THOMAS IRUTHAYAM & ANOR V. LSSC
DEVELOPMENT SDN BHD
HIGH COURT MALAYA, SHAH ALAM
[ORIGINATING SUMMONS NO: MT(2) 1-24-942-1998]
SURIYADI HALIM OMAR J
10 MARCH 2005
Reported by Suresh Nathan
JUDGMENT
Suriyadi Halim Omar J:
The plaintiffs were purchasers (interchangeably referred to as plaintiffs
or purchasers) of a house known as Lot RS 106 Phase 1A, at Bandar Country
Homes, Rawang for RM306,000 from the defendant, who were the developers of
the relevant housing project. A sale and purchase agreement was executed
between them on 19 June 1996. It was one of the conditions of that S&P that
handing over of the house was to occur on 18 June 1998 ie, within 24 months
from the date of the agreement. The relevant clause ie, cl. 7 and their
sub-clauses, which cover the issue of delivery of vacant possession, read as
follows:
7.1 Vacant possession of the said building together with the certificate
of fitness for occupation issued by the appropriate authority and with water
and electricity supply connected thereto shall be handed over to the
purchaser (s) within twenty four (24) months from the date of this
agreement; and
7.2 Upon expiry of fourteen (14) days from the date of a notice from the
vendor (s) requesting the purchaser (s) to take possession of the said
property, whether or not the purchaser (s) has actually entered into
possession or occupation of the said property, the purchaser (s) shall be
deemed to have taken delivery of vacant possession.
7.3 If the vendor (s) fails to hand over vacant possession of the said
building in the manner aforesaid, the vendor (s) shall immediately pay to
the purchaser (s) liquidated damages to be calculated from day to day at the
rate of ten per centum (10%) per annum of the purchase price.
The other relevant provisions are cls. 12 (b) and 18 (h). They
respectively read:
12(b) In the event of a failure and/or default by the vendor (s) to
complete the sale of the said property and to deliver vacant possession of
the same to the purchaser (s) in accordance with the terms herein, the
purchaser (s) shall, without prejudice to the other provisions of this
agreement or any other rights and remedies as may be available to the
purchaser (s) at law or in equity, be entitled to take such action as may be
available to the purchaser (s) at law for specific performance of the terms
and conditions herein and the vendor (s) shall reimburse all cost and
expenses incurred by the purchaser (s) (including but without limitation the
purchaser (s) solicitors' cost on a solicitor-client basis) ...
18(h) Time whenever mentioned shall be of the essence of this agreement.
On 27 May 1998 the plaintiffs had received a notice as regards the
forwarding of the keys for the said property, and of which were accepted by
them (TI5). By 30 May 1998 the plaintiffs had supplied the list of
complaints or defects to the defendant in a pre-prepared form (TI5).
Sometime on 21 July 1998 the plaintiff purchasers, through their solicitor
Messrs. Joseph Iruthayam & Co had sent a letter of rescission of the S&P
contract to the defendant, by invoking cl. 12 (b) of the agreement (supplied
above), on the basis of the infringement of the above cl. 7 by the
defendant.
In a gist the plaintiffs had stated that the defendant had failed to
deliver vacant possession of the property, due to its failure to connect the
water and the electricity and the delivery of the certificate of fitness for
occupation, by 18 June 1998. In no uncertain terms the plaintiffs had
insisted that even until today the defendant had yet to deliver that
certificate of fitness. That fact of non-delivery was further confirmed when
counsel for the defendant had admitted that the certificate of fitness had
been handed over, but unfortunately to the solicitors of the plaintiff's
lending bank. That bank, let alone its solicitors certainly have no nexus or
privity of contract with the defendant. To make matters worse this
irrelevant admission was also made from the bar table. On that premise I
thus must accept the assertion of the plaintiffs as an established fact that
up to-date they have yet to receive that certificate.
On 29 August 1998, the plaintiffs had filed an originating summons,
praying amongst others, a declaration that the defendant had breached the
impugned S&P and that the plaintiffs had rightfully rescinded that agreement
on 21 July 1998, or in the alternative praying for a declaration that the
said agreement was rescinded by reason of breach of the contract by the
defendant. Further the plaintiffs had sought liquidated damages, a refund of
the consideration sum of RM306,000, incidental charges of RM2,980 and other
damages.
Having perused the evidence, with particular reference to cl. 7(2) of the
S&P, I was satisfied that with fourteen (14) days having expired from the
date of the notice sent by the defendant requesting the purchasers to take
possession of the said property, whereupon the keys were handed to them,
they were deemed to have taken delivery of vacant possession of that
property. Despite that stance it is trite that a deeming provision, of which
cl. 7.2 is the playing field, may be rebutted by an aggrieved party. For
purposes of clarification and analogy, in Fisher v. Winch [1939] 1 KB
666 Goddard LJ at 674 had occasion to remark:
... is very often decisive where there is no evidence at all as to what
the boundaries are, but like any other presumption it is rebuttable,
and very often it can be easily rebutted by the production of title deeds
(emphasis added).
As opposed to that provision, cl. 7.1 deals with a factual situation
whereat vacant possession shall have been delivered, if all the
preconditions have been complied with. As the water and electricity supply
were yet to be connected, let alone a certificate of fitness delivered, the
deemed delivery of vacant possession had certainly been rebutted. Without
that conditional vacant possession being satisfied by the defendant within
24 months from the date of execution of the S&P, particularly as time was of
the essence of the agreement, the defendant was certainly in for a rough
time in court.
Although the ascertainment of the meaning of a written contract, in this
case the current S&P, is a question of law, the many steps in the process of
ascertaining that meaning are question of facts. The meaning of an ordinary
word of the English language is not a question of law as compared to the
proper construction of a statute being a question of law (Brutus v. Cozen
[1973] AC 854; Commonwealth Smelting Ltd v. Guardian Royal Exchange
Assurance Ltd [1986] 1 Lloyd's Rep. 121). InHill v. Evans [1862]
4 De G.F & J 288, the approach of deciphering an ordinary word to be a
question of fact, even extended to technical terms. That being so the
ascertainment of the meaning of the term " time " here falls squarely within
the purview of 'question of fact'. This issue of construction will be pieced
together with the issues in the following paragraphs.
It is well established that where a conditional contract fixes a date, by
which date the condition must be fulfilled, that date so fixed must be
strictly adhered to. Despite that statement, I am not unmindful of the
prevalence of cases which establish that time is not of the essence in a
contract of sale and purchase of real estate, unlike contracts for the sale
of shares (Hare v. Nicoll [1966] 2 QB 130). In Re Schwabacher
[1908] 98 LT 127 Parker J aptly had opined:
With regard to contracts for the sale of shares, I think that time is of
the essence both at law and in equity. Shares continually vary in price from
day to day, and that is precisely why courts of equity have considered such
a contract to be one in which time is of the essence of the contract, and
not like a contract for the sale and purchase of real estate, in which
time is not of the essence of the contract (emphasis added).
Contrary to that view, there are also precedents in the like of Cowles
v. Gate [1871] LR 7 Ch App 12, which had dealt with the sale of a public
house as a going concern, and had held a different view. Generally time was
held to be the essence of the relevant contract if provided for there (see
also Lock v. Bell [1930] Ch 35). Lord Jenkins later in Aberfoyle
Plantations v. Cheng [1960] AC 115 had summarised the law in this
manner:
... their Lordships would adopt, as warranted by authority and manifestly
reasonable in themselves, the following principles: (i) where a conditional
contract of sale fixes a date for the completion of the sale, then the
condition must be fulfilled by that date; (ii) ... (iii) where a conditional
contract of sale fixes (whether specifically or by reference to the date
fixed for completion) the date by which the condition is to be fulfilled,
then the date so fixed must be strictly adhered to, and the time allowed is
not to be extended by reference to equitable principles.
Salleh Abas FJ in
Sim Chio Huat v. Wong Ted Fui [1983] 1 CLJ 178; [1983] CLJ (Rep) 363
(refd), in clear terms had also stated that in modern law of
contract, time was not of the essence of a contract, unless parties had
agreed that it be so. For purposes of this case, cl. 18(h) here in all its
simplicity had recorded without any reservation that time whenever
mentioned, shall be the essence of the agreement. Read together with all the
above cases, it is safe to conclude that if an agreement states that where a
conditional contract of sale has fixed the date by which the condition is to
be fulfilled, then the date so fixed must be strictly adhered to. It is also
quite safe to add that, in certain situations even if the time factor were
not sufficiently clarified, it might be quite reasonable to conclude that
where the subject matter of the contract is liable to fluctuate in value, in
the like of selling of shares and scripts, time would be regarded as being
of the essence of the contract (The Interpretation of Contracts by
Kim Lewison, Barrister).
As regards the facts of this case, it must be understood that way back in
1996, when the value of houses would spiral upwards wildly, until the world
saw a swing to uncertainty and recession from 1997 onwards, the intention of
parties when executing the S&P must be taken into consideration. At that
time too when times were good, aside from genuine purchasers who had wanted
to buy matrimonial homes at reasonable prices, there were also enterprising
entrepreneurs who had bought and sold houses as if they were transacting
shares in the stock exchange. In other words time was very important for
those types of speedy transactions.
Returning to current times, it was vehemently asserted by the plaintiffs
that even until now vacant possession had yet to be delivered to the
plaintiffs by the defendants. Surely there was something terribly wrong if
the claim of the plaintiffs could be defeated, despite the long wait, merely
because the contracted matter was a real estate?
The defendant had attempted to convince me that as the deposits for the
water and electricity supply had been late in coming, and if time had been
of the essence of the agreement, it thus had been waived. This was
nit-picking and a measure of the defendant's desperation to extricate itself
from the contract, as the deposits had been paid more than a month earlier
ie, before the delivery date. It must also be understood that the supply of
amenities viz. the flow of water and electricity was not the
responsibility of the defendant, but the connection of the water and
electricity mains were (Salmah
Sulaiman & Anor v. Metroplex Development Sdn Bhd [1997] 2 CLJ 148 CA
(refd);
Syarikat Lean Hup (Liew Bros) Sdn Bhd v. Cheow Choong Thai [1988] 1
LNS 74 [1988] 3 MLJ 221) 1 AMR 592). Here the plaintiffs had managed to
successfully convince me that, come the delivery date the defendant had
failed to deliver vacant possession as the water and electricity mains had
yet to be connected and the certificate of fitness never handed over to
them. In fact the defendant even had failed to establish that they had
submitted an application for that certificate (Syarikat Lean Hup (Liew
Bros) Sdn Bhd v. Cheow Choong Thai (supra)).
On the totality of the evidence, I was satisfied that in 1996 when the
S&P was executed by the plaintiffs and the defendant, time was indeed
intended to be of the essence of the agreement.
With the defendant having breached the contract here, the plaintiffs were
automatically accorded the rights to still enforce the agreement by
demanding specific performance of it pursuant to cl. 12(b), and demand
damages in the process as agreed upon. Regretfully the plaintiffs had taken
the extreme course of action of rescinding the agreement. The pertinent
questions that invariably follow, which had to be resolved emanating from
that scenario could be formulated in the following forms:
1. did the S&P, in particular cl. 12(b) provide for the right of
rescission of the contract by the plaintiffs in the event of a failure
and/or default by the vendor defendant to complete the sale of the said
property and deliver vacant possession of the same to them;
2. even if the agreement did not provide for rescission could the
plaintiffs have invoked any written law or equity to rescind that contract
in the event of a voidable contract or a fundamental breach having been
committed by the defendant; and
3. in the circumstances of the case could the plaintiffs rescind the
contract and demand the return of the RM306,000 together with damages (cl.
7.3)?
The defendant, in no uncertain terms had canvassed that the agreement did
not provide for rescission by the plaintiffs in the event of a breach of the
contract by the defendant, though did concede in the affirmative to the
second question. At a very late stage of the hearing, the defendant modified
its stance and advanced the argument that as the intitulment of the action
did not mention s. 56 of the Contract Act, the plaintiffs thus could not
submit on the importation of law for purposes of rescission.
Having scrutinized cl. 12(b), I found the defendant's stance rather
strange and contradictory, due to the relevant words in cl. 12(b), which
read " ... without prejudice to the other provisions of this agreement or
any other rights and remedies as may be available to the purchaser (s) at
law or in equity ... " . On proper construction of this clause, it clearly
meant that the plaintiffs had the additional right to resort to any law or
right in equity, though outside the provisions of the agreement, for
remedies. As nothing had been inserted in that clause or anywhere in the
agreement that limited the scope of the remedies, by necessity the latter
must include rescission. As those words of cl. 12(b) were provided for in
the agreement, and the intitulment did make mention of that controversial
agreement, though not specifically s. 56 of the Contract Act, the modified
stance of the defendant still did not help its case. On those grounds I was
more than satisfied that cl. 12(b) of the S&P did allow the plaintiffs the
right of rescission, if they so wished, in the event of any failure by the
defendant to deliver vacant possession.
If I might venture a step further, there was also no inhibiting
provisions anywhere in the agreement that prevented the plaintiffs from
adverting to any relevant law, common law, equity, written or otherwise for
a right to rescind the contract in the event of any breaches as provided for
under cl. 12(b). On the other hand, such inclusion of provisions to remove
the effect and oust the protection of relevant laws may run foul of certain
public policy, and in violation of the very purpose of such laws. If the
defendant is permitted to do that, then any S&P may attempt to contract
outside the relevant legislations governing housing developments eg, Housing
Development (Control and Licensing) Act 1966 (Act 118), Housing Developers
(Control & Licensing) Regulations 1989 (effective 1 April 1989) and the
like, legislations meant to protect purchasers (City
Investment Sdn Bhd v. Koperasi Serbaguna Cuepecs Tanggungan Bhd 1985 CLJ
77 [1988] 1 MLJ 69).
Even if I were to err in my findings that the agreement did provide for
rescission, but with the defendant's admission that such rescission was
permissible if any contractual laws were contravened, and as I have
neutralised the late modified view of the defendant, the next step to be
undertaken was the identification of that contravened contractual law. Since
time was provided for to be of the essence in the agreement,
Contracts Act 1950, ss. 56 therefore must take prominence in the current
discussion. This provision in crystalline terms states that when a party to
a contract promises to do a certain thing at or before a specified time, or
certain things at or before specified times, and fails to do any such thing
at or before the specified time, the contract, or so much of it as has not
been performed, becomes voidable at the option of the promise, if the
intention of the parties was at that time should be of the essence of the
contract. As the defendant had failed to deliver vacant possession by 18
June 1998 (within 24 months from date of execution of the contract), bearing
in mind that time was of the essence in the contract, the contract thus
became voidable at the option of the plaintiffs.
Voidable contract means an agreement that is valid and enforceable by law
at the option of one or more of the parties thereto, and in this case the
plaintiffs, but not at the option of the other or others (s. 2(i)). This
option of carrying on or invalidating the agreement by the innocent party,
needless to say arises as a result of the failure of the one without that
option, in this case the defendant, to perform the terms of the provisions
of the agreement (The Commercial Law of Malaysia, Wu Min Aun and
Beatrix Vohrah pp. 30 and 90).
Whether it was sheer defiance or enshrouded by some ulterior motive, even
to-date the defendant have not made any attempts to physically deliver that
certificate of fitness to the plaintiffs, so as to rectify the delay in its
completion of the contract. With that attitude prevailing, and the written
contract rendered voidable, the plaintiffs thus were statutorily entitled to
rescind the contract, as additionally provided for by
Specific Relief Act 1950, s. 34. The fact that the rescission was not
made forthwith on the very day of 18 June 1998 must not be taken against the
plaintiffs. It must be borne in mind that even the agreed defect liability
period was to be 12 months, to begin after the expiry of 14 days from the
date of the letter of delivery of vacant possession. During that lengthy
defect liability period, if a fundamental breach were to be detected, the
plaintiff might even have recourse to the remedy of rescission of the
contract. That being so, by analogy a waiting period of 33 days, before the
letter of rescission was sent was neither unreasonable nor may qualify as
undue delay, construable as a waiving of the plaintiffs'rights to rescind.
It must be understood that the cause of action ie, the day the contractual
duty was broken by the defendant commenced on 18 June 1998, and once the
plaintiffs had handed the letter of rescission, the contract thus had become
void (Insun
Development Sdn Bhd v. Azali Bakar [1996] 2 CLJ 753 FC (refd);
Tan Yang Long & Anor v. Newacres Sdn Bhd [1992] 1 CLJ 211; [1992] 3
CLJ 666 HC (refd),
Loh Wai Lian v. SEA Housing Corp Sdn Bhd [1987] 1 LNS 37 [1987] 2
MLJ 1). Once it was void it had ceased to be enforceable. Even if the
defendant were to succeed in obtaining the certificate of fitness within a
reasonable period after that relevant date, it would already have been too
late in the day.
Factually I had found that by the time vacant possession was due, the
plaintiffs had already paid up everything that was required to be paid, in
accordance with the S&P. This factor was denied by the defendant and had
attempted to make much of a balance sum of money amounting to RM15,300,
supposedly kept by the plaintiffs solicitor's firm as stakeholders of that
money (and the last balance), I was unable to accept that argument as that
firm was the common solicitor of the contending parties!
In the event the court were to declare that the defendant had breached
the agreement, and the plaintiffs had rightfully rescinded the agreement,
there was no difficulty faced by the court in identifying the sums of money
to be returned, as they were easily identifiable. What the defendant would
have to do was to return the sum of RM306,000, together with the interest,
beginning from the date of the filing of the originating summons. Both
parties thus would be returned to their respective pre-agreement position as
none would be permitted to profit from any unconscionable enrichment. With
the contending parties back to square one, the plaintiffs too would be
deregistered as the registered owners of the impugned property in the event
they had been hurriedly so registered earlier. With the contract now
avoided, and as there was nothing in law or any business practice that
prevented the defendant from reselling the impugned property at the current
market price to recoup any losses if any, it thus could do that. As a rider,
in the event the defendant was to incur any loss that was regretful, as it
was the very cause of this long and painful affair.
After having perused the facts and law my orders were as follows:
i. I hereby declare that the defendant had breached the sale and purchase
agreement dated 19 June 1996, and the plaintiffs had rightfully rescinded
the agreement on 21 July 1998 by reason of that breach;
ii. that the defendant refund the plaintiffs all monies paid to them
totalling RM306,000 as the purchase price of the impugned property and
incidental charges of RM2,980;
iii. interest at the rate of 8% per annum on the judgment sum from the
date of the filing of the originating summons to the date of full
settlement;
iv. the plaintiffs be deregistered as the registered owners of the
impugned property on full and final settlement of the adjudged sum; and
v. costs of this application.
(see also- LSSC
DEVELOPMENT SDN BHD V. THOMAS IRUTHAYAM & ANOR
(14 MARCH 2007) COURT OF APPEAL, PUTRAJAYA[CIVIL APPEAL NO:
B-02-407-2005] )
|