CHYE FOOK & ANOR V. TEH TENG SENG REALTY
SDN BHD
HIGH COURT [IPOH]
CIVIL SUIT NO 22-38-87
ABDUL MALEK, J
27 SEPTEMBER 1988
Abdul Malek J
By a consent order dated 22 February 1988 (encl 17) following a summons
for directions (encl 13) filed on 2 January 1988, both parties had asked for
the preliminary issue of 'whether the plaintiffs can sue for rescission on
the agreement of 8 August 1984 as the house is not completed by 7 August
1986 which is the completion date' be first determined by arguments in open
court on a date to be fixed by the senior assistant registrar.
It is necessary to refer to cl 7 of the relevant agreement (bundle A of
encl 4) which provides that 'time shall be the essence of the contract in
relation to all the provisions of this agreement and in particular to
the payment of any instalment of the purchase price or any part thereof and
the payment of all moneys due from the purchaser to the vendor under this
agreement' (emphasis mine) and to cl 18(1) of the said agreement which
states that 'the said building shall be completed by the vendor and vacant
possession delivered to the purchaser within twenty-four (24) calendar
months from the date of this agreement'.
However, cl 18(2) of that agreement stipulates that 'if the vendor fails
to deliver vacant possession of the said building in time the vendor shall
pay immediately to the purchaser liquidated damages to be calculated from
day to day at the rate of ten per centum (10%) per annum of the purchase
price'. It is this particular provision of the agreement that had resulted
in this particular preliminary issue having to be determined.
Learned counsel for the defendants had argued that the presence of cl
18(2) demolishes the right of the plaintiffs to sue for rescission while
learned counsel for the plaintiffs had submitted that time has been stated
to be the essence of all the provisions of the contract and a breach of it
entitles the purchaser to rescind. The defendants in their affidavit at encl
7 had admitted that the building was not completed within 24 months and the
plaintiffs accept the fact that the completion was in May 1987 and that the
certificate of fitness was issued on 9 December 1987 but nevertheless had
given notice to the defendants to rescind the agreement on 19 January 1987
which was before the completion of the building.
Learned counsel for the defendants had further submitted that this was
not a case where the defendants had abandoned the project or had failed to
do the work. He also argued that the agreement was in line with housing
regulations as provided in PU(A) 122/82 and that both parties had to adopt
the agreement. In the circumstances, he stated that there was no provision
in the agreement giving the purchaser the option to terminate especially
with the inclusion of cl 18(2) considering the fact that the plaintiffs had
given the notice to terminate while the defendants were still performing the
contract.
It is relevant at this stage to recapitulate the facts. The agreement had
been signed on 8 August 1984 and the completion date was therefore on 7
August 1986 which was exactly 24 months after. The building was not
completed on the completion date and the plaintiffs sent a notice to the
defendants on 19 January 1987 to rescind the agreement in view of the
non-compliance with the two-year period. The building was finally completed
in May 1987 and the certificate of fitness issued on 9 December 1987.
Now, it is pertinent to examine the law on this point. In Mayson v
Clouet & Anor [1924] AC 980 Lord Dunedin had said 'the law is quite
plain. If one party to a contract commits a breach then if that breach is
something that goes to the root of the contract, the other party has his
option. He may still treat the contract as existing and sue for specific
performance; or he may elect to hold the contract as at an end, that is, no
longer binding on him—while retaining the right to sue for damages in
respect of the breach committed.'
Some nine years earlier in Stickney v Keeble & Anor [1915] AC 386,
Lord Parker of Waddington had pragmatically pronounced the principles as
follows:
My Lords, in a contract for the sale and purchase of real estate, the
time fixed by the parties for completion has at law always been regarded
as essential. In other words, courts of law have always held the parties
to their bargain in this respect, with the result that if the vendor is
unable to make a title by the day fixed for completion, the purchaser can
treat the contract as at an end and recover his deposit with interest and
the costs of investigating the title.
In such cases, however, equity having a concurrent jurisdiction did not
look upon the stipulation as to time in precisely the same fight. Where it
could do so without injustice to the contracting parties it decreed
specific performance notwithstanding failure to observe the time fixed by
the contract for completion, and as an incident of specific performance
relieved the party in default by restraining proceedings at law based on
such failure.
This is really all that is meant by and involved in the maxim that in
equity the time fixed for completion is not of the essence of the
contract, but this maxim never had any application to cases in which the
stipulation as to time could not be disregarded without injustice to the
parties, when, for example, the parties, for reasons best known to
themselves, had stipulated that the time fixed should be essential, or
where there was something in the nature of the property or the surrounding
circumstances which would render it inequitable to treat it as a
non-essential term of the contract.
It should be observed, too, that it was only for the purposes of
granting specific performance that equity in this class of cases
interfered with the remedy at law. A vendor who had put it out of his own
power to complete the contract, or had by his conduct lost the right to
specific performance, had no equity to restrain proceedings at law based
on the non-observance of the stipulation as to time. substantial failure
of performance or a breach of an essential term, perhaps what Lord Diplock
said in Photo Production Ltd v Securicor Transport Ltd [1980] AC
827 may throw some light on the matter. He had said that 'where the event
resulting from the failure by one party to perform a primary obligation
has the effect of depriving the other party of substantially the whole
benefit which it was the intention of the parties that he should obtain
from the contract, the party not in default may elect to put an end to all
primary obligations of both parties remaining unperformed.'
Chitty on Contracts, Vol 1, 24th Ed, states at paras 1270-71 that
at common law, in the absence of a contrary intention, performance of the
contract had to be carried out upon the exact date specified in the contract
and a party could treat the contract as at an end if the other party's
performance was not completed on a fixed date, since time was of the essence
of the contract. However, in equity time was not of the essence of the
contract except in three situations, namely, where the parties had expressly
stipulated in their contract that the time fixed for performance must be
exactly complied with, where the circumstances of the contract or the nature
of the subject matter indicates that a fixed date must be exactly complied
with and where time was not originally of the essence of the contract but
one party had been guilty of undue delay and the other party had given
notice requiring the contract to be performed within a reasonable time. It
is clear therefore at both common law and equity that the plaintiff had the
right to rescind the contract where time is of the essence in the contract.
At this stage of the proceedings, this court was not asked to determine
whether the rescission would result in the plaintiffs not being able to
receive the liquidated damages but in passing I would say that, as provided
by s 76 of the Contracts Act 1950, a party who rightly rescinds a contract
is entitled to compensation for any damage which he has sustained through
the nonfulfilment of the contract. I had in fact made it clear in my ruling
that the plaintiffs' entitlement to liquidated damages if the developer
failed to complete within 24 months did not in any way take away the rights
of the purchaser to rescind the contract.
There was no evidence as to what stage of building progress the building
was at at the completion date but from the photographs taken in July 1987,
only the plaintiffs' house had been built out of a row of terrace houses and
also no other houses could be seen in the area. Since, from the photographs,
the plaintiffs' house appears to be the only house built in the area, it is
possible that the construction could have even begun after the completion
date. That, however, is of secondary importance.
What is relevant here is that the plaintiffs had entered into a sale and
purchase agreement with the defendants to buy the house and had expected to
move into the house two years later. They certainly would have made the
necessary preparations for this event and any change in plans would have
caused them a great deal of inconvenience and expense. Therefore, if the
house was not completed on the appointed date and in fact had not been
completed even five months thereafter when the notice to terminate was sent
to the defendants and was only completed nine months later and the
certificate of fitness issued 16 months after the appointed date, the court
is of the view that it is within the right of the purchaser plaintiffs to
rescind the contract with the defendants based on legal principles and case
law.
Consequently, on these facts and having considered the pleadings,
affidavits, arguments and authorities, I would answer in the positive as
regards the preliminary issue raised. There will be no order as to costs. On
their application and in view of the legal questions involved, I also gave
leave to the defendants to appeal.
|