CHUA ENG HONG & ANOR V. PALM SPRINGS
DEVELOPMENT SDN BHD
HIGH COURT MALAYA, KUALA LUMPUR
RK NATHAN J
[SUIT NO: S2-(S1)-22-365-1999]
2 MAY 2001
Land Law: Housing developers - Sale and purchase agreement -
Defendant failed to complete and deliver vacant possession within stipulated
time - Failure to apply for extension under reg. 11(3) of the Housing
Developers (Control & Licensing) Regulations 1989 - Whether the period of 36
months could be waived - Whether extension of time could be given
JUDGMENT
RK Nathan J:
Facts
The plaintiffs as purchasers and the defendant as developer/vendor
entered into a sale and purchase agreement on 5 January 1995 whereby the
plaintiffs agreed to buy and the defendant agreed to sell a fully completed
condominium unit known as Unit No. BV-013-2 Riverine Villas, Palm Springs
Resort, Port Dickson, held under the master title H.S.(D) 12925 Lot No. P.T.
2873 Mukim Pasir Panjang, District of Port Dickson, Negeri Sembilan (the
property) for a purchase price of RM368,995 to be paid in stages, and by
instalments in accordance with the architect's certificates and in
accordance with the terms of the agreement.
Amongst the express terms of the said agreement were the following,
namely:
(a) That in accordance with cl. 22(1) of the agreement, the defendant
agreed and was thereby required to complete and deliver vacant possession
of the property together with connection of water and electricity supply
within 36 calendar months from the date of the agreement.
(b) That in accordance with cl. 24 of the agreement, the defendant
agreed and was thereby required to complete the common facilities of the
property within 36 calendar months from the date of the agreement.
It was also an express term of the agreement in accordance with cl. 7
that time was of the essence. The plaintiffs and the defendant also entered
into a deed of covenant on the same day the agreement was signed for the use
of the Golf Club and Marina Club facilities. The defendant failed to
complete and deliver vacant possession of the said property and also failed
to complete the common facilities, within the stipulated time. The
plaintiffs then gave the defendant notice of termination of the agreement by
their solicitors' letter dated 13 April 1999 and claimed the following:
(1) Refund of monies paid by the plaintiffs to the defendant and/or agents of the defendant towards purchase of the property, refund of utility deposits and legal fees incurred by the plaintiffs towards purchase of the property RM295,637.95
(2) Financing costs incurred by the plaintiffs towards purchase of the property from 28 September 1994 to 26 June 1998 inclusive of interest at the rate of 10% per annum RM 64,847.96
(3) Refund of monthly Golf Club subscriptions paid by plaintiffs from February 1998 to October 1998RM 756
Total RM361,241.91
The plaintiffs also sought a declaration that they had effectively
terminated the agreement and also prayed for damages, interest and costs.
The plaintiffs then took out a summons under
O. 14 r. 3 of the Rules of the High Court 1980(the RHC) and prayed for
judgment for RM295,637.95 and costs.
On 26 January 2000 the learned senior assistant registrar (SAR) heard and
dismissed the said application for summary judgment. The plaintiffs
appealed.
The Appeal
There is no denying the fact that the plaintiffs had indeed paid the sum
of RM295,637.95. Counsel for the defendant/respondent confirmed this as
correct. It is also not in dispute that the time for completion had long
since expired. Since the agreement was signed on 5 January 1995, the 36
months being the completion period would have been 4 January 1998.
The defendant pleaded frustration and argued that as the soil on which
the condominium is constructed is of such a nature, it would be impossible
to complete the construction within the 36 months provided. Mr. Joseph for
the respondent confirmed that that was his only defence before me.
Mr. Wong for the appellant pointed out that since the agreement was in
the statutory form in compliance with reg. 11(1) of the Housing Developers
(Control & Licensing) Regulations 1989 and the period of completion had been
stipulated as 36 months and time being stipulated as being the essence of
the contract, the defendant ought to have completed the condominium within
the stipulated period. It is necessary for a proper consideration of the
respective submissions to reproduce reg. 11. It reads as follows:
11 Contract of sale
(1) Every contract of sale for the sale and purchase of a housing
accommodation together with the subdivisional portion of land
appurtenant thereto shall be in the form prescribed in Schedule G and
where the contract of sale is for the sale and purchase of a housing
accommodation in a subdivided building, it shall be in the form
prescribed in Schedule H.
(2) No housing developer shall collect any payment by whatever name
called except as prescribed by the contract of sale.
(3) Where the Controller is satisfied that owing to special
circumstances or hardship or necessity compliance with any of the
provisions in the contract of sale is impracticable or unnecessary, he
may, by a certificate in writing, waive or modify such provisions:
Provided that no such waiver or modification shall be approved if
such application is made after the expiry of the time stipulated for
the handing over of vacant possession under the contract of sale or
after the validity of any extension of time, if any, granted by the
Controller.
Having considered the said Regulation, I accept the submission of the
appellant that for the controller to waive the period of 36 months and to
give such further extended time as is necessary the defendant ought to have
applied for such extension under reg. 11(3). Unfortunately, the defendant
has not in any of its affidavits provided any evidence that, (a) such
application had been made, (b) that it was made before the expiry of the 36
months, and (c) that the controller had waived or modified such compliance.
Having perused the affidavits of the defendant I note that the defendant has
failed to show why it was unable to complete within the required period. In
any case even if it can show the reason, that does not provide it a way out.
It still ought to apply to the controller for a waiver by showing to the
controller why it is unable to comply. The special circumstances referred to
in the proviso to reg. 11(3) can mean the doctrine of frustration, but it is
not for this court to decide on the issue of frustration. That ought firstly
to be raised before the controller.
When asked by the court as to what the present position of the said
project is, counsel for the defendant requested for time to file an
affidavit. I did not see the need to adjourn on that score. Since the
defendant had failed to show it had complied with reg. 11(3) I set aside the
order of the learned SAR given on 26 January 2000 and entered judgment for
the plaintiffs in the undisputed sum of RM295,637.95 and decided that the
case do proceed in respect of the rest of the prayers. I also awarded the
plaintiffs the costs of the appeal and fixed a date for case management.
|