Sakinas Sdn Bhd v Siew Yik Hau & Anor
HIGH COURT (KUALA LUMPUR)
CIVIL APPEAL NO R1-11-139 OF 2000
ABDUL AZIZ J
19 MARCH 2002
Civil Law Act - Assignment
- Whether deed of assignment an absolute one or by way of charge only -
Right of assignor to sue - Whether necessary to join assignee - Civil Law
Act 1956 s 4(3)
Contract
- Breach - Performance of contract - Purchasers took vacant possession after
agreed date of delivery of vacant possession - Whether purchasers
had accepted performance of the developer's promise at a time other than
the agreed date of delivery of vacant possession - Whether purchasers had
to give developer notice of their intention to claim compensation for late
delivery - Contracts Act 1950 s 56 (3)
Contract
- Damages - Liquidated damages - Damages for late delivery
of vacant possession agreed to in sale and purchase agreement - Liquidated
damages provided by legislation - Whether necessary for purchaser to adduce
evidence of actual loss or damage suffered - Contracts Act 1950 s 75
Equity
- Assignment - Civil Law Act 1956 s 4(3) - Whether deed of
assignment an absolute one or by way of charge only - Right of assignor
to sue - Whether necessary to joint assignee
Land Law
- Housing developers - Damages for late delivery - Whether
purchasers must prove actual damage of loss - Whether method of calculating
liquidated damages as prescribed in Housing Developers (Control and Licensing)
Regulations 1989 was incapable of overriding s 75 of Contracts Act 1950
- Reasonable compensation under s 75 of Contracts Act 1950 - Whether liquidated
damages prescribed in Housing Developers (Control and Licensing) Regulations
1989 constituted reasonable compensation
The respondents entered into an agreement
("SPA") to purchase an apartment from the developer. To finance the purchase
of the apartment, the respondents obtained a loan from CCM and CCM entered
into a deed of assignment with the respondents as security for the loan.
There was a failure on the part of the appellant to hand over vacant possession
of the apartment and to complete the common facilities in time. The respondents
brought an action in the magistrate's court to claim damages for the delay.
The respondents applied for summary judgement and succeeded. The appellant
appealed. The first ground relied by the appellant was that the respondents
did not have the right to sue under the SPA because their rights therein
had been assigned to CCM. CCM had, by its letter of 7 July 1999, consented
to the respondents suing the appellant. The appellant further contended
that by taking vacant possession on 15 September 1998, the respondents had
accepted performance of the appellant's promise at a time other than the
agreed date of delivery of vacant possession, that is, 13 December 1997.
Since the respondents did not give to the appellant notice of their intention
to claim compensation for late delivery on 15 September 1998 pursuant to
s 56(3) of the Contracts Act 1950 ('the CA'), the appellant argued that
the respondents could not claim compensation now. Lastly, the appellant
contended that the respondents were not entitled to summary judgement as
they has not adduced evidence of the actual loss or damage suffered by them
as a result of the delay in completion.
Held, dismissing
the appeal:
(1) It was necessary to determine whether
the assignment in the instant case, which was an assignmnet of a chose in
action, fell within s 4(3) of the Civil Law Act 1956 ('the CLA'). If it
did, then the respondents, being the assignors, did not have the right to
sue. To fall under s 4(3) the assignment must be an absolute assignment
and must not purport to by way of charge only. Even if an assignment purported
to be absolute, it would not fall within s 4(3) of the CLA is it also purported
to be way of charge only. As such, even if the assignment has used the word
'absolutely', it would not fall within s 4(3) of the CLA if the intention
was to give a charge only (see p 506E-H) ; Durham Brothers v Robertson
(1898) 1QB 765 followed.
(2) There were good grounds for saying
that the assignment in the instant case was by way of charge only and therefore
did not fall within s 4 (3) of the CLA. This was because the assignment
was an alternative form of security necessitated by the fact that a charge
under the National Land Code 1965 could not be created as strata title had
not been issued in respect of the apartment. Upon the issuance of the strata
title, a charge would be created and the assignment would then cease. Further,
it was stated in the deed of assignment that the assignment was intended
as security for loan. Since the assignment was intended as security, and
for no other purpose, it could rightly be said to purport to be by way of
charge only (see pp 507G-508A).
(3) In spite of its purporting to be an
absolute assignment, the assignment in this case was clearly intended to
give a charge only. Since the intention was to give a charge only, it could
not at the same time pass all the rights of the assignor so as to render
the assignment as one falling within s 4(3) of the CLA (see p 509C).
(4) Since the assignment did not fall
within s 4 (3) of the CLA, the next issue to consider was the position in
regard to the assignor's right to sue. An assignee was not free to sue for
the debt as he had to make the assignor the party. The reason was to protect
the debtor from being sued again by the assignor. The fact that if the assignee
wanted to sue, he had to join the assignor implied that otherwise, the assignor
would have the right to sue for the debt (see p 509G-H); Durham Brothers
v Robertson followed.
(5) An assignor may sue alone, but the
court, if it deemed fit may compel the assignor to join the assignee. The
compulsion was a matter of procedural requirement and not one that reflected
absence of locus standi. The compulsion was to save the debtor from the
risk of having to pay the same debt twice. It followed that if there was
no such risk, there was no reason to compel the assignor to join the assignee.
It was therefore necessary to consider whether, in the instant case, should
the respondents recover compensation from the appellant, there would be
a risk that CCM would sue the appellant for the same compensation by virtue
of the assignment. By not objecting or by consenting to the respondents
suing the appellant for compensation, CCM must be taken to have relinquished
any interest in the compensation. That being the case, there was no possibility
of CCM bringing an action to claim the compensation (see pp 510F-H, 511C-D);
Three Rivers District Council & Ors v Governor & Company of the Bank
of England [1996] QB 292 followed.
(6) Section 56(3) of the CA did not apply
to the respondent unless, when the contract became voidable on 13 December
1997, the respondents indicated to the appellant that it was acceptable
if the appellant fulfilled its promise at some time. In the instant case,
there was no evidence to that effect (see p 513H-I).
(7) The Federal Court in Selva Kumar
a/l Murugiah v Thiagamjah a/l Retnasamy [1995] 1 MLJ 817 did not decide
that in every case falling under s 75 of the CA. there must be proof of
actual loss or damage. In the first class of the cases, even if there was
no evidence of actual damage or loss, the court ought nevertheless to award
substantial damages not exceeding the sum so named in the contractual provision,
being a sum which was reasonable and fair according to the court's good
sense and fair play. In such cases, the evidence must clearly show some
real loss inherently and that such loss was not too remote but that it would
be difficult for the court to assess damages or the actual damage or loss
because there was no known measure of damages employable. The second class
of cases was where he damage for such loss was not too remote and could
be assessed by settled rules. In such an event, the failure to bring in
further evidence or to prove damages for such actual loss or damage would
result in the court's refusal to award such damages despite the words in
question (see p 515B-C, E-G)..
(8) A case of delay in completion such
as the instant case should be treated as belonging to the first class of
cases, which did not require proof of actual damage of loss. The method
of calculating the liquidated damages for failure to hand over vacant possession
in time was prescribed in the SPA by virtue of the Housing Developers (Control
and Licensing) Regulations 1989, which was a subsidiary legislation. As
such, the method was incapable of overriding s 75 of the CA. In determining
the reasonable compensation under s 75 of the CA, the court ought not to
disregard the fact that the Minister, in balancing the interest of the house-buyers
and the developers, had considered the method prescribed in the SPA to be
a fair method. Therefore, to ensure fairness all round, compensation for
delay in the delivery of vacant possession of houses purchased from housing
developers should be determined by a simple formula as provided in the SPA
Accordingly, the liquidated damages prescribed in the SPA constituted reasonable
compensation and the respondents ought to be given it in full to the limit
prescribed (see pp 516D-H, 517A).
Notes
For a case on whether deed of assignment
an absolute one or by way of charge only, see 1 Mallal's Digest (4th
Ed, 1998 Reissue) para 2627.
For a case on breach of performance of
contract, see 3 (2) Mallal's Digest (4th Ed, 2000 Reissue) para 2041
For cases on liquidated damages, see 3(2)
Mallal's Digest (4th Ed, 2000 Reissue) paras 2492-2503.
For a case on Civil Law Act 1956 s 4(3),
see 6 Mallal's Digest (4th Ed, 1997 Reissue) para 1894
For cases on damages for late delivery,
see 8(2) Mallal's Digest (4th Ed, 2001 Reissue) paras 2448-2449
Cases referred to
Chan Min Swee v Melawangi Sdn Bhd
[2000] MLJU 286 (refd)
Durham Brothers v Robertson
[1998] 1 QB 765 (folld)
Loh Hoon Loi v Ors v Viewpoint Properties
(Sabah) Sdn Bhd [1995] 4 MLJ 804 (refd)
Max-Benefit Sdn Bhd v Phuah Thean An
& Onor [2001] 1 MLJ 553 (folld)
Nouvau Mont Dor (M) Sdn Bhd v Faber
Development Sdn Bhd [1984] 2 MLJ 268 (refd)
Pak Ki Yau & Anor v Kumpulan Promista
Sdn Bhd [1999] 6 MLJ 220 (refd)
Philleo Allied Bank (M) Bhd v Bhupinder
Singh a/l Avtar Singh & Anor [1999] 3 MLJ 157
(refd)
Selva Kumar a/l Murugiah v Thiagamjah
a/l Retnasamy [1995] 1 MLJ 817 (refd)
Tan Yang Long & Anor v Newacres Sdn
Bhd [1992] 1 MLJ 289 (refd)
Three Rivers District Council & Ors
V Governor & Company of the Bank of England [1996]
QB 292 (folld)
Legislation referred to
Civil Law Act 1956 s 4(3)
Contracts Act 1950 ss 56(3), 75
Housing Developers (Control and Licensing)
Act 1966
Housing Developers (Control and Licensing
) Regulations 1989 reg 11, Sch H
Judicature Act 1873 ss 25(6), 26(6)
David Lee (IN Jeganathan
with him) (SK Yeoh & Jeganathan) for the appellants.
Amir Nordin (Khairuddin Ngiam & Tan)
for the respondents.
Abdul Aziz J:
This appeal from the magistrate's court concerns the performance of a sale
and purchase agreement dated 14 October 1994 ('the agreement') whereby the
appellants, who were developing a condominium, agreed to sell an apartment
in the condominium to the respondents, and the respondents agreed to purchase
it. The agreement was in accordance with that prescribed under reg 11 of,
and in Sch H to, the Housing Developers (Control and Licensing) Regulations
1989 made under the Housing Developers (Control and Licensing) Act 1966,
as the mandatory contract for the sale and purchase of a housing accommodation.
There was failure on the part of the appellants
to hand over vacant possession of the apartment in time and there was a
corresponding failure to complete the common facilities in time. The delay
was 336 days in both cases, reckoned from the date when vacant possession
should have been delivered, to the date when vacant possession should have
been delivered, to the date when it was actually delivered. For failure
to hand over vacant possession in time, cl 22(2) of the agreement provided
that 'the vendor shall pay immediately to the purchaser liquidated damages
to be calculated from day to day a the rate of ten per centum (10%) per
annum of the purchase price'. The purchase price was RM167,000. For failure
to complete the common facilities in time, cl 24(1) provided for the payment
of liquidated damages in the same terms and at the same rate, but of 20%
of the purchase price, not of the full purchase price.
The respondents brought an action in the
magistrate's court to claim damages under the two clauses. Under cl 22(2),
the amount claimed was RM15,373,15. Under cl 24(2), it was RM3,074.63. They
applied for summary judgement and succeeded. Thus the instant appeal.
The appellants rely on three grounds for
maintaining that the summary judgement ought not to have been granted. They
are grounds of law.
First ground: Assignment
To finance the purchase of the apartment,
the respondents obtained a loan from a finance company, Credit Corp (M)
Bhd ('CCM'). Because an individual strata title had not been issued for
the apartment to enable it to be charged under the National Land Code 1965
9('the NLC') as security for the loan, CCM entered into a deed of assignment
with the respondents which, according to recital (4), CCM has agreed to
accept as security for the loan.
What the respondents assigned, according
to cl 1. were their 'entire rights, title and interests in and to the said
property, and the full and entire benefit of the sale agreement together
with the full benefit granted thereby, and all stipulations therein contained
and all remedies for enforcing the same'. Clause 1 says that the respondents
assigned them 'absolutely'. Those are benefits and rights. As to burdens,
cl 2 provides that the assignees, CCM, shall not 'be required or obligated
in any manner to observe or perform any of the conditions or obligations
of the assignor(s) under or pursuant to the sale agreement'. The burdens
therefore remained with the respondents. Moreover, even as to benefits,
cl 2 also provides that CCM was not required or obligated 'to present or
file any claim, or to take any other action to enforce the terms of the
sale agreement'. Thus, although 'all remedies for enforcing the [agreement]'
had been assigned to CCM purportedly 'absolutely', they were not obliged
to seek those remedies. So although the right to sue for compensation for
delay to complete had been assigned to them, they were not obliged to do
so.
Clause 7 provides that the deed of assignment
shall be revoked by the registration of a first legal charge over the apartment
in favour of CCM. The respondents would then have become the registered
owners of the apartment. The assignment, having then come to an end, the
respondents' rights under the agreement would automatically revert to them.
The assignment was made on 19 May 1995.
The respondents commenced their action on 31 December 1998. On 7 July 1999,
CCM wrote to the respondents, in response to their letter dated 30 June
1999, to 'confirm that we have no objection to your intention to initiate
legal action against the developer pursuant to the sale and purchase agreement
dated 14 October 1994'. That was before the respondents filed their application
for summary judgement and the appellants filed their statement of defence.
The appellants' counsel argued that the
respondents did not have the right to sue under the agreement because that
right had been assigned by them to CCM, and it does not matter if the assignment
was absolute or by way of charge. He argued that for the respondents to
be able to sue, the right to sue must be reassigned to them, if the assignment
was absolute, or the respondents must join CCM, if it was equitable assignment.
As to CCM's consent, he submitted that it was not for the current action
but for an intended action in the future and that in any case mere consent
is insufficient.
I think what the learned counsel for the
appellants meant to say was that whether or not the assignment fell within
s 4(3) of the Civil Law Act 1956 ('the CLA'), the respondents had no right
to sue because what we are concerned with here is not the assignment of
a debt or a chose in action but one aspect of the entire assignment,
namely the assignment of 'all remedies for enforcing the same' or, to put
it simply, the right to sue. The implication is that if what we were concerned
with here was the assignment of a debt or chose in action, then it would
make a difference whether or not it fell under s 493) of the CLA.
Although the right to sue is included
in the subject of the assignment, I do not think it is right to single it
out and give it a treatment of its own as a thing assigned, and a treatment,
at that, that is unrelated to the nature of the assignment of the debt or
chose in action that is the primary subject of the assignment. That is because,
to my understanding, the position as to the right to sue must depend on,
and is the consequence of the nature of the assignment of the primary subject.
Take the case of an assignment that falls within s 4(3) of the CLA, which
provides, as far as material, as follows:
Any absolute assignment, by writing,
under the hand of the assignor, not purporting to be by way of charge
only, of any debt or other legal chose in action, of which express notice
in writing has been given to the debtor, ... shall be, and be deemed to
have been, effectual in law ... to pass and transfer the legal right to
the debt or chose in action, from the date of the noticed, and all legal
and other remedies for the same, from the power to give a good discharge
for the same, without the concurrence of the assignor.
It can be seen that the passing and transfer
of 'all legal and other remedies' follows the passing and transfer of the
legal right to the debt or chose in action as a consequence of the nature
and incidents of the assignment. Legal and other remedies, which import
the right to sue, do not have to be included in the subject of the assignment,
and I do not think it should make any difference in the position as to the
right to sue if in a particular assignment, as in this case, the right to
sue happens to be included within the scope of the subject of the assignment.
So, I think it is necessary to determine whether the assignment in this
case, which is not an assignment of a debt but is an assignment of a chose
in action, falls within s 4(3) of the CLA because, if it falls within s
4(3) of the CLA, then the respondents being the assignors, do not have the
right to sue.
To fall under s 4(3), the assignment must
be an absolute assignment and must not purport to be by way of charge only.
In Durham Brothers v Robertson [1898] 1 QB 765, Chitty LJ, speaking
of s 26(6) of the Judicature Act 1873, which was the precursor of our s
4(3) of the CLA, said at p 771: ' It is requisite that the assignment should
be, or at all events purport to be, absolute, but it will not suffice if
the assignment purports to be by way of charge only'. I would take that
to mean that even if an assignment purports to be absolute it does not fall
within s 4(3) if it also purports to be by way of charge only.
In Nouvau Mont Dor (M) Sdn Bhd v Faber
Development Sdn Bhd [1984] 2 MLJ 268, Seah FJ, delivering the judgement
of the Federal Court, said at p 270:
It is plain that in every case of this
kind, all the terms of the instrument must be considered; and whatever
may be the phraseology adopted in some particular part of it, if, on consideration
of the whole instrument, it is clear that the intention was to give a
charge only, then the action must be in the name of the assignor.
It is a statement of principle about an
assignment that would not fall within s 4(3). The emphasis is on finding
a clear intention to give a charge only upon consideration of all the terms
of the instrument. The actual phraseology does not matter. I would take
that to mean that even if the assignment were to use the word 'absolutely'
it would not fall within s 4(3) of the CLA if the intention was to give
a charge only. There is substantial consistency in implied meaning between
that statement and Chitty LJ's statement that I quoted before.
As a statement of principle about an assignment
that would fall within s 4(3) of the CLA, Seah FJ went on to say:
While, on the other hand, if it is clear
from the instrument as a whole that the intention was to pass all the
rights of the assignor in the debt or chose in action to the assignee,
then the case will come within s 25 and the action must be brought in
the name of the assignee.
The question that I need to consider now
is whether the assignment fails within s 4(3). Is it an 'absolute assignment
... not purporting to be by way of charge only'? In Max-Benefit Sdn Bhd
v Phuah Thean An & Anor [2001] 1 MLJ 553, where the assignment was in
terms and circumstances similar to that in this case, Vohrah J (as he then
was) held that the assignment did not fall within s 4(3) of the CLA because
it was in effect not absolute but was conditional as it was merely to secure
a loan and therefore was by way of charge only. In Chan Min Swee v Melawangin
Sdn Bhd [2000] MLJU 286, where the assignment was also to provide security
for a loan pending the registration of a charge when title to the property
was eventually issued, and where the purchaser-assignor sued the developers,
the developers were not prepared to submit that the assignment was an absolute
agreement (see p13b-c). The case was considered on the basis that the assignment
did not fall within s 4(3) of the CLA. In that case, three cases were cited
where the High Court held that the assignment, which was made for the same
purpose and in the same circumstances as those in this case, did not fall
within s 4(3) of the CLA either because it was not an absolute assignment
or because it was by way of a charge. The cases are Pak Ki Yau & Anor
v Kumpulan Promista Sdn Bhd [1999] 6 MLJ 220, Loh Hoon Loi & Ors
v Viewpoint Properties (Sabah) Sdn Bhd [1995] 4 MLJ 804, and Tan
Yang Long & Anor v Newacres Sdn Bhd [1992]1 MLJ 289.
I think there are good grounds for saying
that the assignment in this case, whether or not it is an absolute assignment,
is by way of charge only and therefore does not fall within s 4(3) of the
CLA. The assignment is an alternative form of security necessitated by the
fact that the apartment had no title to enable it to be charged under the
NLC as security. If the apartment had a title, the title would have been
charged under the NLC as security for the loan and there would have been
no need for an assignment. The assignment is the second best substitute
for a charge because a charge is not yet possible and it therefore serves
the same kind of purpose as a charge. When title is eventually available,
the apartment would be charged and the assignment would cease. Recital (4)
in the deed of assignment says that it is intended as a security for the
loan. The assignment being intended as a security, and for no other purpose,
it can rightly be said to purport to be by way of charge only.
However, in Nouvau Mont Dor, where
the assignment clause was in the same terms as those in this case and the
reason for and purpose of the assignment were the same, the Federal Court
held that the assignment was an absolute assignment and not purporting to
be by way of charge only. This is what Seah FJ said at p 271:
Looking at the whole document of 18
February 1978 and bearing in mind the provision of s 6 of the Act, and
our opinion, the document was an absolute assignment and not purporting
to be by way of charge only within the meaning of s 4(3) of the Civil
Law Act 1956. The assignment was in terms absolute in the sense that the
assignor (appellant) intended to pass and transfer to the assignee (Public
Bank) absolutely the beneficial interest as well as all the rights title
and interest in the sale agreement dates 1 April 1977 and the remedies
of enforcing them. The instrument clearly purported and was intended in
point of form, to be an absolute assignment because of the use of the
word 'absolutely' in cl 1 thereof (see Fry LJ in Comfort v Betts
[1891] 1 QB 737 at p 740). If the assignment was an absolute one (not
purporting to be by way of charge only) the fact that is had the effect
of passing to the assignee the rights title and interest of the assignor
in the sale agreement and the beneficial interest of the assignor in the
said property under the said sale agreement by way of security only did
not derogate from the absolute character of that assignment (Hughes
v Pump House Hotel Co Ltd [1902] 2 KB 190 and Comfort v Betts).
From the last sentence, I gather that
the Federal Court recognized that the assignment was by way of security.
I am unable to say whether the Federal Court viewed that fact as being tantamount
to the assignment purporting to be by way of charge. What is clear
is that to the Federal Court it did not matter that the assignment was by
way of security. What mattered was the fact that the assignment was by way
of security. What mattered was the fact that the assignment was an absolute
assignment, and being an absolute assignment, it fell within s 4(3) of the
CLA. It almost seems as if to the Federal Court the phrase 'not purporting
to be by way of charge only' does not constitute a separate requirement
but is one that depends on whether the assignment was an absolute assignment.
In other words, an absolute assignment cannot at the same time be one that
purports to be by way of charge only. If it is an absolute assignment, it
is not necessary to consider whether, by virtue of its being by way of a
security, it is also one that purports to be by way of charge only, because
being an absolute assignment, it cannot be seen as purporting to be by way
of charge only, but has to be seen as not purporting so to be. That is what
I would, from the passage, conclude the thinking of the Federal Court to
be. As to why the Federal Court concluded that it was an absolute assignment,
the understanding that I form from the second and third sentences is that
to the Federal Court 'the assignor (appellant) intend to pass and transfer
to the assignee ('Public Bank') absolutely...' because of the use of the
word 'absolutely' in the assignment clause.
In that passage at p 271, the Federal
Court was actually applying the principles in evaluating the particular
document before it. If my understanding of the thinking in that passage
and my understanding of the statement of principle in the passage and my
understanding of the statement of principle in the passage at p 270 that
I have quoted is correct, there appears to be an inconsistency between the
statement of principle and the manner in which it was applied to the particular
document. I am faced with the choice of either following the perceived thinking
that went into the evaluation of the particular document or following the
statement of principle, and I think the correct course is to follow the
statement of principle.
Like Vohrah J in Max-Benefit, I
see the assignment in this case as clearly intended to give a charge only
in spite of its purporting to be an absolute assignment. It therefore does
not fall within s 4 (3) of the CLA. It being clear that the intention was
to give a charge only, it cannot at the same time be the intention to pass
all the rights of the assignor so as, according to the statement of principle,
to render the assignment as one falling within s 4(3) of the CLA.
I would mention that in Phileo Allied
Bank (M) Bhd v Bupinder Singh a/l Avtar Singh & Anor [1999] 3 MLJ 157,
which involved an assignment that purported to be an absolute assignment
and that was in terms similar to those in this case, the Court of Appeal
at p 3121, lines 20-30, held that the assignment was an equitable charge.
The assignment not falling within s 4(3)
of the CLA, what then is the position as the right to sue? The position
will be as what it was before the enactment of s 25 (6) of the Judicature
Act 1873. The law then was as thus stated by Chitty LJ at pp 769-770 of
Durham Brothers:
As is well known, an ordinary debt or
chose in action before the Judicature Act was not assignable so as to
pass the right of action at law, but it was assignable so as to pass the
right to sue in equity. In his suit in equity the assignee of a debt,
even where the assignment was absolute on the face of it, had to make
the assignor, the original creditor, party in order primarily to bind
him and prevent his suing at law, and also to allow him to dispute the
assignment if he thought it.
Although the second sentence in the passage
speaks of the assignment of a debt, it should apply equally, in my opinion,
to the assignment of a chose in action. The state of the law as revealed
by the passage focuses on the freedom to sue of the assignee, not the assignor.
The assignee was not free to sue for the debt. He had to make the assignor
a party, and the reason he had to make the assignor a party was one that
had the protection of the debtor in mind, that is, to prevent the assignor
also suing the debtor at law. The fact that if the assignee wanted to sue,
he had to join the assignor so that the assignor would be prevented
from suing, implies that otherwise the assignor would have a right to sue
for the debt. This implication is fortified when consideration is
given to Chitty LJ's saying that the assignment did not pass the right of
action at law, but only passed the right to sue in equity. What happened
then to the right of action at law? It could only have remained with the
assignor.
In the passage earlier cited at p 270
of Nouvan Mont Dor, Seah FJ said that 'the action must be in the
name of the assignor', which I would take to mean by the assignor in his
name. It cannot mean by the assignee in the name of the assignor because
then the position would be no different from that under an assignment that
falls within s 4(3) of the CLA, where, according to Seah FJ at p 269, the
action should be brought by the assignee in his own name or 'by the assignee
in the name of the assignor'.
In Max-Benefit, Vohrah J held that
since the assignment in this case not falling within s 4(3) of the CLA,
I should have been disposed to hold that the respondents had the right to
sue and could exercise that right even without the consent of CCM, the assignee.
But there are authorities that say otherwise.
These authorities were considered by Abdul Malik Ishak J in Chan Min
Swee, with the resulting conclusion at p 21 that the position at common
law is that the assignor cannot sue without joining the assignee.
There is, however, at p 18 of the judgement,
an enlightening passage from the judgement of Straughton LJ in Three
Rivers District Council & Ors v Governor & Company of the Bank of Englad
[1996] QB 292. It is as follows:
The issue is, whether the assignor of
a chose action retains a cause of action, when the assignment is equitable.
All are agreed that, as a procedural requirement, he may if the court
thinks fit be compelled to join the assignee as a party; so too an equitable
assignee who sues alone may be required to join the assignor. In either
case the effect is to avoid double jeopardy, to save the debtor from the
risk that he may have to pay twice.
It implies that an assignor may sue alone,
but the court if it thinks fit, may compel him to join the assignee. The
court may not think it fit to so compel him. The compulsion is only a matter
of procedural requirement, not one that reflects absence of locus standi,
and the reason for the compulsion is to save the debtor from the risk of
having to pay the same debt twice. It would follow that if there is no such
risk, there is no reason to compel the assignor to join the assignee and
he should not be so compelled and he may sue alone.
It is therefore necessary to consider
whether, should the respondents recover compensation from the appellants,
there would be a risk that CCM would sue the appellants for the same compensation
by virtue of the assignment and would succeed, so that the appellants would
have to pay it again to CCM. This requires a consideration of the effect
of CCMs letter of no objection of 7 July 1999.
Learned counsel for the appellants submitted
that because the letter was given after the respondents commenced their
action against the appellants and referred to 'your intention to initiate
legal action' and not to the action that had been initiated, the letter
was meant for some other action in the future and not for the current action.
It is true that the letter did not specifically
point to the action that the respondents had commenced. It was in response
to a letter of the respondents dated 30 June 1999. What action CCM intended
in their letter can only be conclusively determined by a perusal of the
respondent's letter, which has, unfortunately, not been exhibited. But CCM's
letter was exhibited in connexion with para 6 of the respondents' affidavit
dated 12 March 2000 to support the respondents' averment in that paragraph
that they had the capacity to bring the present action, which averment was
made in response to the appellants' contention that the respondents had
no capacity because of the assignment, and in that paragraph, the respondents
affirmed that the letter gave them consent to bring the current action.
I take the respondents' word for it. I reject the possibility that the respondents
had exhibited a letter meant otherwise than for the current action. I also
take it as a certainty that in their letter to CCM, the respondents informed
CCM of the purpose of the action, that is, to recover compensation for delay
in completion.
By not objecting or by consenting to the
respondents' suing for compensation, CCM must be taken to relinquish any
interest in the compensation. That being the case, I am unable to see the
possibility of CCM bringing an action to claim the compensation or of their
succeeding in recovering the compensation from the appellants after the
respondents have succeeded in doing so.
In any event, the letter of consent apart,
I am unable to see CCM ever wanting to sue the appellants for compensation
for delay in completion. They have indicated in cl 2 of the deed of assignment
that they are not obliged to enforce the terms of the agreement. That clause
must have been inserted out of fear that the respondents would compel them
to sue the appellants for any breach, such as the breach in this case, and
the fear must have arisen from the recognition that the benefit of such
a suit would not be theirs but the respondents'. And that is so because
their interest is only in the apartment as security. Their only concern
is to sell it should the respondents default under the loan agreement, so
as to recover the loan. Had there been a title, the apartment would have
been charged, and there would have no assignment of the respondents' rights
under the agreement, and there would have been no question of CCM suing
the appellants under the agreement. That would also be the position when
the title is eventually available. The apartment would be charged and the
assignment would cease and there would be no question of CCM suing the appellants
for anything under the agreement. The ultimate security for CCM is a charge,
having which, they would have no involvement with the agreement. They would
have no need - indeed they would not be able - to sue the appellants for
compensation for late completion. It cannot be that having an assignment
as an alternative security, CCM would have need to sue the appellants for
such compensation.
I am, therefore, confident that if the
respondents succeeded in recovering compensation from the appellants, there
would be no risk that CCM will also sue the appellants for the compensation
or that they will succeed. The respondents may therefore sue the appellants
without being required to join CCM. I do not think CCM are interested in
the compensation. Their only concern is that the respondents service the
loan faithfully. If the respondents should default, they will resort to
a sale of the apartment to recover the loan Suing for the compensation for
delay will not benefit CCM because, for one thing, I think that CCM recognized
that the compensation rightly belongs to the respondents, and CCM are not
likely to take on a suit that will not benefit them. Neither can the respondents
compel them to sue, because of cl 2. So, if the respondents were to be held
to have no locus standi to sue, it would be manifestly unjust to them. They
would only be able to sue when the assignment comes to an end when they
have settled their loan or when the apartment is charged under the NLC upon
the issue of title to it, whichever is the earlier. By that time, their
suit might encounter problems of limitation.
Second ground: Notice of intention
to claim compensation
Vacant possession of the apartment should
have been given on 13 December 1997. It was not given on that date. According
to para 6(iii) of the respondents' statement of claim, the date of delivery
of vacant possession was 15 September 1998, which was the date of the appellants'
notice of delivery of vacant possession. It is not disputed that the respondents
responded to the notice and took vacant possession accordingly.
Learned counsel for the appellants submitted
that according to s 56(3) of the Contracts Act 1950 ('the CA'), the respondents
cannot claim compensation for late delivery of vacant possession because
at the time when they took vacant possession, they did not give to the appellants
notice of their intention to claim compensation.
Subsection (1) of s 56 of the CA provides
as follows:
When a party to a contract promises
to do a certain thing at or before a specified time, or certain things
at or before specified times, and fails to do any such thing at or before
the specified time, the contract, or so much of it as has not been performed,
becomes voidable at the option of the promisee, if the intention of
the parties was that time should be of the essence of the contract.
As the intention of the appellants and
the respondents was that time should be of the essence of the contract,
the agreement became voidable at the option of the respondents when the
appellants failed to deliver vacant possession on 13 December 1997.
Subsection (3) then comes into play.
It says:
If, in case of a contract voidable
on account of the promisor's failure to perform his promise at the time
agreed, the promisee accepts performance of the promise at any time
other than that agreed, the promisee cannot claim compensation for any
loss occasioned by the non-performance of the promise at the time agreed,
unless, at the time of the acceptance, he gives notice to the promisor
of his intention to do so.
The subsection applies 'If... the promisee
accepts performance of the promise at any time other than that agreed'.
Where it applies, the promisee cannot claim compensation unless he gives
notice of his intention to do so and the notice is given 'at the time of
the acceptance', that is, at the time when he 'accepts performance of the
promise at any time other than that agreed'.
The question to be answered in this case
is, did the respondents accept performance of the appellants' promise at
any time other than that agreed, that is, at any time other than 13 December
1997?
Learned counsel for the appellants' stand
is that by taking delivery of vacant possession on 15 September 1998, the
respondents accepted performance of the appellants' promise at a time other
than the agreed date, 13 December 1997, and that since on 15 September 1998,
the respondents did not give notice of intention to claim compensation for
late delivery, they cannot claim compensation.
In my opinion, the words 'at any time
other than the agreed' do not refer to the act of accepting performance
of the promise, but refer to the performance of the promise itself. The
words, 'If ... the promisee accepts performance of the promise at any time
other than that agreed' do not mean that performance has been delayed but
is now completed and the promisee now, at a time later than the agreed time,
accepts the performance. If that were so, and the promisee now gives notice
of intention to claim compensation, the notice cannot be of any practical
use to the promisor, except to enable him to know in advance that there
will be a claim against him and he had better get ready with the money to
pay his lawyers, and the promisee, if the promisee should succeed, which
I do not think is the intended purpose of the notice. The phrase really
means, in my opinion, the promisee accepting, meaning agreeing, that the
promisor who has been in breach as to time may perform his promise at some
other time, which has to be a time later than the time of the promisee's
so agreeing. At the time of the promisee's so agreeing, the performance
has not been completed yet. The promisee says, 'It's all right. Although
the contract is now voidable because of your delay, I will not void it.
You may complete it later, on such and such a date'. At the time that he
says so, the promisee, if he wants to claim compensation for the delay,
must give notice of his intention to claim compensation, otherwise the promisor
is entitled to assume that he will not be liable to any compensation. The
notice is important as it will enable him to come to a commercial decision
whether it is viable for him to go on performing if he is going to have
to pay compensation.
In my opinion, sub-s (3) does not apply
to the respondents unless when the contract became voidable on 13 December
1997, or soon after that, they indicated to the appellants that it was acceptable
to them if the appellants fulfilled their promise at some other time. There
is no evidence as to that.
Third ground: Proof of damages
The appellants contend, relying on s 75
of the CA and the decision of the Federal Court in Selva Kumar a/l Murugiah
v Thiagamjah a/l Retnasamy [1995] 1 MLJ 817, that the respondents are
not entitled to summary judgement because they have not adduced evidence
of the actual loss or damage suffered by them as a result of the delay in
compensation.
Section 75 of the CA provides as follows:
When a contract has been broken, if
a sum is named in the contract as the amount to be paid in case of such
breach or if the contract contains any other stipulation by way of penalty,
the party complaining of the breach is entitled, whether or not actual
damage or loss is proved to have been caused thereby, to receive from
the party who has broken the contract reasonable compensation not exceeding
the amount so named or, as the case may be, the penalty stipulated for.
It is about breach of contract where either
of two circumstances are present. One circumstance is where 'a sum is named
in the contract as the amount to be paid' for the breach. The other is 'if
the contract contains any other stipulation by way of penalty'. It provides
for the party complaining of the breach to be entitled to reasonable compensation
for the breach, but it must not exceed - so it may be equal to - the named
sum or the stipulated penalty. And the party is so entitled 'whether or
not actual damage or loss is proved' to have been caused by the breach.
Whether it is the circumstance of a named sum or of a stipulated penalty,
the treatment is the same. Reasonable compensation is due. It is to be so
whether or not actual damage or loss is proved. To me it means that even
if actual damage or loss is not proved - either because there is no means
of proving it or because the damage or loss is not calculable in monetary
terms - reasonable compensation must be paid, and in that case the concern
of the court is to determine what the reasonable compensation is in the
circumstances. It therefore makes no difference whether the agreed liquidated
damages in this case were to be regarded as a named sum or as a stipulated
penalty.
That is my understanding of s 75 of
the CA, construing it literally.
In Selva Kumar, however Federal
Court held as regards the words 'whether or not actual damage or loss is
proved to have been incurred thereby' that although they are 'unambiguous
and plain', 'the literal construction should not be strictly adhered to
and the words in question should be given a restricted or limited construction'
(see p 1108).
At p 1112, the Federal Court explained
it by saying that those words 'are limited or restricted to those cases
where the court would find it difficult to assess damages for the actual
damage or loss as distinct from or opposed to all other cases, when a plaintiff
in each of them will have to prove the damages or the reasonable compensation
or the actual damages or loss in the usual ways'.
As to the first class of case, the Federal
Court held at p1113 that 'the precise attributes of such contracts in which
it is difficult for a court to assess damages or the actual damage or loss
are cases where there is not known measure of damages employable, and yet
the evidence clearly shows some real loss inherently and such loss is not
too remote, then the court ought to award, not nominal damages, but instead,
substantial damages not exceeding the sum so named in the contractual provisions;
a sum which is reasonable and fair according to the court's good sense and
fair play'.
As to the second class of cases, the Federal
Court held at p 1114 that 'in any case where there is inherently any actual
loss or damage from the evidence or nature of the claim and damage for such
actual loss is not too remote and could be assessed by settled rules, any
failure to bring in further evidence or to prove damages for such actual
loss or damage will result in the refusal of the court to award such damages
despite the words in questions'.
Selva Kumar
was a case of the sale of a medical practice for RM120,000
where the purchaser, having paid RM96,000 (leaving only RM24,000 to be paid
by six monthly instalments) refused to go on paying and the vendor sought
to forfeit the sum of RM96,000 as agreed liquidated damages for the purchaser's
breach. The Federal Court treated the case as belonging to the second type,
and since there had been no evidence to prove actual loss, it decided that
the vendor was only entitled to forfeit RM12,000 of the sum of RM96,000,
being 10% of the purchase price, which has been paid on the signing of the
agreement and was treated as a deposit or earnest money.
It is therefore clear that the Federal
Court in Selva Kumar did not decide that in every case falling under
s 75 of the CA there must be proof of actual loss or damage. In the first
class of cases, even if there is no evidence of actual damage or loss, the
court ought nevertheless to award 'substantial damages not exceeding the
sum so named in the contractual provision' being 'a sum which is reasonable
and fair according to the court's good sense and fair play'. The first class
of cases are cases where 'the evidence clearly shows some real loss inherently
and such loss is not too remote' but 'it is difficult for a court to assess
damages or the actual damage or loss' because 'there is no known measure
of damages employable'.
In a great number of cases in this country,
home ownership is acquired through purchase from housing developers with
the help of financing from financial institutions on the security of the
property. The developer is paid the purchase price in specific stages according
to the progress of construction. If there is delay in the completion of
the construction, the purchaser may suffer in various ways. He may have
to commence paying the loan instalments without getting the enjoyment of
the house. If he is renting a house, he will have to pay both the rental
and the loan instalments, whereas if there had been no delay in completion,
he could have moved into his new house and pay the loan instalments, without
also having to pay rental. If he bought the house as an investment, he would
have been deprived of the rental that he would have got from renting out
the house. The person who is already living in his own house but is hoping
to live in a better new house, and rent out his present house, will be deprived
of early enjoyment of the new house and the receipt of rental from his present
house, while having to pay his loan instalments. Whatever may be the circumstances
and intention of the house buyer, it can be said that in every case, a delay
in compensation would deprive the purchaser, for the period of delay, at
least of the rental that he would have got from the house had he chosen
to rent it out. It would be a substantial loss in theory. But how can he
prove what the rental would be for the house, in the area and at the particular
time, if, for example, the whole project is delayed so that there is no
case on which to base a fair comparison?
Depending on the skill which a claim is
fought, a trial of the question of rentability may result in different awards
of compensation in respect of the different properties in the same housing
development, whereas the delay suffered is the same. Moreover, there is
the element of hardship in the case, for example, of the person who would
have to pay both the rental of his present accommodation and the loan instalments.
If there no delay, he would have to pay only one thing. He is a man living
on a tight budget. He will have to suffer something from having to pay for
two things. How will this suffering be quantified?
For those reasons, I am of opinion that
a case of delay in completion such as the present case should be treated
as belonging to the first class of cases, which does not require proof of
actual damage or loss. There has to be real loss that is not too remote,
but it is difficult for the court to assess the actual loss because there
is no known measure of damages employable. What the court needs to determine,
in the absence of proof of actual loss, is what is the reasonable compensation,
applying good sense and fair play.
As has been seen, the sale and purchase
agreement in this case is a mandatory one that is prescribed by statute.
The method of calculating the liquidated damages of failure to hand over
vacant possession in time is prescribed in the agreement by regulations
made by the minister. I agree with learned counsel for the appellants that
the method, being prescribed by subsidiary legislation, is incapable of
overriding s 75 of the CA and its effect. But in determining reasonable
compensation under s 75 of the CA, the court ought not to disregard the
fact that the minister, in is wisdom balancing the interests of house buyers
and developers, and after considering the advice of his advisers, considered
that the method prescribed in cl 22(2) is a fair method. I think it is highly
desirable, to ensure fairness all round, that compensation for delay in
the delivery of vacant possession of houses purchased from housing developers
should be determined by a simple standard formula. That is what cl 22(2)
has provided. It prescribed a certain percentage per annum of the purchase
price, which I think is an acceptable principle. The percentage is 10%.
I do not see any point in arguing that the rate should instead be 9% or
8% or 7%. 10% does not strike me as excessive. As learned counsel for the
respondents said, 10% is an acceptable benchmark in the business community.
The same applies to the formula in cl
24(2) in respect of the common property which employs a lower rate of 10%
of 20% of the purchase price.
To conclude, I hold that the liquidated
damages prescribed by cll 22(20 and 24(2) constitute reasonable compensation
and that the respondents ought to be given it in full to the limit prescribed.
As the appellants fail on all grounds,
they fail to show that the respondents are not entitled to summary judgement,
I dismiss the appeal with costs.
Appeal dismissed.
Reported by Lim
Lee Na
|