This website is
 sponsored.gif

banner.gif

 Welcome    Main    Forum    FAQ    Useful Links    Sample Letters   Tribunal  

Irresponsible developer

New Straits Times 08/05/2006

I WAS more than happy to hear in November that I could collect the keys to my condominium in Damansara after a 14-month delay.

Before the vacant possession of the unit could be given, I was requested to agree to a compensation sum for the delay.

Once I agreed to accept the compensation sum, the developer would issue me a release letter to inspect and collect the keys from its site office.

Then, the customer service personnel set an appointment for me with its site office to inspect the unit for defects.

I was more than disappointed to see that the unit was far from ready. There were more than 50 major defects. Even the two parking lots allotted to my unit were not ready.

In December, I sent a 20-page letter listing major defects to the developer. I was assured that the repairs would be finished in a month.

Again, I was disappointed when I was told at the end of January that repair works on my unit had not started. Again, I was assured that the repair works would be over in a month.

Finally, the repairs were completed in mid-April.

I submitted a letter to the developer in February requesting further compensation. There was nothing I could do with the unit for five months (November to April).

Neither could I move in nor rent the unit out. I was losing out, paying the maintenance fee, and loan repayment. The developer has not responded to this letter.

H.S.O.
Kuala Lumpur

 

Main   Forum  FAQ  Useful Links  Sample Letters  Tribunal  

National House Buyers Association (HBA)

No, 31, Level 3, Jalan Barat, Off Jalan Imbi, 55100, Kuala Lumpur, Malaysia
Tel: 03-21422225 | 012-3345 676 Fax: 03-22601803 Email: info@hba.org.my

© 2001-2009, National House Buyers Association of Malaysia. All Rights Reserved.