Developers Liable To Pay
Damages Immediately To Housebuyers, Rules Court Of Appeal
30/04/2008 Bernama
PUTRAJAYA, April 30 (Bernama) -- Housing developers are liable to pay
liquidated damages immediately to housebuyers if they fail to deliver the
property on time, the Court of Appeal ruled Wednesday.
A three-member panel led by Justice Datuk Gopal Sri Ram said housing
developers entering a sale-and-purchase agreement with housebuyers did not
enjoy freedom to make provisions between themselves because it was a special
contract prescribed under the Housing Developers (Control and Licensing) Act
1966.
He said housebuyers were therefore not required to notify the developers of
their intention to claim liquidated damages before making such a claim,
unlike in normal contracts which were governed by the Contracts Act 1950.
Sri Ram made the ruling after dismissing an appeal brought by developer
Sentul Raya Sdn Bhd in the attempt to reverse the decisions of 10 High
Courts holding it liable to pay liquidated damages to 82 buyers of the Sang
Suria condominiums for failing to hand over the units within the time frame
of 36 months.
Sentul Raya was ordered by the High Court to pay liquidated damages to the
housebuyers immediately, to be calculated from day to day at the rate of 10
per cent per annum of the purchase price.
The court also allowed the cross-appeals by 27 housebuyers against four High
Court decisions refusing to award them liquidated damages for the period in
which each of them had taken actual physical possession of their respective
condominium units.
Sri Ram, who presided with Justice Datuk Heliliah Mohd Yusof and Datuk Ahmad
Maarof, said the requirement to give notice under Section 56 (3) of the
Contracts Act was an additional obligation to the detriment of the
purchaser, and cannot be imposed in view of the statutory scheme under the
Housing Developers (Control and Licensing) Act.
"Clause 22 (2) of the sale-and-purchase agreement, making a housing
developer immediately liable to a purchaser in liquidated damages once the
date for completion passes, excludes the application of Section 56 (3) of
the Contracts Act (requiring housebuyers to notify the developer of their
intention to claim liquidated damages).
On Sentul Raya's defence that the 1997 financial crisis had made it
impossible to complete the construction of the condominium units within the
stipulated time, thereby absolving it of discharging the contract, Sri Ram
said the court did not accept the defence.
Sri Ram said the defence that the contract entered between the company and
the housebuyers was frustrated because of the 1997 crisis, which rendered
the performance of the contract radically different from that which was
undertaken by the contract, was not available to Sentul Raya.
"The 1997 financial crisis merely made it more onerous or perhaps more
expensive for Sentul Raya to perform its obligations. It did not render the
contract radically different," he added.
-- BERNAMA |