CHEONG SOO LEONG & ORS V. H'NG AH BA
COURT OF APPEAL, KUALA LUMPUR
[CIVIL APPEAL NO: P-02-532-1997]
MOKHTAR SIDIN JCA, ABDUL KADIR SULAIMAN JCA, PAJAN SINGH GILL JCA
22 DECEMBER 2003
LAND LAW: Housing developers
- Sale and purchase agreement - Land not transferred and house not completed
and delivered within time period agreed - Whether plaintiff purchaser entitled
to specific performance and damages for late delivery - Whether defendants
were developers within Housing Developers (Control and Licensing) Act 1966
- Whether plaintiff entitled to set off payment of purchase price with damages
for late delivery
CONTRACT: Breach - Sale and purchase agreement
- Land not transferred and house not completed and delivered within time
period agreed - Whether plaintiff purchaser entitled to specific performance
and damages for late delivery - Whether defendants were developers within
Housing Developers (Control and Licensing ) Act 1966 - Whether plaintiff
entitled to set off payment of purchase price with damages for late delivery
JUDGMENT
Abdul Kadir Sulaiman JCA:
This is an appeal by the first and the third defendants in High Court Civil
Suit No: 22-507-83 against the decision of the learned judge made on 24
July 1997 allowing the claim of the plaintiff. For convenience, throughout
this judgment, the appellants will be referred to as the defendants and
the respondent as the plaintiff.
The defendants were partners in the firm of Golden City Development Company
("the firm"). The first defendant was at the same time a building contractor
for the firm.
The plaintiff as a purchaser entered into a sale and purchase agreement
dated 1 August 1979 (the first agreement) with the first to the third defendants
as "the vendor", who describe themselves as "the owner of all that piece
of land, known as H.S. (D) 66, P.T. 1426-67 (Private Plot No: S19)" ("the
subject land"). The cost of the subject land was RM21,327. A single storey
semi-detached house was to be constructed on the subject land for the plaintiff.
To that end, the plaintiff entered into another agreement (the second agreement)
also dated 1 August 1979 with the firm. The plaintiff describes himself
as the owner who purchased the said land from the three defendants. The
three defendants executed this second agreement on behalf of the firm which
describes itself as the company. The consideration for the construction
of the semi-detached house was RM33,000. Hence, the total cost to be incurred
by the plaintiff for the price of the land and the house to be constructed
on it, worked out to a total amount of RM54,327. However, the agreement
between the parties did not come about smoothly as expected by the two agreements.
Some payments were made by the plaintiff in pursuance to the two agreements
but the land was not transferred and the house was not completed and delivered
to him in the time period agreed.
By Suit No: 22-507-83, ("the plaintiff's suit), the plaintiff on 13 August
1983 launched a claim against the first to the third defendants for specific
performance in respect of the two agreements, liquidated damages for non-delivery
of the house from 31 January 1981 to the date of delivery of vacant possession
to be assessed, interest at the rate of 8% p.a. from the date of judgment
to the date of satisfaction, and costs. The three defendants filed their
joint defence but did not make any counterclaim in respect of the plaintiff's
suit.
However, only on 25 September 1986, after a lapse of about three years from
the date of the plaintiff's suit, the firm, (and not the defendants), filed
Suit No: 24-786-86, ("the firm's suit), against the plaintiff upon the same
subject matter of the sale of the subject land and the construction of the
semi-detached house, for a declaration that the two agreements mentioned
earlier have been lawfully determined and are null and void and of no legal
effect, damages in the sum of RM16,717.95, interest and costs.
Upon agreement by all parties concerned, the two suits were heard together
by the learned judge in the High Court. At the end of the trial, the learned
judge allowed the claim of the plaintiff against the first to the third
defendants in the plaintiff's suit but dismissed the firm's suit. The order
of the court dated 24 July 1997, which is the subject matter of this appeal,
allowing the plaintiff's claim, however, made no mention of the dismissal
of the suit filed by the firm. But the notice of appeal by the defendants
dated 6 August 1997 against the decision of the learned judge includes an
appeal against the dismissal of the firm's suit.
Be that as it may, however, in the judgment of the learned judge of 24 July
1997, he did touch on the matter of the firm's suit as follows:
the last issue to be addressed by the court is whether the Defendants' claim
against the Plaintiff in C.S. No. 22(24)-786-86 for rescission and for consequential
prayers is statute barred.
Having analysed the evidence before him, the learned judge concluded:
From the pleadings and testimony given in court, it is beyond peradventure
that the whole essence of the Plaintiffs' sic Defendant's defence and their
action for rescission is founded upon their contention that the default
in progress-payment on the part of the Plaintiff occurred on 14.12.79, and
the notice (D2) 'to repudiate the said agreement', under clause 11(d) was
sent on 19/10/83. Thus, time would start to run from this date and the Defendants
had six years to commence action, under Section 6(1) Civil Law Act. However
the Defendants only filed their claim on 25.9.86 when they should have filed
their suit on or before 14.12.85. There was a delay of about 9 months. In
the event, I would hold that the Defendants' claim in C.S. 22-786-86 not
only fails upon grounds adumbrated in Civil Suit No. 22-507-1983 but is
also statute barred and must, for this added reason, be dismissed with costs.
Consequently, the Defendants' claim in C.S. 786-1986 (as plaintiffs therein)
would have to be dismissed with costs, and I so order.
I would therefore allow judgment to the Plaintiff in the following terms
as prayed for in the Statement of Claim in C.S. 507-83 under prayers (a),
(b), (d), (f) and (g), to wit (for clarification): Specific performance
of the first Agreement for the sale of the land by the Defendants to the
Plaintiff; Specific performance of the Second Agreement for the erection
of the said house; Liquidated damages for non-delivery of the said house
from the 31.1.1981 to 20.7.1983 to be assessed by the Senior Assistant Registrar
of this court; Liquidated damages for non-delivery of the said house from
21st July, 1983 to date of delivery of vacant possession also to be assessed
by the Senior Assistant Registrar of this court; Interest on the liquidated
damages referred to in paragraphs (d) and (e) above at the rate of eight
per centum (8%) per annum from the date of judgment to date of satisfaction
or realisation. And the Plaintiff will also be entitled to the costs of
his action.
Since the decision to dismiss the firm's suit is not the subject matter
of the Order appealed against, we need mention no more of it except that
part of the judgment of the learned judge touching on the issue of limitation
over the cause of action of the firm. Limitation is a statutory or legal
remedy as distinct from rescission which remedy is of equitable nature.
For limitation to be an issue before the court, it has to be pleaded. However,
we cannot find anywhere in the defence put up by the plaintiff that this
issue was ever pleaded by him. Hence, it is a non-issue before the learned
judge. However, we do find from the defence that the plaintiff raised various
equitable defences, such as laches and unconscionable conduct on the part
of the defendants in order to defeat the claim for rescission. Unfortunately,
nothing found itself in the judgment of the learned judge on those issues.
However, we fully agree with the learned judge upon his ground of dismissal
on the ground "adumbrated in Civil Suit No. 22-507-1983" ie, the plaintiff's
suit, in that he accepted the version of the plaintiff in the suit as against
the defendants'. The learned judge, in our view, is the best person to assess
and evaluate the evidence of both parties before him and perusing the records
before us, we are in no position to disagree or quarrel with his assessment
and evaluation in deciding the case in favour of the plaintiff in the plaintiff's
suit.
Back to the mainstream. According to the first agreement, the plaintiff
was required to pay towards the cost of the said land, on or before the
execution of the agreement a sum of RM2,132.70 by way of deposit and to
account of the purchase price. The completion and the payment of the balance
of the purchase price shall take place within 18 months from the date of
the agreement.
The schedule of payment provided by the agreement, is a follows:
(a) Booking Fee 2 1/2%
(b) Upon execution of Purchase
Agreement 7 1/2%
(c) On completion of foundation work 10%
(d) On completion of foundation work 15%
(e) On completion of Brickwalls of the
building, door and window frames 15%
(f) On completion of electrical wiring
and plumbing(without fittings) 10%
(g) On completion of roofing and
internal plastering 15%
(h) On completion of roads and drains
serving the said house 15%
(i) On completion and delivery of
certificate of fitness and handing
over 10%
The agreement also made provisions that upon payment of the balance of the
purchase price the defendants will execute a proper assurance to the plaintiff
of the property sold. One of the terms stipulated in cl. 7 of the agreement
is that if the plaintiff shall fail to pay any of the instalments and or
the balance of the purchase price for any period in excess of 14 days after
its due date, the defendants shall be entitled at its option on giving the
plaintiff or his solicitors not less than 30 days notice in writing to treat
the agreement as having been repudiated by the defendants and the agreement
shall at the expiration of the said notice be annulled and in such event:
(a) the defendants shall be entitled to deal with or otherwise dispose of
the said property as they shall see fit as if the agreement had not been
entered into,
(b) the instalments previously paid by the plaintiff shall be refunded to
the plaintiff without interest, and
(c) neither party shall have any further claim against the other for costs,
damages, compensation or otherwise.
According to the second agreement, the consideration of RM33,000 for the
construction of the semi-detached house for the plaintiff on the said land
is to be paid by the plaintiff "by such instalments (according to the progress
of the building operations) as may be requested" and such instalments to
be paid within 14 days "from the receipt of the Registered or ordinary notification
of each such request".
Clause 3 of this second agreement stipulates that the company will complete
the said house of the plaintiff as soon as possible or within 18 months
from the date of the agreement and the final instalment of the sum of RM33,000
shall be paid not later than 14 days after the firm shall have given written
notice to the plaintiff that the said house has been completed as aforesaid
and is fit for occupation. The schedule of payment provided in the agreement
is the same as that stipulated in items (b) to (i) of the first agreement
mentioned in para. 11 above, except for item (b) being substituted with
figure "10%" instead of "7 1/2"
Clause 6 thereof stipulates that if the plaintiff shall fail to pay the
instalments (save and except the final instalment) the firm shall stop work
on the construction, and may take steps as may be advised by its solicitors.
The consequence of the plaintiff failing to comply with the terms of payment
is the same as that provided for in the first agreement.
Thus, it is clear from the reading of the two agreements, it was the intention
of the parties that the plaintiff would ultimately owned the subject land
belonging to the defendants with a semidetached house constructed by the
firm on it for a total consideration of RM54,327 as soon as possible or
within 18 months from the date of the agreements. But as mentioned earlier,
this did not happen. Hence, the suit by the plaintiff.
From the evidence adduced, in regards to the two agreements, the plaintiff,
however, paid only a total sum of RM21,730.80 as follows:
17th November 1978 RM 1,000
8th July, 1979 RM16,298.10
24th July, 1979 RM 4,432.70
Total paid: RM21,730.80
According to the receipts issued by the firm, the payment on 17 November
1978 for RM1,000 was "Being Payment to account of Purchase Price $54,327
of single Storey Semi detached house on plot No: S19, HS(D) 65, KT. 1426-67
and subject to a sale agreement." It is clear that this payment was made
before the execution of the two agreements. The "purchase price" includes
the cost of the land and the house.
The payment on 8 July 1979 for RM16,298.10 was for the purpose of "Progress
Payment on Plot No. S19". This payment was made after the execution of the
two agreements. It is not clear from the detail of payment in the receipt
as to whether this payment was exclusively for the said land or for the
house or for both. But based on the schedule of payment provided in the
two agreements it would not matter very much and the schedule is based on
the progress of the construction on the land.
The payment on 24 July 1979 for RM4,432.70 was for the purpose of "Progress
Payment on Plot S19". Also this payment was made after the execution of
the agreements.
In the statement of claim, the plaintiff pleaded that although the construction
of the house commenced, the defendants neglected and refused to take any
steps towards the completion of it under the second agreement and/or to
execute a transfer of the said land to him under the first agreement despite
a final notice of demand given on 10 June 1983.
In their joint defence, the defendants by their statement of defence dated
29 February 1984 aver that the plaintiff himself had defaulted in his progress
payments in consequence whereof all building works had to come to a halt
for lack of funds. According to the defence, the date of default was 17
July 1979 and onwards. The construction of the house had reached the stage
of brickwalls with door and window frames have been completed, which is
item (e) in the schedule of payment. Hence, the claim of the plaintiff was
disputed and the defendants prayed that the claim of the plaintiff be dismissed
with costs. But, bearing in mind the date of the defence and the date of
the last receipt issued, the reason for the stoppage of work on the land
as given by the defendants cannot be substantiated. Be that as it may, this
defence was, however, amended in February 1996, some 2 1/2 years after the
filing of the plaintiff's suit. Of substance, the date of the alleged default
was now amended to 14th December 1979 and the stage of the house construction
completed was roofing and internal plastering, which is item (g) in the
schedule of payment. However, in his evidence before the learned judge,
the plaintiff as PW1, testified that in November 1979, which was some four
months after the last receipt issued, when he went back to the site office,
he found out that the housing project of the firm had stopped due to dispute
among the three defendants. This incident about the dispute among the defendants
was amply corroborated by the evidence of PW2 who worked for the firm as
a site-clerk for the period from 4 April 1975 to March 1981. The plaintiff
reiterated that he had never defaulted in progress payments as he did not
receive any demand from the defendants with or without the architect's certificate,
and indeed, videletter dated 28 December 1984 the defendants sought to refund
the amount the plaintiff had paid up but was refused by the plaintiff. He
did not pay progressive payments more so because construction works has
stopped, the site office was closed and the site was covered in vegetation.
The first defendant, in his evidence as DW2, however, admitted that the
construction works in the project stopped in October or November 1980 because
the firm was short of fund due to no-payment of progress payments by the
purchasers. The works, however, resumed in June 1984 and the buildings were
completed only on 27 December 1985.
Then as mentioned earlier, on 25 September 1986, after a lapse of about
three years from the date of the suit by the plaintiff, the firm (and not
the defendants in the plaintiff's suit) took out a writ of summons against
the plaintiff: Suit No: 24-786-86 mentioned earlier.
The pleadings averred that based on the two agreements, the firm on 1 August
1979 commenced building operations on the said land. However, in breach
of the relevant provisions of the two agreements, the plaintiff defaulted
in his progress payment. According to the particulars provided, the alleged
progress payment was due on 28 November 1979. As at that date, the plaintiff
had paid a total sum of RM21,730.80 and the balance due as at that date
was RM13,581.75 and by 19 October 1983 there was a delay of 1422 days. On
19 October 1983 the firm gave a written notice to the plaintiff requiring
him to settle all the arrears of payment within 30 days from the date of
the notice failing which the firm would repudiate the said agreements and
refund all instalments previously paid by the plaintiff without interest.
Despite the said notice, the plaintiff had failed and continued to neglect
to pay. So, on 28 December 1984 the amount of money paid so far by the plaintiff
was refunded in accordance with the provisions of the agreements. However,
on 14 January 1985 the said amount was refunded to the firm by the plaintiff
maintaining the two agreements as valid and subsisting. Then on 4 April
1986 the firm's solicitors wrote to the plaintiff informing him that there
was a sum of RM5,012.85 refundable to him after setting off a sum of RM16,717.95
being the resulting damages sustained by the firm as a result of the plaintiff's
willful failure and neglect to comply strictly with the terms and conditions
of the two agreements. The firm explained the set off sum being loss and
damages suffered on account of cost incurred during progress of work and
the difference for price increase. Hence, the firm in the suit claims against
the plaintiff for a declaration that the two agreements have been lawfully
determined and are now null and void and of no legal effect, damages in
the sum of RM16,717.95 above-stated, interest and costs. Be it noted that
in the amended defence to the plaintiff's suit, the date of the alleged
default was said to be 14th December 1979 but in the statement of claim
of the firm the alleged progress payment was due on 28 November 1979. For
the case of the firm or the defendants, it is indeed confusing to say the
least.
In his defence to the firm's suit, the plaintiff averred that the firm did
not continue with the said building works and did not complete the construction
of the house within 18 months as agreed. As to the alleged default in the
progress payment, the plaintiff averred that he was not bound to do so as
the firm's demand for payment, which was denied, was not supported with
the requisite architect's certificate.
As to the rescinding of the agreements by the firm, the plaintiff averred
that it was not entitled to do so for the following reasons:
(a) that it was done only after the partners was aware of the plaintiff's
suit against them,
(b) that as at the date of the company's writ, the sum of RM24,564.73 indemnity
for the delay in the delivery of the house was due and continuing, and the
plaintiff is entitled to have it set-off from the balance of the purchase
price,
(c) that the defendant is not entitled to payments alleged to be due because
he was not supplied with the architect's certificate in respect of the progress
work done,
(d) Housing Developers (Control and Licensing) Act 1966 prohibits rescission,
and
(e) belated exercising of the right, if any, by the defendant.
Hence, the claim is denied except for the balance of such sum after the
setting-off of the indemnity due to him which he is willing and ready to
do so. He prays for the dismissal of the suit with costs.
At the hearing of the two suits before the learned judge the following were
the issues agreed to be resolved:
(a) whether the defendants are developers within the ambit of the Housing
Developers Act 1966,
(b) whether the plaintiff is entitled to damages for late delivery pursuant
to the Act and the Housing Developers Rules,
(c) whether the plaintiff is entitled to set off the payment of the balance
of purchase price if the answer to (b) is in the affirmative,
(d) whether the plaintiff is entitled to specific performance of the two
agreements,
(e) whether the defendants are entitled to rescind the two agreements on
ground of default of progressive payments and to claim damages and whether
rescission by the defendants is permissible in law after an action for specific
performance has already been commenced by the plaintiff.
Having heard the evidence proffered by both parties, the learned judge preferred
the evidence tendered by the plaintiff as against that of the defendants.
On our part, having gone through the records, we see no reason to differ
with the findings made by the learned judge and we duly affirm his findings.
The learned judge found issues (a) to (d) above in the affirmative.
On issue (a), we find that the second agreement entered into with the plaintiff
is not one of constructing a house on his land per se by the firm. The firm
with the three defendants as partners embarked on a project to develop a
total of 75 units of houses spread over three phases. The project for which
the plaintiff is involved was comprised in the third phase comprising of
the construction in all of 26 units of single storey semi-detached houses
of which the plaintiff's house was one. They were therefore, not merely
ordinary contractors engaged to build houses for individuals but are housing
developers involved in housing development within the context of s. 3 of
the Housing Developers (Control and Licensing) Act 1966. So the learned
judge was right in holding that the defendants are in fact developers within
the meaning of the Housing Developers Act 1966.
On issue (b), consequent upon the finding on issue (a) and the default on
the part of the defendants, the firm must be liable in damages to the plaintiff
for late delivery beyond the agreed completion date stipulated in the agreements.
Hence, the learned judge is again right in so holding.
On issue (c), in accordance with the decision in S.E.A. Housing Corporation
Sdn. Bhd. v. Lee Poh Choo[1982] CLJ 355; [1982] CLJ (Rep) 305 cited by the
learned judge, the plaintiff is entitled to set off the payments of the
balance of the purchase price with that of damages for late delivery. So,
the learned judge cannot be faulted for so holding.
On issue (d), upon the finding by the learned judge that the defendants
had committed breach of the agreements, which finding we concur, an order
for specific performance of both the said agreements in favour of the plaintiff
would necessarily follow.
On the last issue, which is issue (e), all we need to say in the light of
what we said earlier, is that the suit by the firm was nothing but an attempt
on its part to find an escape route over the valid action of the plaintiff
filed some three years earlier against the defendants.
For the above reasons, having heard the appeal, we, on 13 August 2002 dismissed
this appeal of the defendants and duly affirmed the decision of the learned
judge in allowing the claim of the plaintiff in Suit No: 22-507-83. We,
however, made no order as to the costs of this appeal.
|