The Star 12/ 8/2002 BY ZARINAH DAUD 
			The turnkey contractor appointed to revive the abandoned 
			Pangsapuri Widuri project in Butterworth is unable to resume work 
			because it has failed to obtain 100% approval from housebuyers for 
			the rescue package. 
			Originally scheduled to take off next month, the project is now 
			likely to be delayed as only 75% of the housebuyers had signed the 
			supplementary sales and purchase agreement as requested by the 
			original bridging financier Maybank Finance Bhd. 
			In a desperate attempt to get all the purchasers to give their 
			endorsement, Pangsapuri Widuri Purchasers Committee chairman Jasper 
			Tan Kok Peng appealed to those who have yet to sign to do so. 
			“The project has been abandoned for three years and it is 
			pointless to further delay the signing as those who wish to sue 
			developer Diamond Crest Sdn Bhd will not get anything at the end of 
			the day. 
			“The rescue package offered by turnkey contractor Harta Intan 
			Con-struction Sdn Bhd is very reasonable and housebuyers are advised 
			to accept it,’’ he said at a meeting with the housebuyers on Sunday.
			
			Present at the meeting were Bagan Jermal state assemblyman Datuk 
			Dr Sak Cheng Lum and Harta Intan developer Amir Hussain Abdul Majid.
			
			Amir Hussain said the total cost of the rescue package was 
			estimated at RM25mil and Maybank had agreed in principle to revive 
			the project. 
			The bank, he added, also agreed to waive the RM5.5mil accumulated 
			interest for the loan given to Diamond Crest so as not to further 
			burden housebuyers. 
			“However, the bank imposed conditions wanting housebuyers not to 
			claim late delivery charges from Diamond Crest and that ground 
			tenants waive the arrears for the RM400 monthly rental which was 
			supposed to be paid by the developer. 
			“All these conditions have been included in the supplementary 
			agreement which housebuyers must sign so that we can restart the 
			project next month with completion expected in October next year,’’ 
			he added. 
			The housebuyers have been left in the lurch after Diamond Crest 
			abandoned the project which comprises 740 low-medium cost units and 
			230 low-cost units. 
			Dr Sak said the package offer was a win-win situation for all, 
			adding that the commencement of the project relies entirely on the 
			remaining 25% housebuyers who have yet to sign the agreement. 
			“The longer the delay, the longer housebuyers would have to wait 
			before they can move in,’’ he said. 
			Those who have yet to sign can contact the appointed law firm 
			Dana Vallen and Associates at 04-3241032 or Tan at 012-4636003