M-CONCEPT SDN BHD V. BERJAYA TIMES
SQUARE SDN BHD
HIGH COURT MALAYA, KUALA LUMPUR
[ORIGINATING SUMMONS NO: S3-24-473-2003]
HISHAMUDIN YUNUS , J
6 MAY 2004
JUDGMENT
Hishamudin Yunus J:
This originating summons
is essentially the plaintiff's application for a declaration that the
plaintiff be entitled to rescind a sale and purchase agreement dated 24
August 1995 (hereinafter referred to as the 'agreement') entered into
between the plaintiff as purchaser and the defendant as seller in respect of
a property known as parcel No. 07-63, Commercial Shop Lot, Berjaya Star City
(now known as Berjaya Times Square) held under Grant No. 7866, Lot No. 339,
and Grant No. 10798, Lot No. 145, both of which located in Section 52 of
Kuala Lumpur (hereinafter referred to as 'the property').
I shall begin with a
summary of the facts relevant to this action. The plaintiff and the
defendant entered into the agreement on 24 August 1995. Pursuant to cl.
22(1) of the agreement, the defendant was required to deliver vacant
possession of the property to the plaintiff on or before 23 November 1998
(hereinafter referred to as 'the stipulated date'). Clause 32 of the
agreement provides that time shall be of the essence in relation to all
provisions.
In fulfillment of its
obligations under cl. 3(1) of the agreement, the plaintiff has paid
RM1,034,793.90, being 90% of the total purchase price to the defendant, part
of which was financed by a loan from AmBank Berhad.
Although the plaintiff has
fulfilled its obligations in respect of the payment, the defendant has
failed to deliver vacant possession of the property to the plaintiff on or
before the stipulated date.
Even on 20 March 2003,
that is the date when the plaintiff filed this originating summons, the
defendant had still failed to deliver vacant possession of the property.
After the stipulated date,
the plaintiff's director, Lee Teen Nguan, had met with the sale and
marketing officers of the defendant and despite several assurances given by,
among others, Ms Esther/Ms Pey Yee, who promised that the property would be
completed by the end of 2001, the defendant still failed to deliver vacant
possession of the property to the plaintiff as promised.
Upon the defendant's
failure to fulfil its obligations under the agreement, the plaintiff's
former solicitors, Messrs Gan & Low, issued a letter dated 27 December 2001
to inform the defendant that the plaintiff had decided to rescind the
agreement on the ground that the defendant had committed a fundamental
breach of its contractual obligation to deliver vacant possession of the
property to the plaintiff by the stipulated date pursuant to cl. 22(1) of
the agreement.
However, the defendant
refused to accept the rescission of the agreement by the plaintiff. By a
letter dated 3 January 2002, the defendant claimed that as the plaintiff
would be entitled to claim for liquidated damages in the event of late
delivery of the property, the plaintiff was not entitled to rescind.
Subsequently, the
plaintiff sought consent and obtained reassignment of all rights, title and
interests from AmBank Berhad to institute legal proceedings against the
defendant.
On 1 October 2002, the
plaintiff's director, Lee Teen Nguan, met with the defendant's sale and
marketing officer, Ms Dianne Chan, and the latter gave her assurance that
vacant possession of the property would be delivered by the end of 2002.
Despite this assurance, the defendant again failed to deliver vacant
possession of the property.
Accordingly, on 5 March
2003 the plaintiff's solicitors sent a letter to demand that the defendant
accept the rescission, to refund the monies paid, and to pay all damages
suffered by the plaintiff within 14 days. However, the defendant again
refused to accept the rescission and to refund the monies paid and to pay
all damages suffered by the plaintiff.
The defendant instead sent
a letter dated 10 March 2003 to the plaintiff's solicitors to inform that
the defendant was not agreeable to the rescission by the plaintiff.
Hence the plaintiff filed
the present originating summons to seek a declaration that it is entitled to
rescind/terminate the agreement; to seek a refund of the monies paid; and to
recover all damages suffered as a result of the defendant's breach of the
agreement.
The essential issue which
needs to be determined by this court is whether the failure by the defendant
to deliver vacant possession of the property on or before the stipulated
date, as provided under cl. 22(1) of the agreement, or on or before any
other date as promised by the defendant, constitutes a fundamental breach of
the contract which entitles the plaintiff to rescind the agreement. In my
judgment, considering the unreasonably long delay to deliver vacant
possession, the answer to this question must be in the affirmative. The
failure of the defendant to deliver vacant possession of the property after
23 November 1998, as agreed under cl. 22(1) of the agreement, for nearly
four years and four months until the present originating summons was filed,
amounts to a fundamental breach of the agreement by the defendant. The delay
on the part of the defendant is excessive and unreasonable given the fact
that the defendant was required to deliver vacant possession of the property
to the plaintiff within 36 months from the date of signing of the agreement.
As under the agreement time is essential, the failure on the part of the
defendant to deliver vacant possession at the stipulated time renders the
agreement voidable at the option of the plaintiff (see s. 56(1) of the
Contracts Act 1950).
The defendant contends
that the plaintiff is not entitled to rescind the agreement since there is
no provision in the agreement giving the plaintiff the right to terminate
the agreement. In the light of s. 56(1) of the Contracts Act, there is
clearly no merit in this argument.
The defendant next
contends that the plaintiff is not entitled to rescind the agreement since
the plaintiff is, in any event, entitled to claim liquidated damages. Again,
based on s. 56(1) there is no merit in this argument.
It is further argued by
the defendant that the plaintiff is estopped from rescinding the agreement
(or had waived its right to do so) because the plaintiff has paid its
installments due under the agreement without protest. This argument too must
be rejected. On the facts, it is unjust to estop the plaintiff from
rescinding the agreement; the plaintiff is the innocent party and all that
it did in making the payments was to honour its obligations under the
agreement. And on the facts it cannot be said that there was no protest from
the plaintiff over the long delay. It must also be pointed out that the
plaintiff was not happy in continuing making the payments but it had been
induced into doing so by the defendant's officers through the latter's
assurances on the completion date that eventually turned out to be nothing
but empty promises as the property was never completed by either the end of
2001 or the end of 2002. Moreover, the defendant by breaching the agreement
has not come to court with clean hands; and a party who has not come to
court with clean hands cannot pray in aid principles of equity such as the
doctrine of estoppel.
Accordingly, the court
granted the declaration prayed for under the originating summons together
with the various ancillary reliefs. That is to say, the court granted the
following prayers:
(1) prayer 1
(declaration on plaintiff's right to rescind);
(2) prayer 2(a) - but
the amount was varied to RM1,149,771 as the plaintiff has fully settled
the purchase price;
(3) prayer 2(b)
(financing costs, legal costs and miscellaneous costs);
(4) prayer 2(c) and (d)
- subject to assessment by the senior assistant registrar;
(5) prayers 3 (usual 8%
interest under the Rules of the High Court;
(6) prayer 4 (costs of
this action).
[Order in terms]
[Oral application for stay
of execution was dismissed on the grounds that the Court was not satisfied
that there are special circumstances.] |