Extended defect liability: Is it meaningful?
NST-Prop 28/10/2006 By S.Y. Kok
A legal opinion of what it really provides, and whether
it should be adopted industry-wide
ON the surface, news that some developers are offering
buyers warranty periods twice as long as what they're obliged to provide for
houses they build sounds welcoming. So too might news that Housing and Local
Government Minister Datuk Seri Ong Ka Ting is contemplating making it a new
standard for the industry.
However, beneath the glitter and "feel-good" sentiments
of having a Defect Liability Period (DLP) of more than the required 18
months, there are reasons for concern.
In my opinion as a solicitor familiar with the laws
governing the housing industry, the move by certain companies to provide an
"18+18" or - as was recently advertised - a five-year DLP, is nothing
more than a sales ploy.
In the light of existing housing laws, we need to
examine if there is a necessity for the Housing Ministry to adapt an
extension.
Origin and purpose of DLP
The DLP, as spelt out in the standard Sale and Purchase
Agreements (SPAs) for housing (Clause 26(1) in Schedule G for landed
properties and Clause (30(1) in Schedule H for stratified units), is
actually a doctrine of implied warranties that came about as a result of our
Sell-Then-Build (STB) mode of housing delivery.
However, this principle (adopted from the United
Kingdom) only operates in favour of buyers of houses under construction. It
is of no relevance to those buying completed houses or units employing the
"Build-Then-Sell" (BTS) formula.
The reason is because BTS turns the tables. Since it
permits buyers or their surveyors to appraise the actual physical condition
of a completed property, the onus is on them to be on their guard and
exercise caveat emptor (meaning buyer beware) when entering into
transactions, responsible (as in the case with STB).
The legislative philosophy underlining STB units is to
ensure that buyers will not be short-changed - that when their homes are
ready, they will be made using good workmanship, with building materials as
specified, and which will be fit for human habitation. And since their units
wouldn't be ready for inspection, caveat emptor cannot apply.
Two types of defects
Another point of interest in the DLP provision is that
I believe the Housing Development (Control & Licensing) Act 1966 (and its
standard SPAs) has divided into minor and major construction defects.
In my opinion, Clauses 26 or 30, as the case may be,
focuses only on minor defects, while major ones are covered by common law
following a breach of the fundamental terms in a contract.
As it stands, minor defects are confined to:
i) Those that become apparent in a housing unit within
18 calendar months from the date of vacant possession is delivered. These
can include water leakages (either from the roof or an upper floor
apartment); from water pipes or water closets; cracks in the wall or floors;
electric wires connected to wrong electrical points; uneven and wavering
floors; doors and windows that are out of alignment; and missing water and
electric fixtures and fittings;
ii) Shrinkage within the same housing unit; and
iii) Other faults not covered by the above two
situations.
Thus, buyers who have taken vacant possession of their
units and discovered defects, shrinkage or other faults needing repairs are
required by law to notify their developers within 18 calendar months.
Such defects may hamper the continued occupation of
their units and make living conditions uncomfortable, but they are not
deemed life threatening, compared to say a structural crack that can lead to
building collapse and loss of lives.
There are several reasons for my opinion that the DLP
as spelt on in the standard SPAs cover only minor defects.
The first can be found in the fact that if faults are
not speedily rectified by a developer, they can be carried out by the
aggrieved buyers after the conditions spelt out in their SPAs have been
satisfied.
Among these conditions is that the cost of repair must
first be made known to the recalcitrant developer and that the work must not
exceed the retention sum of five per cent of the purchase price, as
determined under Item 5 of the SPAs Third Schedule of Payment.
Hence, for a RM100,000 house, a maximum of only RM5,000
can be spent which is certainly too small an amount to meet expenses
associated with major rectification work.
I have also found judicial foundation to support my
opinion. One comes from a judgment delivered by Justice Suriyadi in the High
Court of Malacca in 1996, involving four rows of single-storey terrace
houses that had to be torn down and rebuilt because of serious defects.
Referring to the clause on DLP, the judge held that it
merely lays down the responsibility of the vendor (the developer) "over the
minor defects within one year of the delivery of vacant possession and its
subsequent liability", should new ones be discovered.
In contrast to minor defects, major structural defects
are way beyond the ability of buyers to rectify as they could, eventually,
cause completed housing units to collapse, either totally or partially, and
are without exception, life-threatening.
Because of such grave consequences, buyers don't have
the right to repair or rectify any structural defect.
An example of a major defect was when a 300 gallon
water tank crushed through the ceiling of a double-storey terrace house in
Telok Gedong Indah (New Sunday Times, May 14,2006). Obviously, that
incident was the result of a defect that would not have occurred had it not
been for negligence on the part of the developer.
As for the infamous Highland Towers collapse in Ampang,
Selangor, the soil movement triggered off by a landslide hit the foundation
columns of one of the two blocks, causing it to collapse. The DLP had long
been over, and many lives were lost in the tragedy, but the 18-calendar
month period did not bar civil claims against the developer.
This is because housing SPAs do not expressly rule out
such an action. Neither do they expressly state that after the prescribed 18
calendar months, the developer will no longer be responsible to its buyers
for actions that are to be founded in contract or in tort.
This legal issue was examined by Justice Ramly Ali, who
ruled that buyers can still enforce their rights for breach of contract,
under common law, after the DLP has expired.
The judge was clear in that the end of a DLP does not
restrict or expunge the basic rights of aggrieved buyers to sue a developer
for damages in respect of major defects under common law.
The judge said: "In other words, all provisions in the
SPA are actually statutory requirements that must strictly be complied
with."
He added that the clauses regarding DLP are "meant to
be additional protection for house buyers, without affecting or limiting
their rights under the common law".
Therefore, any major defect that crops up after the
expiry of the 18 month warranty period would require the developer to
rectify it speedily, or face civil suit under common law for breach of
contract.
Should a developer on its own volition want to offer a
36-month (or 18+18) warranty, so be it. Beyond the original 18 months, any
defect that surfaces will, in most likelihood, be a major fault requiring
affected buyers to seek legal redress from a court of law and not from their
SPAs.
The Housing Ministry, being a governmental and
regulatory body, should not react with knee-jerk legislation.
The minister ought to think through the legal issues
before making what may appear to be a rash and impetuous statement about
enforcing a 36 months' warranty period on all developers.
S.Y.Kok is the author of the book, "Law Governing
the Housing Industry". He declares he attempts to project the impartial view
on housing in this Viewpoint column and does not wish to be branded as
favouring either developer or purchaser. |