SYARIKAT KEMAJUAN PERUMAHAN NEGARA SDN BHD V. LEE CHENG & ANOR
COURT OF APPEAL, PUTRAJAYA
[CIVIL APPEAL NO: C-04-28-1999]
ABDUL MALEK AHMAD PCA , TENGKU BAHARUDIN SHAH JCA , JAMES FOONG JCA
8 SEPTEMBER 2005
CONTRACT:
Building Contract - Delivery of vacant possession
- Whether developer obliged to energize supply of water and electricity into
Building before handing over vacant possession of Building - Housing Developers
(Control and Licensing) Regulations 1989.
CONTRACT: Housing development - Sale and purchase
Agreement - Sale and purchase Agreement subject to the Housing Developers
(Control and Licensing) Regulations 1989 - Vacant possession - Whether vacant
possession under the Housing Developers (Control and Licensing) Regulations
1989 presupposes the developer's responsibility to energize the supply of
water and electricity into the Building.
The
respondents bought a shop-house from the appellant developer. A sale and purchase
agreement ('the agreement') dated 16 May 1990 was executed. The agreement
was in compliance with the Housing Developers (Control and Licensing) Regulations
1989. Pursuant to the agreement, the last date for the appellant to deliver
vacant possession was on 16 May 1992. Water pipes and electricity mains were
duly laid and connected to the shop-house on 13 January 1991. Keys to the
shop-house were handed over to the respondent on 30 October 1991. The Certificate
of Fitness was issued on 19 August 1993. However, electricity supply was only
connected to the shop-house on 18 January 1994. The respondents thus claimed
from the appellant damages for late delivery of vacant possession from 16
May 1992 to 18 January 1994. The claim was first allowed in the magistrates'
court. The appellant appealed to the High Court which dismissed its appeal.
The appellant thus appealed to the Court of Appeal. In the Court of Appeal,
the appellant's counsel relying on r. 12(1)(l) of the Housing Developers (Control
and Licensing) Rules 1970 ('the 1970 Rules') submitted inter alia that the
appellant was only obliged to connect the electricity and water mains to the
internal mains of the shop-house. The flow of water and electricity was not
the appellant's responsibility, argued counsel. The respondents' counsel however
contended that the 1970 Rules had been repealed and the regulations applicable
in the instant case were the Housing Developers (Control and Licensing) Regulations
1989 ('the 1989 Regulations'). The 1989 Regulations, said respondents' counsel,
obliged a housing developer to energize water and electricity flow into a
building when handing over vacant possession. Thus, the appellant was required
to connect the electricity supply to the respondents' shop-house before handing
over vacant possession, submitted counsel.
Held
Per James Foong J (dismissing the appeal with costs):
[1] The principles and propositions enunciated in cases associated with late
delivery of vacant possession must be considered in the light of the rules
and regulations specifically applicable to those cases. The principles and
propositions cannot be of universal guide for all cases associated with the
late delivery of vacant possession. (p 146 d-f)
[2] Pursuant to the 1989 Regulations, vacant possession with connection of
water and electricity to a building must include the developer's duty to energize
the water and electricity flow into the building. It is not sufficient for
the developer to just lay the pipes and cables for electricity and water to
connect the said building to the sub-station or water mains. The developer
must ensure at the time of delivery of vacant possession of the said building
that there is supply of water and electricity ready for tapping into the building.
Hoya Holding Sdn Bhd v. Chia Thin Hing & Anor [1994] 4 CLJ 992 (folld); Lew
Yoke Leng & Ors v. Syarikat Kar King Sdn Bhd [2000] 4 CLJ 184 (folld). (p
146 g-h)
Case(s) referred to:
Charles Muriel v. Newacres Sdn Bhd [1994] 2 CLJ 561; [1994] 2 AMR 23 (refd)
Hoya Holding Sdn Bhd v. Chia Thin Hing & Anor [1994] 4 CLJ 992 HC (foll)
Kandasamy Sreenivasagam v. Syarikat Muzwina Development Sdn Bhd [1990] 1 MLJ
15 (refd)
Lew Yoke Leng & Ors v. Syarikat Kar King Sdn Bhd [2000] 4 CLJ 184 HC (foll)
Salmah Sulaiman & Anor v. Metroplex Development Sdn Bhd [1997] 2 CLJ 148 CA(refd)
Syarikat Lean Hup (Liew Brothers) Sdn Bhd v. Cheow Chong Thai [1988] 1 LNS
74 ; [1988] 3 MLJ 221 (refd)
Tay Ket v. Bumibakti Development Sdn Bhd [1994] 3 CLJ 256; [1994] 2 AMR 35
(refd)
Legislation referred to:
Housing Developers (Control and Licensing) Rules 1970, r. 12(1)(l)
For the appellant - Felix Dorairaj; M/s Dorairaj, Low & Teh
For the respondent - KC Cheah; M/s KC Cheah & Co
[Appeal from High Court, Raub; Summons No: 72-18-1995]
JUDGMENT
James Foong JCA:
Introduction
This appeal centres on the perennial dispute as to whether delivery of vacant
possession of a house sold by a developer to a purchaser should include supply
of water and electricity to the house and if so to what extent and manner.
Facts
The undisputed facts of this case are these:
By a sale and purchase agreement dated 16.5.1990 (S & P Agreement), the respondent
purchased from the appellant a shop house in Raub for a sum of RM95,000.00.
Complying with regulation 11(1) of the Housing Developers (Control And Licensing)
Regulations 1989 (1989 Regulations), the S & P Agreement contains the following
clauses, relevant to the dispute in this case:
Clause 17(1)
The Vendor shall, at its own cost and expense, lay or cause to be laid all
necessary water, electricity and sewerage mains, gas piping (if any) and internal
telephone trunking and cabling (if any), to serve the said Estate and at its
own cost and expense undertake to apply for the connection of internal water,
electricity, sanitary and gas installations (if any) of the said Building
to the water, electricity and sewerage mains of the Appropriate Authority,
and the gas mains of the relevant authority.
Clause 17 (2)
The Purchaser shall be liable for and shall pay, within fourteen (14) days
after the receipt of a notice requesting for payment from the Vendor, the
deposits for the installation of water, electricity and gas meters and the
Vendor shall bear all other costs, if any.
Clause 20(1)
The said Building shall be completed by the Vendor and vacant possession with
the connection of water and electricity supply to the said Building, shall
be handed over to the Purchaser within twenty-four (24) calendar months from
the date of this Agreement.
Clause 20(2)
If the Vendor fails to hand over vacant possession of the said Building together
with the connection of water and electricity supply to the said Building in
time, the Vendor shall pay immediately to the Purchaser liquidated damages
to be calculated from day to day at the rate of ten per centum (10%) per annum
of the purchase price.
Clause 21(1)
Upon the issue by the Vendor's Architect of a Certificate certifying that
the construction of the said Building has been duly completed and water and
electricity supply has been connected to said Building and the Purchaser having
paid all monies payable under clause 4(1) in accordance with the Third Schedule
and all other monies due under this Agreement and the Purchaser having performed
and observed all the terms and covenants on his part under this Agreement
the Vendor shall let the Purchaser into possession of the said Property.
The last date for the appellant to deliver vacant possession of the said building
under the S & P Agreement is 16 May 1992. Water pipes and electricity mains
were duly laid and connected to the said building on 13 January 1991. Keys
to the said building were handed over to the respondent on 30 October 1991.
Certificate of Fitness to the said building was issued on 19 August 1993.
However, electricity supply was only connected to the said building on 18
January 1994.
For this, the respondent claimed from the appellant in the Magistrate's Court
in Raub a sum of RM15.902.73 for late delivery of vacant possession of the
said building from 16 May 1992 to 18 January 1994; a total of 611 days.
The learned Magistrate allowed the respondent's claim with interest and costs.
Dissatisfied, the appellant appealed to the High Court in Raub. Judicial Commissioner
Dato' Azhar Ma'ah (as he then was) dismissed the appeal with costs. Still
discontented, the appellant filed this appeal before us.
Appellant's Argument
Mr. Felix Dorairaj, counsel for the appellant, first submitted that the appellant
has complied with its obligation to the respondent to hand over vacant possession
of the said building to the respondent on time. At that time, the appellant
had, at its own cost and expense, laid all the pipes and cables for connection
of water and electricity to the said building as well as having applied to
the appropriate authorities for such connection in accordance with cl. 17(1)
of the S & P Agreement. He then stressed that the appellant is not responsible
to energize the water and electricity flow into the building. To support this,
he relied on r. 12(1)(l) of the Housing Developers (Control and Licensing)
Rules 1970 (1970 Rules) that requires the developer "shall at his own costs
and expenses cause the connection of electricity, water and sewerage mains
of the Appropriate Authority or public authority with the internal electricity,
water and sewerage mains of the housing accommodation erected for the purchaser".
To top this, he cited this court's decision in Salmah binti Sulaiman & Anor
v. Metroplex Development Sdn Bhd [1997] 2 CLJ 148 where, this court has declared:
We agree with Siti Norma Yaakob J that the Rule speaks of connection of the
electrical and water mains and that the respondent's obligation was only to
connect electricity and water mains to the internal electricity and water
mains and not the flow of water and electricity.
In short, what the appellant is maintaining is that the developer is only
obliged "to connect the electricity and water mains to the internal mains
of the said building; the flow of water and electricity is the responsibility
of the relevant authorities".
Respondent's Contention
Mr. K.C. Cheah, counsel for the respondent, was swift to identify the fallacy
of the appellant's argument that relied on an out-dated rule or regulation.
He enlightened this court that the 1970 Rules has been repealed. And subsequent
to this, there has been four amendments to the Housing Developers (Control
and Licensing) Rules, the latest is the Housing Developers (Control and Licensing)
(Amendment) Regulations 2002. But since this case evolved between the period
of 1990 (the date of the S & P Agreement) and 1992 (the date when vacant possession
was supposed to be delivered) the Housing Developers (Control and Licensing)
Regulations 1989 (1989 Regulations) should be applicable. In fact, the entire
terms and conditions in the S & P Agreement are pari materia to the mandatory
formatted sale and purchase agreement set out in Schedule G of the 1989 Regulations
where all developers had to adopt when selling their developed properties.
Under cls. 20(1), 20(2) and 21(1) of the S & P Agreement, as spelt out in
the earlier part of this judgment, the appellant when delivering vacant possession
must have water and electricity supply connected to the said building. This
means that the appellant, as developer, must energize the water and electricity
flow into the said building. To support this contention, Mr. Cheah cited a
number of High Court authorities which I shall dwell into in the latter part
of this judgment.
Analysis
With such disclosure, at the outset, it is clear that the appellant has relied
on an out dated 1970 Rules where r. 12(1)(l) therein merely states:
provisions binding on the licensed housing developer that he shall at his
own costs and expenses cause the connection of electricity, water and sewerage
mains of the Appropriate Authority or public authority with the internal electricity,
water and sewerage mains of the housing accommodation erected for the purchaser.
After the 1970 Rules were repealed, the Housing Developers (Control And Licensing)
Regulations 1982 (1982 Regulations) came into force. The 1982 Regulations
requires every sale and purchase agreement for houses constructed and sold
within the definition of the said Act to comply with the prescribed formatted
sale and purchase agreement set out in Schedule E thereof. And cl. 15(1) of
the prescribed agreement states:
The Vendor shall at its own cost and expense cause to be laid all necessary
water, electricity and sewerage mains to serve the said Building and undertakes
to apply for at its own cost and expense the connection of the internal water,
electricity and sanitary installations of the said Building to the water,
electricity and sewerage mains of the Appropriate Authority.
Then cl. 18(1) spells out:
The said Building shall be completed by the Vendor and vacant possession delivered
to the Purchaser within twenty-four (24) calendar months from the date of
this Agreement.
In April 1989, the 1982 Regulations were replaced by the 1989 Regulations.
Clause 20(1) in the formatted sale and purchase agreement listed under Schedule
G of the 1989 Regulation demands:
The said Building shall be competed by the Vendor and vacant possession, with
the connection of water and electricity supply to the said Building, shall
be handed over to the Purchaser within twenty four (24) calendar months from
the date of this Agreement.
Then cl. 20(2) states that:
If the Vendor fails to hand over vacant possession of the said Building, together
with the connection of water and electricity supply to the said Building,
in time, the Vendor shall pay immediately to the Purchaser liquidated damages
to be calculated from day to day at the rate of ten per centum (10%) per annum
of the purchase price.
From the above, one can observe that the phraseology with regard to water
and electricity supply is tied-up with vacant possession and the demand for
such amenities to be supplied and connected to the building constructed has
changed since the 1970 Rules and the 1982 Regulations. The 1989 Regulations
requires the developer to complete and hand over vacant possession of the
building within a specific time "with the connection of water and electricity
supply to the said Building". As a result of this, a number of High Court
authorities have interpreted this provision in the 1989 Regulations to mean
that "there must be water and electricity supplies actually running through
the internal water pipes, electric lines and power lines in the dwelling house
before the question of whether or not vacant possession has been delivered
could even be considered" - Abdul Malik Hj. Ishak J in Hoya Holding Sdn Bhd
v. Chia Thin Hing & Anor [1994] 4 CLJ 992.
In another case, Lew Yoke Leng & 2 Ors v. Syarikat Kar King Sdn Bhd [2000]
4 CLJ 184, decided by me as judge of first instance, I have also interpreted
cl. 20(1) and (2) of the formatted sale and purchase agreement under Schedule
G of the 1989 Regulations to say that "water and electricity must be connected
to the house before it is considered to be completed with vacant possession
for the purpose of calculating time to hand over the property to the plaintiffs".
I then went on to add that "Simply put: it means when the plaintiffs entered
the house upon delivery of vacant possession and turned on the lights it will
be illuminated when he affixes a bulb to it. I cannot comprehend it to mean
electricity supply only to a sub-station in the housing estate where the house
is erected, be that becomes near or far".
Admittedly, there are cases that were decided otherwise. In Tay Ket @ Chan
Kong Seong v. Bumibakti Development Sdn Bhd [1994] 2 AMR 35:1832, Wan Adnan
Ismail J expressed the following views:
As at February 18, 1987, the defendants had already caused electricity to
be connected to the sub-station. As the developer, the defendants had to build
the sub-station for the supply of electricity to all the houses in the project.
The sub-station had been energized. What was left to be done was for meters
to be installed at the houses within the project. This the defendants could
not do even if they wanted to ... Only LLN can install the meters and connect
the electricity to the houses.
But it must be noted that this case was decided based on the 1982 Regulations
where the words: "with connection of water and electricity supply to the said
Building" are absent. This is evidenced from the statement by the learned
judge who said at p. 1836: "Therefore item 3 of the Third Schedule of the
Housing Developers (Control and Licensing) Regulations 1982 was complied with
as soon as the defendant has energized the sub-station to enable electricity
to be connected to all the houses in the project". Thus, it is my view that
this case was not decided on the same set of laws applicable to the present
case.
This similar approach is shown in Salmah binti Suleiman & Anor v. Metroplex
Development Sdn Bhd (supra), a decision of this court. Zakaria Yatim JCA,
delivering the judgment of this court then, declared that he had "to examine
the relevant provision of the law ... Rule 12(1)(l) of the Housing Developers
(Control and Licensing) Rules 1970" in deciding on the case. But as disclosed,
the 1970 Rules, similar to the 1982 Regulations, does not contain the words
"with connection of water and electricity supply to the said Building" that
is evident in the 1989 Regulations.
But even before the coming into force of the 1989 Regulations, there is already
a line of authorities that differs from the approach of two cases mentioned
above. In Syarikat Lean Hup (Liew Brothers) Sdn Bhd v. Cheow Chong Thai [1988]
1 LNS 74 ; [1988] 3 MLJ 221, Mustapha Hussain J had even decided that under
the 1982 Regulations, vacant possession has to include the connection of water
and electricity to the said house. The Supreme Court affirmed this decision
in 1989.
Then in Kandasamy a/l Sreenivasagam v. Syarikat Muzwina Development Sdn
Bhd [1990] 1 MLJ 15 Abdul Malek J (as he then was) followed and adopted
the approach of Syarikat Lean Hup (Liew Brothers) Sdn Bhd v. Cheow Chong
Thai (supra). Again, this was repeated in Charles Muriel (f) v. Newacres
Sdn Bhd [1994] 2 AMR 23:1145, a decision of Abu Mansor J (as he then was).
From the line of authorities cited, most cases were decided in accordance
with the respective rules and regulations applicable to the facts of each
case. Thus whatever principles and propositions enunciated in these cases
must be considered in the light of those rules and regulations that were applicable.
They cannot be of universal guide for all cases associated with late delivery
of vacant possession of houses classified under the Housing Developers (Control
and Licensing) Act except when the appropriate rules and regulations so applied
are similar. Thus, one must be cautious when relying on such authorities to
support or argue against the scope and extent of water and electricity to
be supplied to the constructed building under the said Act. Here, what sauce
is good for the goose is not necessarily good for the gander. The respective
rules or regulations used in each case must be fully appreciated. In our instant
case, there is no doubt that the 1989 Regulations are applicable. With the
phase "vacant possession of the said Building together with the connection
of water and electricity supply to the said Building" expressly and unambiguously
stated in mandatory statutory provision of cls. 20(1) and (2) of the formatted
agreement set out in Schedule E in the 1989 Regulations and repeated in identical
fashion by cl. 20(1) and (2) in the S & P Agreement, I am convinced that all
those statements expressed by Abdul Malik Hj. Ishak J in Hoya Holding Sdn
Bhd v. Chia Thin Hing @ Cheah Thin Heng & Anor (supra) and me in Lew Yoke
Leng & 2 Ors v. Syarikat Kar King Sdn Bhd (supra) is the correct state of
the law relating to the meaning of this term in respect of the 1989 Regulations.
To add, I would say that vacant possession with connection of water and electricity
to the said building must include the developer's duty to energize the water
and electricity flow into the building. It is not sufficient for the developer
to just lay the pipes and cables for electricity and water to connect the
said building to the sub-station or water mains. The developer must ensure,
at the time of delivery of vacant possession of the said building, that there
is supply of water and electricity ready for tapping into the building.
Conclusion
On these considerations, I am of the view that this appeal should be dismissed
with costs.
My two brother judges have concurred with the grounds as stated above.
|