    SPN ready to take over construction of 
    teachers' quarters 03/01/2002 BT
 SYARIKAT Perumahan Negara (SPN) yesterday expressed its willingness to take 
    over the construction of 10,000 units of teachers' quarters which are facing 
    delays if asked to do so by the Government. SPN chairman Datuk Zahid Hamidi 
    said the company has the capacity and expertise to carry out the task based 
    on its current performance and its future and current projects.
 | 
  
    | 
    
    Rumah guru: Kesatuan mahu siasatan terperinci
    04/01/2002 BH By Syuhada Choo Abdullah
 KEMENTERIAN Pendidikan digesa menjalankan siasatan terperinci bagi mengenal 
    pasti punca kegagalan program penswastaan rumah guru yang hanya menyiapkan 2.1 
    peratus daripada sasaran pembinaan 19,000 unit kediaman di luar kawasan sekolah 
    dalam tempoh ditetapkan. Sambil meminta mengambil tindakan segera, pertubuhan 
    keguruan yang dihubungi Berita Harian rata-rata berasa kesal dan menyifatkan 
    kegagalan itu sebagai serius serta perlu ditangani sebaik mungkin.
 | 
  
    | 
    
    
    Buyers: 
    Stalled mall project yet to resume work 08/01/2002 The Star
 PENANG: Shoplot buyers of the stalled Bayan World Megamall are upset that work 
    on the RM75mil project has yet to resume after nearly four years.A spokesman 
    for the purchasers, Ang Thean Hock, said the five-storey megamall project was 
    only 60% completed although the Penang Develop-ment Corporation (PDC), which 
    holds 30% stake in the company, had set a new deadline for its completion in 
    December this year.
 | 
  
    | 
    
    Pembeli tanggung masalah pemaju 
    09/01/2002 HM By Hamid Karim
 MEMILIKI rumah sendiri sebahagian daripada impian hidup kita. Ini kerana rumah 
    adalah antara keperluan asas yang sama pentingnya dengan pakaian dan makanan 
    dalam kehidupan seharian manusia. Namun, tidak semua impian memiliki rumah sentiasa 
    indah, kerana sejak bertahun-tahun lalu pembeli di negara kita sering dihantui 
    pelbagai kerenah dan masalah yang sekali gus menjadi igauan yang menakutkan.
 | 
  
    | 
    
    Usaha teruskan projek Plaza Rakyat masih samar 10/01/2002 HM
 KUALA LUMPUR: Plaza Rakyat bersebelahan Hentian Puduraya yang sepatutnya siap 
    tiga tahun lalu tidak akan dibiarkan menjadi projek terbengkalai yang mencacatkan 
    pemandangan ibu kota. Timbalan Menteri di Jabatan Perdana Menteri, Datuk Seri 
    Tengku Azlan Sultan Abu Bakar, berkata kerajaan tidak akan membiarkan projek 
    raksasa yang terhenti berikutan kegawatan ekonomi itu terbiar begitu saja.
 | 
  
    | 
    
    Usah jejas imej negara11/01/2002 HM By Si Kalam
 KALAM tidak dapat menerima hakikat projek Plaza Rakyat bersebelahan Hentian 
    Pudu Raya yang sepatutnya siap tiga tahun lalu masih terbiar. Anak buah Kalam 
    yang meninjau kawasan itu kelmarin mendapati pemandangan terbiar tapak berkenaan 
    boleh dilihat dengan jelas ketika menaiki LRT di Hentian Plaza Rakyat.
 | 
  
    | 
    
    Buyers not interested in reviving abandoned projects 11/01/2002 MM
 SOME buyers of abandoned housing projects have no interest in reviving them. 
    This was what the government discovered after conducting in-depth studies into 
    such projects. Of the 156 abandoned projects that were looked at, about 20 per 
    cent of such projects in Peninsular Malaysia fell into this category. Most of 
    the buyers who declined to have the projects revived had only paid the 10 per 
    cent deposit. This is in contrast to those buyers who have paid up to 80 per 
    cent of the purchase price. These buyers undoubtedly were keen on having the 
    projects in question revived. The study also revealed that only 52 abandoned 
    projects were still viable.
 | 
  
    | 
    
    Ramai sokong kerja disambung 12/01/2002 HM
 KUALA LUMPUR: Orang ramai bersetuju projek Plaza Rakyat yang terbengkalai diteruskan 
    bagi keselesaan kawasan berhampiran di masa hadapan. Projek yang terbengkalai 
    memberi gambaran buruk kepada orang ramai terutama pelancong asing kerana ia 
    terletak di pusat bandar raya.
 | 
  
    | 
    
    PM mahu projek Plaza Rakyat diteruskan 12/01/2002 HM By Norlaila Hamima Jamaluddin
 KUALA LUMPUR: Kerajaan akan berusaha bagi meneruskan projek Plaza Rakyat yang 
    tertangguh sejak tiga tahun lalu bagi mengelak ia menjadi projek "gajah putih". 
    Datuk Seri Dr Mahathir Mohamad, berkata beliau akan meminta semua pihak yang 
    terbabit dengan projek itu meneruskannya seberapa segera bagi mengelak kos lebih 
    tinggi.
 | 
  
    | 
    
    UKM to revive RM60m hostel 28/01/2002 NST By Farrah Naz Karim
 BANGI, Sun. - The RM60 million abandoned hostel project in Universiti Kebangsaan 
    Malaysia, which was previously awarded to UKM Alumni Organisation and Pandan 
    Mulia Development Sdn Bhd, will resume construction once a new developer is 
    identified. UKM vice-chancellor Prof Datuk Dr Anuwar Ali said the university's 
    administration was negotiating with Pengurusan Danaharta Nasional Berhad on 
    reviving the project and the undertaking would then be open for tendering.
 | 
  
    | 
    
    Penagih lepas gian di halaman rumah
     04/02/2002 HM
 KUALA LUMPUR: Sebuah bangunan tiga tingkat yang terbengkalai di jalan Raja Alang, 
    dekat sini, dikesan menjadi `syurga' bagi beratus-ratus penagih dadah melepaskan 
    gian mereka. Harian Metro difahamkan, bangunan itu mula dibina awal tahun 80-an. 
    tetapi pembinaannya gagal disiapkan kontraktor.
 | 
  
    | 
    
    
    Projek jadi 
    belukar 14/02/2002 HM By Idris Musa
 KAJANG: Lebih 100 unit rumah kos sederhana di Taman Kantan Permai, di sini, 
    yang tidak disiapkan pemaju kira-kira 10 tahun lalu kini ditumbuhi semak-samun 
    dan belukar, menjadi sarang binatang berbisa seperti ular. Tinjauan Harian Metro, 
    di kawasan itu semalam, mendapati projek rumah tingkat itu dalam peringkat akhir 
    untuk disiapkan. Angkara pemaju bermasalah, projek itu terbengkalai, hingga 
    keadaannya berubah wajah kepada belukar.
 | 
  
    | 
    
    Projek perumahan terbengkalai jadi kediaman
    15/02/2002 HM
 SUBANG: Pendatang Indonesia dan Bangladesh kini menjadikan projek perumahan 
    yang terbengkalai sebagai kediaman bagi mengelak diserbu pihak berkuasa seperti 
    yang dialami rakan mereka di rumah kongsi atau setinggan. Tinjauan Harian Metro 
    di Taman Subang Dua di Pinggiran Subang dekat sini mendapati kedudukan lot kedai 
    dan kawasan perumahan yang begitu terpencil memberi peluang kepada mereka tinggal 
    di situ tanpa diketahui.
 | 
  
    | 
    
    Hotel site a mosquito breeding ground 
    15/02/2002 NST
 SEREMBAN, Thurs. - The uncompleted low-budget hotel facing the King George Five 
    school, abandoned almost four years ago, has become a mosquito breeding ground 
    besides being an eyesore. Pools of stagnant rainwater have collected at the 
    site and some of the structures have given way, posing a danger to passers-by.
 | 
  
    | 
    
    Woolley to revive abandoned project
     16/02/2002 NST-BUSS By Noor Adzman Baharuddin
 WOOLLEY Development Sdn Bhd has big plans to develop more commercial properties 
    in Penang. For a start, it is rehabilitating the abandoned Raja Tun Uda commercial 
    district near Butterworth in mainland Penang.
 | 
  
    | 
    
    Bangunan terbengkalai musnah terbakar
    17/02/2002 BM
 KUALA LUMPUR: Dua menara bangunan di tapak projek pembangunan bercampur, Sentul 
    Raya, yang terbengkalai sejak kira-kira tujuh tahun lalu musnah dalam kebakaran, 
    malam semalam. Kejadian kira-kira jam 7.30 malam itu memusnahkan binaan di bangunan 
    separuh siap projek bernilai RM1.3 bilion di Jalan Perhentian, Sentul dekat 
    sini.
 | 
  
    | 
    
    Persatuan ragui bangunan terbakar angkara penagih 
    19/02/2002 BH
 KUALA LUMPUR, Isnin - Persatuan Pembeli Hartanah Sentul Raya Kuala Lumpur (PPHSR), 
    meragui kebakaran bangunan terbengkalai, Villa Perhentian di Jalan Perhentian, 
    Sentul dekat sini dilakukan oleh penagih dadah dan meminta ia disiasat. Presidennya, 
    Moideen Kutty berkata, agak sukar mempercayai penagih dadah terbabit dalam kebakaran 
    itu kerana bangunan yang terbengkalai sejak tujuh tahun lalu, berpagar dan dijaga 
    rapi oleh pegawai keselamatan.
 | 
  
    | 
    
    Housebuyers file suit against new developer
    22/02/2002 NST
 MALACCA, Thurs. - Five housebuyers from Taman Bukit Tembakau in Umbai have filed 
    a suit in the High Court against housing developer Jejaka Megah Sdn Bhd and 
    government-owned Tabung Pemulihan Perumahan Terbengkalai Sdn Bhd (TPPT). A. 
    Chelvadurai, K. Arajunan, Mahfar Alwee, Redzuan Mohd Said and Hamidah Md Noor, 
    who is the widow of Ibrahim Amat, the original houseowner, filed the writ through 
    the firm of Mogan Karupiah and Co.
 | 
  
    | 
    
    
    
    Problems facing 70 abandoned projects
     27/02/2002 NST By A. Hafiz Yatim
 MALACCA, Tues. - Problems have been encountered in reviving about 70 abandoned 
    housing projects in the country. These include failure to attract new developers, 
    problem pertaining to the status of the affected land, and house buyers who 
    could not strike a deal with the new developers.
 | 
  
    | 
    
    
    
    840 pembeli diminta beri peluang pemaju siapkan rumah
    20/03/2002 BH By Hasnira Hassan
 SUBANG, Selasa - Kira-kira 840 pembeli rumah di Seksyen 2, Bandar Pinggiran 
    Subang, Sungai Buloh, Shah Alam di sini diminta memberi peluang kedua kepada 
    pemaju, Unique Creation Sdn Bhd (Unique Creation) menyiapkan projek yang terbengkalai. 
    Pengerusi Jawatankuasa Tetap Pelancongan, Sains dan Teknologi dan Pembangunan 
    Organisasi negeri, Datuk Ir Lum Weng Keong, berkata pihaknya yakin pemaju terbabit 
    ingin menunaikan tanggungjawab menyiapkan projek.
 | 
  
    | 
    
    Rumah tak siap, ansuran terus bayar 20/03/2002 HM
 SUBANG: Kira-kira 50 pembeli rumah teres Delima dan apartmen Orkid di Seksyen 
    2, Bandar Pinggiran Subang, di sini, merungut kerana terpaksa membayar ansuran 
    pinjaman bank walaupun kediaman yang dibeli terbengkalai. Projek perumahan yang 
    mula dibina pada tahun 1997 dijangka siap pada tahun lalu tetapi masih terbengkalai.
 | 
  
    | 
    
    Malton unit to revive RM350m project in 
    Malacca 21/03/2002 BT
 MALTON Bhd's subsidiary, Domain Resources Sdn Bhd, has been given the task to 
    revive the RM350 million Malaysia China Light Industrial City (MCLIC) project 
    in Malacca. Domain Resources has been appointed as the project manager for the 
    162.8-ha MCLIC, said Malton executive director Philip Ho during a media tour 
    at the project site in Malacca yesterday.
 | 
  
    | 
    
    Domain Resources pulih projek terbengkalai
    22/03/2002 BH By Daud Awang
 DOMAIN Resources Sdn Bhd (Domain Resources) memperoleh hak memulihkan projek 
    perumahan dan bangunan komersial terbengkalai bernilai RM350 juta di Bandar 
    Industri Ringan Malaysia China (MCLIC) di Tanjung Minyak, Melaka. Berikutan 
    itu, Domain Resources, iaitu sebuah syarikat milik penuh Malton Bhd kini bertanggungjawab 
    sepenuhnya terhadap pembangunan projek di tapak seluas 162.8 hektar yang sudah 
    terbengkalai sejak 1999 itu.
 | 
  
    | 
    
    Pencen habis bayar rumah 
    25/03/2002  HM By Munir Ana'am Zuljadan
 SEMENYIH: "Saya tidak merasa wang pencen sejak bersara pada 1995 kerana semua 
    habis untuk bayaran ansuran rumah terbengkalai," kata Mohd Zin Abdullah, 62. 
    Pesara kerani sekolah menengah di Jinjang itu mendakwa dia terpaksa melunaskan 
    ansuran RM262 sebulan sejak membeli rumah kos rendah Taman Dalma, di sini, pada 
    1994.
 | 
  
    | 
    
    
    
    SPN bela nasib pemilik rumah 
    25/03/2002 HM
 SEMENYIH: Syarikat Perumahan Negara Berhad (SPN) memberi jaminan membela nasib 
    106 pemilik rumah kos rendah Taman Dalma, di sini, sehingga mereka dapat menduduki 
    rumah masing-masing. Penolong Pengurus Besarnya, Mohd Amin Mohd Salleh berkata, 
    pemilik rumah Taman Dalma tidak perlu mengeluarkan belanja kerana semuanya ditanggung 
    SPN.
 | 
  
    | 
    
    Taman Dalma project revived after 7 years 03/04/2002 NST-CITY By L.H. Lim
 AFTER a seven-year wait, 102 house buyers of Taman Dalma at Km2 Jalan Bangi, 
    Semenyih, Selangor will get their houses by September under a rescue scheme 
    by Syarikat Perumahan Negara Berhad. Beranang State Assemblyman Ahmad Kuris 
    Mohd Nor said under the RM2 million aid scheme by the national housing company 
    (SPNB) of the Housing and Local Government Ministry, the project will be revived 
    this month.
 | 
  
    | 
    
    
    
    1,400 waiting for white knight to come along 15/04/2002 The Star
 About 1,400 purchasers of the stalled Taman Cemerlang housing scheme are still 
    waiting for a white knight to rescue the project in Bandar Baru Air Itam.  
    Housebuyers committee chairman Chang Yeong Shen said most buyers were from the 
    low income group and could not afford to come up with additional money to take 
    over the project themselves.
 | 
  
    | 
    
    
    
    Pembeli rayu kerajaan Johor segera siapkan rumah murah 
    16/04/2002  BH
 SAYA mewakili pembeli rumah pangsa Taman Desa Rakyat Perdana, Jalan Kong-Kong, 
    Pasir Gudang, Johor, bersebelahan Politeknik Johor Bahru dan berdepan Taman 
    Kampung Kopok Baru merayu kerajaan Johor memberi perhatian kepada masalah kami 
    yang tidak selesai sejak Mei 1998. Projek ini dimiliki Kumpulan Prasarana Rakyat 
    Johor Sdn Bhd iaitu syarikat Kerajaan Negeri Johor. Taman perumahan ini sepatutnya 
    siap pertengahan 2001, seperti yang tertera pada papan tanda projek.
 | 
  
    | 
    
    YTL mahu jadi pemaju utama 
    17/04/2002 BH By Abdul Halim Yusoff
 KUMPULAN YTL menjangka pembangunan hartanah bakal muncul sebagai penyumbang 
    utama pendapatannya dengan pelaksanaan projek pembangunan semula perbandaran 
    Sentul di Kuala Lumpur. YTL Land & Development Bhd (YTL Land), iaitu syarikat 
    hartanah Kumpulan YTL semalam membentangkan rancangannya untuk menghidupkan 
    semula projek pembangunan perbandaran itu yang sudah terbengkalai sejak krisis 
    kewangan Asia pada 1997,1998.
 | 
  
    | 
    
    
    
    Lebih 26,000 rumah terbengkalai dipulih 
    21/04/2002  BM By Ziauddin Sharuddin
 SEREMBAN: Kementerian Perumahan dan Kerajaan Tempatan mengenal pasti 70 projek 
    perumahan terbengkalai membabitkan 26,510 unit rumah di seluruh negara untuk 
    dipulihkan segera oleh Syarikat Perumahan Negara Bhd (SPNB). Daripada keseluruhan 
    projek bernilai RM3.2 bilion itu, 12 adalah di Selangor, Pahang (10), Wilayah 
    Persekutuan (9), Johor (7), Kelantan (7), Negeri Sembilan (6), Perak (5), Kedah 
    (4), Pulau Pinang (4), Melaka (3), Terengganu (2) dan Perlis (1).
 | 
  
    | 
    
    
    
    SPNB mahu pulih 70 projek 21/04/2002 MA
 SEREMBAN: Kementerian Perumahan dan Kerajaan Tempatan melalui Bahagian Pengawasan 
    dan Penguatkuasa mengenal pasti 70 projek perumahan terbengkalai di seluruh 
    negara untuk dipulihkan Syarikat Perumahan Negara Bhd (SPNB). Penolong Pengurus 
    Besar SPNB, Mohd Amin Mohd Salleh berkata, daripada 70 projek perumahan terbengkalai 
    itu, 12 di Selangor, Pahang (10), Wilayah Persekutuan (9), Johor (7), Kelantan 
    (7), Negeri Sembilan (6), Perak (5), Kedah (4), Pulau Pinang (4), Melaka (3), 
    Terengganu (2) dan Perlis (1).
 | 
  
    | 
    
    
    
    Firm to revive 70 failed projects
    21/04/2002  Sunday Star
 SEREMBAN: Some 26,000 houses, with an estimated value of RM3.23bil and left 
    incomplete more than five years ago, are expected to be ready by next year. 
    Syarikat Perumahan Negara Berhad assistant general manager (project rehabilitation) 
    Mohd Amin Mohd Salleh said the company was targeting to complete the abandoned 
    projects by next year.
 | 
  
    | 
    
    
    Revival 
    of abandoned projects 21/04/2002 NSUNT
 SEREMBAN, Sat. - The Government has directed Syarikat Perumahan Negara Berhad 
    (SPNB) to revive some 70 of 514 housing projects abandoned by developers during 
    the economic slowdown of 1997. Wholly-owned by the Finance Ministry, the company, 
    incorporated in May, 2001, had initially been allocated a total of RM1 billion 
    for the purpose, said its assistant general manager (rehabilitation project) 
    Mohd Amin Mohd Salleh.
 | 
  
    | 
    
    Pemaju kutip RM1 bilion, rumah tak siap
    24/04/2002 HM
 SUBANG: Pemaju sudah pungut Wang lebih RM1 bilion, tetapi sehingga ini pembeli 
    belum memiliki rumah. Presiden Persatuan Pengguna Subang dan Shah Alam (CASSA), 
    Datuk Dr Jacob George berkata, projek berkenaan membabitkan 880 unit apartmen 
    di Rhythm Avenue, USJ di sini yang sehingga kini masih terbengkalai.
 | 
  
    | 
    
    Abandoned office tower project a big eyesore
    25/04/2002 NST By Mohd Rashdan Jamaludin
 ANYONE driving from the PLUS toll exit to Seremban town would immediately notice 
    the abandoned construction of an office tower, adjacent to the bus and taxi 
    terminal. I have nicknamed it the "Tower of Eyesore". It has been in that sorry 
    state since the Asian financial crisis in 1997-98 and that was almost four to 
    five years ago. Couldn't the State Government or the local town council take 
    over the abandoned project? Why leave the building in a mess?
 | 
  
    | 
    
    Buyers seek legal redress 29/04/2002  
    NSTBUYERS of Rhythm Avenue apartments in USJ19, Subang Jaya, Selangor are running 
    out of patience with the project developer, Sanjung Utama Sdn Bhd. They say 
    construction work on the project stopped eight months ago and they are now seeking 
    legal action against the developer.
 | 
  
    | 
    
    
    
    Four out of five housing projects abandoned since 1999 revived
    02/05/2002 NST
 April 30: Five housing and industrial projects were reported to have been abandoned 
    in Malacca since 1999 and they involve some 3,143 units and 1,418 buyers. However, 
    four have been revived and works are expected to resume soon.
 | 
  
    | 
    
    
    880 Pembeli rumah teraniaya 08/05/2002 HMBy Zaitie Satibi
 SHAH ALAM: Seramai 880 pembeli rumah di USJ19, Subang Jaya, mendakwa dianiaya 
    kerana terpaksa membuat bayaran untuk projek perumahan terbengkalai sejak lapan 
    bulan lalu. Mereka juga mendakwa dilayan secara kasar oleh pemaju selain terpaksa 
    menanggung risiko diisytiharkan muflis oleh institusi kewangan.
 | 
  
    | 
    
    Buat laporan polis, tuntut ganti rugi 
    08/05/2002 HM
 SUBANG: Pembeli pangsapuri Rhythm Avenue, USJ 19, dekat sini, yang hilang keyakinan 
    terhadap pemaju Sanjung Utama Sdn Bhd kerana belum menyiapkan rumah yang dibeli, 
    membuat laporan di Balai Polis Shah Alam, di sini kira- kira jam 11 pagi semalam.
 | 
  
    | 
    
    Rhythm Avenue folk want probe into wrongdoings 
    by builder 13/05/2002 MM
 RESIDENTS of Rhythm Avenue in Jalan USJ 19, Subang Jaya, will submit a letter 
    to the Board of Architects tomorrow asking them to investigate allegations of 
    wrongdoings among board members. A similar letter will also be sent to the Bar 
    Council, said Consumers Association of Subang and Shah Alam (CASSA) president 
    Jacob George.
 | 
  
    | 
    
    
    
    Turnkey contractors to revive 12 projects
    14/05/2002 The Star
 PENANG: The state government has engaged turnkey contractors to revive and complete 
    12 abandoned low and low medium-cost housing projects in various phases of development.  
    The 12 projects are Taman Sri Semarak, Taman Cemerlang, Taman Terubong Indah 
    (Majestic Heights) and Fettes Villa in the northeast district; Taman Sri Bayu 
    in southwest district; Pangsapuri Widuri, Taman Sejahtera, PAKR Kuala Muda Phase 
    2 and PAKR Ekor Kucing Phase 2 in north Seberang Prai; and Taman Pekatra, Taman 
    Widuri and PAKR Sungai Dua in south Seberang Prai.
 | 
  
    | 
    
    
    
    Rescue plan hinges on bank’s nod
    21/05/2002 The Star
 Work on the abandoned Pangsapuri Widuri project at Lorong Cempa, Butterworth, 
    would begin in July if the financing bank agrees to a rescue package submitted 
    by a turnkey contractor who has been entrusted by buyers to revive the project.
 | 
  
    | 
    
    
    
    Builder issued ultimatum 
    29/05/2002  The Star
 If held-back projects Rhythm Avenue and Newgate Apartments are not revived by 
    the end of this month, the developer will have to face the 1,500 house buyers 
    in front of the press. Subang Jaya assemblyman Datuk Lee Hwa Beng had made this 
    clear at a press conference he arranged to highlight the plight of the house 
    buyers.
 | 
  
    | 
    
    
    Pembeli gelisah rumah lewat disiapkan
    11/06/2002 BH
 SERDANG, Isnin - Seramai 1,369 pembeli unit kedai apartmen dan pangsapuri kos 
    sederhana di Seksyen 5, Serdang Perdana dekat sini, berharap projek pembangunan 
    yang terbengkalai sejak November lalu, dapat diteruskan semula, secepat mungkin. 
    Ahli Dewan Undangan Negeri (Adun) Seri Kembangan, Datuk Liew Yuen Keong, berkata 
    projek berkenaan terpaksa ditangguhkan berikutan syarikat induk pemaju, Hiap 
    Aik Construction Bhd menghadapi masalah kewangan, menyebabkan projek itu terpaksa 
    diambil alih oleh Pengurusan Danaharta Nasional Bhd (Danaharta) iaitu agensi 
    kerajaan yang bertanggungjawab mengurus aset bermasalah.
 | 
  
    | 
    
    Pembeli mahu projek disiapkan 11/06/2002 HM
 SERDANG: Seramai 1,369 pembeli unit kedai pangsapuri dan apartment kos sederhana 
    di Seksyen 5, Serdang Perdana berharap projek yang terbengkalai sejak November 
    lalu, di kawasan itu dapat diteruskan semula. Ia berikutan kebanyakan pembeli 
    sudah membuat pembayaran tetapi masih tidak boleh menduduki unit kedai itu.
 | 
  
    | 
    
    
    Taman Lingakaran Nur project revived 
    20/06/2002 NST-CITY By Siti Hajar Abd Aziz
 AFTER waiting for 12 years, 250 house buyers of Taman Lingkaran Nur, Phase 1, 
    in Batu 12, Cheras, Hulu Langat are hopeful again that they will finally get 
    their homes. The project, which was abandoned in 1993, has been revived in a 
    rescue scheme being carried out by Syarikat Perumahan Negara Berhad (SPNB).
 | 
  
    | 
    
    
    RM25m 
    rescue package to revive project 20/06/2002 The Star
 A turnkey contractor is ready to inject RM1mil to kick start efforts to revive 
    Pangsapuri Widuri in Butterworth, which has been abandoned for nearly three 
    years. Harta Intan Construction Sdn Bhd director Amir Hussain Abdul Majid said 
    the total cost of the rescue package was estimated at RM25mil, provided all 
    house buyers agreed not to claim late delivery charges from the developer, Diamond 
    Crest Sdn Bhd.
 | 
  
    | 
    
    The town centre that never was 25/06/2002 MM
 LOOKING for "true stories" that can subsequently be used as the backdrop of 
    a legal commentary can sometimes be a difficult task. Sometimes, though, the 
    search can be very short, sweet and simple. Just the other day, whilst waiting 
    for one of World Cup matches to start, I was ambling through cyber space and 
    by sheer chance, happened to visit the House Buyers Association website.
 | 
  
    | 
    
    Buyers seek details on status of stalled project 27/06/2002 NST-CITY
 "WE demand an explanation!" Purchasers of commercial units and service apartments 
    offered under the Rhythm Avenue project in USJ19 in Subang Jaya, Selangor want 
    its developer, Sanjung Utama Sdn Bhd, to provide an explanation on what is happening 
    to the stalled project.
 | 
  
    | 
    
    Syarikat sambung projek 28/06/2002 BH
 KUALA LUMPUR, Khamis - Land and General Berhad (L&G) akan menyambung semula 
    projek perumahannya yang terbengkalai di Lembah Beringin pada Ogos ini dan menjangka 
    dapat menyiapkannya dalam tempoh 12 bulan. Pengarah Eksekutifnya, Mohd Razeek 
    Hussain, berkata anak syarikatnya, Lembah Beringin Sdn Bhd, pemaju projek itu 
    akan menyambung semula kerja membina 1,000 unit rumah projek itu.
 | 
  
    | 
    
    Condo eyesore 29/06/2002 MM By Rita Jong
 AN abandoned condominium project in Brickfields has become a haven for dadah 
    addicts, causing concern to residents in the area. Located at Jalan Tun Sambanthan 
    1, the 249-unit Sri Impian Condominium project was abandoned two years ago.
 | 
  
    | 
    
    
    
    Desticom gets deal to revive housing projects 02/07/2002 MM
 LITTLE-known Desticom Sdn Bhd has been assigned to revive housing projects abandoned 
    by developers during the economic slowdown of 1997, government sources said 
    yesterday. The company has so far secured an initial RM200 million contract 
    to complete the projects, and more contracts are expected. The company is now 
    expected to revive projects comprising low-cost and low-medium houses as well 
    as shophouses, the source told Mail Money yesterday.
 | 
  
    | 
    
    House not delivered as promised 04/07/2002 MM By Sushma Veera; Hasnita Shaari
 THE developer of the Villaria Apartment in Jalan Klang Lama told buyers that 
    the project would be completed by December last year. But KAS is still waiting.
 | 
  
    | 
    
    Call to look into plight of unfortunate house buyers 
    04/07/2002 NST By Shahrum Sayuthi
 THE State's special committee forreviving abandoned housing projects was yesterday 
    urged to solve the problems faced by buyers of half-completed apartments at 
    Skudai Villa Apartments and shoplot owners at the Skudai Plaza. Khoo Kong Ek 
    (BN-Skudai) said construction of the Skudai Villa Apartments, which started 
    in 1996, was halted a year later when the developer was declared bankrupt.
 | 
  
    | 
    
    
    Another housing headache for rep 
    08/07/2002 The Star
 Another abandoned housing project, Seri Semarak in Bandar Baru Air Itam, has 
    been added to the “headaches” of Paya Terubong assemblyman Dr Loh Hock Hun. 
    He said Seri Semarak, consisting of 1,306 units of low and medium cost flats, 
    was the third abandoned project after Majestic Heights and Taman Cemerlang in 
    his constituency.
 | 
  
    | 
    
    
    
    60 pembeli rumah kecewa 09/07/2002 HM By Idris Musa
 KUALA LUMPUR: Kira-kira 60 pembeli rumah Newgate Avenue di USJ 21, dekat sini, 
    berasa tertipu berikutan projek itu terbengkalai sedangkan mereka terpaksa melunaskan 
    faedah bulanan pinjaman bank. Disebabkan terlalu kecewa dan kesal dengan sikap 
    pemaju projek terbabit, mereka membuat laporan kepada Persatuan Pengguna Subang 
    & Shah Alam (Cassa), Jabatan Siasatan Jenayah Perdagangan, Majlis Peguam, Kementerian 
    Perumahan dan Kerajaan Tempatan, Badan Arkitek dan Bank Negara.
 | 
  
    | 
    
    
    
    House buyers: Declare project abandoned 24/07/2002 The Star By Sira Habibu
 The stalled Taman Widuri Housing Project action committee wants the authorities 
    to officially declare the project in Sungai Duri abandoned. Its chairman Lionell 
    L. Joeshua said banks would continue making progress payment to the developer 
    because there is no official declaration that the project is abandoned.
 | 
  
    | 
    
    Pemaju rumah lepas tangan 27/07/2002 HM
 SAYA adalah di antara 200 pembeli rumah dari syarikat Coopas Sdn Bhd yang memajukan 
    projek Kampung Tersusun, Jalan Gula Simpang Empat, Semanggol Perak amat dukacita 
    apabila pemaju tidak menjalankan tugas dengan sempurna. Mengikut perjanjian 
    jual beli di antara syarikat berkenaan dengan pembeli, rumah terbabit siap dalam 
    tempoh 24 bulan (2 tahun) dan sepatutnya pembeli sudah boleh menduduki.
 | 
  
    | 
    
    Restraint from filing petition 27/07/2002  BT
 A HOUSE buyer has served a winding-up petition on Lembah Beringin Sdn Bhd but 
    the Land & General Bhd subsidiary is scheduled for a hearing on its application 
    to restrain him from filing the petition. L&G said it had applied for the injunction 
    on June 11, and the hearing will be held on August 13. It said the buyer won 
    his case last year, and got an order for Lembah Beringin to refund roughly RM280,000 
    that he had paid. L&G said it had invested RM16.1 million in Lembah Beringin 
    and the expected loss from the winding-up proceedings is insignificant.
 | 
  
    | 
    
    Pembeli kecewa 29/07/2002 HM
 HULU KLANG: Pembeli pangsapuri Blok B Estana Court, di sini kecewa dengan pemaju 
    kerana gagal menyiapkan rumah mereka selepas tergangguh lebih dua tahun. Lebih 
    mengecewakan pembeli pangsapuri berkenaan terpaksa membayar faedah bagi pinjaman 
    perumahan kepada institusi kewangan.
 | 
  
    | 
    
    Rumah belum nampak bayang 29/07/2002 HM
 SAYA membeli sebuah rumah di Bandar Puncak Alam Fasa 2 pada Mac 1998. Sebenarnya 
    saya adalah mangsa rumah retak yang sepatutnya siap pada Mac 2000. Memandangkan 
    masalah terbabit, kami diberitahu yang ia akan diruntuhkan dan dibina semula, 
    seterusnya dijangka siap Mac 2002. Bagaimanapun selepas itu kami langsung tidak 
    mendapat apa-apa laporan kemajuan sehingga saya melawat sendiri ke tapak projek 
    pada Januari 2002 dan mendapati tapak terbabit baru sahaja diratakan
 | 
  
    | 
    
    Contractors sought for Majestic Heights project 04/08/2002 NSUNT
 PENANG, Sat. - The ad hoc committees of Phases 2A and 3A of Majestic Heights, 
    the country's largest abandoned housing project, is seeking qualified developers 
    or contractors to revive the housing scheme. Committee adviser for Phases 2A, 
    2B and 3A Lau Heng Loon said contractors with a minimum qualification of the 
    Contractors' Service Centre Grade 5 certification and the Construction Industry 
    Development Board (CIDB) or from the Malaysian Architects' Association are encouraged 
    to apply.
 | 
  
    | 
    
    10 tahun rumah tak siap 05/08/2002 HM By Norainon Othman
 KUALA LUMPUR: Penduduk Kampung Pasir Wardieburn, Sentul, di sini, berharap Flet 
    Danau Kota yang dibina bagi pemindahan semula setinggan itu disiapkan segera 
    selepas terbengkalai beberapa tahun. Daripada lima blok 20 tingkat yang dibina, 
    hanya dua blok sudah disiapkan manakala tiga blok lagi gagal disiapkan mengikut 
    jadual menyebabkan pembeli rumah ternanti-nanti.
 | 
  
    | 
    
    Pemaju beri alasan kewangan 05/08/2002 HM
 KUALA LUMPUR: "Saya ingatkan cuma saya yang mengalami masalah ini tetapi bila 
    ada pembeli yang tidak mendapat rumah sejak 1997, saya rasa ada sesuatu yang 
    tidak kena," kata setiausaha, Siti Azura Mohd Anuar, 37, mengenai rumah yang 
    dibelinya tetapi masih terbengkalai. Siti Azura yang membeli satu unit pangsapuri 
    Blok B Estana Court, Hulu Klang sejak 1999 tidak berpuas hati dengan prestasi 
    yang ditunjukkan pemaju perumahan itu yang melambatkan pembinaan pangsapuri 
    itu.
 | 
  
    | 
    
    Mycom's restructuring exercise may face 
    hitch06/08/2002 MM By Rizalman Hammim
 MYCOM Bhd's restructuring exercise is expected to face a hitch as one of its 
    subsidiaries will be served with a winding-up petition over an uncompleted property 
    development project. Sentul Murni Sdn Bhd will be served with the petition by 
    the buyers of its abandoned Riverside Condominium project in Bandar Sentul Utama 
    soon.
 | 
  
    | 
    
    
    New hopes for buyers 
    07/08/2002 The Star
 The Pangsapuri Widuri apartment project in Lorong Chempa, Butterworth, which 
    had stalled for nearly three years, will soon be revived as the financing bank 
    has approved a rescue package plan.
 | 
  
    | 
    
    Hope for abandoned Bandar Sentul Utama project 
    08/08/2002 MM
 THE Bandar Sentul Utama Phase 2 project, which was abandoned in 1997, will be 
    given a new lease of life. The purchasers' protem committee was given the green 
    light to be the receiver and manager of the abandoned project, after a meeting 
    with the Ministry of Housing and Local Governments on Aug 21, 2001.
 | 
  
    | 
    
    Mycom sees no impact08/08/2002 MM
 MYCOM Bhd said there will no impact on its restructuring scheme should a winding-up 
    action is taken against its subsidiary Sentul Murni Sdn Bhd as the unit's involvement 
    in the scheme is only in respect of restructuring of loans to financial institutions.
 | 
  
    | 
    
    Sentul project not abandoned 10/08/2002 MM By Muzli Mohd Zin
 BANDAR Sentul Utama Phase 2's developer has never abandoned the project as claimed 
    by buyers. Sentul Murni Sdn Bhd spokesman said they are committed to completing 
    it despite being saddled with problems, including a legal action by purchasers.
 | 
  
    | 
    
    Dashed dreams 12/08/2002 MM By Chow Ee-Tan
 AN exclusive address. Resort-style living away from the city. Such were the 
    dream homes and lifestyles that were promised by Emville Golf Resort near Sepang. 
    But nine years on, more than 700 purchasers of the project's phase one bungalow 
    lots are getting weary that their investment was going down the drain.
 | 
  
    | 
    
    
    25% buyers delaying resumption of project
    12/8/2002 The Star
 The turnkey contractor appointed to revive the abandoned Pangsapuri Widuri project 
    in Butterworth is unable to resume work because it has failed to obtain 100% 
    approval from housebuyers for the rescue package.
 | 
  
    | 
    
    Buyers to fight back14/08/2002 MM By Chow Ee-Tan
 PROPERTY developer Emville Sdn Bhd may have gone into liquidation but the purchasers 
    of Emville Golf Resort bungalow lots are still claiming their rights as spelt 
    out in the sale and purchase agreement. This was decided by the purchasers' 
    pro-tem committee at their first meeting last Sunday.
 | 
  
    | 
    
    Seeking solution to stalled housing projects 15/08/2002 NST-CITYBy Shuib Taib
 BUYERS of the two stalled housing projects in Subang Jaya - Rhythm Avenue Apartments 
    and Newgate Apartments - are advised to attend a buyers' committee meeting this 
    Sunday to determine their next course of action. "At the meeting, buyers will 
    be professionally advised on their rights as purchasers in the sales and purchase 
    agreement and under the law of this country.
 | 
  
    | 
    
    
    
    Developer unable to revive abandoned project 16/08/2002 
    The Star
 BUTTERWORTH: The turnkey contractor appointed to revive the abandoned Pangsapuri 
    Widuri project here is unable to resume work because it had failed to obtain 
    approval from all the house buyers for the rescue package.
 | 
  
    | 
    
    Worried over halt in construction 17/08/2002 MM By Sushma Veera; Sangeetha Nair
 PAYMENT has been made but there is no sign of work. NOR, of Sunway, wonders 
    when Worldwide Holdings Bhd will resume work on Pangsapuri Baiduri in Section 
    7, Shah Alam.
 | 
  
    | 
    
    Buyers of stalled projects taking developers to court 
    20/08/2002 NST-CITY
 SOME buyers of the stalled Rhythm and Newgate Avenue service apartment projects 
    in USJ, Subang Jaya are initiating legal action against the developers to reclaim 
    their monies with interest. The buyers met officials of the Consumers Association 
    of Subang and Shah Alam, Selangor (Cassa) last Saturday to request further action 
    by the association to protect their rights and interests in the matter.
 | 
  
    | 
    
    Seeking ways to revive stalled housing projects 
    22/08/2002 NST-CITY
 BUYERS of the stalled Rhythm Avenue and Newgate Avenue service apartment projects 
    in USJ Subang, have formed a "Buyers Committee" to solve their problems. The 
    20-member committee had their first meeting yesterday with the senior managers 
    of Sanjung Utama Sdn Bhd and Solarglow Sdn Bhd, the developers of the projects, 
    which have stalled for 11 months.
 | 
  
    | 
    
    Kecewa flet tak siap23/08/2002 HM By Abdul Samad
 KAMI pembeli projek perumahan Taman Desa Rakyat Perdana, Pasir Gudang, Johor 
    Bahru kecewa dengan sikap pemaju yang masih gagal menyiapkan projek perumahan 
    yang terbengkalai lebih setahun lalu. Pelbagai alasan diberikan pemaju projek 
    berkenaan berhubung kelewatan menyiapkan projek kos rendah jenis flet tiga bilik 
    satu bilik air itu yang berharga RM25,000 seunit.
 | 
  
    | 
    
    Former mining workers tired of long delay 
    in project  26/08/2002 MM
 FOR four years, former workers of Killing Hall Tin Malaysia have been waiting 
    for their low-cost houses to be completed but their patience has run thin. Construction 
    work on their new homes has been so slow and only 142 out of 204 units have 
    been built on the 2.8 hectare ex-mining land in Batu 18 off Jalan Puchong.
 | 
  
    | 
    
    26,000 houses to be ready by 2005 29/08/2002 NST By Alina Simon
 ALOR STAR, Wed. - Syarikat Perumahan Negara Berhad (SPNB) is confident of completing 
    all 91 abandoned housing projects involving 26,000 low- and medium-cost houses 
    nationwide by 2005. Its chairman, Datuk Ahmad Zahid Hamidi, said the company, 
    a wholly-owned subsidiary of Ministry of Finance Incorporated, had been given 
    RM3 billion to rescue these projects.
 | 
  
    | 
    
    SPN siapkan 15 projek perumahan tergendala
    29/08/2002 BH
 ALOR STAR, Rabu - Syarikat Perumahan Negara (SPN) sudah menyerahkan 15 projek 
    perumahan yang tergendala, siap dengan Sijil Kelayakan Menduduki (CF) kepada 
    pembelinya sepanjang tahun lalu, kata Pengerusinya, Datuk Ahmad Zahid Hamidi.
 | 
  
    | 
    
    
    
    Work at abandon housing project restarts
    20/09/2002 The Star
 The 289 purchasers of the abandoned housing project, Seri Semarak and Eternal 
    Heights in Bandar Baru Air Itam, Penang, can now look forward to moving into 
    their new homes in three years’ time.
 | 
  
    | 
    
    
    
    Fresh hope for stalled project
    26/9/2002 The Star
 THE stalled Menara Kuda Lari project in Jalan Lumba Kuda, Penang, is expected 
    to be completed within six months following the appointment of a project manager. 
    Project receiver Lee Jong Ki said the developer Ever Noble Sdn Bhd had entered 
    into a project management agreement with Januari Properties Sdn Bhd on Sept 
    9 to resume construction of the medium-cost apartments.
 | 
  
    | 
    
    
    Light at the end of tunnel for 1,100 flat buyers03/10/2002 The Star By Ng Su-Ann
 About 1,100 buyers of the stalled Green Garden low-medium cost flats project 
    in Paya Terubong in Penang may soon be able to move into their respective units 
    as the Certificate of Occupancy is expected to be issued in two weeks. Housebuyer 
    P.K. Ng, 67, said she had received a letter from the developer stating that 
    vacant possession had been issued and the buyers would receive their keys after 
    making the final payment of RM10,000 each.
 | 
  
    | 
    
    
    Purchasers ‘satisfied’ 
    24/10/2002 The Star
 Purchasers of Penang’s RM270mil Bayan World Mega-mall project are satisfied 
    with the measures taken by the developer to revive the project.
 | 
  
    | 
    
    
    Project delay burdens buyers 25/10/2002 The Star By Maizatul Nazlina
 PASIR GUDANG: Factory worker Fatimah Zulaida Mohd Yusof, who wanted her own 
    home, scrimped and saved to buy a low-cost house in Taman Desa Rakyat Perdana 
    when the offer came in 1998. Fatimah and her husband made plans on how they 
    could decorate the house and could not wait for it to be completed last February, 
    as stated in the sales and purchase agreement.
 | 
  
    | 
    
    Projek rumah terbengkalai ditarik balik 
     29/10/2002 BH
 KLANG, Isnin - Semua projek rumah kos rendah yang gagal dibina pemaju perumahan 
    swasta sehingga November ini, akan ditarik balik. Pengerusi Jawatankuasa Tetap 
    Kerajaan Tempatan, Perumahan dan Setinggan dan Alam Sekitar, Datuk Mokhtar Dahlan, 
    berkata ada kira-kira 60 projek lama dan baru yang belum dilaksanakan.
 | 
  
    | 
    
    
    House buyers ‘assured’ 08/11/2002 The Star By Manjit Kaur
 Financial consultancy firm Deloitte KassimChan has been appointed to manage, 
    monitor and to see that the stalled Taman Kasawari housing project in Simpang 
    Ampat gets off the ground again.
 | 
  
    | 
    
    22 abandoned private housing projects revived, completed
     09/11/2002 NST
 TWENTY-TWO of the 33 abandoned private housing projects in Pahang have been 
    revived and have since been completed. With the revival of the 22 projects costing 
    RM169.7 million, some 3,619 houses had been completed and sold to 2,631 buyers.
 | 
  
    | 
    
    Projek rumah terbiar biak nyamuk 11/11/2002 HM
 KUALA LUMPUR: Tapak perumahan terbengkalai di Persiaran Titiwangsa 1, Setapak, 
    di sini, sejak tiga tahun lalu menyebabkan bau busuk dan menjadi tempat pembiakan 
    nyamuk. Tinjauan Harian Metro mendapati bau busuk dan pembiakan nyamuk itu berpunca 
    daripada pembuangan sampah oleh penduduk setempat.
 | 
  
    | 
    
    95 projek perumahan terbengkalai 13/11/2002 HM
 DEWAN Rakyat dimaklumkan sekurang-kurangnya 95 projek perumahan dikenal pasti 
    terbengkalai manakala 43,541 unit rumah gagal dijual pemaju sehingga Oktober 
    lalu.HM 14/02/2002 By Idris Musa
 KAJANG: Lebih 100 unit rumah kos sederhana di Taman Kantan Permai, di sini, 
    yang tidak disiapkan pemaju kira-kira 10 tahun lalu kini ditumbuhi semak-samun 
    dan belukar, menjadi sarang binatang berbisa seperti ular. Tinjauan Harian Metro, 
    di kawasan itu semalam, mendapati projek rumah tingkat itu dalam peringkat akhir 
    untuk disiapkan. Angkara pemaju bermasalah, projek itu terbengkalai, hingga 
    keadaannya berubah wajah kepada belukar.
 | 
  
    | 
    
    Abandoned high-rise buildings a safety hazard 15/11/2002 NST By Annie Freeda Cruez
 KUALA LUMPUR, Thurs. - Hundreds of abandoned high-rise buildings around the 
    country pose a threat to passers-by and vehicles as their conditions deteriorate. 
    A large number of these buildings have rusting tower cranes on the top which 
    are in danger of toppling over.
 | 
  
    | 
    
    
    Housebuyers to meet Pulau Berkembar developer over completion 
    delay25/11/2002 NST By A. Hafiz Yatim
 MALACCA, Nov 24: Several buyers of development projects on Pulau Melaka would 
    be meeting developer Pulau Berkembar Sdn Bhd (previously known as Inno Enhance 
    Sdn Bhd) on Thursday over the delay in completion.
 | 
  
    | 
    
    
    
    Buyers must sign new S&P agreement
    02/12/2002 The Star
 The 290 buyers of the stalled low medium-cost Seri Semarak apartment project 
    in Bandar Baru Air Itam have to sign a new sales and purchase (S & P) agreement 
    as a new developer has taken over the project.
 | 
  
    | 
    
    
    
    Housebuyers ‘must decide’ 02/12/2002 The Star By Ng Su-Ann
 SOME 600 housebuyers of the stalled Fettes Villa project in Fettes Park, Penang, 
    have to make a decision. They have been told to decide whether they want the 
    project to continue or try to get back their downpayment of between RM10,000 
    and RM15,000 each.
 | 
  
    | 
    
    Developer of stalled project gets summons 
    08/12/2002 NST-CITY
 THE developer for the abandoned Rhythm Avenue apartment project in Subang Jaya, 
    Selangor was served with a writ of summons last Friday. Those named as co-defendants 
    were Rhythm Avenue developer Sanjung Utama Sdn Bhd, company directors Yap Kwee 
    Huat and Yap Kwee Chai and project architect Goh Day Ren.
 | 
  
    |  |