Developers agree with pre-application inspection
NST-PROP
20/09/2003 By Nicholas Mun
They
insist that local councils issue the CFs within 14 days of
application
Now that
all local councils are obliged to issue Certificate of Fitness for
Occupation (CFs) 14 days after an application had been received from
a developer, many agencies are not accepting the applications until
after a project has been physically inspected and approved by them
in principal. However, many developers see no problem with this
method of work-flow which is becoming the norm.
In fact,
some welcome the procedure as they can nip in the bud any problem
that might affect the chances of a successful application.
Paramoden
Sdn Bhd marketing manager Rustam Hamidon Drury said "local councils
and the relevant technical departments are always invited to our
sites before CF applications are submitted.
He said
the company, a wholly owned subsidiary of MK Land Holdings Bhd,
prefers this practice as it allows them to work hand in hand with
the authorities to rectify any problems.
"It helps
ensure there are no unnecessary delays once an application is
submitted," he said.
Talam Corp
Bhd general manager of marketing Adam Yap agreed.
"When a
developer submits (the requisite application) Borang E, it means all
requirements of the relevant technical departments have been
satisfied," he said.
According
to Yap, the only issue is whether the CF is issued within 14 days as
required by the Ministry of Housing and Local Government.
Speaking
on condition of anonymity, another developer said local councils are
still taking a couple of months to issue CFs, despite the Borang E
being in order.
This is
the problem National House Buyers Association (HBA) hopes would be
addressed with developers needing the approval of only one technical
agency - the Sewerage Service Department - from November.
Developers
currently need the green light of another six departments that
include Fire and Rescue Services, Waterworks, Public Works and
Drainage and Irrigation Departments, Tenaga Nasional Bhd and Telekom
Malaysia Bhd.
HBA
secretary-general Chang Kim Loong, however, pointed out that the
directive to issue CFs within 14 days of an application is not
something new.
"For the
record, amendments made some three years ago to By-law 25 of the
Uniform Building By Laws provided for the issuance of CFs by local
councils within 14 days from the date of acceptance of Borang E,
failing which they are deemed to have been issued immediately after
the expiry of the 14-day period," he said.
Chang
proposed that in order for the industry to improve further, vacant
possession should only be given after CFs have been issued.
"Since it
is only a matter of 14 days between submission of Borang E and
getting a CF, it is more meaningful if keys are given with immediate
occupation to buyers." |