    kompleks 11/01/1999 HM By Osman Lisut
 SERI KEMBANGAN: Sebuah kompleks perniagaan yang terbengkalai di sini dijadikan 
    tempat kediaman oleh sekumpulan warga asing tanpa dikesan pihak berkuasa sejak 
    lebih lima bulan lalu. Kompleks yang hampir 70 peratus siap itu dibahagikan 
    kepada beberapa bilik dan belum mempunyai bekalan air serta elektrik tetapi 
    didiami golongan itu yang dikatakan tidak mempunyai sebarang pekerjaan.
 | 
  
    | 
    Petition filed 
    to wind up condo developer 14/01/1999
    NST
 KUANTAN, Wed. - A group of 19 buyers of a high-end condominium project in Sungai 
    Karang today filed a petition in the High Court to wind up the developer in 
    their bid to revive and complete the project. The project, called Sunny Beach 
    Resort, was supposed to be completed in 1995. It was abandoned in 1996 after 
    only 90 per cent completed.
 | 
  
    | 
    Keen to move into 
    new home  26/01/1999 MM By Rosma Omar; Pauline Almeida
 SEN HOCK and his wife were looking forward to moving into their apartment at 
    Block G, Riverdale Park, Bukit Antarabangsa, Hulu Kelang, last year. However, 
    their hopes were dashed when they were not issued with vacant possession of 
    their property.
 | 
  
    | 
    Projek rumah terbengkalai 
    diteruskan 28/01/1999  HM By Hassan Omar
 ALOR STAR: Projek pembinaan rumah pangsa nelayan di Kuala Kedah, dekat sini 
    yang terbengkalai sejak dua tahun lalu akan diteruskan, tidak lama lagi. Projek 
    membabitkan penempatan semula kira-kira 600 nelayan di beberapa kampung sekitar 
    Kuala Kedah itu akan diteruskan secepat mungkin tanpa mengubah struktur.
 | 
  
    | 
    Pembinaan 219 unit 
    kilang berharga RM80 juta diteruskan 05/02/1999 BH
 JOHOR BAHRU, Khamis - Kerajaan negeri memberi jaminan projek pembinaan 219 unit 
    kilang di Taman Perindustrian Tiram, Ulu Tiram, dekat sini bernilai RM80 juta 
    yang terbengkalai sejak tahun lalu, dapat disiapkan dan beroperasi 1 Julai depan. 
    Ketika ini, projek pembinaan kilang bagi kemudahan kegiatan Industri Kecil dan 
    Sederhana (IKS) yang dijangka beroperasi awal tahun ini, gagal disiapkan mengikut 
    jadual disebabkan pemajunya tidak berkemampuan meneruskan pembinaannya termasuk 
    kerana menghadapi masalah kewangan.
 | 
  
    | 
    Empat bulan untuk 
    pemaju siapkan kilang 05/02/1999 HM
 JOHOR BAHRU: Kerajaan negeri memberi tempoh empat bulan sehingga 15 Jun depan, 
    bagi pemaju baru menyiapkan pembinaan kilang menempatkan industri ringan seperti 
    pengeluaran plastik dan perabot yang terbengkalai di Taman Perindustrian Tiram, 
    Ulu Tiram, dekat sini. Kilang berkenaan sepatutnya beroperasi awal tahun ini, 
    tetapi gagal disiapkan mengikut jadual disebabkan pemajunya tidak berkemampuan 
    meneruskan pembinaannya termasuk kerana menghadapi masalah kewangan.
 | 
  
    | 
    Tapak projek penuh 
    semak 17/02/1999 HM By Ahmad Saufi Mansor; Daut Noor; Azna 
    Rizan Mohamad
 WONG See Nam dari Jalan Ipoh, Kuala Lumpur berkata ada sebuah tapak pembinaan 
    terbengkalai yang terbiar sejak lima bulan lalu menimbulkan masalah kepada pesekitaran. 
    Menurutnya, kawasan itu dipenuhi semak samun di samping terdapat lopak air kotor 
    sehingga menjijikkan pemandangan walaupun kawasan itu berpagar.
 | 
  
    | 
    Pemaju dakwa terus 
    projek 19/02/1999 HM By Ahmad Shahrul Nizam Muhammad
 KAJANG: Projek perumahaan Taman Kantan Permai, di sini, yang didakwa pembeli 
    terbengkalai masih diteruskan secara berperingkat-peringkat. Pemaju projek itu, 
    Rajo Sdn Bhd, tidak menghentikan projek berkenaan seperti yang didakwa pembeli.
 | 
  
    | 
    Baiki semula Konkos 
    RM2j 24/02/1999 HM
 KUALA PERLIS: Bangunan Konkos berharga RM2 juta, di sini yang terbengkalai lima 
    tahun lalu akan dibangunkan sebagai pusat perniagaan komersial dan pelancongan, 
    tidak lama lagi. Yang Dipertua Majlis Perbandaran Kangar (MPK), Baharuddin Ahmad, 
    berkata bangunan berkenaan yang terletak berhampiran jeti lama itu akan dibaik 
    pulih dijangka membabitkan kos kira-kira RM10,000.
 | 
  
    | 
    Projek perumahan 
    terbengkalai selesai 26/02/1999  
    BH By Abdul Razak Raaff
 JOHOR BAHRU, Khamis - Projek perumahan rumah kos rendah Taman Puteri Wangsa, 
    di Ulu Tiram, dekat sini adalah projek perumahan terbengkalai terakhir di negeri 
    ini dapat diselesaikan, selepas menerima Sijil Layak Menduduki (CF) bulan lalu. 
    Projek perumahan membabitkan 1,422 unit rumah kos rendah itu terbengkalai sejak 
    12 tahun lalu, tetapi 896 unit daripada jumlah keseluruhan rumah jenis itu sudah 
    disiapkan dua tahun lalu.
 | 
  
    | 
    Successful rehabilitation 
    relieves Johor of abandoned housing woes 26/02/1999 NST
 JOHOR BARU, Thurs. - Johor's last remaining abandoned housing project at Taman 
    Putri Wangsa near Ulu Tiram here has been successfully rehabilitated. "This 
    effectively means that there are no more abandoned projects in Johor," State 
    Executive Councillor Adam Hamid said here today.
 | 
  
    | 
    It all started 
    in 1986 ... 02/03/1999 MM
 SIGNS that the City Homes apartment project would be abandoned appeared in late 
    1986 when the original developer, Sri Hartamas Development Sdn Bhd, began having 
    financial difficulties. Early that year, buyers received letters from the developer's 
    creditors explaining the financial straits.
 | 
  
    | 
    `Paper' houses
    02/03/1999 MM By Shamsul Yunos; Azlan Ramli
 THEY have waited 13 years. And if they do see their houses built, it would be 
    in the new millennium. Gerald Lawrence and his wife Geetha were among several 
    hundred people who had booked City Homes Apartments in Sri Hartamas, off Jalan 
    Duta, Kuala Lumpur. Back when their apartments were priced at RM70,000 each.
 | 
  
    | 
    Tapak projek sarang 
    penagih 06/03/1999 HM By Srihanasham Noordin; Hassan Muin; 
    Daut Noor
 SALLEH Ishak dari Jalan Pangkor, Kuala Lumpur, meminta Dewan Bandaraya Kuala 
    Lumpur (DBKL) mengambil tindakan terhadap aduan orang ramai yang dibuat ke pejabat 
    pihak berkuasa tempatan itu. Menurutnya, beberapa bulan lalu, dia pernah membuat 
    aduan mengenai projek DBKL yang terbengkalai di jalan itu berhampiran Hotel 
    Vistana.
 | 
  
    | 
    Projek terbengkalai 
    sarang penagih 17/03/1999 HM
 KAJANG: Projek perumahan Taman Lingkaran Nor, di sini, yang terbengkalai lebih 
    10 tahun lalu membimbangkan penduduk taman berhampiran terutama Taman Rakan 
    kerana dipercayai menjadi sarang penagih dadah dan penjenayah. Beberapa penduduk 
    Taman Rakan yang ditemui mendakwa rumah terbiar dan kawasan sekitar yang ditumbuhi 
    semak-samun memudahkan kegiatan itu dijalankan.
 | 
  
    | 
    Tak sungguh tak 
    kata 17/03/1999 HM By Si Kalam
 BAGAIKAN tunggu buah tak gugur. Itulah rungutan seorang pembeli rumah kepada 
    Kalam, apabila rumah yang ditempahnya 10 tahun lalu tidak siap- siap. Apa yang 
    dia dapat tenguk hanya tiang rumah dalam kawasan semak samun, yang mungkin menjadi 
    sarang penagih dadah atau penjenayah.
 | 
  
    | 
    CF: 100 pembeli 
    kecewa 27/03/1999 HM By Naim Tahir
 BATU PAHAT: Hasrat lebih 100 pembeli sebuah projek perumahan di bandar ini untuk 
    berpindah ke kediaman sendiri di taman berkenaan sehingga kini masih belum tercapai 
    walaupun antara mereka sudah menunggu sejak lebih 20 tahun lalu. Ini kerana, 
    walaupun sudah mendapat kunci rumah masing-masing daripada pemaju, projek terbabit 
    masih belum memperolehi sijil layak menduduki (CF) daripada pihak berkuasa tempatan.
 | 
  
    | 
    RM2j baik pulih 
    Konkos 30/03/1999
    BH
 KUALA PERLIS, Isnin - Majlis Perbandaran Kangar (MPK) akan membaik pulih bangunan 
    Konkos di sini berharga RM2 juta yang terbengkalai lebih lima tahun sebagai 
    pusat perniagaan komersial dan pelancongan. Yang Dipertuanya, Baharuddin Ahmad, 
    berkata bagi menjayakan tujuan itu, beberapa bahagian bangunan itu yang didapati 
    tidak sesuai akan dirobohkan di samping membina beberapa gerai baru sesuai dengan 
    matlamatnya.
 | 
  
    | 
    Rumah tak siap, 
    ansuran kena bayar08/04/1999 HM  By Hamid Karim; Ahmad Saufi Mansor
 RAHIM Rahmat dari Kulai, mengadu dibebani hutang bank kerana terpaksa membayar 
    ansuran bulanan kerana membeli sebuah rumah murah di sebuah taman perumahan 
    di Kulai, Johor. Bagaimanapun, taman itu kini terbengkalai walaupun dibina sejak 
    1985 menyebabkan ramai lagi pembeli dibebani hutang.
 | 
  
    | 
    Pembeli rumah harap 
    projek diteruskan 12/04/1999  BH By Lebai Dugong
 KAMI warga Institut Teknologi Mara (ITM) Cawangan Melaka gembira dengan kemenangan 
    Barisan Nasional (BN) pada pilihan raya Sabah baru-baru ini. Lebih menggembirakan 
    dengan kenyataan Timbalan Perdana Menteri yang mengarahkan semua projek perumahan 
    yang terbengkalai mesti diambil tindakan dan ditangani segera. Ini bagi mengelakkan 
    kemarahan rakyat kepada kerajaan BN.
 | 
  
    | 
    Isu pembinaan kilang 
    diatasi 29/04/1999 HM
 SUBANG JAYA: Masalah yang dihadapi kira-kira 400 pembeli bangunan kilang yang 
    terbengkalai di Taman Perindustrian Subang Mewah, di sini, dijangka dapat diselesaikan 
    tidak lama lagi. Ahli Dewan Undangan Negeri (Adun) Subang Jaya, Datuk Lee Hwa 
    Beng, berkata majlis perjumpaan antara pembeli dengan wakil Kementerian Perumahan 
    dan Kerajaan Tempatan akan diadakan di pejabat Majlis Perbandaran Subang Jaya 
    (MPSJ), esok.
 | 
  
    | 
    `Revive project'
    29/04/1999 MM By Rosma Omar
 SO near but yet so far. That's the feeling of the 478 buyers of factory lots 
    at the Taman Perindustrian Subang Mewah Jaya project, which is about 90 per 
    cent completed.
 | 
  
    | 
    Meeting over plight 
    of 478 house buyers 29/04/1999 
    NST-LTIMES By Angela Rao
 LOCAL Government and Housing Ministry officials from the abandoned projects 
    unit will attend a meeting tomorrow to discuss the plight of more than 478 buyers 
    of factory units at the abandoned Subang Mewah Industrial Park project in Subang 
    Jaya. Subang Jaya State Assemblyman Datuk Lee Hwa Beng said the developer, Korakyat 
    Plantations Sdn Bhd, had stopped work since last year, leaving the buyers in 
    debt as they had been paying more than RM5,000 in interest to service their 
    loans since 1994.
 | 
  
    | 
    Cheer for factory 
    buyers 01/05/1999 MM By Dennis Chua
 WHEN businessmen who bought factory lots in Taman Perindustrian Korakyat (formerly 
    Taman Perindustrian Subang Mewah) found out in 1997 that the project had been 
    abandoned, they felt as if darkness had descended upon them. Following a meeting 
    between the buyers' pro-tem committee, the local council and representatives 
    of the project's current managers, many of them now see light at the end of 
    the tunnel.
 | 
  
    | 
    Bangunan terbiar 
    biak nyamuk 03/05/1999 HM
 JOHOR BAHRU: Sebuah bangunan terbengkalai di Jalan Lumba Kuda di sini, didakwa 
    menjadi sarang pembiakan nyamuk dan mengancam keselamatan penduduk berhampiran. 
    Projek pembinaan bangunan untuk tujuan komersil dan terbengkalai sejak setahun 
    lalu itu dikatakan dipenuhi air yang menjadi tempat pembiakan nyamuk.
 | 
  
    | 
    Exploring ways 
    to revive abandoned housing schemes 12/05/1999 NST
 PENANG, Tues. - The State Government is exploring ways to revive 21 low- cost 
    housing schemes, undertaken by the private sector, that have been abandoned 
    since 1997. Chief Minister Tan Sri Dr Koh Tsu Koon said the State Government 
    wanted to facilitate the completion of these projects involving 5,381 units 
    with the help of the Finance Ministry, Bank Negara, the Housing and Local Government 
    Ministry and financial institutions.
 | 
  
    | 
    Worry over flooded 
    basement in abandoned project 12/05/1999 MM By Alina Simon
 EXCUSE me. Is this Venice? Recreating the famous Italian lagoon city is not 
    what the developer of this abandoned project (picture) in Taman Seri Sentosa, 
    Jalan Kelang Lama, had in mind.
 | 
  
    | 
    28 Penang housing 
    projects abandoned 19/05/1999 BT
 TWENTY-eight housing projects involving 7,668 houses were abandoned in Penang 
    between 1997 and 1998, Deputy Chief Minister Datuk Mohd Shariff Omar said yesterday. 
    He said of these, 10 were in Seberang Perai Utara, seven in Seberang Perai Tengah, 
    10 in Seberang Perai Selatan and one in Northeast District.
 | 
  
    | 
    Koperasi cari kontraktor 
    baru BH 21/05/1999 By Jamaludin Husin
 MUAR, Khamis - Koperasi Kakitangan Kerajaan Muar Berhad sedang mencari syarikat 
    kontraktor berwibawa bagi meneruskan kerja membina projek rumah kos rendah koperasi 
    itu di Jalan Kampung Tengah, Bakri, di sini yang terbengkalai sejak lapan tahun 
    lalu. Projek bernilai kira-kira RM3 juta mengandungi 118 unit rumah kos rendah 
    itu khusus untuk ahli terdiri daripada kakitangan berpendapatan rendah dengan 
    harga jualan RM25,000 seunit.
 | 
  
    | 
    Kedai tak siap 
    kena ceroboh 24/05/1999 HM By Hadzlan Hassan
 KAJANG: Beberapa blok rumah kedai yang terbengkalai berhampiran Taman Cuepacs, 
    di sini, didapati dicerobohi dan dijadikan pelbagai premis perniagaan termasuk 
    pusat permainan mesin slot video berunsur judi. Kegiatan itu dikesan berhampiran 
    Jalan Emas 5 dan Jalan Alam Jaya 19, manakala Jalan Alam Jaya 21 turut kelihatan 
    terbiar sekaligus menimbulkan keraguan mengenai status bangunan itu.
 | 
  
    | 
    EPF cheer for buyers 
    of houses that were never built31/05/1999 NST
 KUALA LUMPUR, Sun. - In 1987, 92 people withdrew part of their Employees' Provident 
    Fund savings to buy houses in Slim River, Perak. Twelve years later, they are 
    still without a home of their own. But now, thanks to the EPF, the 92 people, 
    many of them estate workers, will be allowed to withdraw their life savings 
    for a second time to purchase a house.
 | 
  
    | 
    KWSP akhiri masalah 
    pembeli rumah 31/05/1999 BH
 KUALA LUMPUR, Ahad - Pada 1987, seramai 92 orang, kebanyakannya pekerja ladang, 
    mengeluarkan wang daripada Kumpulan Wang Simpanan Pekerja (KWSP) untuk membeli 
    rumah di Slim River, Perak, tetapi hampir 12 tahun telah berlalu, mereka masih 
    tidak mempunyai rumah sendiri. Sekarang, terima kasih kepada KWSP, mereka dibenarkan 
    untuk mengeluarkan wang sekali lagi untuk membeli rumah.
 | 
  
    | 
    City Hall staff 
    not around at briefing 03/06/1999 NST-LTIMES
 BUYERS of units in the stalled Block G of the Kolam Air Apartments in Kampung 
    Kerinchi felt cheated on Monday when representatives from the Kuala Lumpur City 
    Hall were not around to brief the MP for Lembah Pantai Datuk Shahrizat Abdul 
    Jalil on the project. Shahrizat was to have met City Hall's privatisation and 
    joint venture unit deputy director Normah Malik for a briefing on the low cost 
    project, a joint venture between KL City Hall and Kensinar Sdn Bhd.
 | 
  
    | 
    Left to rot 22/06/1999 MM
 THIS building project in Port Dickson, near the NUBE Training Centre, is apparently 
    another abandoned project that begs attention from the local authority. Stagnant 
    water in the dug-up area is a potential breeding ground for mosquitoes.
 | 
  
    | 
    Low-cost housing 
    case sent to A-G 22/07/1999 BT
 THE case of 156 purchasers of low cost housing units in Bandar Baru Slim River, 
    Perak, who are still waiting for their houses after 12 years has been referred 
    to the Attorney-General's Chambers. Housing and Local Government Minister Datuk 
    Dr Ting Chew Peh said the AG's Chambers was looking into how the whole project 
    was auctioned off without protecting the rights of the purchasers who had paid 
    up to 30 per cent of the purchase price.
 | 
  
    | 
    Siasat pemaju lelong 
    rumah: Ting 22/07/1999
    BH
 KUALA LUMPUR, Rabu - Jabatan Peguam Negara diminta menyiasat aduan 156 pembeli 
    rumah di Bandar Baru Slim River, Perak mengenai projek itu yang dilelong oleh 
    pemaju asal kepada pihak lain tanpa memberi perlindungan kepada pembeli. Menteri 
    Perumahan dan Kerajaan Tempatan, Datuk Dr Ting Chew Peh, yang mengesahkan menerima 
    aduan penduduk, berkata perkara itu turut dibincangkan dalam mesyuarat jemaah 
    menteri beberapa minggu lalu.
 | 
  
    | 
    Work to resume 
    on low-cost houses for Kg Penaga squatters 23/07/1999 MM
 KAMPUNG PENAGA squatters will soon move into their low-cost houses. The housing 
    developer, TD Management Sdn Bhd, will resume work on the low-cost houses after 
    resolving some financial problems.
 | 
  
    | 
    Cabinet to be briefed 
    on abandoned project24/07/1999 NST
 IPOH, Fri. - A detailed study will be conducted by the Attorney-General's Chambers 
    on the plight of the 133 buyers of the abandoned Bandar Baru Slim River Phase 
    III low-cost housing project. Housing and Local Government Minister Datuk Dr 
    Ting Chew Peh said once all the information had been compiled, a report would 
    be submitted to the Cabinet on the next course of action.
 | 
  
    | 
    Families in a fix 
    over abandoned housing project 09/08/1999
    NST
 PENANG, Sun. - Imagine having to wait a lifetime just to live in a home you 
    can call your own and yet have your hopes dashed when the entire housing project 
    is abandoned. This was the case with Hong Kok Kwang, 57, a former trishaw rider, 
    and 362 other families who signed up for a low-medium-cost flat in Tanjung Tokong 
    in March 1996.
 | 
  
    | 
    Dream homes ready 
    but no moving in 16/08/1999 MM
 THIS is our house but we can't move in! Self-employed lorry driver S. Tharmalingam 
    and his wife are among the 102 owners of low-cost houses in Taman Desa Ayer 
    Hitam, Sepang, who cannot move into their new homes although the developer issued 
    a notice allowing them to collect the keys.
 | 
  
    | 
    Buyer sore over 
    delay in mall project 28/08/1999 NST
 PENANG, Fri. - Gift shop owner Teoh Teik Gek's hopes of owning a retail outlet 
    at the prestigious Bayan Bay Shopping Mall in Bayan Baru have been shattered. 
    She found out that work on the project was abandoned since August last year.
 | 
  
    | 
    Masalah projek 
    Le Chateau perlu dirunding 02/09/1999 BH
 KUALA LUMPUR, Rabu - Isu projek pembinaan Kondominum Le Chateau di sini yang 
    tertangguh sejak tujuh tahun lalu, seharusnya tidak dipolitikkan dan perlu diselesaikan 
    di meja perundingan. Timbalan Menteri Perumahan dan Kerajaan Tempatan, Datuk 
    Shafie Apdal, berkata kementerian itu memang bertanggungjawab menyelesaikan 
    kes berkenaan tetapi ia perlu dilaksanakan menerusi perundingan.
 | 
  
    | 
    Osu: 26 abandoned 
    projects revived 29/09/1999
    NST
 KOTA KINABALU, Tues. - The State government, in collaboration with the private 
    sector, has reactivated 26 abandoned housing projects in the State consisting 
    of 2,410 units of houses. Chief Minister Datuk Osu Sukam said the Ministry of 
    Local Government and Housing was in the process of reactivating two more abandoned 
    housing projects consisting of 153 units.
 | 
  
    | 
    10 tahun terbengkalai
    17/11/1999 HM  By Noor Sham Saleh
 KUALA LUMPUR: Lebih 800 pembeli rumah di Taman Kantan Permai Fasa 1B dan 1C, 
    kesal dengan sikap sambil lewa pemaju hingga projek perumahan untuk mereka terbengkalai 
    sejak 10 tahun lalu. Pengerusi jawatankuasa bertindak projek perumahan itu, 
    Mohd Isa Mat Nasir, berkata mereka membeli rumah berkenaan sejak 1990 tetapi 
    hingga kini rumah itu terbiar begitu saja.
 | 
  
    | 
    Isu rumah murah 
    selesai 06/12/1999 HM By Ahmad Saufi Mansor
 SETAPAK: Masalah penempatan penduduk setinggan dan rumah panjang di Kampung 
    Pasir Wardieburn, di sini berakhir apabila projek flet kos rendah yang terbengkalai 
    empat tahun lalu siap menjelang akhir tahun depan. Flet kos rendah bernilai 
    RM25,000 itu mula dibina pada 1992, tetapi terbengkalai pada 1995 berikutan 
    kegawatan ekonomi.
 | 
  
    | 
    Terbengkalai 10 
    tahun 13/12/1999  HM By Azwani Abdul Ghani
 KAJANG: Lebih 300 keluarga di taman perumahan Sungai Sekamat di sini, terpaksa 
    menanggung hutang apabila pemaju perumahan itu gagal menyiapkan projek perumahan 
    itu, sejak 10 tahun lalu. Ahli Dewan Undangan kawasan Kajang, Dr Shafie Abu 
    Bakar, ketika melawat kawasan itu semalam berkata keluarga malang itu sudah 
    menandatangani perjanjian jual beli dengan pemaju perumahan fasa satu projek 
    perumahan di situ sejak 1991.
 | 
  
    | 
    10 long, painful 
    years of waiting for Taman Lingkaran Nur housebuyers
    21/12/1999
    NST
 KAJANG, Mon. - Housebuyers of the abandoned Taman Lingkaran Nur housing scheme 
    near here have been waiting for 10 years and there seems to be no solution in 
    sight for them. The wait has been painful and their plight has been largely 
    ignored despite countless pleas to the developer, Saktimuna Sdn Bhd, to resolve 
    the situation.
 | 
  
    | 
    Illegals at home 
    in abandoned project 21/12/1999 NST
 KAJANG, Mon. - Hundreds of Malaysians who paid thousands of ringgit to buy houses 
    10 years ago are still waiting while these incomplete buildings have become 
    home to illegal immigrants. Ironic but true, and anyone who cares to make their 
    way to Taman Lingkaran Nur at Km19 Jalan Cheras can see it for themselves.
 | 
  
    | 
    Buyers lodge report 
    over abandoned project 22/12/1999 NST
 KUALA LUMPUR, Tues. - A group representing 554 property buyers in Bukit OUG 
    in Jalan Kelang Lama lodged a report with the city police commercial crime department 
    today claiming that the developer had failed to deliver their homes. Speaking 
    on behalf of the group, Loh Kwong Cheng, a Singapore national, claimed in his 
    report that the developer (Sri Keladi Sdn Bhd) had defaulted in delivering their 
    homes since 1997, as per their sales and purchase agreement.
 | 
  
    |  |