			 1,124 buyers can 
			move into new homes next year 
			 
			21/06/2001 
            The Star  
			After a delay of 15 months, the 1,124 housebuyers 
			of Taman Hijau Phase 1 in Paya Terubong can look forward to moving 
			into their low-medium cost units early next year.  
			The remaining 1,101 housebuyers under the 
			project's Phase 2 can expect to occupy their units in 2003.  
			 
			According to project developer, Gelanggang Kemilau Sdn Bhd, Phase 1, 
			comprising the 27-storey Block A, is expected to be completed with 
			vacant possession before March 2002.  
			 
			Its general manager Tean Kok Pin said structure work for Block A was 
			now 100% completed while construction of walls and plastering works 
			was in progress.  
			 
			"Construction of the 26-storey Block B is in progress and is 
			expected to be completed by the end of next year," he said.  
			 
			Taman Hijau was launched in mid-1996 and the RM50,000 units were 
			sold to housebuyers registered with the state housing department, 
			many of whom were affected by the repeal of the Rent Control Act in 
			inner George Town.  
			 
			Construction took off in December 1996 but stalled in early 1998 due 
			to the economic slowdown. Work resumed in Aug 1999.  
			 
			When it was launched, the project was touted to be the first 
			low-medium cost project in Penang to be equipped with a swimming 
			pool. Other amenities include a wet market, badminton, 
			basketball/volleyball courts, a multi-storey carpark and 
			kindergarten.  
			 
			Affected housebuyers can contact Taman Hijau pro tem housebuyers 
			committee chairman Tai Teik Hock at Tel: 012-4565423 for more 
			details.   |