PYWATECH (M) SDN BHD V. VISTA-PRISMA SDN
BHD
HIGH COURT MALAYA, KUALA LUMPUR
[ORIGINATING SUMMONS NO: S5-24-2345-2002]
ABDUL MALIK ISHAK J
14 FEBRUARY 2003
JUDGMENT
Abdul Malik Ishak J:
Introduction
By way of an originating summons in encl. (1) the plaintiff sought for
the following prayers:
(1) for a declaration that the defendant has breached the sale and
purchase agreement dated 8 September 1997 (hereinafter referred to as the
"said agreement") and that the plaintiff has rightfully rescinded the said
agreement on 19 April 2002 by way of a letter from the plaintiff's
solicitor or at any date which this Honourable Court thinks fit and proper
or, by way of an alternative, a declaration that the said agreement has
been terminated by virtue of a breach of the said agreement by the
defendant;
(2) that the plaintiff be refunded for the amount of RM20,190.10 being
the 10% deposit paid for the purchase of the land (referring to the
bungalow lot) that was purchased by the plaintiff from the defendant;
(3) further or in the alternative, damages payable to the plaintiff for
the breach of the said agreement by the defendant;
(4) interest at the rate of 8% per annum from 19 April 2002 until the
date of judgment;
(5) interest at the rate of 8% per annum upon the judgment sum that has
been adjudicated from the date of the judgment till the date of full
settlement;
(6) costs of and ancillary costs pertaining to the application payable
by the defendant to the plaintiff;
(7) any other order or relief which this Honourable Court deems fair
and suitable; and
(8) any other order which is regarded as necessary and fair by this
Honourable Court.
The application in encl. (1) was supported by an affidavit of Gan Boon
Kian that was affirmed on 20 June 2002 as seen in encl. 2. Gan Boon Kian was
described as the director of the plaintiff's company. The response to encl.
2 can be seen in encl. 4 which was an affidavit in reply of Lim Choo Kee @
Lim Teck Yow, a director of the defendant's company, who affirmed the
affidavit in reply on 26 July 2002. Enclosure 6 would be in response to
encl. 4 and encl. 6 was the affidavit in reply of Gan Boon Kian that was
affirmed on 22 August 2002.
At the outset, the parties magnanimously agreed that the decision of this
case would bind the two other cases, namely:
(1) originating summons no: S3-24-2330-2002 between C.I. Trading Sdn
Bhd and Vista-Prisma Sdn Bhd; and
(2) originating summons no: S5-24-1248-2002 between Bina Sing Yap Sdn
Bhd and Vista-Prisma Sdn Bhd.
That was indeed a wise move.
I am grateful to the parties because they have magnanimously prepared the
"statement of agreed facts" and it can be found in encl. 8 and I now need to
reproduce them verbatim. It is worded in this way:
1. The Defendant is a private limited company incorporated in Malaysia,
licensed under the Housing Developers Act (Control and Licensing) 1966 and
having its registered address at 5th Floor, Campbell Complex, 98 Jalan
Dang Wangi, 50100 Kuala Lumpur.
2. The Plaintiff and the Defendant have entered into a Sale and
Purchase Agreement dated 08/09/97 (hereinafter referred to as 'the said
agreement') to buy a property known as Plot No. 69, Barbara Forest Park,
Lenggeng for RM201,901.00 subject to the terms and conditions in the said
Agreement. [A copy of the said Sale and Purchase Agreement is found in
Exhibit 'GBK-1' of Enclosure 2].
3. According to Clause 16(1) of the said Agreement, vacant possession
of the said Property must be handed over to the Plaintiff upon completion
of the infrastructure works referred to in Clause 11 which in any case
shall not be later than thirty (30) calendar months from the date of the
Sale and Purchase Agreement.
4. Clause 11(1) of the said Agreement states that the Defendant shall
at its own cost and expense construct or cause to be constructed the Basic
infrastructure in accordance with the requirements and standards of the
Appropriate Authority concerned and the Plaintiff shall be responsible for
the cost and expense in maintaining and constructing all internal drains,
internal roads, septic tank, water pipes, electrical works and internal
infrastructure.
5. Clause 25 of the said Agreement provides that time shall be the
essence of the contract.
6. The Plaintiff has signed a Supplemental Agreement with the Defendant
on 23/03/98 to replace the words 'thirty (30) months' in Clause 16(1) of
the said Sale and Purchase Agreement to 'fifty four (54) months' in
respect of the delivery of vacant possession of the said property.
7. The date for the delivery of vacant possession is on or before
25/02/02.
8. The Defendant failed to deliver the vacant possession to the
Plaintiff on or before 25/02/02.
9. The Plaintiff purportedly terminated the said Agreement and the said
Supplemental Agreement by giving notice of termination dated 19/04/02 to
the Defendant.
10. The Plaintiff has paid a sum of RM20,190.10 being the deposit only
for the Sale and Purchase Agreement.
11. The Defendant has sent various notices via letters dated 15/12/01,
16/01/02 and 28/02/02 requesting for the instalments but the Plaintiff
have not paid despite the notices.
12. The Defendant has further sent out a letter dated 12/04/02
requiring the Plaintiff to take vacant possession failing which vacant
possession would be deemed delivered on 26/04/02.
It must be mentioned here that paras. 10, 11 and 12 as reproduced above
constituted the "supplementary agreed facts" that were added by the parties
at a later stage. That clearly showed the generosity on both sides. It is
apparent that there was a supplemental agreement dated 23 March 1998 but
that supplemental agreement was not alluded to in prayer (1) of encl. (1).
Upon reading encl. 4, I cannot help but notice that the defendant too had by
letter dated 30 April 2002 terminated the said agreement dated 8 September
1997 and the supplemental agreement as well. Exhibit "LCK 5" of encl. 4 is
the letter of termination advanced by the defendant and it is dated 30 April
2002 and it is worded in this way:
VISTA-PRISMA SDN BHD
30th April 2002
PYWATECH (M) Sdn BhdBy A.R. REGISTERED/POST/FAX
No. 5B & C, Jalan Kenari 17/D
Bandar Puchong Jaya
Puchong
47100 Selangor Darul Ehsan
Attn: Mr. Gan Boon Kian
Dear Mr. Gan
RE: TERMINATION OF SALE & PURCHASE AGREEMENT DATED 08/09/1997 &
SUPPLEMENTAL AGREEMENT DATED 23/03/1998
PLOT NO : 16
PROPERTY TYPE : ORCHARD LAND
PROJECT : BARBARA FOREST PARK, LENGGENG
INDIVIDUAL TITLE : H.S.(D) No. 138504 P.T. No. 1221
PURCHASE PRICE : RM201,901.00
We refer to our letter dated 28th February 2002 and regret to note that
you have failed/neglected and/or refused to settle the outstanding payment
within the period stated in the said letter.
Please be informed that by your default you had breached the above Sale
and Purchase Agreement dated 08/09/1997 and the Supplemental Agreement
dated 23/03/1998 and the said Agreements are deemed to be terminated. In
the circumstances we have forfeited your payment of RM20,190.10 as per
Clause 8 of the Sale and Purchase Agreement.
Thank you.
Yours faithfully
VISTA-PRISMA SDN BHD
Sgd. (Illegible)
JAMES T.Y. LIM
Director
The parties too magnanimously agreed and put forward a "statement of
agreed issues" as seen in encl. 7 and it is worded in this fashion:
1. Whether there was a breach of the Sale and Purchase Agreement dated
08/09/97 and the Supplemental Agreement dated 23/03/98 by the Defendant.
2. If the answer for the above is (in the) affirmative, then whether
the breach entitles the Plaintiff to terminate the said Agreement and the
said Supplemental Agreement.
The issues seemed to have been narrowed down and agreed by the parties
but the oral submissions of the learned counsel for both sides brought forth
other matters which were quite germane to the occasion and I will allude to
them in the course of this judgment.
Both the parties also agreed that in the course of submitting on encl.
(1), they are not relying on the Housing Developers (Control and Licensing)
Act, 1966 and the Housing Developers (Control and Licensing) Regulations
1989.
It must be put on record that Mr Arthur Wang Ming Way assisted by Mr Mohd
Azmil bin Md Zain acted for the plaintiff in the present originating summons
as well as for the other plaintiffs in originating summons no:
S3-24-2330-2002 and in originating summons no: S5-24-1248-2002. While Mr
Dallumah Krishna assisted by Mr Tan Foong Luen acted for the defendant in
the present originating summons as well as the other defendants in
originating summons no: S3-24-2330-2002 and in originating summons no:
S5-24-1248-2002.
To The Heart Of The Matter
It was argued that the plaintiff had the right to rescind the said
agreement and the supplemental agreement because the defendant had breached
both these agreements by not delivering vacant possession of the bungalow
lot at Barbara Forest Park, Lenggeng on or before 25 February 2002. Relying
on s. 56(1) of the Contracts Act 1950, it was argued on behalf of the
plaintiff that both these agreements have become voidable at the option of
the plaintiff. And that in exercising its option the plaintiff had chosen to
rescind both these two agreements. It is interesting to note that in Chye
Fook & Anor v. Teh Teng Seng Realty Sdn Bhd[1988] 1 LNS 213; [1989] 1
MLJ 308, Abdul Malek Ahmad J (now a Senior Federal Court judge) was of the
view that under s. 56 of the Contracts Act 1950 a contract will be construed
to be voidable at the option of the promisee if the intention of the parties
at the relevant point of time is that time is the essence of the contract. I
had occasion to vigorously apply Chye Fook's case when I heard the
case ofKang Yoon Mook Xavier v. Insun Development Sdn Bhd [1995] 2
CLJ 471. Now, inKang Yoon Mook Xavier v. Insun Development Sdn Bhd
(supra), I was of the view that as time was of the essence, the time
fixed to deliver the single-storey low cost house to the purchaser became
the essential condition of the agreement between the parties and that since
the developer had breached that condition, the purchaser had the right to
elect whether to rescind the contract and claim for damages under s. 56(1)
and s. 65 of the Contracts Act 1950 or to treat the agreement as continuing
and to sue for damages. I too held that the purchaser in that case had
rightly exercised his former option and thus he was entitled to terminate
the agreement and obtain the refund of the money which he had paid and also
to secure the post-rescissionary damages as envisaged under s. 76 of the
Contracts Act 1950.
It must be borne in mind that both the agreements inChye Fook's
case and that ofKang Yoon Mook Xavier v. Insun Development Sdn Bhd
(supra) followed the standard formats as prescribed in Schedule E of the
Housing Developers (Control and Licensing) Act 1966 where there were no
provisions providing for the purchasers to terminate the agreements. But
nevertheless it was the submission of the learned counsel for the plaintiff
here that these two cases - referring toChye Fook's case andKang
Yoon Mook Xavier v. Insun Development Sdn Bhd (supra), are applicable
and should be vigorously applied in the context of the principles of law
which they enunciated and that they are of universal application. It was a
submission that was certainly thought provoking. Another interesting case
would be that ofYeow Kim Pong Realty Ltd v. Ng Kim Pong[1961] 1 LNS
157; [1962] MLJ 118, a decision of the Privy Council with the coram of Lord
Hodson, Lord Guest and the Rt Hon LMD De Silva. The facts in that case may
be stated as follows. There the plaintiff, who was the respondent in the
appeal, had on 24 March 1956 entered into an agreement with the defendant,
who was the appellant in the appeal, for the purchase of 22 lots of land. It
was one of the terms of the agreement that an initial payment of $15,000
should be made followed by a further sum of $24,000 on or before 28 June
1956 and a final payment of $27,000 on or before 23 December 1956. The
respondent failed to pay the stipulated $24,000 by the date specified and
the appellant informed the respondent that in consequence thereof the
deposit of $15,000 was forfeited and the contract was to come to an end. The
respondent then asked for an extension of time to pay the said $24,000. The
appellant agreed to an extension of time provided that certain conditions as
laid down in a supplementary agreement were satisfied, namely:
(1) To pay the sum of $5,000 forthwith and the balance of $19,000 to be
paid on or before 31 July 1956.
(2) Construction work on the above land to be commenced within one week
of the date hereof.
(3) Construction must have begun on any land that was sought to be
transferred.
(4) Should there be any breach of the above conditions, the sum of
$5,000 that was paid, was to be forfeited and the extension of time
withdrawn.
The respondent failed to abide by and in accordance to the supplementary
agreement and so the appellant terminated the contract in writing on 1
September 1956 and forfeited the moneys that were paid. The question that
arose for consideration of the court was whether the supplementary agreement
was binding on the respondent. The learned trial judge held that the
supplementary agreement was binding on the parties, and as the respondent
was in breach of it, the learned trial judge dismissed the respondent's
action. The decision of the learned trial judge was subsequently reversed by
the Court of Appeal. On appeal to the Privy Council by the appellant, the
decision of the Court of Appeal was reversed. The Privy Council held that
the supplementary agreement was binding on the parties and that time was of
the essence of the agreement. The Privy Council also held that there was a
breach of the supplementary agreement by the respondent and that the
appellant was entitled to rescind the contract on 1 September 1956 and this
was accordingly done by the appellant.
In brief, the Privy Council in the case of Yeow Kim Pong Realty Ltd v.
Ng Kim Pong (supra) held that the appellant there was entitled to
rescind the supplementary agreement as there was a breach on the part of the
respondent to pay and to commence works as stipulated in the supplementary
agreement and that time too was of the essence of the supplementary
agreement.
Yet another interesting case would be that of Tan Hock Chan v. Kho
Teck Seng[1979] 1 LNS 110; [1980] 1 MLJ 308, a decision of the then
Federal Court (Chang Min Tat FJ, Salleh Abas FJ, and Charles Ho J) and the
facts may be stated as follows. There the respondent was a building
contractor who was employed by the appellant to build 6 units of 3 storeyed
shop houses at the agreed cost of $223,000. Payment for the construction was
by progress payments dependent on the completion of the several stages of
construction. The contractor completed 5 of the 6 shop houses. The
respondent contractor put some work on the sixth shop house but he was
unable to complete it because of a claim by the occupier of the land - the
third party, to ground tenancy rights. The respondent claimed the balance of
the contract price less the amount paid to him under the progress payments
and also for extra work and materials supplied. The learned trial judge
awarded the respondent $5,540 on a quantum meruit and $6,500 assessed as the
reasonable profit which the respondent contractor could expect to make on
that sixth house. The appellant appealed. The then Federal Court held:
(1) that by the appellant's failure to give effective possession of the
lot for the sixth house, the appellant had broken his covenant and the
respondent contractor could rescind the contract;
(2) that the respondent contractor had rescinded the contract when he
served the writ and the statement of claim on the appellant; and
(3) that the claim by the respondent contractor for quantum meruit for
work done and for cost of extras must succeed but the claim for loss of
profits could not succeed and towards this extent the appeal was allowed.
Reference to the case of Beca (Malaysia) Sdn Bhd v. Tan Choong Kuang &
Anor [1986] CLJ 64 (Rep) [1986] 1 CLJ 20, a decision of the then Supreme
Court with a coram of Lee Hun Hoe CJ (Borneo), Wan Suleiman and Seah SCJJ
should also be made. There the then Supreme Court held that the agreement in
that case had become voidable at the option of the purchasers and therefore
the purchasers had elected to rescind the contract and were entitled to the
refund of the deposit. It must be emphasised that the appellants in
Beca's case were housing developers who developed an area of land in
Sandakan at mile 2, Leila Road, Tanah Merah into a commercial and
residential complex known as Leila Komplex. The respondents purchasers had
agreed to buy three units of flats costing $703,685 from the appellants and
on 1 May 1981 paid a deposit of $20,000. It was common ground that the
deposit was made before the issuance of the developers' licence and the sale
advertisement permit on 26 September 1981. The respondents purchasers were
asked to sign the sale and purchase agreement on 23 May 1981 and they
refused. Instead, through their solicitors, the respondents purchasers
claimed for the refund of the deposit on the ground that the deposit was
collected illegally under r. 10(2) of the Housing (Control and Licensing of
Developers) Rules 1980 and that these Rules were made under the Housing
(Control and Licensing of Developers) Enactment 1978 on 23 January 1980 and
were gazetted on 15 May 1980 to come into force on 1 July 1980.
This would be followed by the case of Eng Mee Yong & Ors v.
Letchumanan[1979] 1 LNS 18; [1979] 2 MLJ 212 PC, where Lord Diplock
(delivering the judgment of the Privy Council), in considering the effect of
the failure to perform the contract within the prescribed time, held (see p.
218 of the report):
Time being of the essence of the provisions in the Sale Agreement for
payment of the purchase price, the failure of the caveator to pay on the
due date was a breach of condition which the caveatees were entitled to
elect to treat as bringing the contract to an end.
Now, flowing from all these salient authorities, submissions were made on
behalf of the plaintiff to the effect that the plaintiff was entitled under
the law to rescind the said agreement and the supplemental agreement and
that the plaintiff was further entitled to obtain compensation for any
damages suffered by it during the non-fulfillment of both these two
agreements. And germane to the occasion would be s. 76 of the Contracts Act
1950 which enacts as follows:
76. Party rightfully rescinding contract entitled to compensation.
A person who rightly rescinds a contract is entitled to compensation for
any damage which he has sustained through the non-fulfilment of the
contract.
ILLUSTRATION
A, a singer, contracts with B, the manager of a theatre, to sing at his
theatre for two nights in every week during the next two months, and B
engages to pay her $100 for each night's performance. On the sixth night A
willfully absents herself from the theatre, and B, in consequence, rescinds
the contract. B is entitled to claim compensation for the damage which he
has sustained through the non-fulfilment of the contract.
But the facts of this case showed that both parties were at fault. The
plaintiff only paid the first 10% amounting to RM20,190.10 and subsequently
refused to pay the balance despite repeated demands. The defendant, on the
other hand, was prepared to hand over vacant possession after the deadline
period.
It must be emphasised that the purchase price of the bungalow lot was in
the sum of RM201,901. And that the deadline to hand over vacant possession
of the bungalow lot was on 25 February 2002.
The affidavit in reply in encl. 4 was worth reading. It revealed that the
defendant had sent various notices of demand to the plaintiff to pay the
purchase price in accordance with cl. 5 of the said agreement which was
worded in this way: -
5 SCHEDULE OF PAYMENTS
(1) The Purchase Price shall be paid by the Purchaser to the Vendor by
instalments at the time and in the manner as prescribed in the Fourth
Schedule hereto.
(2) Every notice referred to in the Fourth Schedule requesting for any
payment shall be supported by a certificate signed by the vendor's
Consultant Engineer or Architect or such other consultant in charge of the
project and every such certificate so signed shall be proof of the fact
that the works therein referred to have commenced and or have been
completed as the case may be.
The various notices of demand sent by the defendant may be categorised as
follows: -
(i) notice of demand dated 15 December 2001 as seen in exh. "LCK1" of
encl. 4 showing the sums that were due from stage 2 to stage 6 in the
amount of RM107,525.66 inclusive of accumulated interests;
(ii) notice of demand dated 16 January 2002 as reflected in exh.
"LCK2" of encl. 4 showing the sums that were due from stage 2 to stage 6
amounting to RM108,587.72 inclusive of accumulated interests;
(iii) notice of demand dated 28 February 2002 as reflected in exhibit
"LCK3" of encl. 4 mirroring the sums that were due from stage 2 to stage
6 amounting to RM110,014.86 inclusive of accumulated interests;
(iv) notice of demand dated 12 April 2002 as reflected in exh. "LCK4"
of enclosure 4 showing the total sums that were due amounting to
RM181,710.90 and vacant possession was also given and I will revert to
this in due course; and
(v) notice of demand dated 30 April 2002 as reflected in exh. "LCK5"
of encl. 4 evidencing termination of the said agreement as well as the
supplemental agreement and this has been reproduced earlier in this
judgment.
It must be borne in mind that only after the first four notices as
alluded to above were sent to the plaintiff, did the plaintiff quickly acted
to instruct its solicitors to send their notice of termination dated 19
April 2002 as reflected in exh. "GBK4" of encl. 2 to the defendant. That
notice of termination by the plaintiff was sent to the defendant
notwithstanding the fact that the plaintiff did not comply with the
defendant's notices of demand requesting for payments as alluded to in para.
(i) to para. (iii) of the above. The AR card that accompanied the
plaintiff's notice of termination was exhibited as exh. "GBK4" of encl. 2
and it showed that the plaintiff's notice of termination was received by the
defendant on 29 April 2002.
Now, reverting back to the notice of demand that was sent by the
defendant to the plaintiff dated 12 April 2002 as seen in exh. "LCK4" of
encl. 4, it would be ideal to reproduce that notice of demand as it also
showed that by that notice (which was, in fact, a letter) the defendant
required the plaintiff "to take delivery of vacant possession of the
aforesaid property within 14 days from the date hereof". That notice of
demand (which was, in fact, a letter) was worded as follows: -
VISTA-PRISMA SDN BHD
12th April 2002
Pywatech (M) Sdn BhdBY REGISTERED
No. 5B & C, Jalan Kenari 17/D
Bandar Puchong Jaya
Puchong
47100 Selangor Darul Ehsan
Attn: Mr Gan Boon Kian
Dear Sirs
RE: DELIVERY OF VACANT POSSESSION
PLOT NO : 16
PROPERTY TYPE : ORCHARD LAND
PROJECT : BARBARA FOREST PARK, LENGGENG
INDIVIDUAL TITLE : H.S.(D) No.138504 P.T. No. 1221
PURCHASE PRICE : RM201,901.00
We are pleased to inform you that vacant possession of the aforesaid
property is ready to be delivered to you. Kindly therefore settle your
outstanding amount of RM193,158.42 (as per statement attached) by way of
Bank Draft/cash within fourteen (14) days from the date hereof.
Please be informed that the handing over of the above said property is
subjected to the full settlement of the purchase price (inclusive of your
financiers portion), maintenance/miscellaneous charges and interest on
late payment (if any).
Kindly note that you are required to comply with the above and to take
delivery of Vacant Possession of the aforesaid property within 14 days
from the date hereof. We shall not be held liable for any loss or damage
to the said property upon the expiration of the aforesaid fourteen (14)
days period pursuant to the provisions of the Sale & Purchase Agreement.
Yours faithfully
VISTA-PRISMA SDN BHD
Sgd. (Illegible)
JAMES T.Y. LIM
Director
c.c. M/s Rashid Asari & Co - [Ref: 1181/971/C/RAS(S)/VP/PMSB]
And the statement which was also annexed as exh. "LCK4" of encl. 4 was
worded in this way and the amount computed was not inclusive of the interest
that was leviable:
VISTA-PRISMA SDN BHD
Pywatech (M) Sdn Bhd Date : 12-04-2002
No. 5B & C, Jalan Kenari 17/D Due Date : 26-04-2002
BANDAR PUCHONG JAYA Invoice Number : IV10492
47100 PUCHONG, SELANGOR DARUL EHSAN.
REGISTERED
Dear Sir(s)/Mdm
RE: PLOT NO : 016
PROJECT : BARBARA FOREST PARK, LENGGENG
PURCHASE PRICE : RM 201,901.00
PURCHASER'S NAME : PYWATECH (M) SDN BHD
NOTICE OF PAYMENT
We are pleased to inform (you) that the construction of the said plot
has reached the stage of: PRACTICAL COMPLETION OF BASIC INFRASTRUCTURE
WORKS AND DUE FOR DELIVERY OF VACANT POSSESSION OF THE SAID PLOT as
certified by the Engineer's Certificate enclosed. The progress payments as
shown in the FOURTH SCHEDULE below is due to us:
FOURTH SCHEDULE: - PURCHASER'S OUTSTANDING - FINANCIER'S OUTSTANDING -
TOTAL OUTSTANDING
1. 10% UPON SIGNING OF THE SALE AND PURCHASE AGREEMENT - RM 20,190.10 -
20,190.10
2. 10% AT THE EXPIRY OF TWO CALENDAR MONTHS FROM THE DATE OF THE S & P
AGREEMENT - RM 20,190.10 - 20,190.10
3. 10% THE COMMENCEMENT OF SITE CLEARING FOR ROAD WORKS SERVING THE
SAID PLOT - RM 20,190.10 - 20,190.10
4. 10% THE COMPLETION OF SITE CLEARING FOR ROAD WORKS SERVING THE SAID
RM 20,190.10 20,190.10
5. 10% THE COMPLETION OF EARTHWORKS FOR ROAD WORKS SERVING THE SAID
PLOT - RM 20,190.10 - 20,190.10
6. 10% THE COMPLETION OF CRUSHER-RUN FOR ROAD WORKS SERVING THE SAID RM
20,190.10 20,190.10 PLOT
7. 10% THE COMPLETION OF PREMIXING FOR ROAD WORKS SERVING THE SAID PLOT
- RM 20,190.10 - 20,190.10
8. 10% THE COMPLETION OF WATER RETICULATION SERVING THE SAID PLOT - RM
20,190.10 - 20,190.10
9. 10% THE COMPLETION OF ELECTRICAL CABLING SERVING THE SAID PLOT - RM
20,190.10 - 20,190.10
10. 10% PRACTICAL COMPLETION - OF BASIC INFRASTRUCTURE WORKS AND DUE
FOR DELIVERY OF VACANT POSSESSION OF THE SAID PLOT - RM 20,190.10 -
20,190.10
TOTAL RM 201,901.00 - 0.00 -
201,901.00
Amount Paid RM 20,190.10 0.00 -
20,190.10
AMOUNT DUE FOR PAYMENT RM 181,710.90 - 0.00 -
181,710.90
We shall be pleased if you could kindly forward your remittance soonest
possible in favour of VISTA-PRISMA SDN BHD.
Without prejudice to our rights and remedies under the Sale & Purchase
Agreement, please note that interest of 12.00% per annum will be charged
on the overdue amount until payment is received by us.
Yours faithfully,
VISTA-PRISMA SDN BHD c.c. 1)
Sgd. (Illegible)
...
Authorised Signatory
Now, prior to the defendant sending out the letter dated 12 April 2002
via the registered mail on 13 April 2002 as reflected in the "resit
pengeposan pos daftar dalam negeri" marked as exh. "LCK4" of encl. 4, the
plaintiff had delayed and failed to make the necessary payments for the
following stages of development of the bungalow lot at Barbara Forest Park,
Lenggeng computed from 28 February 2002 as seen in exh. "LCK3" of encl. 4:
(a) stage 2 - delay of 476 days by the plaintiff in paying and it is
still continuing;
(b) stage 3 - delay of 350 days by the plaintiff in paying and it is
still continuing;
(c) stage 4 - delay of 233 days by the plaintiff in paying and it is
still continuing;
(d) stage 5 - delay of 198 days by the plaintiff in paying and it is
still continuing; and
(e) stage 6 - delay of 106 days by the plaintiff in paying and it is
still continuing.
The sum that was due on 28 February 2002 as seen in exh. "LCK3" of
encl. 4 was computed in this fashion:
Please prepare payment for: Stage(s) 2, 3, 4, 5 & 6 RM100,950.50
Add: interest accumulated stage(s) 2, 3, 4, 5 & 6 RM 9,047.36
Quit rent RM17.00
Total due to usRM110,014.86
So, from all these factual background, the learned counsel for the
defendant submitted that the party that initially breached the said
agreement by defaulting to pay and failing to pay the instalments of the
purchase price payable under cl. 5(1) of the said agreement was none other
than the plaintiff. And that payment of the purchase price was certainly the
essence of the contract between the parties. In cl. 25 of the said
agreement, it specifically states that:
Time shall be the essence of the contract in relation to all the
provisions of the Agreement.
And this means that time too is considered to be of the essence of the
contract "in relation to all the provisions of the agreement." And when
translated to the factual matrix of the present case, it meant that
promptness in the payment of the instalments was also the essence of the
contract between the parties.
Calculation wise, the parties entered into the said agreement on 8
September 1997 and vacant possession was supposed to be delivered not later
than thirty (30) calendar months from that date and this meant that on 8
March 2000 the defendant had to deliver vacant possession. But when the
period for delivery of vacant possession was extended to not later than
fifty four months from 8 September 1997 the defendant had to deliver vacant
possession on 8 March 2002. That would be the correct calculation, but the
parties by way of a statement of agreed facts had agreed that the date for
the delivery of vacant possession would be on or before 25 February 2002. Be
that as it may, it must be recalled that by the "supplementary agreed facts"
the parties agreed that the defendant had sent out a letter dated 12 April
2002 requiring the plaintiff to take vacant possession and failing which
vacant possession would be deemed delivered on 26 April 2002. So, the delay
in delivering vacant possession by the defendant was for a period of 1 month
18 days which was equivalent to 48 days (26 April 2002 minus 8 March 2002).
Or, if the calculation was based from 12 April 2002, then the delay came up
to 1 month 4 days which was equivalent to 34 days (12 April 2002 minus 8
March 2002). Or, if the calculation was based from 25 February 2002, then
the delay would be for 2 months 1 day or 61 days (26 April 2002 minus 25
February 2002). It seemed that the parties accepted the delay of the
defendant to be for 34 days. This delay of 34 days will be the length of the
delay to deliver vacant possession on the part of the defendant and it is
this period of delay that this court is bound to hold and will hold
accordingly. But the delay on the part of the plaintiff to pay the defendant
for the stages of development of the bungalow lot was far more serious. For
instance, for stage two, the delay was for 476 days and still continuing
until today. It is said that rescission is not only a legal remedy; but it
is also an equitable remedy and the maxim that he who comes to equity must
come with clean hands should be put in the forefront. So, it was vigorously
argued for the defendant that the plaintiff had failed to come with clean
hands. It was also argued that that the plaintiff should not be given the
right to rescind both the agreements because to do so would cause grave
injustice to the defendant. These submissions are indeed interesting. I have
this to add.
According to the case ofMeyers v. Casey [1913] 17 CLR 90 at p.
124, "No court of equity will aid a man to derive advantage from his own
wrong, and this is really the meaning of the maxim." But, according to a
long line of authorities, the undesirable behaviour must involve more than
merely a "general depravity"; and that it must have "an immediate and
necessary relation to the equity sued for; it must be a depravity in a legal
as well as in a moral sense" (Dering v. Earl of Winchelsea[1787] 1
Cox 318 at p. 319 to p. 320;Moody v. Cox [1917] 2 Ch 71;Argyll v.
Argyll [1967] Ch 302 at p. 331 to p. 332; andMyers v. Casey (supra)).
But Brandeis J inLoughran v. Loughran [1934] 292 US 216 at 229 aptly
said that, "Equity does not demand that its suitors shall have led blameless
lives." As against this, it is also said that the plaintiff must be prepared
to do what is right and fair and that the plaintiff must show that his past
record in the transaction was clean, after all "he who has committed
iniquity ... shall have Equity" (Jones v. Lenthal [1669] 1 Ch Cas
154).
The learned counsel for the defendant drew my attention to s. 55 of the
Contracts Act 1950 where it is enacted as follows:
55. Effect of default as to that promise which should be first
performed, in contract consisting of reciprocal promises.
When a contract consists of reciprocal promises, such that one of them
cannot be performed, or that its performance cannot be claimed till the
other has been performed, and the promisor of the promise last mentioned
fails to perform it, the promisor cannot claim the performance of the
reciprocal promise, and must make compensation to the other party to the
contract for any loss which the other party may sustain by the
non-performance of the contract.
ILLUSTRATIONS
(a) A hires B's ship to take in and convey, from Kelang to Singapore, a
cargo to be provided by A, B receiving a certain freight for its
conveyance. A does not provide any cargo for the ship. A cannot claim the
performance of B's promise, and must make compensation to B for the loss
which B sustains by the non-performance of the contract.
(b) A contracts with B to execute certain builders' work for a fixed
price, B supplying the scaffolding and timber necessary for the work. B
refuses to furnish any scaffolding or timber, and the work cannot be
executed. A need not execute the work, and B is bound to make compensation
to A for any loss caused to him by the non-performance of the contract.
(c) A contracts with B to deliver to him, at a specified price, certain
merchandise on board a ship which cannot arrive for a month, and B engages
to pay for the merchandise within a week from the date of the contract. B
does not pay within the week. A's promise to deliver need not be
performed, and B must make compensation.
(d) A promises B to sell him one hundred bales of merchandise, to be
delivered next day, and B promises A to pay for them within a month. A
does not deliver according to his promise. B's promise to pay need not be
performed, and A must make compensation.
and he stressed that by the illustrations thereto it clearly showed that
the plaintiff as the promisor of the promise had failed to perform its part
of the bargain and so it cannot now claim the performance of the reciprocal
promise and that it was the plaintiff who must make the compensation to the
defendant for the defendant's loss. Reliance was also placed by the learned
counsel for the defendant on s. 37 of the Specific Relief Act 1950 which
enacts as follows:
37. Court may require party rescinding to do equity.
On adjudging the rescission of a contract, the court may require the
party to whom the relief is granted to make any compensation to the other
which justice may require.
and he too relied on the case of Ganam d/o Rajamany v. Somoo s/o
Sinnah [1984] 1 CLJ 123 (Rep) [1984] 2 CLJ 268; [1984] 2 MLJ 290, where
Seah FJ (as he then was) writing for the then Federal Court had this to say
(see p. 299 of the report):
Now, section 37 provides that 'on adjudging the rescission of a contract,
the court may require the party to whom the relief is granted to make any
compensation to the other which justice may require'. The principle
underlying this section is whether compensation should be awarded at all or
what should be the measure of compensation must depend on the special
circumstances of each case. The aim shall be to restore the contracting
parties as much as possible to the same position which existed before the
contract. In other words, there should be a restitution of the benefits
received. As Lord Blackburn rightly pointed out in Erlanger v. New
Sombrero Phosphate Co. (supra) at page 1278:
It would be obviously unjust that a person who has been in possession of
property under the contract which he seeks to repudiate should be allowed to
throw that back on the other party's hands without discounting for any
benefit he may have derived from the use of the property, or if the
property, though not destroyed, has been in the interval deteriorated,
without making compensation for that deterioration.
In short, he who seeks equity must do equity. Applying this to the facts
of this case, we would make an order that the defendant should be entitled
to compensation only by way of the return of the sum of $26,000.00 paid by
him to the plaintiff and we so order. In our opinion, no man can at once
treat the contract as avoided by him, so as to assume the property which he
parted with it, and at the same time keep the money or other advantage which
he has obtained under it. In our judgment, the defendant is not entitled to
damages when the contracts are cancelled by the court under section 36 of
the Specific Relief Act 1950, and we make no order under this head.
Earlier on his Lordship Seah FJ spoke of s. 36 of the Specific Relief Act
1950 and this was what he said (see p. 298 to p. 299 of the report):
Now, the power of the court to make an order rescinding a contract is
contained in Chapter IV of the Specific Relief Act 1950 and the second
limb of section 36 is particularly relevant to this case and it reads:
... and the court, if it refuses to enforce the contract specifically
may direct it to be rescinded and delivered up accordingly.'
But the rescission of a contract in writing cannot be adjudged unless the
party against whom it is adjudged can be restored to substantially the same
position as if the contract had not been made (see section 35). This is what
Lord Blackburn had to say about this in the case ofErlanger v. New
Sombrero Phosphate Co.(1877-78) 3 App Cas 1218, 1278:
It is, I think, clear on principles of general justice, that as a
condition to a rescission there must be restitutio in integrum. The
parties must be put in status quo. See per Lord Cranworth inAddie vs.
The Western Bank LR. 1 HL 165. It is a doctrine which has often been
acted upon both at law and in equity ... '
In our judgment, having regard to the facts of this case, it is a fit and
proper case for us to exercise our jurisdiction contained in the second limb
of section 36 since we are satisfied that there is no difficulty in
restoring the plaintiff and the defendant to their original position and we
hereby rescind the contracts marked as Ex. P1 and P2 accordingly. Afortiori,a
considerable time (almost ten years) has lapsed since the parties executed
the said contracts.
Finally, at p. 300 of the report, his Lordship Seah FJ rounded up the
matter in these words:
Under the circumstances of the case, we allow the plaintiff to set-off
against the $26,000.00 which she is ordered to pay to the defendant as
compensation.
Now, using Ganam's case as an authority, a submission was made to
the effect that in all fairness the defendant was willing to pay for the
damages for late delivery to be set off against the purchase price but the
plaintiff who had breached both the agreements was unwilling to make the
necessary payment that was due to the defendant. It was emphasised by the
learned counsel for the defendant that under the said agreement, the
plaintiff had no right of termination and that the right to terminate under
the said agreement was accorded only to the defendant. for this proposition
he relied on the judgment of Siti Norma Yaakob JCA (now FCJ) in the case of
Pusat Bandar Damansara Sdn Bhd & Anor v. Yap Han Soo & Sons Sdn Bhd
[2000] 1 CLJ 346 and there her Ladyship aptly said at p. 354 of the report:
The rights, interests and obligations of all parties to the agreement are
spelt out in the various sections of the agreement and it is within the four
corners of the agreement that such interests have to be interpreted and
determined.
I am required to look at the said agreement and by clause 8 thereto it is
the defendant who is authorised to terminate the said agreement. That cl. 8
of the said agreement is worded as follows (see exh. "GBK1" of encl. 2):
8. DEFAULT BY PURCHASER AND DETERMINATION OF AGREEMENT
(1) If the Purchaser:
(a) fails to pay any instalment of the purchase price payable under
Clause 5(1) in accordance with the Fourth Schedule hereto or any part
thereof or any interest payable under Clause 7 hereof; or
(b) fails to pay any other sum or sums payable under this Agreement
within the time stipulated for payment; or
(c) commits any breach of the terms or conditions contained in this
Agreement or fails to perform or observe all or any of the Purchaser's
covenants herein contained; or
(d) before payment in full of the purchase price of the said Plot,
commits an act of bankruptcy or enters into any composition or
arrangement with his creditors or, being a company, enters into
liquidation, whether compulsory or voluntary; or
(e) suffers any execution to be levied upon him or his goods;
the Vendor may, subject to sub-clause (2) hereof, take such legal
action as it deems fit in the circumstances or annul the sale of the said
Plot and forthwith terminate this Agreement and in such an event:
(i) the Vendor shall be entitled to deal with or otherwise, dispose off
the said Plot in such manner as the Vendor shall see fit as if this
Agreement had not been entered into and shall not be accountable to the
Purchaser for any profit arising from the re-sale of the said Plot;
(ii) the instalments or payment(s) previously paid by the Purchaser to
the Vendor, excluding any interest paid, shall be dealt with and disposed
off as follows:
(a) firstly, all interest(s) calculated in accordance with Clause 7
hereof owing and unpaid shall be paid to the Vendor;
(b) secondly, all payment(s) other than interest(s) and instalments
due and payable to the Vendor under this Agreement shall be paid to the
Vendor;
(c) thirdly, a sum equivalent to twenty per centum (20%) of the
purchase price of the said Plot (if already paid) shall be forfeited to
the Vendor as agreed liquidated damages; and
(d) lastly, the residue thereof (if any) shall be refunded to the
Purchaser free of any interest.
(iii) neither party hereto shall have any further claim against the
other for costs, damages, compensation or otherwise hereunder; and
(iv) the Purchaser shall pay any other costs and expenses (including
the Vendor's Solicitor's costs and expenses) incurred in the matter.
(2) If the Purchaser fails to comply with any of the terms of this
Agreement or if any monies shall remain unpaid on the due date, the Vendor
shall give the Purchaser or his solicitors not less than fourteen (14) days
notice in writing by A.R. Registered post to remedy the breach and unless in
the meanwhile such default and/or breach alleged is rectified or such unpaid
monies and interest(s) are paid, the Vendor may forthwith proceed with such
legal action as it deems fit or as the case may be, this Agreement shall, at
the expiration of the said notice, be deemed to be terminated.
Clause 8 (1) of the said agreement as reproduced above would be of
relevance and this very clause will be referred to at a later stage of this
judgment.
By way of a reply, the learned counsel for the plaintiff submitted along
the following lines:
(1) That the defendant had relied heavily on the principle of equity.
(2) That exhs. "LCK1", "LCK2", "LCK3", "LCK4" and "LCK5" of encl. 4
were mere reminders and not notices to rescind the said agreement.
(3) That the allegation by the defendant that the plaintiff could not
rely on the defendant's delay in handing over vacant possession since the
plaintiff itself had breached the said agreement by not paying the
progressive payments was said to be unsustainable as there was no notice
to rescind the said agreement by the defendant and that at best the
defendant had waived their right to terminate the said agreement. Reliance
was placed on the case of Sea Housing Corporation Sdn Bhd v. Lee Poh
Choo [1982] CLJ 355; [1982] CLJ (Rep) 305 FC.
I pause here to say that as alluded to in the early part of this
judgment, the defendant had by letter dated 30 April 2002 terminated both
the agreements and I had reproduced that letter earlier. So it is wrong to
say that the defendant did not terminate both the agreements. Moreover, the
case ofSea Housing Corporation Sdn Bhd v. Lee Poh Choo (supra)was
governed by the Housing Developers (Control and Licensing) Act, 1966 and the
Housing Developers (Control and Licensing) Rules, 1970, whereas the present
case are outside the purview of the said Act and the Rules. In that case too
- referring to the case ofSea Housing Corporation Sdn Bhd v. Lee Poh Choo
(supra), the issue before the then Federal Court was whether the
purchaser who was claiming for liquidated damages in the sum of RM27,826.66
as from 2 July 1975 to 1 June 1977 was entitled to set off the damages for
the delay against the last payment of RM17,907.20 due to the developer. And
the then Federal Court held that as the transaction was governed by the
Housing Developers (Control and Licensing) Act 1966 and the Housing
Developers (Control and Licensing) Rules 1970, the developer could not rely
on cl. 32 which was inconsistent with the said Act and the Rules and that
the purchaser was entitled to the set-off as it would be manifestly unjust
to allow the developer to enforce payment without taking into account the
cross-claim. Here, however, the facts are entirely different. Here, the
plaintiff was not claiming a right of set-off. But the defendant was willing
to concede to a set-off as the sum owing to the defendant by the plaintiff
purchaser (exclusive of interest) is said to be in the sum of RM181,710.99 -
being the balance of the purchase price, while the liquidated damages for
the delay of delivering vacant possession of the bungalow lot for 34 days
would amount to RM2,256.87 where the calculation would be on the following
basis:
34x RM 201,901 x 12%
These were the submissions of the learned counsel for the defendant and
the calculation advanced by that learned counsel was certainly ingenious.
The 12% constituted the rate per annum of the purchase price as envisaged
under cl. 16 (3) of the said agreement. And so the defendant prayed that the
plaintiff's claim be dismissed with costs.
But the plaintiff through its learned counsel continued to submit and he
submitted that the fact that the plaintiff did not pay the instalments did
not mean that the plaintiff had breached both the agreements because the
plaintiff had rightfully terminated both the agreements by their solicitors'
notice dated 19.4.2002 even before the defendant had taken any action to
terminate. It was further submitted by the learned counsel for the plaintiff
that it was irrelevant that the late delivery for vacant possession was a
mere 34 days because the issue was whether the defendant had breached cl.
16(1) of the said agreement and the supplemental agreement by not handing
over delivery of vacant possession to the plaintiff within fifty four (54)
months - namely, before or on 25 February 2002. It was because of the breach
by the defendant to deliver vacant possession some 34 days later, that the
learned counsel for the plaintiff submitted vigorously that the plaintiff
was entitled to rescind both the agreements. It was further submitted by the
learned counsel for the plaintiff that it was misconceived and wrong in law
for the defendant to rely on s. 55 of the Contracts Act 1950 since time was
the essence of both the agreements and that the defendant had failed to
perform within the prescribed time as stipulated under both the agreements.
It was submitted by the learned counsel for the plaintiff that the correct
section of the law would be s. 56 of the Contracts Act 1950 which enacts as
follows:
56 Effect of failure to perform at fixed time, a contract in which time
is essential.
(1) When a party to a contract promises to do a certain thing at or
before a specified time, or certain things at or before specified times,
and fails to do any such thing at or before the specified time, the
contract, or so much of it as has not been performed, becomes voidable
at the option of the promisee, if the intention of the parties was that
time should be of the essence of the contract.
Effect of failure when time is not essential.
(2) If it was not the intention of the parties that time should be of
the essence of the contract, the contract does not become voidable by
the failure to do the thing at or before the specified time; but the
promisee is entitled to compensation from the promisor for any loss
occasioned to him by the failure.
Effect of acceptance of performance at time other than that agreed
upon.
(3) If, in case of a contract voidable on account of the promisor's
failure to perform his promise at the time agreed, the promisee accepts
performance of the promise at any time other than that agreed, the
promisee cannot claim compensation for any loss occasioned by the
non-performance of the promise at the time agreed, unless, at the time
of the acceptance, he gives notice to the promisor of his intention to
do so.
The learned counsel for the plaintiff then proceeded to distinguishGanam's
case - a case that was relied upon by the defendant. He pointed out that inGanam's
case, time was not the essence of the contract and that there was no notice
that was given to rescind the contract. Whereas in the present case at hand,
time was said to be of the essence of both the agreements and that the
plaintiff had rightfully given the notice of termination. In regard to the
case ofPusat Bandar Damansara Sdn Bhd & Anor v. Yap Han Soo & Sons Sdn
Bhd (supra), a case which was relied upon by the defendant, it was
submitted by the learned counsel for the plaintiff that that case was
distinguishable and irrelevant for the following reasons:
(1) that time being of the essence was not alluded to in that judgment;
(2) that s. 56 of the Contracts Act 1950 was not referred to in that
case;
(3) that there was no issue pertaining to the question of late
delivery;
(4) that the purchaser in that case had defaulted in paying the balance
of the purchase price and the appellant there had given a proper notice to
terminate the contract; and
(5) that the right of termination was not accorded to the purchaser
because there was no such default or breach by the developer.
All these distinguishing features were dutifully noted. The learned
counsel for the plaintiff submitted that it was crystal clear and manifest
that the defendant had breached both the agreements by not handing over the
delivery of vacant possession within the prescribed time and that breach was
said to have given the plaintiff the right to rescind both the agreements
and to seek a refund of the deposit that was paid. For all these reasons, it
was submitted that the plaintiff's originating summons in encl. (1) should
be allowed with costs.
Not to be outwitted, the learned counsel for the defendant responded. He
proceeded to distinguishChye Fook's case and he relied on the
passages in that judgment and he referred to p. 310 to p. 311 of the report
of that case:
Since it is a question of construction depending on the facts of each
case as to whether there has been a substantial failure of performance or
a breach of an essential term, perhaps what Lord Diplock said inPhoto
Production Ltd v. Securicor Transport Ltd [1980] AC 827 may throw some
light on the matter. He had said that 'where the event resulting from the
failure by one party to perform a primary obligation has the effect of
depriving the other party of substantially the whole benefit which it was
the intention of the parties that he should obtain from the contract, the
party not in default may elect to put an end to all primary obligations of
both parties remaining un-performed'.
and he submitted that in the present case the plaintiff was not an
innocent party as he was also in default in not paying the instalments when
it fell due. InChye Fook's case too, only "the plaintiffs' house had
been built out of a row of terrace houses and also no other houses could be
seen in the area. Since, from the photographs, the plaintiffs' house appears
to be the only house built in the area, it is possible that the construction
could have even begun after the completion date" (see p. 311 of the report).
Here, vacant possession was handed over; but it was delayed by 34 days.
The learned counsel for the defendant then referred to the case ofKang
Yoon Mook Xavier v. Insun Development Sdn Bhd (supra), and he submitted
that the plaintiff in that case was an innocent party. Here, however, the
plaintiff was not the innocent party or the injured party because the
plaintiff had also breached both the agreements by failing to pay the
instalments that were due and forthcoming. The defendant then prayed that
the plaintiff's originating summons in encl. (1) should be dismissed with
costs.
Should I grant the prayers as sought for in encl. (1)? That is the
crucial question to pose.
There was reference to s. 56 of the Contracts Act 1950 and that section
provides that failure to perform within a fixed time in a contract,
especially where time is an essential element, would render the contract
voidable. But as is usual, difficulties still remain until today, when one
is faced with the question of determining when time would be regarded as of
the essence of the contract. It is quite apt to say that at common law -
everyone who is schooled in law ought to know, that time was always regarded
as of the essence of the contract in a land transaction - particularly in
the sale of land. But, equity did not adopt such a view. It seems that the
application of equity towards time would not apply in those cases where the
parties had expressly agreed that time should be of the essence. In
Jamshed Khodaram Irani v. Burjorji Dunjibhai[1916] LR 43 IA 26, the
Privy Council held that s. 56 of the Indian Contracts Act did not lay down
any principle of law which differed from the equitable principles under the
English law in relation to time in contracts for the sale of land. It is
noteworthy to note that this view of the Privy Council in that case has been
readily adopted and applied in two cases, namely,Ayadurai v. Lim Hye
[1959] MLJ 143; and Ismail Bin Haji Embong v. Lau Kong Han [1970] 1
LNS 40;[1970] 2 MLJ 213. The Privy Council in the case of Yeow Kim Pong
(Realty) Ltd v. Ng Kim Pong [1961] 1 LNS 157; [1962] MLJ 118, was of the
view that the effect of s. 56(3) of the Contracts Act 1950 was only to
prevent a party from bringing a subsequent action for compensation for
non-performance. The section too, according to the Privy Council, did not
prevent the parties from reaffirming the contract in its original form or
even in its varied form. The Privy Council also held that the parties could
still be bound by the original contract.
But it must be emphasised that in most commercial transactions time is
always listed to be of the essence of the contract (Himatsing & Co. v.
Joitaram [1970] 1 LNS 37; [1970] 2 MLJ 246). InSharikat Eastern
Plastics Industry v. Sharikat Lam Seng Trading [1971] 1 LNS 132; [1972]
1 MLJ 21 , Mohamed Azmi J (who later rose to be the Supreme Court judge)
held that when time is of the essence of the contract, it may be waived by
granting an extension of time for performance. Of pertinence would be the
Privy Council's case of Aberfoyle Plantations Ltd v. Khaw Bian Cheng
[1959] 1 LNS 3 [1962] MLJ 174 and there the following germane principles
were laid down in relation to time in conditional contracts:
(1) where a date for the completion of the sale is fixed by contract,
then by that date the contract must be fulfilled;
(2) where no date is fixed for the completion of the sale, then the
fulfillment of the contract must be within a reasonable time; and
(3) in a situation as envisaged in (1), then the date for completion of
the sale must be strictly adhered to and that time is not to be extended
by reference to equitable principles.
At common law, a strict approach is always adopted. To illustrate, I need
to refer to the case of Parkin v. Thorold[1852] 16 Beav 59, 65, where
Sir John Romilly MR, aptly said, "at law time is always of the essence of
the contract. When any time is fixed for the completion of it, the contract
must be completed on the day specified, or an action will lie for breach of
it." At common law, it is very clearly stated that: references to time are
generally regarded to be of the essence of the contract and that a party
could treat the contract as being repudiated if the other party failed to
perform his side of the bargain on the date as specified in the contract.
But in equity, the rule is very relaxed. In Lock v. Bell[1931] 1
Ch 35, 43, it was held that:
The court of equity was accustomed to relieve against a failure to keep
the date assigned .... if it could do justice between the parties.
In my judgment, the question as to whether a stipulation as to time is of
the essence may readily be resolved by looking at the terms of the contract
itself. This is the best approach to adopt and it will never go wrong. Thus,
in the context of the present case, time was certainly regarded to be of the
essence of the contract and it would extend "to all the provisions of the
agreement". That being the case, time would dictate all the provisions of
the said agreement. So time plays a role in the following crucial areas:
(1) in paying the instalments that were due and the delays for stage 2,
stage 3, stage 4, stage 5, and stage 6 as alluded to somewhere in this
judgment should not have happened; and
(2) in delivering vacant possession on or before 25 February 2002.
Unfortunately, the plaintiff only paid the first 10% and thereafter there
was no payment made at all despite the notices as alluded to earlier. There
was blatant non compliance by the plaintiff of the "Schedule of Payments" as
set out in cl. 5 of the said agreement which was reproduced earlier. These
were my judgments and I so hold accordingly.
When the defendant did not deliver vacant possession on or before 25
February 2002, the plaintiff proceeded to give the notice of termination
dated 19 April 2002 to the defendant. But the defendant by letter dated 12
April 2002 required the plaintiff to take vacant possession and failing
which vacant possession would be deemed to be delivered on 26 April 2002.
This was a case where the defendant gave vacant possession 34 days after the
deadline. The redeeming feature would be this: that the defendant had,
unlike some other unscrupulous developers, given vacant possession to the
plaintiff. So, when the defendant gave vacant possession 34 days past the
scheduled dateline, the defendant as the vendor "shall pay immediately to
the purchaser (referring to the plaintiff) liquidated damages to be
calculated from day to day at the rate of twelve per centum (12%) per annum
of the purchase price" (see cl. 16(3) of the said agreement). The liquidated
damages as calculated and suggested by the learned counsel for the defendant
is in the sum of RM2,256.87 and this was alluded to earlier. And by letter
dated 30 April 2002, the defendant terminated both the agreements.
This was also a case where both the parties - the plaintiff and the
defendant, have terminated both the agreements. They were no longer
interested in contracting with one another. In fact, under the said
agreement only the defendant is authorised to terminate the said agreement.
The plaintiff has no power to terminate the said agreement and this is
clearly borne out in cl. 8 of the said agreement. So, after the defendant
had terminated both the agreements by letter dated 30 April 2002, the
defendant was entitled to those remedies as exemplified in cl. 8(1)(i) to cl.
8(1)(iv) of the said agreement. These remedies are certainly of great
benefit to the defendant.
To answer the crucial question posed by me earlier as to whether I should
grant the prayers as sought for by the plaintiff in encl. (1), I would
answer it in the following manner:
(1) Under prayer (8) of encl. (1), a necessary and fair order would be
to declare that both the agreements have been terminated. Both the parties
are no longer interested in contracting with one another.
(2) The defendant as the vendor is entitled to deal with or dispose off
the bungalow lot in such manner as the defendant shall see fit as if both
the agreements had not been entered into and the defendant shall not be
accountable to the plaintiff as the purchaser for any profit arising from
the re-sale of the bungalow lot.
(3) The instalments or payments previously paid by the plaintiff as the
purchaser to the defendant as the vendor, excluding any interest paid,
shall be dealt with and disposed off according to cl. 8(1)(ii)(a) to cl.
8(1)(ii)(d) of the said agreement.
(4) Whatever monies paid by the plaintiff as the purchaser to the
defendant as the vendor, excluding any interest paid, which must include
the 10% deposit amounting to RM20,190.10, shall be dealt with and disposed
off according to cl. 8(1)(ii)(a) to cl. 8(1)(ii)(d) of the said agreement.
(5) Clause 8(1)(ii)(a) to cl. 8(1)(ii)(d) of the said agreement read as
follows:
(a) all interests calculated in accordance with cl. 7 hereof owing
and unpaid shall be paid to the defendant as the vendor;
(b) all payments other than interest(s) and instalments due and
payable to the defendant as the vendor under the said agreement shall be
paid to the defendant as the vendor;
(c) a sum equivalent to 20% of the purchase price of the bungalow lot
(if already paid) shall be forfeited to the defendant as the vendor as
agreed liquidated damages; and
(d) the residue thereof (if any) shall be refunded to the plaintiff
as the purchaser free of any interest.
(6) Neither party (be it the plaintiff or the defendant) shall have any
further claim against the other for costs, damages, compensation or
otherwise hereunder.
(7) The plaintiff as the purchaser shall pay any other costs and
expenses (including the defendant's solicitor's costs and expenses)
incurred in these proceedings.
In order to ensure compliance with the Orders of this court at numbers
(3), (4), 5 (a) to 5 (d), (6) and (7) as stipulated above, the matter should
be referred to either the senior assistant registrar or the deputy registrar
forthwith for an in-depth assessment of the damages.
And as agreed by the parties hereto, the decision in this judgment binds
the two other cases as alluded to earlier, namely:
(1) originating summons no: S3-24-2330-2002; and
(2) originating summons no: S5-24-1248-2002.
|