoned projects
21/04/2002 NSUNT
SEREMBAN, Sat. - The Government has
directed Syarikat Perumahan Negara
Berhad (SPNB) to revive some 70 of 514
housing projects abandoned by
developers during the economic
slowdown of 1997. Wholly-owned by the
Finance Ministry, the company,
incorporated in May, 2001, had
initially been allocated a total of
RM1 billion for the purpose, said its
assistant general manager
(rehabilitation project) Mohd Amin
Mohd Salleh.
-
Pemaju kutip RM1 bilion, rumah
tak siap 24/04/2002 HM
SUBANG: Pemaju sudah pungut Wang lebih RM1 bilion, tetapi sehingga ini
pembeli belum memiliki rumah. Presiden Persatuan Pengguna Subang dan Shah
Alam (CASSA), Datuk Dr Jacob George berkata, projek berkenaan membabitkan
880 unit apartmen di Rhythm Avenue, USJ di sini yang sehingga kini masih
terbengkalai.
-
Abandoned office tower project
a big eyesore
25/04/2002 NST By Mohd Rashdan Jamaludin
ANYONE driving from the PLUS toll exit to Seremban town would immediately
notice the abandoned construction of an office tower, adjacent to the bus
and taxi terminal. I have nicknamed it the "Tower of Eyesore". It has been
in that sorry state since the Asian financial crisis in 1997-98 and that was
almost four to five years ago. Couldn't the State Government or the local
town council take over the abandoned project? Why leave the building in a
mess?
-
Buyers seek legal redress
29/04/2002 NST
BUYERS of Rhythm Avenue apartments in USJ19,
Subang Jaya, Selangor are running out of patience with the project developer, Sanjung Utama Sdn Bhd. They say construction work on
the project stopped eight months ago and they are now seeking legal action against the developer.
-
Four out of five housing projects
abandoned since 1999 revived
02/05/2002 NST
April 30: Five housing and industrial
projects were reported to have been
abandoned in Malacca since 1999 and they
involve some 3,143 units and 1,418
buyers. However, four have been revived
and works are expected to resume soon.
-
880 Pembeli rumah teraniaya
08/05/2002 HMBy Zaitie Satibi
SHAH ALAM: Seramai 880 pembeli rumah di USJ19, Subang Jaya, mendakwa
dianiaya kerana terpaksa membuat bayaran untuk projek perumahan terbengkalai
sejak lapan bulan lalu. Mereka juga mendakwa dilayan secara kasar oleh
pemaju selain terpaksa menanggung risiko diisytiharkan muflis oleh institusi
kewangan.
-
Buat laporan polis, tuntut
ganti rugi 08/05/2002 HM
SUBANG: Pembeli pangsapuri Rhythm Avenue, USJ 19, dekat sini, yang hilang
keyakinan terhadap pemaju Sanjung Utama Sdn Bhd kerana belum menyiapkan
rumah yang dibeli, membuat laporan di Balai Polis Shah Alam, di sini kira-
kira jam 11 pagi semalam.
-
Rhythm Avenue folk want probe into
wrongdoings by builder
13/05/2002 MM
RESIDENTS of Rhythm
Avenue in Jalan USJ 19, Subang Jaya, will submit a letter to the Board of Architects tomorrow asking them to investigate
allegations of wrongdoings among board members. A similar letter will also be sent to the Bar Council, said Consumers Association
of Subang and Shah Alam (CASSA) president Jacob George.
-
Turnkey
contractors to revive 12 projects
14/05/2002 The Star
PENANG: The state government has engaged turnkey contractors to
revive and complete 12 abandoned low and low medium-cost housing
projects in various phases of development. The 12 projects are
Taman Sri Semarak, Taman Cemerlang, Taman Terubong Indah (Majestic
Heights) and Fettes Villa in the northeast district; Taman Sri Bayu
in southwest district; Pangsapuri Widuri, Taman Sejahtera, PAKR
Kuala Muda Phase 2 and PAKR Ekor Kucing Phase 2 in north Seberang
Prai; and Taman Pekatra, Taman Widuri and PAKR Sungai Dua in south
Seberang Prai.
-
Rescue plan hinges on bank’s nod
21/05/2002 The Star
Work on the abandoned Pangsapuri Widuri project at Lorong Cempa, Butterworth, would begin in July if the financing bank agrees to a rescue package submitted by a turnkey contractor who has been entrusted by buyers to revive the project.
-
Builder issued ultimatum
29/05/2002 The
Star
If held-back projects Rhythm Avenue and Newgate Apartments are not
revived by the end of this month, the developer will have to face
the 1,500 house buyers in front of the press. Subang Jaya
assemblyman Datuk Lee Hwa Beng had made this clear at a press
conference he arranged to highlight the plight of the house buyers.
-
Pembeli gelisah rumah lewat disiapkan 11/06/2002 BH
SERDANG, Isnin - Seramai 1,369 pembeli unit kedai apartmen dan pangsapuri
kos sederhana di Seksyen 5, Serdang Perdana dekat sini, berharap projek
pembangunan yang terbengkalai sejak November lalu, dapat diteruskan semula,
secepat mungkin. Ahli Dewan Undangan Negeri (Adun) Seri Kembangan, Datuk
Liew Yuen Keong, berkata projek berkenaan terpaksa ditangguhkan berikutan
syarikat induk pemaju, Hiap Aik Construction Bhd menghadapi masalah kewangan,
menyebabkan projek itu terpaksa diambil alih oleh Pengurusan Danaharta
Nasional Bhd (Danaharta) iaitu agensi kerajaan yang bertanggungjawab
mengurus aset bermasalah.
-
Pembeli mahu projek disiapkan
11/06/2002 HM
SERDANG: Seramai 1,369 pembeli unit kedai pangsapuri dan apartment kos
sederhana di Seksyen 5, Serdang Perdana berharap projek yang terbengkalai
sejak November lalu, di kawasan itu dapat diteruskan semula. Ia berikutan
kebanyakan pembeli sudah membuat pembayaran tetapi masih tidak boleh
menduduki unit kedai itu.
-
Taman Lingakaran Nur
project revived
20/06/2002 NST-CITY By Siti Hajar Abd Aziz
AFTER waiting for 12 years, 250 house buyers of Taman Lingkaran Nur, Phase
1, in Batu 12, Cheras, Hulu Langat are hopeful again that they will finally
get their homes. The project, which was abandoned in 1993, has been revived
in a rescue scheme being carried out by Syarikat Perumahan Negara Berhad (SPNB).
-
RM25m rescue package to revive project
20/06/2002 The Star
A turnkey contractor is ready to inject
RM1mil to kick start efforts to revive
Pangsapuri Widuri in Butterworth, which
has been abandoned for nearly three
years. Harta Intan Construction Sdn Bhd
director Amir Hussain Abdul Majid said
the total cost of the rescue package was
estimated at RM25mil, provided all house
buyers agreed not to claim late delivery
charges from the developer, Diamond
Crest Sdn Bhd.
-
The town centre that never was
25/06/2002 MM
LOOKING
for "true stories" that can subsequently
be used as the backdrop of a legal
commentary can sometimes be a difficult
task. Sometimes, though, the search can
be very short, sweet and simple. Just
the other day, whilst waiting for one of
World Cup matches to start, I was
ambling through cyber space and by sheer
chance, happened to visit the House
Buyers Association website.
-
Buyers seek details on status of
stalled project
27/06/2002 NST-CITY
"WE demand an
explanation!" Purchasers of commercial units and service apartments offered under the Rhythm Avenue project in USJ19 in Subang
Jaya, Selangor want its developer, Sanjung Utama Sdn Bhd, to provide an explanation on what is happening to the stalled project.
-
Syarikat sambung projek
28/06/2002
BH
KUALA LUMPUR, Khamis - Land and General Berhad (L&G) akan menyambung semula
projek perumahannya yang terbengkalai di Lembah Beringin pada Ogos ini dan
menjangka dapat menyiapkannya dalam tempoh 12 bulan. Pengarah Eksekutifnya,
Mohd Razeek Hussain, berkata anak syarikatnya, Lembah Beringin Sdn Bhd,
pemaju projek itu akan menyambung semula kerja membina 1,000 unit rumah
projek itu.
-
Condo eyesore
29/06/2002 MM By Rita Jong
AN abandoned condominium project in Brickfields has become a haven for dadah
addicts, causing concern to residents in the area. Located at Jalan Tun
Sambanthan 1, the 249-unit Sri Impian Condominium project was abandoned two
years ago.
-
Desticom gets deal to revive housing projects
02/07/2002 MM
LITTLE-known Desticom Sdn Bhd has been
assigned to revive housing projects
abandoned by developers during the
economic slowdown of 1997, government
sources said yesterday. The company has
so far secured an initial RM200 million
contract to complete the projects, and
more contracts are expected. The company
is now expected to revive projects
comprising low-cost and low-medium
houses as well as shophouses, the source
told Mail Money yesterday.
-
House not delivered as
promised
04/07/2002 MM By Sushma Veera; Hasnita Shaari
THE developer of the Villaria Apartment in Jalan Klang Lama told buyers that
the project would be completed by December last year. But KAS is still
waiting.
-
Call to look into plight of
unfortunate house buyers
04/07/2002 NST By Shahrum Sayuthi
THE State's special committee forreviving abandoned housing projects was
yesterday urged to solve the problems faced by buyers of half-completed
apartments at Skudai Villa Apartments and shoplot owners at the Skudai Plaza.
Khoo Kong Ek (BN-Skudai) said construction of the Skudai Villa Apartments,
which started in 1996, was halted a year later when the developer was
declared bankrupt.
-
Another
housing headache for rep
08/07/2002 The Star
Another abandoned housing project, Seri Semarak in Bandar
Baru Air Itam, has been added to the “headaches” of Paya
Terubong assemblyman Dr Loh Hock Hun. He said Seri Semarak,
consisting of 1,306 units of low and medium cost flats, was
the third abandoned project after Majestic Heights and Taman
Cemerlang in his constituency.
-
60 pembeli rumah kecewa 09/07/2002 HM By Idris Musa
KUALA LUMPUR: Kira-kira 60 pembeli rumah Newgate Avenue di USJ 21, dekat
sini, berasa tertipu berikutan projek itu terbengkalai sedangkan mereka
terpaksa melunaskan faedah bulanan pinjaman bank. Disebabkan terlalu kecewa
dan kesal dengan sikap pemaju projek terbabit, mereka membuat laporan kepada
Persatuan Pengguna Subang & Shah Alam (Cassa), Jabatan Siasatan Jenayah
Perdagangan, Majlis Peguam, Kementerian Perumahan dan Kerajaan Tempatan,
Badan Arkitek dan Bank Negara.
-
House buyers: Declare project abandoned
24/07/2002 The Star
By Sira Habibu
The stalled Taman Widuri Housing Project
action committee wants the authorities
to officially declare the project in
Sungai Duri abandoned. Its chairman
Lionell L. Joeshua said banks would
continue making progress payment to the
developer because there is no official
declaration that the project is
abandoned.
-
Pemaju rumah lepas tangan
27/07/2002 HM
SAYA adalah di antara 200 pembeli rumah dari
syarikat Coopas Sdn Bhd yang memajukan projek Kampung Tersusun, Jalan Gula Simpang Empat, Semanggol Perak amat dukacita apabila
pemaju tidak menjalankan tugas dengan sempurna. Mengikut perjanjian jual beli di antara syarikat berkenaan dengan pembeli, rumah
terbabit siap dalam tempoh 24 bulan (2 tahun) dan sepatutnya pembeli sudah boleh menduduki.
-
Restraint from filing petition
27/07/2002 BT
A HOUSE buyer has served a winding-up petition on Lembah
Beringin Sdn Bhd but the Land & General Bhd subsidiary is scheduled for a hearing on its application to restrain him from filing
the petition. L&G said it had applied for the injunction on June 11, and the hearing will be held on August 13. It said the buyer
won his case last year, and got an order for Lembah Beringin to refund roughly RM280,000 that he had paid. L&G said it had
invested RM16.1 million in Lembah Beringin and the expected loss from the winding-up proceedings is insignificant.
-
Pembeli kecewa
29/07/2002 HM
HULU KLANG: Pembeli pangsapuri Blok B Estana
Court, di sini kecewa dengan pemaju kerana gagal menyiapkan rumah mereka selepas tergangguh lebih dua tahun. Lebih mengecewakan
pembeli pangsapuri berkenaan terpaksa membayar faedah bagi pinjaman perumahan kepada institusi kewangan.
-
Rumah belum nampak bayang 29/07/2002 HM
SAYA membeli sebuah rumah di Bandar
Puncak Alam Fasa 2 pada Mac 1998. Sebenarnya saya adalah mangsa rumah retak yang sepatutnya siap pada Mac 2000. Memandangkan
masalah terbabit, kami diberitahu yang ia akan diruntuhkan dan dibina semula, seterusnya dijangka siap Mac 2002. Bagaimanapun
selepas itu kami langsung tidak mendapat apa-apa laporan kemajuan sehingga saya melawat sendiri ke tapak projek pada Januari 2002
dan mendapati tapak terbabit baru sahaja diratakan
-
Contractors sought for
Majestic Heights project
04/08/2002 NSUNT
PENANG, Sat. - The ad hoc committees of Phases 2A and 3A of Majestic
Heights, the country's largest abandoned housing project, is seeking
qualified developers or contractors to revive the housing scheme. Committee
adviser for Phases 2A, 2B and 3A Lau Heng Loon said contractors with a
minimum qualification of the Contractors' Service Centre Grade 5
certification and the Construction Industry Development Board (CIDB) or from
the Malaysian Architects' Association are encouraged to apply.
-
10 tahun rumah tak siap
05/08/2002 HM By Norainon Othman
KUALA LUMPUR: Penduduk Kampung Pasir Wardieburn, Sentul, di sini, berharap
Flet Danau Kota yang dibina bagi pemindahan semula setinggan itu disiapkan
segera selepas terbengkalai beberapa tahun. Daripada lima blok 20 tingkat
yang dibina, hanya dua blok sudah disiapkan manakala tiga blok lagi gagal
disiapkan mengikut jadual menyebabkan pembeli rumah ternanti-nanti.
-
Pemaju beri alasan kewangan
05/08/2002 HM
KUALA LUMPUR: "Saya ingatkan cuma saya yang mengalami masalah ini tetapi
bila ada pembeli yang tidak mendapat rumah sejak 1997, saya rasa ada sesuatu
yang tidak kena," kata setiausaha, Siti Azura Mohd Anuar, 37, mengenai rumah
yang dibelinya tetapi masih terbengkalai. Siti Azura yang membeli satu unit
pangsapuri Blok B Estana Court, Hulu Klang sejak 1999 tidak berpuas hati
dengan prestasi yang ditunjukkan pemaju perumahan itu yang melambatkan
pembinaan pangsapuri itu.
-
Mycom's restructuring exercise
may face hitch
06/08/2002 MM By Rizalman Hammim
MYCOM Bhd's restructuring exercise is expected to face a hitch as one of its
subsidiaries will be served with a winding-up petition over an uncompleted
property development project. Sentul Murni Sdn Bhd will be served with the
petition by the buyers of its abandoned Riverside Condominium project in
Bandar Sentul Utama soon.
-
New hopes for buyers
07/08/2002 The Star
The Pangsapuri Widuri apartment project in Lorong Chempa, Butterworth,
which had stalled for nearly three years, will soon be revived as the
financing bank has approved a rescue package plan.
-
Hope for abandoned Bandar
Sentul Utama project
08/08/2002 MM
THE Bandar Sentul Utama Phase 2 project, which was abandoned in 1997, will
be given a new lease of life. The purchasers' protem committee was given the
green light to be the receiver and manager of the abandoned project, after a
meeting with the Ministry of Housing and Local Governments on Aug 21, 2001.
-
Mycom sees no impact 08/08/2002 MM
MYCOM Bhd said there will no impact on its restructuring scheme should a
winding-up action is taken against its subsidiary Sentul Murni Sdn Bhd as
the unit's involvement in the scheme is only in respect of restructuring of
loans to financial institutions.
-
Sentul project not abandoned
10/08/2002 MM By Muzli Mohd Zin
BANDAR Sentul Utama Phase 2's developer has never abandoned the project as
claimed by buyers. Sentul Murni Sdn Bhd spokesman said they are committed to
completing it despite being saddled with problems, including a legal action
by purchasers.
-
Dashed dreams
12/08/2002 MM By Chow Ee-Tan
AN exclusive address. Resort-style living away from the city. Such were the
dream homes and lifestyles that were promised by Emville Golf Resort near
Sepang. But nine years on, more than 700 purchasers of the project's phase
one bungalow lots are getting weary that their investment was going down the
drain.
-
25% buyers delaying resumption of project
12/8/2002 The Star
The turnkey contractor appointed to revive the abandoned Pangsapuri Widuri
project in Butterworth is unable to resume work because it has failed to
obtain 100% approval from housebuyers for the rescue package.
-
Buyers to fight back
14/08/2002 MM By Chow Ee-Tan
PROPERTY developer Emville Sdn Bhd may have gone into liquidation but the
purchasers of Emville Golf Resort bungalow lots are still claiming their
rights as spelt out in the sale and purchase agreement. This was decided by
the purchasers' pro-tem committee at their first meeting last Sunday.
-
Seeking solution to stalled
housing projects
15/08/2002 NST-CITYBy Shuib Taib
BUYERS of the two stalled housing projects in Subang Jaya - Rhythm Avenue
Apartments and Newgate Apartments - are advised to attend a buyers'
committee meeting this Sunday to determine their next course of action. "At
the meeting, buyers will be professionally advised on their rights as
purchasers in the sales and purchase agreement and under the law of this
country.
-
Developer unable to revive abandoned project
16/08/2002
The Star
BUTTERWORTH: The turnkey contractor appointed to revive the abandoned
Pangsapuri Widuri project here is unable to resume work because it had
failed to obtain approval from all the house buyers for the rescue
package. -
Worried over halt in
construction
17/08/2002 MM By Sushma Veera; Sangeetha Nair
PAYMENT has been made but there is no sign of work. NOR, of Sunway, wonders
when Worldwide Holdings Bhd will resume work on Pangsapuri Baiduri in
Section 7, Shah Alam.
-
Buyers of stalled projects taking developers to court 20/08/2002 NST-CITY
SOME buyers of the stalled Rhythm and Newgate Avenue service
apartment projects in USJ, Subang Jaya are initiating legal action against
the developers to reclaim their monies with interest. The buyers met officials
of the Consumers Association of Subang and Shah Alam, Selangor (Cassa) last
Saturday to request further action by the association to protect their rights
and interests in the matter.
-
Seeking ways to revive stalled housing projects
22/08/2002 NST-CITY
BUYERS of the stalled Rhythm Avenue and Newgate Avenue service
apartment projects in USJ Subang, have formed a "Buyers Committee" to solve
their problems. The 20-member committee had their first meeting yesterday
with the senior managers of Sanjung Utama Sdn Bhd and Solarglow Sdn Bhd, the
developers of the projects, which have stalled for 11 months.
-
Kecewa flet tak siap
23/08/2002 HM By Abdul Samad
KAMI pembeli projek perumahan Taman Desa Rakyat Perdana, Pasir Gudang, Johor
Bahru kecewa dengan sikap pemaju yang masih gagal menyiapkan projek
perumahan yang terbengkalai lebih setahun lalu. Pelbagai alasan diberikan
pemaju projek berkenaan berhubung kelewatan menyiapkan projek kos rendah
jenis flet tiga bilik satu bilik air itu yang berharga RM25,000 seunit.
-
Former mining workers tired of long delay in project
26/08/2002 MM
FOR four years, former workers of Killing Hall Tin Malaysia
have been waiting for their low-cost houses to be completed but their patience
has run thin. Construction work on their new homes has been so slow and only
142 out of 204 units have been built on the 2.8 hectare ex-mining land in
Batu 18 off Jalan Puchong.
-
26,000 houses to be ready by
2005
29/08/2002 NST By Alina Simon
ALOR STAR, Wed. - Syarikat Perumahan Negara Berhad (SPNB) is confident of
completing all 91 abandoned housing projects involving 26,000 low- and
medium-cost houses nationwide by 2005. Its chairman, Datuk Ahmad Zahid
Hamidi, said the company, a wholly-owned subsidiary of Ministry of Finance
Incorporated, had been given RM3 billion to rescue these projects.
-
SPN siapkan 15 projek
perumahan tergendala 29/08/2002
BH
ALOR STAR, Rabu - Syarikat Perumahan Negara (SPN) sudah menyerahkan 15
projek perumahan yang tergendala, siap dengan Sijil Kelayakan Menduduki (CF)
kepada pembelinya sepanjang tahun lalu, kata Pengerusinya, Datuk Ahmad Zahid
Hamidi.
-
Work at abandon housing project restarts
20/09/2002 The Star
The 289 purchasers of the abandoned housing project, Seri Semarak
and Eternal Heights in Bandar Baru Air Itam, Penang, can now look forward
to moving into their new homes in three years’ time.
-
Fresh hope for stalled project
26/9/2002 The Star
THE stalled Menara Kuda Lari project in Jalan Lumba Kuda, Penang, is
expected to be completed within six months following the appointment of a
project manager. Project receiver Lee Jong Ki said the developer Ever
Noble Sdn Bhd had entered into a project management agreement with Januari
Properties Sdn Bhd on Sept 9 to resume construction of the medium-cost
apartments.
-
Light at the end of tunnel for 1,100
flat buyers
03/10/2002 The Star
By Ng Su-Ann
About 1,100 buyers of the stalled Green
Garden low-medium cost flats project in
Paya Terubong in Penang may soon be able
to move into their respective units as
the Certificate of Occupancy is expected
to be issued in two weeks. Housebuyer
P.K. Ng, 67, said she had received a
letter from the developer stating that
vacant possession had been issued and
the buyers would receive their keys
after making the final payment of
RM10,000 each.
-
Purchasers ‘satisfied’
24/10/2002 The Star
Purchasers of Penang’s RM270mil Bayan
World Mega-mall project are satisfied
with the measures taken by the developer
to revive the project.
-
Project delay burdens buyers
25/10/2002 The Star
By Maizatul Nazlina
PASIR GUDANG: Factory worker Fatimah
Zulaida Mohd Yusof, who wanted her own
home, scrimped and saved to buy a
low-cost house in Taman Desa Rakyat
Perdana when the offer came in 1998.
Fatimah and her husband made plans on
how they could decorate the house and
could not wait for it to be completed
last February, as stated in the sales
and purchase agreement.
-
Projek rumah terbengkalai
ditarik balik 29/10/2002
BH
KLANG, Isnin - Semua projek rumah kos rendah yang gagal dibina pemaju
perumahan swasta sehingga November ini, akan ditarik balik. Pengerusi
Jawatankuasa Tetap Kerajaan Tempatan, Perumahan dan Setinggan dan Alam
Sekitar, Datuk Mokhtar Dahlan, berkata ada kira-kira 60 projek lama dan baru
yang belum dilaksanakan.
-
House buyers ‘assured’
08/11/2002 The Star By Manjit Kaur
Financial consultancy firm Deloitte
KassimChan has been appointed to manage,
monitor and to see that the stalled
Taman Kasawari housing project in
Simpang Ampat gets off the ground again.
-
22 abandoned private housing
projects revived, completed 09/11/2002
NST
TWENTY-TWO of the 33 abandoned private housing projects in Pahang have been
revived and have since been completed. With the revival of the 22 projects
costing RM169.7 million, some 3,619 houses had been completed and sold to
2,631 buyers.
-
Projek rumah terbiar biak
nyamuk 11/11/2002 HM
KUALA LUMPUR: Tapak perumahan terbengkalai di Persiaran Titiwangsa 1,
Setapak, di sini, sejak tiga tahun lalu menyebabkan bau busuk dan menjadi
tempat pembiakan nyamuk. Tinjauan Harian Metro mendapati bau busuk dan
pembiakan nyamuk itu berpunca daripada pembuangan sampah oleh penduduk
setempat.
-
95 projek perumahan
terbengkalai 13/11/2002 HM
DEWAN Rakyat dimaklumkan sekurang-kurangnya 95 projek perumahan dikenal
pasti terbengkalai manakala 43,541 unit rumah gagal dijual pemaju sehingga
Oktober lalu.HM 14/02/2002 By Idris Musa
KAJANG: Lebih 100 unit rumah kos sederhana di Taman Kantan Permai, di sini,
yang tidak disiapkan pemaju kira-kira 10 tahun lalu kini ditumbuhi
semak-samun dan belukar, menjadi sarang binatang berbisa seperti ular.
Tinjauan Harian Metro, di kawasan itu semalam, mendapati projek rumah
tingkat itu dalam peringkat akhir untuk disiapkan. Angkara pemaju bermasalah,
projek itu terbengkalai, hingga keadaannya berubah wajah kepada belukar.
-
Abandoned high-rise buildings
a safety hazard
15/11/2002 NST By Annie Freeda Cruez
KUALA LUMPUR, Thurs. - Hundreds of abandoned high-rise buildings around the
country pose a threat to passers-by and vehicles as their conditions
deteriorate. A large number of these buildings have rusting tower cranes on
the top which are in danger of toppling over.
-
Housebuyers to meet Pulau Berkembar developer over completion delay
25/11/2002 NST By A. Hafiz Yatim
MALACCA, Nov 24: Several buyers of development projects on Pulau Melaka
would be meeting developer Pulau Berkembar Sdn Bhd (previously known as Inno
Enhance Sdn Bhd) on Thursday over the delay in completion.
-
Developer of stalled project
gets summons
8/12/2002 NST-CITY
THE developer for the abandoned Rhythm Avenue apartment project in Subang
Jaya, Selangor was served with a writ of summons last Friday. Those named as
co-defendants were Rhythm Avenue developer Sanjung Utama Sdn Bhd, company
directors Yap Kwee Huat and Yap Kwee Chai and project architect Goh Day Ren.
-
Buyers must
sign new S&P agreement
02/12/2002 The Star
The 290 buyers of the stalled low medium-cost Seri Semarak apartment
project in Bandar Baru Air Itam have to sign a new sales and
purchase (S & P) agreement as a new developer has taken over the
project.
-
Housebuyers ‘must decide’
02/12/2002 The Star By Ng Su-Ann
SOME 600 housebuyers of the stalled Fettes Villa project in
Fettes Park, Penang, have to make a decision. They have been
told to decide whether they want the project to continue or
try to get back their downpayment of between RM10,000 and
RM15,000 each.