			 Court orders 
			appointment of receiver and manager 
			The Star 
			17/04/2001 
  
			A High Court yesterday ordered, by consent, the appointment of a 
			receiver and manager to continue with the completion of a stalled 
			medium-cost apartment project in Jalan Lumba Kuda.  
			Justice Md Raus Sharif recorded the consent after 
			counsel K.Thangesvaran for plaintiffs U.G.Jayantha and Lim Beng Poh, 
			and counsel K.Saravana Kumar for defendant Ever Noble Sdn Bhd 
			informed the court that both parties had agreed to appoint Datuk Ong 
			Gim Huat and Teoh Teik Huat as either a single or joint Receiver and 
			Manager in accordance with a memorandum of understanding between the 
			parties on Oct 6, last year.  
			 
			The consent order also recorded that Ever Noble as developer of the 
			project defaulted in its contractual obligations to the 205 
			purchasers as the company had failed to complete construction and 
			hand over possession of the apartment units to them.  
			 
			It was also agreed that since the developer had defaulted in its 
			contractual obligations, the buyers were entitled to terminate their 
			sales and purchase agreement and enter a claim against the developer 
			for damages.  
			 
			Jayantha as chairman and Lim as secretary of the Menara Kuda Lari 
			Purchasers' Committee who brought the action on behalf of themselves 
			and 193 other buyers, in their affidavit said Ever Noble was the 
			developer of Menara Kuda Lari which consists of 219 units.  
			 
			The project commenced in December 1994 and vacant possession was 
			scheduled to have been given to the buyers within 36 months of the 
			commencement of the sales and purchase agreement.  
			 
			Later, outside court Lim appealed to the buyers to pay up their 
			balance payment to enable the project to proceed smoothly.  
			 
			"Lim also appealed to purchasers for co-operation in settling the 
			balance payment because without the money, the project even though 
			with the order, cannot go on.''   |