Check first, pay later
NST-PROP 23/11/2001 By Akbal Singh Sandhu
Before releasing progress payments,
financial institutions should inspect project sites to verify physical
progress
As a purchaser of a new property, you
need to keep constant tabs on whether the monies being released by your
financier to the developer commensurates with the physical progress of the
site in accordance with your Sale and Purchase Agreement.
Don't expect your contractor or
developer to inform you of any delay in the project. At the same time, do
not assume your financial institution is on top of things - often bank
takes it for granted that works at site are as true as per the architect's
certificate and really do not bother to visit the site themselves.
As far as the contractor or builder is
concerned, he has no duty to you as his contract to construct is entirely
with the developer. As for the architect, his scope of work related to
contractor is purely that of ensuring the construction is kept on schedule
with the overall delivery programmed to enable the latter to claim his
monies from the developer. The sooner he completes, the faster he takes
his money.
A competent and vigilant contractor may
complete his work sooner than required, only to be slowed down by the
irregular or delayed honouring of progress payments by the developer.
Alternatively, the situation could be
reverse, whereby the inability of the contractor will undoubtedly affect
the progress of delivery to purchasers.
Such a situation can happen either due
to poor management by the contractor or if the developer is slow or
defaults in payment to the contractor, thus making it difficult for the
latter to balance his cash flow. This is why as a buyer, it is important
for you to do some preliminary findings to satisfy yourself about the
financial stability of not only the developer but also to be aware of whom
the contractor is. You may locate this information on the project's
construction signboard, which also lists all the consultants. Occasionally
it could be the subsidiary company of the developer or even a relative of
the developer who has been commissioned to construct the property.
Where a developer is unable to deliver
or where the developer feels that his financial situation will affect
delivery of houses to purchasers, the developer is required under Section
7(g) "where he considers that he is likely to become unable to meet his
obligation to the purchasers, forthwith to inform the controller of such
fact." This rarely happens.
The numerous abandoned housing projects
are testimony that they have escaped the watchful eyes of the Ministry of
Housing and Local Government and the local authorities. You may also be
surprised to find that the developer without your knowledge can also seek
an extension to the delivery period as allowed for in the Housing
Developers Act under Regulation 11 - Contract of Sale. Sadly, the Act does
not require the developer to seek the consent of purchasers let alone
inform them.
In this respect, the present Act fails
to safeguard the interest of purchasers. Rightly, it should be the duty of
the developer to inform the purchaser but I am yet to see an instance of
this happening. It is rather for the Housing Ministry to grant such an
extension without due regard to purchasers who might be living in rented
accommodation while awaiting the completion of their new home.
If the physical progress at site is more
or beyond the stage billed to you by the developer, you should not have
any complaint. But what happens if you discover that the actual physical
progress on your property is less than that required according to the
schedule in the guidelines to the Architects?
In this instance, you are advised to
take photographs or make a record in writing and question both the
financier (if the progress payment has been released) and the developer.
Although the guidelines to the
architects are pretty specific, many an architect has been penalised for
wrong certification. Architects can argue otherwise, but there are always
some who will play to the tune of their developer paymasters despite their
duty in tort to the purchaser. It is for this reason that is imperative
that you question your financial institution as to whether its
representatives have conducted a physical on-site inspection of your
property before releasing monies.
Buyers' liability on interest payments
is calculated based on the amounts of monies released to the developer on
their behalf by the financial institution. The sums are released from the
total principal sum that would have been set aside by the financier.
Hence, should the developer abandon or delay the project, the buyer would
still be liable to the interest on the amounts of monies released by the
bank on his behalf. While the financial institution may proceed to take
the necessary action of recovery of its monies from the developer, the
institution will also seek recovery from the buyer or borrower.
It is immaterial for the financial
institution as to where it recovers its money. This is why I stand by my
opinion that financial institutions will not extend their umbrella on
rainy days to anyone. It would therefore be worthwhile for you to put in
writing to the financial institution giving out your loan as soon as it is
approved that the liability will be upon it should it be found that the
release of monies to the developer on stage completion is found not to
tally with the physical progress so claimed or stated in the Architect's
certificate.
It is an exclusion clause to protect
yourself and it worthy of exploring; after all, inserting exclusion
clauses are quite a norm for the financial institutions themselves, so why
should a buyer not protect himself too? This is primarily because the
present arrangement between the developer and the financier is that monies
will be released upon the developer presenting the architect's certificate
to the financier.
Akbal Singh Sandhu is a chartered
architect and town planner. Saddened by the quality of building
construction today, he has set up BIS Building Inspection Services
specialising in independent assessment of defects. |