LSSC DEVELOPMENT SDN BHD V. THOMAS
IRUTHAYAM & ANOR
COURT OF APPEAL, PUTRAJAYA
[CIVIL APPEAL NO: B-02-407-2005]
GOPAL SRI RAM JCA , ZALEHA ZAHARI JCA , ZAINUN ALI JCA
14 MARCH 2007
JUDGMENT
Gopal Sri Ram JCA:
[1] This appeal raises a short question. It is this. What are the
remedies open to an innocent party where there is a breach of contract? One
would have thought that this rather basic question had been answered by the
courts of England at least by the mid 19th Century through the doctrine of
repudiation. See, Philpot v. Evans [1839] 151 ER 200, 202; Ripley
v. M'Clure [1849] 154 ER 1245, 1251. Where a promisor wrongfully
repudiates a contract in its entirety, the promisee has a choice. He or she
may elect to accept the repudiation, treat the contract as at an end and sue
for damages. The rationale is that the primary obligation to perform the
promise made is substituted with a secondary obligation to compensate the
promisee for the breach. See, Moschi v. Lep Air Services Ltd [1973]
AC 331. Alternatively, he or she may elect to reject the repudiation and
treat the contract as subsisting. Whether the one or the other course was
adopted by the promisee - the innocent party - is a fact that is to be
inferred by the court from the objective facts, including the words and
conduct of the parties. An election once made is irreversible. See,
Sargent v. ASL Developments Ltd [1974] 131 CLR 634, 655. But it is the
essence of the doctrine of repudiation that the breach must go to the root
of the contract. See, Mayson v. Clouet & Anor [1924] AC 980; Bowes
v. Chaleyer [1923] 32 CLR 159; Hongkong Fir Shipping Co Ltd v.
Kawasaki Kisen Kaisha [1962] 2 QB 26.
[2] Now, there is another way of putting across the doctrine of
repudiation. If a promisor does not perform his promise, the promisee may
terminate the contract. This right of termination was referred to by the
common law lawyers of the 19th Century as a right to rescind. Some lawyers
continue to use the word rescind in this sense. Professor G.H Treitel is
one. See, Trietel's "Law of Contract", (11th edn). But this
"rescission" is very different from the specific relief of rescission
invented by the Court of Chancery. The right to terminate puts an end to the
contract only as to the future. All past rights and duties under the
contract remain unaffected. But that is not. So in the case of the equitable
remedy of rescission, which, when exercised, restores the parties to the
same position as though the contract was never made. In other words, there
is restitutio in integrum. Where it is impossible to restore the
staus quo ante, the court may grant equitable compensation. This is what
happened in Longstaff v. Birtles [2001] EWCA (Civ) 1219, a case
involving the breach of fiduciary duty.
[3] But, the common law right to "rescind" and the equitable
remedy of rescission should never be equated. Mark, that one is a right that
may or may not be exercised whist the other is a remedy available in a Court
of Equity, and, in our jurisdiction, given statutory force by sections 34 to
37 of the Specific Relief Act 1950. No doubt, there is a very limited right
of rescission at common law (Lim
Ah Moi v. AMS Periasamy Suppiah Pillay [1997] 3 CLJ 629) which, on
closer examination is actually the quasi-contractual remedy of restitution
in cases where there has been a total failure of consideration. See,
Fibrosa Spolka Akcyjna v. Fairbairn Lawson Combe Barbour Ltd [1943] AC
32. A simple example serves to illustrate the common law right to rescind.
If I pay you to sell me a ton of wheat and you deliver a ton of maize, I am
entitled to return the maize to you and to have the price refunded.
[4] That there must be a total failure of consideration before the
limited common law right to rescind may be exercised is borne out by the
following passage at p. 502, para. 20-007 in "The Law of Restitution"
(6th edn) by Goff & Jones which is the leading text on the subject:
A breach of contract may be so fundamental that it deprives the 'party
who has further undertakings still to perform of substantially the whole
benefit which it was the intention of the parties as expressed in the
contract that he should obtain as the consideration for performing those
undertakings.' (Hong Kong Fir Shipping Co Ltd v. Kawasaki Kaisen Kaisha
Ltd [1962] 2 QB 26]. The innocent party has then an election. He may
affirm the contract or he may bring it to an end. In the latter event, if
he has paid money to the defendant under the contract, he can, as an
alternative to claiming damages, sue for recovery of the money provided
that the consideration for the payment has wholly failed; if the
consideration has partially failed, his only action is for damages.
[5] Despite the existence of this limited right of rescission at
common law, it is best, I think, that the expressions "rescission" and
"rescind" be avoided when dealing with a case of breach of contract as they
may lead to much confusion. In this context I would repeat what was said by
this court in
Abdul
Razak bin Datuk Abu Samah v. Shah Alam Properties Sdn Bhd [1999] 3 CLJ
231:
The right of an innocent party to put an end to future obligations
under a contract is sometimes referred to as 'the right to rescind" and
the act of termination as 'rescission'. This terminology is erroneous and
misleading. True rescission is specific relief. It is available to a
litigant either as self-help upon satisfaction of certain conditions (see
Car & Universal Finance Co Ltd v. Caldwell [1965] 1 QB 525) or as a
judicial remedy obtainable in an action. It was invented by the Court of
Chancery and now finds its place in Chapter IV of our Specific Relief Act
1950. It has the effect of setting at naught the contract ab initio
and not merely as to obligations de futuro. It places the parties on a
footing as though a contract had never been made. The difference between
the so-called 'rescission' which is in truth nothing more than the act of
terminating future obligations under a contract and rescission in its true
sense is brought out in the following passage in the speech of Lord
Wilberforce in Johnson v. Agnew [1980] AC 367 at pp 392, 393:
At this point it is important to dissipate a fertile source of
confusion and to make clear that although the vendor is sometimes
referred to in the above situation as 'rescinding' the contract, this
so-called 'rescission' is quite different from rescission ab initio,
such as may arise for example in cases of mistake, fraud or lack of
consent. In those cases, the contract is treated in law as never having
come into existence. (Cases of a contractual right to rescind may fall
under this principle but are not relevant to the present discussion.) In
the case of an accepted repudiatory breach the contract has come into
existence but has been put an end to or discharged. Whatever contrary
indications may be disinterred from old authorities, it is now quite
clear, under the general law of contract, that acceptance of a
repudiatory breach does not bring about 'rescission ab initio'.
[6] In Photo Production Ltd v. Securicor Transport Ltd
[1980] 1 All ER 556, Lord Wilberforce repeated the caveat he had delivered
in Johnson v. Agnew:
... when in the context of a breach of contract one speaks of
'termination' what is meant is no more than that the innocent party or, in
some cases, both parties are excused from further performance. Damages, in
such cases, are then claimed under the contract, so what reason in
principle can there be for disregarding what the contract itself says
about damages, whether it 'liquidates' them, or limits them, or excludes
them? These difficulties arise in part from uncertain or inconsistent
terminology. A vast number of expressions are used to describe situations
where a breach has been committed by one party of such a character as to
entitle the other party to refuse further performance; discharge,
rescission, termination, the contract is at an end, or dead, or displaced;
clauses cannot survive, or simply go. I have come to think that some of
these difficulties can be avoided; in particular the use of 'rescission',
even if distinguished from rescission ab initio, as an equivalent for
discharge, ... may lead to confusion in others. To plead for complete
uniformity may be to cry for the moon. But what can and ought to be
avoided is to make use of these confusions in order to produce a concealed
and unreasoned legal innovation ...
[7] Lord Diplock also deprecated the use of the expressions
"determination" and "rescission" to the consequences flowing from a breach
going to the root of the contract. He said:
When there has been a fundamental breach or breach of condition, the
coming to an end of the primary obligations of both parties to the
contract at the election of the party not in default is often referred to
as the 'determination' or 'rescission' of the contract or, as in the Sale
of Goods Act 1893, 'treating the contract as repudiated'. The first two of
these expressions, however, are misleading unless it is borne in mind that
for the unperformed primary obligations of the party in default there are
substituted by operation of law what I have called the secondary
obligations.
[8] I have spent some time on the law because what the plaintiffs
in this case have done is to produce - in the words of Lord Wilberforce - an
"unreasoned legal innovation" - through a misinterpretation of the relevant
legal principles that are applicable to the particular facts of this case.
And those facts are as follows.
[9] On 19 June 1996, the defendant (appellant before us) entered
into a sale and purchase agreement with the plaintiffs (respondents before
us) under the terms of which it undertook a number of obligations of which
three are of immediate relevance. First, it promised to sell and transfer a
piece of land together with a 2 1/2 storied bungalow which it promised to
erect. The price was agreed at RM306,000. The plaintiffs paid this in full.
They also paid some other charges as required by the defendant. Second, it
promised that the bungalow would be delivered equipped with water and
electricity together with the certificate of fitness issued by the
appropriate authority within 24 months from the date of the agreement, that
is to say, not later than 18 June 1998. I must add for completeness that
time was expressly made of the essence of the contract by a term of the
agreement. Third, it promised that if it did not deliver the bungalow within
the agreed time, it would pay the plaintiffs liquidated damages calculated
on a daily basis at the rate of 10% per annum of the purchase price which,
in this case, works out to RM83 per day.
[10] The defendant transferred the land to the plaintiff. It did
erect the bungalow. But delivered it beyond the 24 months. And without water
or electricity or the certificate of fitness. By a letter dated 21 July
1998, the plaintiffs terminated the agreement. They then took out an
originating summons in which they claimed the following relief (which I
paraphrase):
(i) a declaration that the defendant had breached the terms of the sale
and purchase agreement and that the plaintiffs had terminated it on 21
July 1998;
(ii) an alternate declaration that the sale and purchase agreement had
terminated due to the breach of contract by the defendant;
(iii) an order that the defendant pay the plaintiffs damages in the
liquidated sum calculated at the rate of 10% per annum over the purchase
price of RM306,000 computed from the date on which vacant possession ought
to have been delivered, that is, from 18 June 1998 until the agreement had
been terminated;
(iv) an order that the defendant refund to the plaintiffs all moneys
paid to it, that is, the purchase price RM306,000 and other charges
amounting to RM2,980.
(v) further or alternatively, damages for breach of contract;
There were also prayers for the usual consequential relief.
[11] After a trial conducted on written evidence, the learned
judge in a reserved judgment found for the plaintiff. In respect of the
relief claimed, he said this:
i. I hereby declare that the defendant had breached the sale and
purchase agreement dated 19 June 1996, and the plaintiffs had rightfully
rescinded the agreement on 21 July 1998 by reason of that breach;
ii. that the defendant refund the plaintiffs all monies paid to them
totalling RM306,000 as the purchase price of the impugned property and
incidental charges of RM2,980;
iii. interest at the rate of 8% per annum on the judgment sum from the
date of the filing of the originating summons to the date of full
settlement;
iv. the plaintiffs be deregistered as the registered owners of the
impugned property on full and final settlement of the adjudged sum; and
(v) costs of this application.
[12] In the course of his argument before us, learned counsel for
the plaintiffs sought to support the orders made by the learned judge. He
says that the learned judge was entitled to set aside the whole transaction.
Because, having found that the agreement had been rightfully rescinded, the
learned judge had to unravel the transaction and restore the parties to
their original position as if the contract had never been made. And this
involved the return of the land and house to the defendant through the
process of de-registration. The basis for this submission is that the
defendant's breach in failing to deliver the house with water, electricity
and the certificate of fitness within the specified time rendered the
contract voidable by reason of s. 56(1) of the Contracts Act 1950 ("the
Act"). The plaintiffs had avoided the contract by their letter of
termination and were entitled to restitutio in integrum. With
respect, I am unable to agree with the plaintiffs' argument. My reasons now
follow.
[13] In the first place, as I have already demonstrated, at common
law the right to "rescind" a contract by way of termination only arises when
there has been a total failure of consideration. In the second place, as
pointed out by Lords Wilberforce and Diplock in Photo Production,
where there is a breach of contract there is no right in an innocent party
to reverse the transaction to status quoante; there is only a right
to recover damages for breach of contract. In the third place, the position
is no different under the Act as I shall now demonstrate by reference to its
relevant provisions.
[14]Section 40 is the first provision. This is what it says:
When a party to a contract has refused to perform, or disabled himself
from performing, his promise in its entirety, the promisee may put an end
to the contract, unless he has signified, by words or conduct, his
acquiescence in its continuance.
[15] Next is s. 56(1) which reads:
When a party to a contract promises to do a certain thing at or before
a specified time, or certain things at or before specified times, and
fails to do any such thing at or before the specified time, the contract,
or so much of it as has not been performed, becomes voidable at the option
of the promisee, if the intention of the parties was that time should be
of the essence of the contract.
[16] Notice that s. 40 uses the phrase "in its entirety" to
describe the extent of the breach. So, the contract breaker must have
"refused to perform ... his promise in its entirety" before "the promisee
may put an end to the contract". This is a reproduction of the common law.
To re-call, at common law:
Where the event resulting from the failure by one party to perform a
primary obligation has the effect of depriving the other party of
substantially the whole benefit which it was the intention of the parties
that he should obtain from the contract, the party not in default may
elect to put an end to all primary obligations of both parties remaining
unperformed. See, Photo Productions, per Lord Diplock.
[17] Now I turn to s. 56(1). It uses the phrase "fails to do any
such thing at or before the specified time" to describe the nature of the
breach which would bring a particular fact pattern within it to make a
contract voidable. The question, then, in each case must be this: Did the
defendant fail to perform every part of his promise? If the answer is "No",
then s. 56(1) has no application. In my judgment, given the facts of the
present instance, ss. 40 and 56(1) should be read together. When that is
done, the question that arises for determination is whether the instant
defendant refused to perform its promise in its entirety by not doing any of
the things it promised to do within the time specified by the contract. On
the facts that question must receive a negative response.
[18] Here, the defendant promised to convey the land and house. It
did that. All that it did not do is to connect the electricity and water and
obtain the certificate of fitness. This did not in my judgment amount to a
failure or refusal to perform the contract in its entirety or a failure to
do any of the things it had promised. It follows that this is not a case
where there was a fundamental breach by the defendant which resulted in the
plaintiffs being deprived of - to borrow the words of Lord Diplock in
Photo Productions - substantially the whole benefit which it was the
intention of the parties that they should obtain from the contract. The
defendant's breach did not go to the root of the contract. The contract was
therefore not "voidable" under s. 56(1). Hence, the plaintiffs were not
entitled to terminate it. Their termination was therefore not lawful.
[19] Of course, the plaintiffs were supplied a defective house out
of time. As for the defects, this is something for which they were entitled
to be compensated. And as for the delay in delivery, the contract itself
contains a clause which provides the formula for the compensation that the
defendant must pay for its lateness. This is the clause to which the
plaintiffs must have recourse as it created a contractual obligation to pay
a single sum by way of liquidated damages for the period during which they
were kept out of the building for which they had already paid, such sum
being calculated upon the basis set out in the agreement. See,
Loh Wai Lian v. SEA Housing Corporation
Sdn Bhd [1987] 1 LNS 37; [1987] 2 MLJ 1.
[20] I now turn to the cases relied on by learned counsel for the
plaintiffs. First, there is
Tan
Yang Loong v. Newacres Sdn Bhd [1992] 1 CLJ 211; [1992] 3 CLJ (Rep) 666.
In that case, the purchasers had entered into an agreement with the
developer under which the latter was to construct and deliver a house with
vacant possession within 36 months from the date of the agreement. The
purchasers had made several payments to the developer. But the developer
never constructed the house. In short, he failed or refused to perform his
promise in its entirety within the time limited by the agreement. In fact
the house had not even been constructed as at the date when the purchasers'
action was tried. Hence, Shankar J had no difficulty in upholding the
purchasers' claim for a declaration that they were no longer bound by the
agreement and ordering a refund of the sums paid by them. That was a case in
which there was a total failure of consideration. Put another way, it was a
case in which the developer did not do any of the things it had promised to
do within the time specified by the contract. The contract was therefore
voidable under s. 56(1). But the facts of Tan Yang Loong are far
removed from the present case. Here there was no refusal to perform the
contract in its entirety. A house was delivered. As such there was no
failure by the defendant to do any of the things it had promised to do
within the time specified by the contract. The breach did not go to the root
of the contract and therefore the contract was not voidable under s. 56(1).
[21] Next, there is
M Concept Sdn Bhd
v. Berjaya Times Square Sdn Bhd [2004] 4 CLJ 852 the facts of which
are, for present purposes, indistinguishable from Tan Yang Loong.
There too, the parcel contracted for had never been delivered. Hence it is
once again readily distinguishable from the present instance because here
there was no breach that went to the root of the contract.
[22] Last, there is
Chye Fook
v. Teh Teng Seng Realty Sdn Bhd [1988] 1 LNS 213; [1989] 1 MLJ 308.
In that case, the purchaser entered into an agreement dated 8 August 1984
with the developer under the terms of which the house was to be completed on
7 August 1986, that is to say, 24 months after the date of the agreement.
Time was of the essence of the contract. Also, there was a clause which said
that "if the vendor fails to deliver vacant possession of the said building
in time the vendor shall pay immediately to the purchaser liquidated damages
to be calculated from day to day at the rate of ten per centum (10%) per
annum of the purchase price". The building was not completed on the agreed
date. The purchaser then wrote to the developer on 19 January 1987
rescinding the agreement because the building had not been delivered within
the agreed 24-month period. But the building was finally completed in May
1987 and the certificate of fitness was issued on 9 December 1987. The
purchaser successfully brought an action for rescission. When giving
judgment, Abdul Malek J (as he then was) referred to Mayson v. Clouet &
Anor where Lord Dunedin said this:
If one party to a contract commits a breach then if that breach is
something that goes to the root of the contract, the other party has his
option. He may still treat the contract as existing and sue for specific
performance; or he may elect to hold the contract as at an end, that is,
no longer binding on him - while retaining the right to sue for damages in
respect of the breach committed.
[23] Having cited other authorities, including Johnson v. Agnew
and Photo Productions, the learned judge said this:
There was no evidence as to what stage of building progress the
building was at the completion date but from the photographs taken in July
1987, only the plaintiffs' house had been built out of a row of terrace
houses and also no other houses could be seen in the area. Since, from the
photographs, the plaintiffs' house appears to be the only house built in
the area, it is possible that the construction could have even begun after
the completion date. That, however, is of secondary importance.
What is relevant here is that the plaintiffs had entered into a sale
and purchase agreement with the defendants to buy the house and had
expected to move into the house two years later. They certainly would have
made the necessary preparations for this event and any change in plans
would have caused them a great deal of inconvenience and expense.
Therefore, if the house was not completed on the appointed date and in
fact had not been completed even five months thereafter when the notice to
terminate was sent to the defendants and was only completed nine months
later and the certificate of fitness issued 16 months after the appointed
date, the court is of the view that it is within the right of the
purchaser plaintiffs to rescind the contract with the defendants based on
legal principles and case law.
[24] In my respectful view the learned judge in that case fell
into error in equating the right to terminate for a fundamental breach of
contract ie, a breach going to the root of the contract on the one hand with
the equitable remedy of rescission on the other. But the decision is
nevertheless correct on its peculiar facts because as may be seen from the
judgment, that was a case in which, at the material time the building had
not even been constructed. So, as at the date on which the purchaser was to
have the house, it had not even been built. Hence that was a case which fell
within s. 56(1) of the Act because at the material time, the developer had
not done any of the things it had promised to do within the time specified
by the contract. But in the case before us the facts are very different.
Here, the land was in fact transferred and registered in the plaintiffs'
name. So there was part performance in that the defendant had done some of
the things it had promised to do. Hence there was no total failure of
consideration and s. 56(1) does not apply here.
[25] There is one other authority which counsel drew to our
attention. It is Buckand v. Farmer [1979] 1 WLR 221. It was decided
after Johnson v. Agnew had been decided by the Court of Appeal but
before the Delphic pronouncements of Lord Wilberforce in the House of Lords
in that case and in Photo Productions had been handed down. From my
reading of that case, there is nothing in the judgment of Buckley LJ that
supports the instant plaintiffs. All that the learned Lord Justice said at
p. 233 of the report was that the court there found it unnecessary to go
into the question whether an innocent party faced with a breach of contract
may rescind the transaction ab initio. That such a thing cannot be
done was most strongly affirmed by the House of Lords in
Johnson v.
Agnew.
[26] For the reasons already given I am unable to agree with the
decision of the High Court. I would therefore allow the appeal. The
declaration and all other orders are set aside. In their place I would enter
judgment for the plaintiffs for damages for late delivery and for breach of
contract. These shall be assessed by the senior assistant registrar of the
High Court to whom this matter is forthwith remitted. In view of the fact
that this is an old case, I would, subject to convenience of counsel, fix a
very early date for the suit to be mentioned before the senior assistant
registrar with a direction to fix an early date for the hearing of the
assessment. The appellant/defendant shall have 2/3 of its costs here and in
the court below. The deposit is to be refunded to it.
[27] My learned sisters Zaleha Zahari and Zainun bt. Ali, JJCA
have seen this judgment in draft and have expressed their agreement with it. |