SPN ready to take over construction of
teachers' quarters
03/01/2002 BT
SYARIKAT Perumahan Negara (SPN) yesterday expressed its willingness to take
over the construction of 10,000 units of teachers' quarters which are facing
delays if asked to do so by the Government. SPN chairman Datuk Zahid Hamidi
said the company has the capacity and expertise to carry out the task based
on its current performance and its future and current projects.
|
Rumah guru: Kesatuan mahu siasatan terperinci
04/01/2002 BH By Syuhada Choo Abdullah
KEMENTERIAN Pendidikan digesa menjalankan siasatan terperinci bagi mengenal
pasti punca kegagalan program penswastaan rumah guru yang hanya menyiapkan 2.1
peratus daripada sasaran pembinaan 19,000 unit kediaman di luar kawasan sekolah
dalam tempoh ditetapkan. Sambil meminta mengambil tindakan segera, pertubuhan
keguruan yang dihubungi Berita Harian rata-rata berasa kesal dan menyifatkan
kegagalan itu sebagai serius serta perlu ditangani sebaik mungkin.
|
Buyers:
Stalled mall project yet to resume work
08/01/2002 The Star
PENANG: Shoplot buyers of the stalled Bayan World Megamall are upset that work
on the RM75mil project has yet to resume after nearly four years.A spokesman
for the purchasers, Ang Thean Hock, said the five-storey megamall project was
only 60% completed although the Penang Develop-ment Corporation (PDC), which
holds 30% stake in the company, had set a new deadline for its completion in
December this year.
|
Pembeli tanggung masalah pemaju
09/01/2002 HM By Hamid Karim
MEMILIKI rumah sendiri sebahagian daripada impian hidup kita. Ini kerana rumah
adalah antara keperluan asas yang sama pentingnya dengan pakaian dan makanan
dalam kehidupan seharian manusia. Namun, tidak semua impian memiliki rumah sentiasa
indah, kerana sejak bertahun-tahun lalu pembeli di negara kita sering dihantui
pelbagai kerenah dan masalah yang sekali gus menjadi igauan yang menakutkan.
|
Usaha teruskan projek Plaza Rakyat masih samar
10/01/2002 HM
KUALA LUMPUR: Plaza Rakyat bersebelahan Hentian Puduraya yang sepatutnya siap
tiga tahun lalu tidak akan dibiarkan menjadi projek terbengkalai yang mencacatkan
pemandangan ibu kota. Timbalan Menteri di Jabatan Perdana Menteri, Datuk Seri
Tengku Azlan Sultan Abu Bakar, berkata kerajaan tidak akan membiarkan projek
raksasa yang terhenti berikutan kegawatan ekonomi itu terbiar begitu saja.
|
Usah jejas imej negara
11/01/2002 HM By Si Kalam
KALAM tidak dapat menerima hakikat projek Plaza Rakyat bersebelahan Hentian
Pudu Raya yang sepatutnya siap tiga tahun lalu masih terbiar. Anak buah Kalam
yang meninjau kawasan itu kelmarin mendapati pemandangan terbiar tapak berkenaan
boleh dilihat dengan jelas ketika menaiki LRT di Hentian Plaza Rakyat.
|
Buyers not interested in reviving abandoned projects
11/01/2002 MM
SOME buyers of abandoned housing projects have no interest in reviving them.
This was what the government discovered after conducting in-depth studies into
such projects. Of the 156 abandoned projects that were looked at, about 20 per
cent of such projects in Peninsular Malaysia fell into this category. Most of
the buyers who declined to have the projects revived had only paid the 10 per
cent deposit. This is in contrast to those buyers who have paid up to 80 per
cent of the purchase price. These buyers undoubtedly were keen on having the
projects in question revived. The study also revealed that only 52 abandoned
projects were still viable.
|
Ramai sokong kerja disambung
12/01/2002 HM
KUALA LUMPUR: Orang ramai bersetuju projek Plaza Rakyat yang terbengkalai diteruskan
bagi keselesaan kawasan berhampiran di masa hadapan. Projek yang terbengkalai
memberi gambaran buruk kepada orang ramai terutama pelancong asing kerana ia
terletak di pusat bandar raya.
|
PM mahu projek Plaza Rakyat diteruskan
12/01/2002 HM By Norlaila Hamima Jamaluddin
KUALA LUMPUR: Kerajaan akan berusaha bagi meneruskan projek Plaza Rakyat yang
tertangguh sejak tiga tahun lalu bagi mengelak ia menjadi projek "gajah putih".
Datuk Seri Dr Mahathir Mohamad, berkata beliau akan meminta semua pihak yang
terbabit dengan projek itu meneruskannya seberapa segera bagi mengelak kos lebih
tinggi.
|
UKM to revive RM60m hostel
28/01/2002 NST By Farrah Naz Karim
BANGI, Sun. - The RM60 million abandoned hostel project in Universiti Kebangsaan
Malaysia, which was previously awarded to UKM Alumni Organisation and Pandan
Mulia Development Sdn Bhd, will resume construction once a new developer is
identified. UKM vice-chancellor Prof Datuk Dr Anuwar Ali said the university's
administration was negotiating with Pengurusan Danaharta Nasional Berhad on
reviving the project and the undertaking would then be open for tendering.
|
Penagih lepas gian di halaman rumah
04/02/2002 HM
KUALA LUMPUR: Sebuah bangunan tiga tingkat yang terbengkalai di jalan Raja Alang,
dekat sini, dikesan menjadi `syurga' bagi beratus-ratus penagih dadah melepaskan
gian mereka. Harian Metro difahamkan, bangunan itu mula dibina awal tahun 80-an.
tetapi pembinaannya gagal disiapkan kontraktor.
|
Projek jadi
belukar
14/02/2002 HM By Idris Musa
KAJANG: Lebih 100 unit rumah kos sederhana di Taman Kantan Permai, di sini,
yang tidak disiapkan pemaju kira-kira 10 tahun lalu kini ditumbuhi semak-samun
dan belukar, menjadi sarang binatang berbisa seperti ular. Tinjauan Harian Metro,
di kawasan itu semalam, mendapati projek rumah tingkat itu dalam peringkat akhir
untuk disiapkan. Angkara pemaju bermasalah, projek itu terbengkalai, hingga
keadaannya berubah wajah kepada belukar.
|
Projek perumahan terbengkalai jadi kediaman
15/02/2002 HM
SUBANG: Pendatang Indonesia dan Bangladesh kini menjadikan projek perumahan
yang terbengkalai sebagai kediaman bagi mengelak diserbu pihak berkuasa seperti
yang dialami rakan mereka di rumah kongsi atau setinggan. Tinjauan Harian Metro
di Taman Subang Dua di Pinggiran Subang dekat sini mendapati kedudukan lot kedai
dan kawasan perumahan yang begitu terpencil memberi peluang kepada mereka tinggal
di situ tanpa diketahui.
|
Hotel site a mosquito breeding ground
15/02/2002 NST
SEREMBAN, Thurs. - The uncompleted low-budget hotel facing the King George Five
school, abandoned almost four years ago, has become a mosquito breeding ground
besides being an eyesore. Pools of stagnant rainwater have collected at the
site and some of the structures have given way, posing a danger to passers-by.
|
Woolley to revive abandoned project
16/02/2002 NST-BUSS By Noor Adzman Baharuddin
WOOLLEY Development Sdn Bhd has big plans to develop more commercial properties
in Penang. For a start, it is rehabilitating the abandoned Raja Tun Uda commercial
district near Butterworth in mainland Penang.
|
Bangunan terbengkalai musnah terbakar
17/02/2002 BM
KUALA LUMPUR: Dua menara bangunan di tapak projek pembangunan bercampur, Sentul
Raya, yang terbengkalai sejak kira-kira tujuh tahun lalu musnah dalam kebakaran,
malam semalam. Kejadian kira-kira jam 7.30 malam itu memusnahkan binaan di bangunan
separuh siap projek bernilai RM1.3 bilion di Jalan Perhentian, Sentul dekat
sini.
|
Persatuan ragui bangunan terbakar angkara penagih
19/02/2002 BH
KUALA LUMPUR, Isnin - Persatuan Pembeli Hartanah Sentul Raya Kuala Lumpur (PPHSR),
meragui kebakaran bangunan terbengkalai, Villa Perhentian di Jalan Perhentian,
Sentul dekat sini dilakukan oleh penagih dadah dan meminta ia disiasat. Presidennya,
Moideen Kutty berkata, agak sukar mempercayai penagih dadah terbabit dalam kebakaran
itu kerana bangunan yang terbengkalai sejak tujuh tahun lalu, berpagar dan dijaga
rapi oleh pegawai keselamatan.
|
Housebuyers file suit against new developer
22/02/2002 NST
MALACCA, Thurs. - Five housebuyers from Taman Bukit Tembakau in Umbai have filed
a suit in the High Court against housing developer Jejaka Megah Sdn Bhd and
government-owned Tabung Pemulihan Perumahan Terbengkalai Sdn Bhd (TPPT). A.
Chelvadurai, K. Arajunan, Mahfar Alwee, Redzuan Mohd Said and Hamidah Md Noor,
who is the widow of Ibrahim Amat, the original houseowner, filed the writ through
the firm of Mogan Karupiah and Co.
|
Problems facing 70 abandoned projects
27/02/2002 NST By A. Hafiz Yatim
MALACCA, Tues. - Problems have been encountered in reviving about 70 abandoned
housing projects in the country. These include failure to attract new developers,
problem pertaining to the status of the affected land, and house buyers who
could not strike a deal with the new developers.
|
840 pembeli diminta beri peluang pemaju siapkan rumah
20/03/2002 BH By Hasnira Hassan
SUBANG, Selasa - Kira-kira 840 pembeli rumah di Seksyen 2, Bandar Pinggiran
Subang, Sungai Buloh, Shah Alam di sini diminta memberi peluang kedua kepada
pemaju, Unique Creation Sdn Bhd (Unique Creation) menyiapkan projek yang terbengkalai.
Pengerusi Jawatankuasa Tetap Pelancongan, Sains dan Teknologi dan Pembangunan
Organisasi negeri, Datuk Ir Lum Weng Keong, berkata pihaknya yakin pemaju terbabit
ingin menunaikan tanggungjawab menyiapkan projek.
|
Rumah tak siap, ansuran terus bayar
20/03/2002 HM
SUBANG: Kira-kira 50 pembeli rumah teres Delima dan apartmen Orkid di Seksyen
2, Bandar Pinggiran Subang, di sini, merungut kerana terpaksa membayar ansuran
pinjaman bank walaupun kediaman yang dibeli terbengkalai. Projek perumahan yang
mula dibina pada tahun 1997 dijangka siap pada tahun lalu tetapi masih terbengkalai.
|
Malton unit to revive RM350m project in
Malacca
21/03/2002 BT
MALTON Bhd's subsidiary, Domain Resources Sdn Bhd, has been given the task to
revive the RM350 million Malaysia China Light Industrial City (MCLIC) project
in Malacca. Domain Resources has been appointed as the project manager for the
162.8-ha MCLIC, said Malton executive director Philip Ho during a media tour
at the project site in Malacca yesterday.
|
Domain Resources pulih projek terbengkalai
22/03/2002 BH By Daud Awang
DOMAIN Resources Sdn Bhd (Domain Resources) memperoleh hak memulihkan projek
perumahan dan bangunan komersial terbengkalai bernilai RM350 juta di Bandar
Industri Ringan Malaysia China (MCLIC) di Tanjung Minyak, Melaka. Berikutan
itu, Domain Resources, iaitu sebuah syarikat milik penuh Malton Bhd kini bertanggungjawab
sepenuhnya terhadap pembangunan projek di tapak seluas 162.8 hektar yang sudah
terbengkalai sejak 1999 itu.
|
Pencen habis bayar rumah
25/03/2002 HM By Munir Ana'am Zuljadan
SEMENYIH: "Saya tidak merasa wang pencen sejak bersara pada 1995 kerana semua
habis untuk bayaran ansuran rumah terbengkalai," kata Mohd Zin Abdullah, 62.
Pesara kerani sekolah menengah di Jinjang itu mendakwa dia terpaksa melunaskan
ansuran RM262 sebulan sejak membeli rumah kos rendah Taman Dalma, di sini, pada
1994.
|
SPN bela nasib pemilik rumah
25/03/2002 HM
SEMENYIH: Syarikat Perumahan Negara Berhad (SPN) memberi jaminan membela nasib
106 pemilik rumah kos rendah Taman Dalma, di sini, sehingga mereka dapat menduduki
rumah masing-masing. Penolong Pengurus Besarnya, Mohd Amin Mohd Salleh berkata,
pemilik rumah Taman Dalma tidak perlu mengeluarkan belanja kerana semuanya ditanggung
SPN.
|
Taman Dalma project revived after 7 years
03/04/2002 NST-CITY By L.H. Lim
AFTER a seven-year wait, 102 house buyers of Taman Dalma at Km2 Jalan Bangi,
Semenyih, Selangor will get their houses by September under a rescue scheme
by Syarikat Perumahan Negara Berhad. Beranang State Assemblyman Ahmad Kuris
Mohd Nor said under the RM2 million aid scheme by the national housing company
(SPNB) of the Housing and Local Government Ministry, the project will be revived
this month.
|
1,400 waiting for white knight to come along
15/04/2002 The Star
About 1,400 purchasers of the stalled Taman Cemerlang housing scheme are still
waiting for a white knight to rescue the project in Bandar Baru Air Itam.
Housebuyers committee chairman Chang Yeong Shen said most buyers were from the
low income group and could not afford to come up with additional money to take
over the project themselves.
|
Pembeli rayu kerajaan Johor segera siapkan rumah murah
16/04/2002 BH
SAYA mewakili pembeli rumah pangsa Taman Desa Rakyat Perdana, Jalan Kong-Kong,
Pasir Gudang, Johor, bersebelahan Politeknik Johor Bahru dan berdepan Taman
Kampung Kopok Baru merayu kerajaan Johor memberi perhatian kepada masalah kami
yang tidak selesai sejak Mei 1998. Projek ini dimiliki Kumpulan Prasarana Rakyat
Johor Sdn Bhd iaitu syarikat Kerajaan Negeri Johor. Taman perumahan ini sepatutnya
siap pertengahan 2001, seperti yang tertera pada papan tanda projek.
|
YTL mahu jadi pemaju utama
17/04/2002 BH By Abdul Halim Yusoff
KUMPULAN YTL menjangka pembangunan hartanah bakal muncul sebagai penyumbang
utama pendapatannya dengan pelaksanaan projek pembangunan semula perbandaran
Sentul di Kuala Lumpur. YTL Land & Development Bhd (YTL Land), iaitu syarikat
hartanah Kumpulan YTL semalam membentangkan rancangannya untuk menghidupkan
semula projek pembangunan perbandaran itu yang sudah terbengkalai sejak krisis
kewangan Asia pada 1997,1998.
|
Lebih 26,000 rumah terbengkalai dipulih
21/04/2002 BM By Ziauddin Sharuddin
SEREMBAN: Kementerian Perumahan dan Kerajaan Tempatan mengenal pasti 70 projek
perumahan terbengkalai membabitkan 26,510 unit rumah di seluruh negara untuk
dipulihkan segera oleh Syarikat Perumahan Negara Bhd (SPNB). Daripada keseluruhan
projek bernilai RM3.2 bilion itu, 12 adalah di Selangor, Pahang (10), Wilayah
Persekutuan (9), Johor (7), Kelantan (7), Negeri Sembilan (6), Perak (5), Kedah
(4), Pulau Pinang (4), Melaka (3), Terengganu (2) dan Perlis (1).
|
SPNB mahu pulih 70 projek
21/04/2002 MA
SEREMBAN: Kementerian Perumahan dan Kerajaan Tempatan melalui Bahagian Pengawasan
dan Penguatkuasa mengenal pasti 70 projek perumahan terbengkalai di seluruh
negara untuk dipulihkan Syarikat Perumahan Negara Bhd (SPNB). Penolong Pengurus
Besar SPNB, Mohd Amin Mohd Salleh berkata, daripada 70 projek perumahan terbengkalai
itu, 12 di Selangor, Pahang (10), Wilayah Persekutuan (9), Johor (7), Kelantan
(7), Negeri Sembilan (6), Perak (5), Kedah (4), Pulau Pinang (4), Melaka (3),
Terengganu (2) dan Perlis (1).
|
Firm to revive 70 failed projects
21/04/2002 Sunday Star
SEREMBAN: Some 26,000 houses, with an estimated value of RM3.23bil and left
incomplete more than five years ago, are expected to be ready by next year.
Syarikat Perumahan Negara Berhad assistant general manager (project rehabilitation)
Mohd Amin Mohd Salleh said the company was targeting to complete the abandoned
projects by next year.
|
Revival
of abandoned projects
21/04/2002 NSUNT
SEREMBAN, Sat. - The Government has directed Syarikat Perumahan Negara Berhad
(SPNB) to revive some 70 of 514 housing projects abandoned by developers during
the economic slowdown of 1997. Wholly-owned by the Finance Ministry, the company,
incorporated in May, 2001, had initially been allocated a total of RM1 billion
for the purpose, said its assistant general manager (rehabilitation project)
Mohd Amin Mohd Salleh.
|
Pemaju kutip RM1 bilion, rumah tak siap
24/04/2002 HM
SUBANG: Pemaju sudah pungut Wang lebih RM1 bilion, tetapi sehingga ini pembeli
belum memiliki rumah. Presiden Persatuan Pengguna Subang dan Shah Alam (CASSA),
Datuk Dr Jacob George berkata, projek berkenaan membabitkan 880 unit apartmen
di Rhythm Avenue, USJ di sini yang sehingga kini masih terbengkalai.
|
Abandoned office tower project a big eyesore
25/04/2002 NST By Mohd Rashdan Jamaludin
ANYONE driving from the PLUS toll exit to Seremban town would immediately notice
the abandoned construction of an office tower, adjacent to the bus and taxi
terminal. I have nicknamed it the "Tower of Eyesore". It has been in that sorry
state since the Asian financial crisis in 1997-98 and that was almost four to
five years ago. Couldn't the State Government or the local town council take
over the abandoned project? Why leave the building in a mess?
|
Buyers seek legal redress 29/04/2002
NST
BUYERS of Rhythm Avenue apartments in USJ19, Subang Jaya, Selangor are running
out of patience with the project developer, Sanjung Utama Sdn Bhd. They say
construction work on the project stopped eight months ago and they are now seeking
legal action against the developer.
|
Four out of five housing projects abandoned since 1999 revived
02/05/2002 NST
April 30: Five housing and industrial projects were reported to have been abandoned
in Malacca since 1999 and they involve some 3,143 units and 1,418 buyers. However,
four have been revived and works are expected to resume soon.
|
880 Pembeli rumah teraniaya
08/05/2002 HMBy Zaitie Satibi
SHAH ALAM: Seramai 880 pembeli rumah di USJ19, Subang Jaya, mendakwa dianiaya
kerana terpaksa membuat bayaran untuk projek perumahan terbengkalai sejak lapan
bulan lalu. Mereka juga mendakwa dilayan secara kasar oleh pemaju selain terpaksa
menanggung risiko diisytiharkan muflis oleh institusi kewangan.
|
Buat laporan polis, tuntut ganti rugi
08/05/2002 HM
SUBANG: Pembeli pangsapuri Rhythm Avenue, USJ 19, dekat sini, yang hilang keyakinan
terhadap pemaju Sanjung Utama Sdn Bhd kerana belum menyiapkan rumah yang dibeli,
membuat laporan di Balai Polis Shah Alam, di sini kira- kira jam 11 pagi semalam.
|
Rhythm Avenue folk want probe into wrongdoings
by builder
13/05/2002 MM
RESIDENTS of Rhythm Avenue in Jalan USJ 19, Subang Jaya, will submit a letter
to the Board of Architects tomorrow asking them to investigate allegations of
wrongdoings among board members. A similar letter will also be sent to the Bar
Council, said Consumers Association of Subang and Shah Alam (CASSA) president
Jacob George.
|
Turnkey contractors to revive 12 projects
14/05/2002 The Star
PENANG: The state government has engaged turnkey contractors to revive and complete
12 abandoned low and low medium-cost housing projects in various phases of development.
The 12 projects are Taman Sri Semarak, Taman Cemerlang, Taman Terubong Indah
(Majestic Heights) and Fettes Villa in the northeast district; Taman Sri Bayu
in southwest district; Pangsapuri Widuri, Taman Sejahtera, PAKR Kuala Muda Phase
2 and PAKR Ekor Kucing Phase 2 in north Seberang Prai; and Taman Pekatra, Taman
Widuri and PAKR Sungai Dua in south Seberang Prai.
|
Rescue plan hinges on bank’s nod
21/05/2002 The Star
Work on the abandoned Pangsapuri Widuri project at Lorong Cempa, Butterworth,
would begin in July if the financing bank agrees to a rescue package submitted
by a turnkey contractor who has been entrusted by buyers to revive the project.
|
Builder issued ultimatum
29/05/2002 The Star
If held-back projects Rhythm Avenue and Newgate Apartments are not revived by
the end of this month, the developer will have to face the 1,500 house buyers
in front of the press. Subang Jaya assemblyman Datuk Lee Hwa Beng had made this
clear at a press conference he arranged to highlight the plight of the house
buyers.
|
Pembeli gelisah rumah lewat disiapkan
11/06/2002 BH
SERDANG, Isnin - Seramai 1,369 pembeli unit kedai apartmen dan pangsapuri kos
sederhana di Seksyen 5, Serdang Perdana dekat sini, berharap projek pembangunan
yang terbengkalai sejak November lalu, dapat diteruskan semula, secepat mungkin.
Ahli Dewan Undangan Negeri (Adun) Seri Kembangan, Datuk Liew Yuen Keong, berkata
projek berkenaan terpaksa ditangguhkan berikutan syarikat induk pemaju, Hiap
Aik Construction Bhd menghadapi masalah kewangan, menyebabkan projek itu terpaksa
diambil alih oleh Pengurusan Danaharta Nasional Bhd (Danaharta) iaitu agensi
kerajaan yang bertanggungjawab mengurus aset bermasalah.
|
Pembeli mahu projek disiapkan
11/06/2002 HM
SERDANG: Seramai 1,369 pembeli unit kedai pangsapuri dan apartment kos sederhana
di Seksyen 5, Serdang Perdana berharap projek yang terbengkalai sejak November
lalu, di kawasan itu dapat diteruskan semula. Ia berikutan kebanyakan pembeli
sudah membuat pembayaran tetapi masih tidak boleh menduduki unit kedai itu.
|
Taman Lingakaran Nur project revived
20/06/2002 NST-CITY By Siti Hajar Abd Aziz
AFTER waiting for 12 years, 250 house buyers of Taman Lingkaran Nur, Phase 1,
in Batu 12, Cheras, Hulu Langat are hopeful again that they will finally get
their homes. The project, which was abandoned in 1993, has been revived in a
rescue scheme being carried out by Syarikat Perumahan Negara Berhad (SPNB).
|
RM25m
rescue package to revive project
20/06/2002 The Star
A turnkey contractor is ready to inject RM1mil to kick start efforts to revive
Pangsapuri Widuri in Butterworth, which has been abandoned for nearly three
years. Harta Intan Construction Sdn Bhd director Amir Hussain Abdul Majid said
the total cost of the rescue package was estimated at RM25mil, provided all
house buyers agreed not to claim late delivery charges from the developer, Diamond
Crest Sdn Bhd.
|
The town centre that never was
25/06/2002 MM
LOOKING for "true stories" that can subsequently be used as the backdrop of
a legal commentary can sometimes be a difficult task. Sometimes, though, the
search can be very short, sweet and simple. Just the other day, whilst waiting
for one of World Cup matches to start, I was ambling through cyber space and
by sheer chance, happened to visit the House Buyers Association website.
|
Buyers seek details on status of stalled project
27/06/2002 NST-CITY
"WE demand an explanation!" Purchasers of commercial units and service apartments
offered under the Rhythm Avenue project in USJ19 in Subang Jaya, Selangor want
its developer, Sanjung Utama Sdn Bhd, to provide an explanation on what is happening
to the stalled project.
|
Syarikat sambung projek
28/06/2002 BH
KUALA LUMPUR, Khamis - Land and General Berhad (L&G) akan menyambung semula
projek perumahannya yang terbengkalai di Lembah Beringin pada Ogos ini dan menjangka
dapat menyiapkannya dalam tempoh 12 bulan. Pengarah Eksekutifnya, Mohd Razeek
Hussain, berkata anak syarikatnya, Lembah Beringin Sdn Bhd, pemaju projek itu
akan menyambung semula kerja membina 1,000 unit rumah projek itu.
|
Condo eyesore
29/06/2002 MM By Rita Jong
AN abandoned condominium project in Brickfields has become a haven for dadah
addicts, causing concern to residents in the area. Located at Jalan Tun Sambanthan
1, the 249-unit Sri Impian Condominium project was abandoned two years ago.
|
Desticom gets deal to revive housing projects
02/07/2002 MM
LITTLE-known Desticom Sdn Bhd has been assigned to revive housing projects abandoned
by developers during the economic slowdown of 1997, government sources said
yesterday. The company has so far secured an initial RM200 million contract
to complete the projects, and more contracts are expected. The company is now
expected to revive projects comprising low-cost and low-medium houses as well
as shophouses, the source told Mail Money yesterday.
|
House not delivered as promised
04/07/2002 MM By Sushma Veera; Hasnita Shaari
THE developer of the Villaria Apartment in Jalan Klang Lama told buyers that
the project would be completed by December last year. But KAS is still waiting.
|
Call to look into plight of unfortunate house buyers
04/07/2002 NST By Shahrum Sayuthi
THE State's special committee forreviving abandoned housing projects was yesterday
urged to solve the problems faced by buyers of half-completed apartments at
Skudai Villa Apartments and shoplot owners at the Skudai Plaza. Khoo Kong Ek
(BN-Skudai) said construction of the Skudai Villa Apartments, which started
in 1996, was halted a year later when the developer was declared bankrupt.
|
Another housing headache for rep
08/07/2002 The Star
Another abandoned housing project, Seri Semarak in Bandar Baru Air Itam, has
been added to the “headaches” of Paya Terubong assemblyman Dr Loh Hock Hun.
He said Seri Semarak, consisting of 1,306 units of low and medium cost flats,
was the third abandoned project after Majestic Heights and Taman Cemerlang in
his constituency.
|
60 pembeli rumah kecewa
09/07/2002 HM By Idris Musa
KUALA LUMPUR: Kira-kira 60 pembeli rumah Newgate Avenue di USJ 21, dekat sini,
berasa tertipu berikutan projek itu terbengkalai sedangkan mereka terpaksa melunaskan
faedah bulanan pinjaman bank. Disebabkan terlalu kecewa dan kesal dengan sikap
pemaju projek terbabit, mereka membuat laporan kepada Persatuan Pengguna Subang
& Shah Alam (Cassa), Jabatan Siasatan Jenayah Perdagangan, Majlis Peguam, Kementerian
Perumahan dan Kerajaan Tempatan, Badan Arkitek dan Bank Negara.
|
House buyers: Declare project abandoned
24/07/2002 The Star By Sira Habibu
The stalled Taman Widuri Housing Project action committee wants the authorities
to officially declare the project in Sungai Duri abandoned. Its chairman Lionell
L. Joeshua said banks would continue making progress payment to the developer
because there is no official declaration that the project is abandoned.
|
Pemaju rumah lepas tangan
27/07/2002 HM
SAYA adalah di antara 200 pembeli rumah dari syarikat Coopas Sdn Bhd yang memajukan
projek Kampung Tersusun, Jalan Gula Simpang Empat, Semanggol Perak amat dukacita
apabila pemaju tidak menjalankan tugas dengan sempurna. Mengikut perjanjian
jual beli di antara syarikat berkenaan dengan pembeli, rumah terbabit siap dalam
tempoh 24 bulan (2 tahun) dan sepatutnya pembeli sudah boleh menduduki.
|
Restraint from filing petition
27/07/2002 BT
A HOUSE buyer has served a winding-up petition on Lembah Beringin Sdn Bhd but
the Land & General Bhd subsidiary is scheduled for a hearing on its application
to restrain him from filing the petition. L&G said it had applied for the injunction
on June 11, and the hearing will be held on August 13. It said the buyer won
his case last year, and got an order for Lembah Beringin to refund roughly RM280,000
that he had paid. L&G said it had invested RM16.1 million in Lembah Beringin
and the expected loss from the winding-up proceedings is insignificant.
|
Pembeli kecewa
29/07/2002 HM
HULU KLANG: Pembeli pangsapuri Blok B Estana Court, di sini kecewa dengan pemaju
kerana gagal menyiapkan rumah mereka selepas tergangguh lebih dua tahun. Lebih
mengecewakan pembeli pangsapuri berkenaan terpaksa membayar faedah bagi pinjaman
perumahan kepada institusi kewangan.
|
Rumah belum nampak bayang
29/07/2002 HM
SAYA membeli sebuah rumah di Bandar Puncak Alam Fasa 2 pada Mac 1998. Sebenarnya
saya adalah mangsa rumah retak yang sepatutnya siap pada Mac 2000. Memandangkan
masalah terbabit, kami diberitahu yang ia akan diruntuhkan dan dibina semula,
seterusnya dijangka siap Mac 2002. Bagaimanapun selepas itu kami langsung tidak
mendapat apa-apa laporan kemajuan sehingga saya melawat sendiri ke tapak projek
pada Januari 2002 dan mendapati tapak terbabit baru sahaja diratakan
|
Contractors sought for Majestic Heights project
04/08/2002 NSUNT
PENANG, Sat. - The ad hoc committees of Phases 2A and 3A of Majestic Heights,
the country's largest abandoned housing project, is seeking qualified developers
or contractors to revive the housing scheme. Committee adviser for Phases 2A,
2B and 3A Lau Heng Loon said contractors with a minimum qualification of the
Contractors' Service Centre Grade 5 certification and the Construction Industry
Development Board (CIDB) or from the Malaysian Architects' Association are encouraged
to apply.
|
10 tahun rumah tak siap
05/08/2002 HM By Norainon Othman
KUALA LUMPUR: Penduduk Kampung Pasir Wardieburn, Sentul, di sini, berharap Flet
Danau Kota yang dibina bagi pemindahan semula setinggan itu disiapkan segera
selepas terbengkalai beberapa tahun. Daripada lima blok 20 tingkat yang dibina,
hanya dua blok sudah disiapkan manakala tiga blok lagi gagal disiapkan mengikut
jadual menyebabkan pembeli rumah ternanti-nanti.
|
Pemaju beri alasan kewangan
05/08/2002 HM
KUALA LUMPUR: "Saya ingatkan cuma saya yang mengalami masalah ini tetapi bila
ada pembeli yang tidak mendapat rumah sejak 1997, saya rasa ada sesuatu yang
tidak kena," kata setiausaha, Siti Azura Mohd Anuar, 37, mengenai rumah yang
dibelinya tetapi masih terbengkalai. Siti Azura yang membeli satu unit pangsapuri
Blok B Estana Court, Hulu Klang sejak 1999 tidak berpuas hati dengan prestasi
yang ditunjukkan pemaju perumahan itu yang melambatkan pembinaan pangsapuri
itu.
|
Mycom's restructuring exercise may face
hitch
06/08/2002 MM By Rizalman Hammim
MYCOM Bhd's restructuring exercise is expected to face a hitch as one of its
subsidiaries will be served with a winding-up petition over an uncompleted property
development project. Sentul Murni Sdn Bhd will be served with the petition by
the buyers of its abandoned Riverside Condominium project in Bandar Sentul Utama
soon.
|
New hopes for buyers
07/08/2002 The Star
The Pangsapuri Widuri apartment project in Lorong Chempa, Butterworth, which
had stalled for nearly three years, will soon be revived as the financing bank
has approved a rescue package plan.
|
Hope for abandoned Bandar Sentul Utama project
08/08/2002 MM
THE Bandar Sentul Utama Phase 2 project, which was abandoned in 1997, will be
given a new lease of life. The purchasers' protem committee was given the green
light to be the receiver and manager of the abandoned project, after a meeting
with the Ministry of Housing and Local Governments on Aug 21, 2001.
|
Mycom sees no impact
08/08/2002 MM
MYCOM Bhd said there will no impact on its restructuring scheme should a winding-up
action is taken against its subsidiary Sentul Murni Sdn Bhd as the unit's involvement
in the scheme is only in respect of restructuring of loans to financial institutions.
|
Sentul project not abandoned
10/08/2002 MM By Muzli Mohd Zin
BANDAR Sentul Utama Phase 2's developer has never abandoned the project as claimed
by buyers. Sentul Murni Sdn Bhd spokesman said they are committed to completing
it despite being saddled with problems, including a legal action by purchasers.
|
Dashed dreams
12/08/2002 MM By Chow Ee-Tan
AN exclusive address. Resort-style living away from the city. Such were the
dream homes and lifestyles that were promised by Emville Golf Resort near Sepang.
But nine years on, more than 700 purchasers of the project's phase one bungalow
lots are getting weary that their investment was going down the drain.
|
25% buyers delaying resumption of project
12/8/2002 The Star
The turnkey contractor appointed to revive the abandoned Pangsapuri Widuri project
in Butterworth is unable to resume work because it has failed to obtain 100%
approval from housebuyers for the rescue package.
|
Buyers to fight back
14/08/2002 MM By Chow Ee-Tan
PROPERTY developer Emville Sdn Bhd may have gone into liquidation but the purchasers
of Emville Golf Resort bungalow lots are still claiming their rights as spelt
out in the sale and purchase agreement. This was decided by the purchasers'
pro-tem committee at their first meeting last Sunday.
|
Seeking solution to stalled housing projects
15/08/2002 NST-CITYBy Shuib Taib
BUYERS of the two stalled housing projects in Subang Jaya - Rhythm Avenue Apartments
and Newgate Apartments - are advised to attend a buyers' committee meeting this
Sunday to determine their next course of action. "At the meeting, buyers will
be professionally advised on their rights as purchasers in the sales and purchase
agreement and under the law of this country.
|
Developer unable to revive abandoned project
16/08/2002
The Star
BUTTERWORTH: The turnkey contractor appointed to revive the abandoned Pangsapuri
Widuri project here is unable to resume work because it had failed to obtain
approval from all the house buyers for the rescue package.
|
Worried over halt in construction
17/08/2002 MM By Sushma Veera; Sangeetha Nair
PAYMENT has been made but there is no sign of work. NOR, of Sunway, wonders
when Worldwide Holdings Bhd will resume work on Pangsapuri Baiduri in Section
7, Shah Alam.
|
Buyers of stalled projects taking developers to court
20/08/2002 NST-CITY
SOME buyers of the stalled Rhythm and Newgate Avenue service apartment projects
in USJ, Subang Jaya are initiating legal action against the developers to reclaim
their monies with interest. The buyers met officials of the Consumers Association
of Subang and Shah Alam, Selangor (Cassa) last Saturday to request further action
by the association to protect their rights and interests in the matter.
|
Seeking ways to revive stalled housing projects
22/08/2002 NST-CITY
BUYERS of the stalled Rhythm Avenue and Newgate Avenue service apartment projects
in USJ Subang, have formed a "Buyers Committee" to solve their problems. The
20-member committee had their first meeting yesterday with the senior managers
of Sanjung Utama Sdn Bhd and Solarglow Sdn Bhd, the developers of the projects,
which have stalled for 11 months.
|
Kecewa flet tak siap
23/08/2002 HM By Abdul Samad
KAMI pembeli projek perumahan Taman Desa Rakyat Perdana, Pasir Gudang, Johor
Bahru kecewa dengan sikap pemaju yang masih gagal menyiapkan projek perumahan
yang terbengkalai lebih setahun lalu. Pelbagai alasan diberikan pemaju projek
berkenaan berhubung kelewatan menyiapkan projek kos rendah jenis flet tiga bilik
satu bilik air itu yang berharga RM25,000 seunit.
|
Former mining workers tired of long delay
in project
26/08/2002 MM
FOR four years, former workers of Killing Hall Tin Malaysia have been waiting
for their low-cost houses to be completed but their patience has run thin. Construction
work on their new homes has been so slow and only 142 out of 204 units have
been built on the 2.8 hectare ex-mining land in Batu 18 off Jalan Puchong.
|
26,000 houses to be ready by 2005
29/08/2002 NST By Alina Simon
ALOR STAR, Wed. - Syarikat Perumahan Negara Berhad (SPNB) is confident of completing
all 91 abandoned housing projects involving 26,000 low- and medium-cost houses
nationwide by 2005. Its chairman, Datuk Ahmad Zahid Hamidi, said the company,
a wholly-owned subsidiary of Ministry of Finance Incorporated, had been given
RM3 billion to rescue these projects.
|
SPN siapkan 15 projek perumahan tergendala
29/08/2002 BH
ALOR STAR, Rabu - Syarikat Perumahan Negara (SPN) sudah menyerahkan 15 projek
perumahan yang tergendala, siap dengan Sijil Kelayakan Menduduki (CF) kepada
pembelinya sepanjang tahun lalu, kata Pengerusinya, Datuk Ahmad Zahid Hamidi.
|
Work at abandon housing project restarts
20/09/2002 The Star
The 289 purchasers of the abandoned housing project, Seri Semarak and Eternal
Heights in Bandar Baru Air Itam, Penang, can now look forward to moving into
their new homes in three years’ time.
|
Fresh hope for stalled project
26/9/2002 The Star
THE stalled Menara Kuda Lari project in Jalan Lumba Kuda, Penang, is expected
to be completed within six months following the appointment of a project manager.
Project receiver Lee Jong Ki said the developer Ever Noble Sdn Bhd had entered
into a project management agreement with Januari Properties Sdn Bhd on Sept
9 to resume construction of the medium-cost apartments.
|
Light at the end of tunnel for 1,100 flat buyers
03/10/2002 The Star By Ng Su-Ann
About 1,100 buyers of the stalled Green Garden low-medium cost flats project
in Paya Terubong in Penang may soon be able to move into their respective units
as the Certificate of Occupancy is expected to be issued in two weeks. Housebuyer
P.K. Ng, 67, said she had received a letter from the developer stating that
vacant possession had been issued and the buyers would receive their keys after
making the final payment of RM10,000 each.
|
Purchasers ‘satisfied’
24/10/2002 The Star
Purchasers of Penang’s RM270mil Bayan World Mega-mall project are satisfied
with the measures taken by the developer to revive the project.
|
Project delay burdens buyers
25/10/2002 The Star By Maizatul Nazlina
PASIR GUDANG: Factory worker Fatimah Zulaida Mohd Yusof, who wanted her own
home, scrimped and saved to buy a low-cost house in Taman Desa Rakyat Perdana
when the offer came in 1998. Fatimah and her husband made plans on how they
could decorate the house and could not wait for it to be completed last February,
as stated in the sales and purchase agreement.
|
Projek rumah terbengkalai ditarik balik
29/10/2002 BH
KLANG, Isnin - Semua projek rumah kos rendah yang gagal dibina pemaju perumahan
swasta sehingga November ini, akan ditarik balik. Pengerusi Jawatankuasa Tetap
Kerajaan Tempatan, Perumahan dan Setinggan dan Alam Sekitar, Datuk Mokhtar Dahlan,
berkata ada kira-kira 60 projek lama dan baru yang belum dilaksanakan.
|
House buyers ‘assured’
08/11/2002 The Star By Manjit Kaur
Financial consultancy firm Deloitte KassimChan has been appointed to manage,
monitor and to see that the stalled Taman Kasawari housing project in Simpang
Ampat gets off the ground again.
|
22 abandoned private housing projects revived, completed
09/11/2002 NST
TWENTY-TWO of the 33 abandoned private housing projects in Pahang have been
revived and have since been completed. With the revival of the 22 projects costing
RM169.7 million, some 3,619 houses had been completed and sold to 2,631 buyers.
|
Projek rumah terbiar biak nyamuk
11/11/2002 HM
KUALA LUMPUR: Tapak perumahan terbengkalai di Persiaran Titiwangsa 1, Setapak,
di sini, sejak tiga tahun lalu menyebabkan bau busuk dan menjadi tempat pembiakan
nyamuk. Tinjauan Harian Metro mendapati bau busuk dan pembiakan nyamuk itu berpunca
daripada pembuangan sampah oleh penduduk setempat.
|
95 projek perumahan terbengkalai
13/11/2002 HM
DEWAN Rakyat dimaklumkan sekurang-kurangnya 95 projek perumahan dikenal pasti
terbengkalai manakala 43,541 unit rumah gagal dijual pemaju sehingga Oktober
lalu.HM 14/02/2002 By Idris Musa
KAJANG: Lebih 100 unit rumah kos sederhana di Taman Kantan Permai, di sini,
yang tidak disiapkan pemaju kira-kira 10 tahun lalu kini ditumbuhi semak-samun
dan belukar, menjadi sarang binatang berbisa seperti ular. Tinjauan Harian Metro,
di kawasan itu semalam, mendapati projek rumah tingkat itu dalam peringkat akhir
untuk disiapkan. Angkara pemaju bermasalah, projek itu terbengkalai, hingga
keadaannya berubah wajah kepada belukar.
|
Abandoned high-rise buildings a safety hazard
15/11/2002 NST By Annie Freeda Cruez
KUALA LUMPUR, Thurs. - Hundreds of abandoned high-rise buildings around the
country pose a threat to passers-by and vehicles as their conditions deteriorate.
A large number of these buildings have rusting tower cranes on the top which
are in danger of toppling over.
|
Housebuyers to meet Pulau Berkembar developer over completion
delay
25/11/2002 NST By A. Hafiz Yatim
MALACCA, Nov 24: Several buyers of development projects on Pulau Melaka would
be meeting developer Pulau Berkembar Sdn Bhd (previously known as Inno Enhance
Sdn Bhd) on Thursday over the delay in completion.
|
Buyers must sign new S&P agreement
02/12/2002 The Star
The 290 buyers of the stalled low medium-cost Seri Semarak apartment project
in Bandar Baru Air Itam have to sign a new sales and purchase (S & P) agreement
as a new developer has taken over the project.
|
Housebuyers ‘must decide’
02/12/2002 The Star By Ng Su-Ann
SOME 600 housebuyers of the stalled Fettes Villa project in Fettes Park, Penang,
have to make a decision. They have been told to decide whether they want the
project to continue or try to get back their downpayment of between RM10,000
and RM15,000 each.
|
Developer of stalled project gets summons
08/12/2002 NST-CITY
THE developer for the abandoned Rhythm Avenue apartment project in Subang Jaya,
Selangor was served with a writ of summons last Friday. Those named as co-defendants
were Rhythm Avenue developer Sanjung Utama Sdn Bhd, company directors Yap Kwee
Huat and Yap Kwee Chai and project architect Goh Day Ren.
|
|