| 
			 Developers agree with pre-application inspection 
			NST-PROP 
			20/09/2003 By Nicholas Mun  
  
			They 
			insist that local councils issue the CFs within 14 days of 
			application 
			Now that 
			all local councils are obliged to issue Certificate of Fitness for 
			Occupation (CFs) 14 days after an application had been received from 
			a developer, many agencies are not accepting the applications until 
			after a project has been physically inspected and approved by them 
			in principal. However, many developers see no problem with this 
			method of work-flow which  is becoming the norm. 
			  
			In fact, 
			some welcome the procedure as they can nip in the bud any problem 
			that might affect the chances of a successful application. 
			  
			Paramoden 
			Sdn Bhd marketing manager Rustam Hamidon Drury said "local councils 
			and the relevant technical departments are always invited to our 
			sites before CF applications are submitted. 
			  
			He said 
			the company, a wholly owned subsidiary of MK Land Holdings Bhd, 
			prefers this practice as it allows them to work hand in hand with 
			the authorities to rectify any problems.  
			  
			"It helps 
			ensure there are no unnecessary delays once an application is 
			submitted," he said.  
			  
			Talam Corp 
			Bhd general manager of marketing Adam Yap agreed. 
			  
			"When a 
			developer submits (the requisite application) Borang E, it means all 
			requirements of the relevant technical departments have been 
			satisfied," he said. 
			  
			According 
			to Yap, the only issue is whether the CF is issued within 14 days as 
			required by the Ministry of Housing and Local Government. 
			  
			Speaking 
			on condition of anonymity, another developer said local councils are 
			still taking a couple of months to issue CFs, despite the Borang E 
			being in order. 
			  
			This is 
			the problem National House Buyers Association (HBA) hopes would be 
			addressed with developers needing the approval of only one technical 
			agency - the Sewerage Service Department - from November. 
			  
			Developers 
			currently need the green light of another six departments that 
			include Fire and Rescue Services, Waterworks, Public Works and 
			Drainage and Irrigation Departments, Tenaga Nasional Bhd and Telekom 
			Malaysia Bhd. 
			  
			HBA 
			secretary-general Chang Kim Loong, however, pointed out that the 
			directive to issue CFs within 14 days of an application is not 
			something new. 
			  
			"For the 
			record, amendments made some three years ago to By-law 25 of the 
			Uniform Building By Laws provided for the issuance of CFs by local 
			councils within 14 days from the date of acceptance of Borang E, 
			failing which they are deemed to have been issued immediately after 
			the expiry of the 14-day period," he said. 
			  
			Chang 
			proposed that in order for the industry to improve further, vacant 
			possession should only be given after CFs have been issued. 
			  
			"Since it 
			is only a matter of 14 days between submission of Borang E and 
			getting a CF, it is more meaningful if keys are given with immediate 
			occupation to buyers."  |