Vacant
possession not an issue
Malay Mail
22/10/2004
KUALA LUMPUR: Vacant possession was not an issue in a ruling made by
the House Buyer Claims Tribunal on Sept 29.
This was pointed out by the Housing and Local Government Ministry
following a call by the Consumers' Association of Penang (CAP) on
Oct 17 for the Ministry to clarify why developers do not have to
hand over the keys to buyers to deliver vacant possession.
In a statement yesterday, the Ministry's public relations head,
Abdul
Halim Mohd Sharif, said the ruling was for a case in which the
claimant sued the developer for Liquidated Ascertained Damages (LAD)
for late delivery of vacant possession of a house bought in June
2001.
The claimant, he said, claimed LAD had to be calculated until the
handing over of the house keys, on Dec 17, 2003.
The developer, he said, argued that there was no late delivery as
notice of delivery of vacant possession was issued on May 7, 2003,
well within the 24 months stipulated by the sale and purchase
agreement.
He said: "Water and electricity could only be ready for connection
on
Oct 20, 2003 at the very least. Thus, the tribunal opined that
vacant
possession could only be delivered to the claimant on or after Oct
20, and allowed LAD to be calculated until that date."
He said that LAD was to be calculated until Oct 20 and not Dec 17 as
the claimant wanted.
"In a 1997 case, Salmah Sulaiman and Others versus Metroplex
Development Sdn Bhd, LAD was calculated until the date of delivery
of vacant possession which was earlier than the actual date of
handing over keys."
He said although the decision of the tribunal was final, the
claimant could still appeal to the High Court for a review of the
tribunal's decision within 40 days from the date of the award.
CAP president S.M. Mohd Idris had said that CAP was unhappy that the
tribunal ruled that it was not necessary for developers to hand over
the keys to effect vacant possession.
The tribunal had stated that such was the law after the 1994
amendments to the Housing Developers Act.
He had said that developers should strictly adhere to the provisions
of sale and purchase agreements and not place an unfair burden on
buyers.
Furthermore, they should hand over possession to buyers only when
water and electricity supplies are connected.
He said developers should also send notices to buyers requesting
them to take possession within 14 days, based on the sale and
purchase agreement, instead of expecting them to do so.
|