| THOMAS IRUTHAYAM & ANOR V. LSSC 
    DEVELOPMENT SDN BHD   HIGH COURT MALAYA, SHAH ALAM [ORIGINATING SUMMONS NO: MT(2) 1-24-942-1998] SURIYADI HALIM OMAR J 10 MARCH 2005 Reported by Suresh Nathan JUDGMENT   Suriyadi Halim Omar J: The plaintiffs were purchasers (interchangeably referred to as plaintiffs 
    or purchasers) of a house known as Lot RS 106 Phase 1A, at Bandar Country 
    Homes, Rawang for RM306,000 from the defendant, who were the developers of 
    the relevant housing project. A sale and purchase agreement was executed 
    between them on 19 June 1996. It was one of the conditions of that S&P that 
    handing over of the house was to occur on 18 June 1998 ie, within 24 months 
    from the date of the agreement. The relevant clause ie, cl. 7 and their 
    sub-clauses, which cover the issue of delivery of vacant possession, read as 
    follows:   7.1 Vacant possession of the said building together with the certificate 
    of fitness for occupation issued by the appropriate authority and with water 
    and electricity supply connected thereto shall be handed over to the 
    purchaser (s) within twenty four (24) months from the date of this 
    agreement; and   7.2 Upon expiry of fourteen (14) days from the date of a notice from the 
    vendor (s) requesting the purchaser (s) to take possession of the said 
    property, whether or not the purchaser (s) has actually entered into 
    possession or occupation of the said property, the purchaser (s) shall be 
    deemed to have taken delivery of vacant possession. 7.3 If the vendor (s) fails to hand over vacant possession of the said 
    building in the manner aforesaid, the vendor (s) shall immediately pay to 
    the purchaser (s) liquidated damages to be calculated from day to day at the 
    rate of ten per centum (10%) per annum of the purchase price. The other relevant provisions are cls. 12 (b) and 18 (h). They 
    respectively read: 12(b) In the event of a failure and/or default by the vendor (s) to 
    complete the sale of the said property and to deliver vacant possession of 
    the same to the purchaser (s) in accordance with the terms herein, the 
    purchaser (s) shall, without prejudice to the other provisions of this 
    agreement or any other rights and remedies as may be available to the 
    purchaser (s) at law or in equity, be entitled to take such action as may be 
    available to the purchaser (s) at law for specific performance of the terms 
    and conditions herein and the vendor (s) shall reimburse all cost and 
    expenses incurred by the purchaser (s) (including but without limitation the 
    purchaser (s) solicitors' cost on a solicitor-client basis) ... 18(h) Time whenever mentioned shall be of the essence of this agreement. On 27 May 1998 the plaintiffs had received a notice as regards the 
    forwarding of the keys for the said property, and of which were accepted by 
    them (TI5). By 30 May 1998 the plaintiffs had supplied the list of 
    complaints or defects to the defendant in a pre-prepared form (TI5). 
    Sometime on 21 July 1998 the plaintiff purchasers, through their solicitor 
    Messrs. Joseph Iruthayam & Co had sent a letter of rescission of the S&P 
    contract to the defendant, by invoking cl. 12 (b) of the agreement (supplied 
    above), on the basis of the infringement of the above cl. 7 by the 
    defendant. In a gist the plaintiffs had stated that the defendant had failed to 
    deliver vacant possession of the property, due to its failure to connect the 
    water and the electricity and the delivery of the certificate of fitness for 
    occupation, by 18 June 1998. In no uncertain terms the plaintiffs had 
    insisted that even until today the defendant had yet to deliver that 
    certificate of fitness. That fact of non-delivery was further confirmed when 
    counsel for the defendant had admitted that the certificate of fitness had 
    been handed over, but unfortunately to the solicitors of the plaintiff's 
    lending bank. That bank, let alone its solicitors certainly have no nexus or 
    privity of contract with the defendant. To make matters worse this 
    irrelevant admission was also made from the bar table. On that premise I 
    thus must accept the assertion of the plaintiffs as an established fact that 
    up to-date they have yet to receive that certificate. On 29 August 1998, the plaintiffs had filed an originating summons, 
    praying amongst others, a declaration that the defendant had breached the 
    impugned S&P and that the plaintiffs had rightfully rescinded that agreement 
    on 21 July 1998, or in the alternative praying for a declaration that the 
    said agreement was rescinded by reason of breach of the contract by the 
    defendant. Further the plaintiffs had sought liquidated damages, a refund of 
    the consideration sum of RM306,000, incidental charges of RM2,980 and other 
    damages. Having perused the evidence, with particular reference to cl. 7(2) of the 
    S&P, I was satisfied that with fourteen (14) days having expired from the 
    date of the notice sent by the defendant requesting the purchasers to take 
    possession of the said property, whereupon the keys were handed to them, 
    they were deemed to have taken delivery of vacant possession of that 
    property. Despite that stance it is trite that a deeming provision, of which 
    cl. 7.2 is the playing field, may be rebutted by an aggrieved party. For 
    purposes of clarification and analogy, in Fisher v. Winch [1939] 1 KB 
    666 Goddard LJ at 674 had occasion to remark:   ... is very often decisive where there is no evidence at all as to what 
    the boundaries are, but like any other presumption it is rebuttable, 
    and very often it can be easily rebutted by the production of title deeds 
    (emphasis added). As opposed to that provision, cl. 7.1 deals with a factual situation 
    whereat vacant possession shall have been delivered, if all the 
    preconditions have been complied with. As the water and electricity supply 
    were yet to be connected, let alone a certificate of fitness delivered, the 
    deemed delivery of vacant possession had certainly been rebutted. Without 
    that conditional vacant possession being satisfied by the defendant within 
    24 months from the date of execution of the S&P, particularly as time was of 
    the essence of the agreement, the defendant was certainly in for a rough 
    time in court. Although the ascertainment of the meaning of a written contract, in this 
    case the current S&P, is a question of law, the many steps in the process of 
    ascertaining that meaning are question of facts. The meaning of an ordinary 
    word of the English language is not a question of law as compared to the 
    proper construction of a statute being a question of law (Brutus v. Cozen 
    [1973] AC 854; Commonwealth Smelting Ltd v. Guardian Royal Exchange 
    Assurance Ltd [1986] 1 Lloyd's Rep. 121). InHill v. Evans [1862] 
    4 De G.F & J 288, the approach of deciphering an ordinary word to be a 
    question of fact, even extended to technical terms. That being so the 
    ascertainment of the meaning of the term " time " here falls squarely within 
    the purview of 'question of fact'. This issue of construction will be pieced 
    together with the issues in the following paragraphs. It is well established that where a conditional contract fixes a date, by 
    which date the condition must be fulfilled, that date so fixed must be 
    strictly adhered to. Despite that statement, I am not unmindful of the 
    prevalence of cases which establish that time is not of the essence in a 
    contract of sale and purchase of real estate, unlike contracts for the sale 
    of shares (Hare v. Nicoll [1966] 2 QB 130). In Re Schwabacher 
    [1908] 98 LT 127 Parker J aptly had opined: With regard to contracts for the sale of shares, I think that time is of 
    the essence both at law and in equity. Shares continually vary in price from 
    day to day, and that is precisely why courts of equity have considered such 
    a contract to be one in which time is of the essence of the contract, and 
    not like a contract for the sale and purchase of real estate, in which 
    time is not of the essence of the contract (emphasis added). Contrary to that view, there are also precedents in the like of Cowles 
    v. Gate [1871] LR 7 Ch App 12, which had dealt with the sale of a public 
    house as a going concern, and had held a different view. Generally time was 
    held to be the essence of the relevant contract if provided for there (see 
    also Lock v. Bell [1930] Ch 35). Lord Jenkins later in Aberfoyle 
    Plantations v. Cheng [1960] AC 115 had summarised the law in this 
    manner:   ... their Lordships would adopt, as warranted by authority and manifestly 
    reasonable in themselves, the following principles: (i) where a conditional 
    contract of sale fixes a date for the completion of the sale, then the 
    condition must be fulfilled by that date; (ii) ... (iii) where a conditional 
    contract of sale fixes (whether specifically or by reference to the date 
    fixed for completion) the date by which the condition is to be fulfilled, 
    then the date so fixed must be strictly adhered to, and the time allowed is 
    not to be extended by reference to equitable principles. Salleh Abas FJ in
    Sim Chio Huat v. Wong Ted Fui [1983] 1 CLJ 178; [1983] CLJ (Rep) 363
    (refd), in clear terms had also stated that in modern law of 
    contract, time was not of the essence of a contract, unless parties had 
    agreed that it be so. For purposes of this case, cl. 18(h) here in all its 
    simplicity had recorded without any reservation that time whenever 
    mentioned, shall be the essence of the agreement. Read together with all the 
    above cases, it is safe to conclude that if an agreement states that where a 
    conditional contract of sale has fixed the date by which the condition is to 
    be fulfilled, then the date so fixed must be strictly adhered to. It is also 
    quite safe to add that, in certain situations even if the time factor were 
    not sufficiently clarified, it might be quite reasonable to conclude that 
    where the subject matter of the contract is liable to fluctuate in value, in 
    the like of selling of shares and scripts, time would be regarded as being 
    of the essence of the contract (The Interpretation of Contracts by 
    Kim Lewison, Barrister). As regards the facts of this case, it must be understood that way back in 
    1996, when the value of houses would spiral upwards wildly, until the world 
    saw a swing to uncertainty and recession from 1997 onwards, the intention of 
    parties when executing the S&P must be taken into consideration. At that 
    time too when times were good, aside from genuine purchasers who had wanted 
    to buy matrimonial homes at reasonable prices, there were also enterprising 
    entrepreneurs who had bought and sold houses as if they were transacting 
    shares in the stock exchange. In other words time was very important for 
    those types of speedy transactions. Returning to current times, it was vehemently asserted by the plaintiffs 
    that even until now vacant possession had yet to be delivered to the 
    plaintiffs by the defendants. Surely there was something terribly wrong if 
    the claim of the plaintiffs could be defeated, despite the long wait, merely 
    because the contracted matter was a real estate?   The defendant had attempted to convince me that as the deposits for the 
    water and electricity supply had been late in coming, and if time had been 
    of the essence of the agreement, it thus had been waived. This was 
    nit-picking and a measure of the defendant's desperation to extricate itself 
    from the contract, as the deposits had been paid more than a month earlier 
    ie, before the delivery date. It must also be understood that the supply of 
    amenities viz. the flow of water and electricity was not the 
    responsibility of the defendant, but the connection of the water and 
    electricity mains were (Salmah 
    Sulaiman & Anor v. Metroplex Development Sdn Bhd [1997] 2 CLJ 148 CA 
    (refd);
    Syarikat Lean Hup (Liew Bros) Sdn Bhd v. Cheow Choong Thai [1988] 1 
    LNS 74 [1988] 3 MLJ 221) 1 AMR 592). Here the plaintiffs had managed to 
    successfully convince me that, come the delivery date the defendant had 
    failed to deliver vacant possession as the water and electricity mains had 
    yet to be connected and the certificate of fitness never handed over to 
    them. In fact the defendant even had failed to establish that they had 
    submitted an application for that certificate  (Syarikat Lean Hup (Liew 
    Bros) Sdn Bhd v. Cheow Choong Thai (supra)). On the totality of the evidence, I was satisfied that in 1996 when the 
    S&P was executed by the plaintiffs and the defendant, time was indeed 
    intended to be of the essence of the agreement. With the defendant having breached the contract here, the plaintiffs were 
    automatically accorded the rights to still enforce the agreement by 
    demanding specific performance of it pursuant to cl. 12(b), and demand 
    damages in the process as agreed upon. Regretfully the plaintiffs had taken 
    the extreme course of action of rescinding the agreement. The pertinent 
    questions that invariably follow, which had to be resolved emanating from 
    that scenario could be formulated in the following forms:   1. did the S&P, in particular cl. 12(b) provide for the right of 
    rescission of the contract by the plaintiffs in the event of a failure 
    and/or default by the vendor defendant to complete the sale of the said 
    property and deliver vacant possession of the same to them;   2. even if the agreement did not provide for rescission could the 
    plaintiffs have invoked any written law or equity to rescind that contract 
    in the event of a voidable contract or a fundamental breach having been 
    committed by the defendant; and   3. in the circumstances of the case could the plaintiffs rescind the 
    contract and demand the return of the RM306,000 together with damages (cl. 
    7.3)?   The defendant, in no uncertain terms had canvassed that the agreement did 
    not provide for rescission by the plaintiffs in the event of a breach of the 
    contract by the defendant, though did concede in the affirmative to the 
    second question. At a very late stage of the hearing, the defendant modified 
    its stance and advanced the argument that as the intitulment of the action 
    did not mention s. 56 of the Contract Act, the plaintiffs thus could not 
    submit on the importation of law for purposes of rescission. Having scrutinized cl. 12(b), I found the defendant's stance rather 
    strange and contradictory, due to the relevant words in cl. 12(b), which 
    read " ... without prejudice to the other provisions of this agreement or 
    any other rights and remedies as may be available to the purchaser (s) at 
    law or in equity ... " . On proper construction of this clause, it clearly 
    meant that the plaintiffs had the additional right to resort to any law or 
    right in equity, though outside the provisions of the agreement, for 
    remedies. As nothing had been inserted in that clause or anywhere in the 
    agreement that limited the scope of the remedies, by necessity the latter 
    must include rescission. As those words of cl. 12(b) were provided for in 
    the agreement, and the intitulment did make mention of that controversial 
    agreement, though not specifically s. 56 of the Contract Act, the modified 
    stance of the defendant still did not help its case. On those grounds I was 
    more than satisfied that cl. 12(b) of the S&P did allow the plaintiffs the 
    right of rescission, if they so wished, in the event of any failure by the 
    defendant to deliver vacant possession. If I might venture a step further, there was also no inhibiting 
    provisions anywhere in the agreement that prevented the plaintiffs from 
    adverting to any relevant law, common law, equity, written or otherwise for 
    a right to rescind the contract in the event of any breaches as provided for 
    under cl. 12(b). On the other hand, such inclusion of provisions to remove 
    the effect and oust the protection of relevant laws may run foul of certain 
    public policy, and in violation of the very purpose of such laws. If the 
    defendant is permitted to do that, then any S&P may attempt to contract 
    outside the relevant legislations governing housing developments eg, Housing 
    Development (Control and Licensing) Act 1966 (Act 118), Housing Developers 
    (Control & Licensing) Regulations 1989 (effective 1 April 1989) and the 
    like, legislations meant to protect purchasers (City 
    Investment Sdn Bhd v. Koperasi Serbaguna Cuepecs Tanggungan Bhd 1985 CLJ 
    77 [1988] 1 MLJ 69). Even if I were to err in my findings that the agreement did provide for 
    rescission, but with the defendant's admission that such rescission was 
    permissible if any contractual laws were contravened, and as I have 
    neutralised the late modified view of the defendant, the next step to be 
    undertaken was the identification of that contravened contractual law. Since 
    time was provided for to be of the essence in the agreement,
    Contracts Act 1950, ss. 56 therefore must take prominence in the current 
    discussion. This provision in crystalline terms states that when a party to 
    a contract promises to do a certain thing at or before a specified time, or 
    certain things at or before specified times, and fails to do any such thing 
    at or before the specified time, the contract, or so much of it as has not 
    been performed, becomes voidable at the option of the promise, if the 
    intention of the parties was at that time should be of the essence of the 
    contract. As the defendant had failed to deliver vacant possession by 18 
    June 1998 (within 24 months from date of execution of the contract), bearing 
    in mind that time was of the essence in the contract, the contract thus 
    became voidable at the option of the plaintiffs. Voidable contract means an agreement that is valid and enforceable by law 
    at the option of one or more of the parties thereto, and in this case the 
    plaintiffs, but not at the option of the other or others (s. 2(i)). This 
    option of carrying on or invalidating the agreement by the innocent party, 
    needless to say arises as a result of the failure of the one without that 
    option, in this case the defendant, to perform the terms of the provisions 
    of the agreement (The Commercial Law of Malaysia, Wu Min Aun and 
    Beatrix Vohrah pp. 30 and 90). Whether it was sheer defiance or enshrouded by some ulterior motive, even 
    to-date the defendant have not made any attempts to physically deliver that 
    certificate of fitness to the plaintiffs, so as to rectify the delay in its 
    completion of the contract. With that attitude prevailing, and the written 
    contract rendered voidable, the plaintiffs thus were statutorily entitled to 
    rescind the contract, as additionally provided for by
    Specific Relief Act 1950, s. 34. The fact that the rescission was not 
    made forthwith on the very day of 18 June 1998 must not be taken against the 
    plaintiffs. It must be borne in mind that even the agreed defect liability 
    period was to be 12 months, to begin after the expiry of 14 days from the 
    date of the letter of delivery of vacant possession. During that lengthy 
    defect liability period, if a fundamental breach were to be detected, the 
    plaintiff might even have recourse to the remedy of rescission of the 
    contract. That being so, by analogy a waiting period of 33 days, before the 
    letter of rescission was sent was neither unreasonable nor may qualify as 
    undue delay, construable as a waiving of the plaintiffs'rights to rescind. 
    It must be understood that the cause of action ie, the day the contractual 
    duty was broken by the defendant commenced on 18 June 1998, and once the 
    plaintiffs had handed the letter of rescission, the contract thus had become 
    void (Insun 
    Development Sdn Bhd v. Azali Bakar [1996] 2 CLJ 753 FC (refd);
    Tan Yang Long & Anor v. Newacres Sdn Bhd [1992] 1 CLJ 211; [1992] 3 
    CLJ 666 HC (refd),
    Loh Wai Lian v. SEA Housing Corp Sdn Bhd [1987] 1 LNS 37 [1987] 2 
    MLJ 1). Once it was void it had ceased to be enforceable. Even if the 
    defendant were to succeed in obtaining the certificate of fitness within a 
    reasonable period after that relevant date, it would already have been too 
    late in the day. Factually I had found that by the time vacant possession was due, the 
    plaintiffs had already paid up everything that was required to be paid, in 
    accordance with the S&P. This factor was denied by the defendant and had 
    attempted to make much of a balance sum of money amounting to RM15,300, 
    supposedly kept by the plaintiffs solicitor's firm as stakeholders of that 
    money (and the last balance), I was unable to accept that argument as that 
    firm was the common solicitor of the contending parties!   In the event the court were to declare that the defendant had breached 
    the agreement, and the plaintiffs had rightfully rescinded the agreement, 
    there was no difficulty faced by the court in identifying the sums of money 
    to be returned, as they were easily identifiable. What the defendant would 
    have to do was to return the sum of RM306,000, together with the interest, 
    beginning from the date of the filing of the originating summons. Both 
    parties thus would be returned to their respective pre-agreement position as 
    none would be permitted to profit from any unconscionable enrichment. With 
    the contending parties back to square one, the plaintiffs too would be 
    deregistered as the registered owners of the impugned property in the event 
    they had been hurriedly so registered earlier. With the contract now 
    avoided, and as there was nothing in law or any business practice that 
    prevented the defendant from reselling the impugned property at the current 
    market price to recoup any losses if any, it thus could do that. As a rider, 
    in the event the defendant was to incur any loss that was regretful, as it 
    was the very cause of this long and painful affair. After having perused the facts and law my orders were as follows:
      i. I hereby declare that the defendant had breached the sale and purchase 
    agreement dated 19 June 1996, and the plaintiffs had rightfully rescinded 
    the agreement on 21 July 1998 by reason of that breach;   ii. that the defendant refund the plaintiffs all monies paid to them 
    totalling RM306,000 as the purchase price of the impugned property and 
    incidental charges of RM2,980;   iii. interest at the rate of 8% per annum on the judgment sum from the 
    date of the filing of the originating summons to the date of full 
    settlement;   iv. the plaintiffs be deregistered as the registered owners of the 
    impugned property on full and final settlement of the adjudged sum; and
      v. costs of this application. 
  (see also- LSSC 
  DEVELOPMENT SDN BHD V. THOMAS IRUTHAYAM & ANOR (14 MARCH 2007) COURT OF APPEAL, PUTRAJAYA[CIVIL APPEAL NO: 
  B-02-407-2005] )
 
 |