Last call for Plaza Rakyat
developer
16/10/2007 NST By Minderjeet Kaur
The three-month grace period for the developer of the abandoned Plaza Rakyat
project is up.
It will be the end of the road if Plaza Rakyat Sdn Bhd fails to show proof
that it is capable of reviving the RM1.2 billion bus and taxi terminal with
service apartments, hotels and office blocks.
Federal Territories Minister Datuk Seri Zulhasnan Rafique said the developer
would be called for a meeting with City Hall soon.
"We are going to discuss issues with them. The meeting is also to find a
solution so that the government and the developer will benefit in the long
run," he said during his Hari Raya open house for the media in Setiawangsa
yesterday.
The Plaza Rakyat project is adjacent to the Puduraya bus terminal.
The federal government had given Plaza Rakyat Sdn Bhd the tender to build a
new terminal to replace the congested and stuffy Puduraya.
Despite receiving extensions five times since 1995, it is only 33 per cent
completed.
Zulhasnan said that City Hall had been given the task of finding a solution
to ensure both the government and the developer benefit from the meeting.
"Once City Hall comes up with a solution, it will get back to me."
The developer had started the project in December 1992 and was supposed to
complete it in 1999.
However, the financial crisis in 1997 saw the project run into difficulties
and construction work stopped.
So far, the developer has completed a Star-LRT station which is now in use.
Two tunnels linking the Pudu area to Plaza Rakyat were also completed and
are in use.
The ministry's parliamentary secretary, Yew Teong Look, had said the
developer had sought an extension from March 31 last year to May 31 this
year, but little work had been done.
The matter was raised in the Dewan Rakyat last June by Bukit Bintang MP Fong
Kui Lun who said the delay in the project had caused losses for those who
had invested in Plaza Rakyat and are now servicing loans for properties they
had not possessed. |