Chai Lai Fook & 18 Ors v. Sentul Raya Sdn Bhd
15 JULY 2004 - HIGH COURT [KUALA LUMPUR]
SAMAN PEMULA NO; S5-24-225-2003
CONTRACT:
Frustration - Sale and purchase agreement - Delay in handing over vacant
possession of condominium units - Delay blamed on economic downturn beyond
developer's control - Application by developer to Controller of Housing
for extension of time to deliver vacant possession rejected - Whether High
Court ought to allow developer's defence of frustration - Whether such defence
would allow developer to escape liability for late delivery - Whether such
defence would have effect of overriding decision of Controller of Housing
- Contracts Acts 1950 s. 57(2)
LAND LAW: Housing developers - Delay in completion - Delay blamed
on economic downturn beyond developer's control - Action by purchasers for
damages for late delivery - Whether developer's defence of frustration could
succeed
|
Cheong Bee Yong v. MBF Finance Bhd & Anor
19 JANUARY 2001 - HIGH COURT MALAYA, KUALA LUMPUR
[ORIGINATING SUMMONS NO: S6-24-2576-99]
LAND LAW: Housing developers - Promotional brochure
for sale of condominium units - Brochure stated developer would pay for
interest on loan until Certificate of Fitness issued - Whether developer
bound by words therein - Whether plaintiff relied on brochure to purchase
condominium unit
CONTRACT: Loan - Interest payments - Interest payments on loan before
issuance of Certificate of Fitness - Whether developer undertook to pay
for interest before issuance of Certificate of Fitness in promotional brochure
for sale of property - Whether plaintiff relied on such undertaking to purchase
property
|
Cheong Soo Leng
& ors v
H'ng Ah Ba 22 December 2003 - IN THE COURT OF APPEAL OF MALAYSIA
[CIVIL APPEAL NO: P-02-532-1997]
LAND LAW: Housing developers - Sale and purchase agreement
- Land not transferred and house not completed and delivered within time
period agreed - Whether plaintiff purchaser entitled to specific performance
and damages for late delivery - Whether defendants were developers within
Housing Developers (Control and Licensing) Act 1966 - Whether plaintiff
entitled to set off payment of purchase price with damages for late delivery
CONTRACT: Breach - Sale and purchase agreement - Land not transferred
and house not completed and delivered within time period agreed - Whether
plaintiff purchaser entitled to specific performance and damages for late
delivery - Whether defendants were developers within Housing Developers
(Control and Licensing ) Act 1966 - Whether plaintiff entitled to set off
payment of purchase price with damages for late delivery
|
Chiharu
Yabe (Zaugg) & Anor v. Pentadbir Tanah Wilayah Persekutuan Kuala Lumpur 05 AUGUST 2002 - HIGH COURT MALAYA, KUALA
LUMPUR
[ORIGINATING MOTION NO: R1-25-39-2001]
LAND LAW: Restraint on dealings - Restrictions in respect of non-citizens
for purchase of property - Rejection of application to purchase property
- Bumiputera quota - Whether applicable
WORDS & PHRASES: "Bumiputera quota" - Garis Panduan Perolehan Tanah
oleh Warganegara Asing/Syarikat Asing 1998
CIVIL PROCEDURE: Appeal - Time - Limitation to file appeal - National
Land Code, s. 418- Whether appeal filed beyond limitation period - Whether
to be dismissed
ADMINISTRATIVE LAW: Exercise of administrative powers - Discretion
- Restrictions in respect of non-citizens for purchase of property - National
Land Code, s. 433B - Requirement of approval from State Authority - Whether
discretion vested in Land Executive Committee - Rejection of application
to purchase property - Whether decision null and void
|
Chin
Kit Yee & Anor v. Yeng Chong Realty Bhd17 AUGUST 2006 - HIGH COURT MALAYA, MELAKA
[CIVIL SUIT NO: MT1-22-167-2003] |
Chua Eng Hong & Anor v. Palm Springs Development Sdn Bhd
02 MAY 2001 - HIGH COURT MALAYA, KUALA LUMPUR
[SUIT NO: S2-(S1)-22-365-1999]
Land Law:
Housing developers - Sale and purchase agreement - Defendant failed to complete
and deliver vacant possession within stipulated time - Failure to apply
for extension under reg. 11(3) of the Housing Developers (Control & Licensing)
Regulations 1989 - Whether the period of 36 months could be waived - Whether
extension of time could be given
|
Chung May Yen v. Puncakdana Development Sdn Bhd
20 SEPTEMBER 2002 - HIGH COURT MALAYA, KUALA LUMPUR
[ORIGINATING SUMMONS NO: S6-24-1604-2001]
Contract: Housing development contract - Breach -
Delay in delivering vacant possession of property - Whether caused by relevant
authorities - Defence of waiver - Whether defendant entitled - Whether purchaser
entitled to terminate agreement
Land Law: Housing developers - Sale and purchase agreement - Non-delivery
of vacant possession - Whether delay caused by relevant authorities - Whether
plaintiff waived right to terminate agreement - Whether plaintiff entitled
to terminate agreement
|
Chye Fook & Anor v. Teh Teng Seng Realty Sdn Bhd
27 SEPTEMBER 1988 - HIGH COURT IPOH
CIVIL SUIT NO 22-38-87 |
City
Investment Sdn Bhd. V. Koperasi Serbaguna Cuepacs Tanggungan Bhd
17 DECEMBER 1984 - FEDERAL COURT, KUALA LUMPUR
[CIVIL APPEAL NO. 30 OF 1984] |
|