PUBLIC FINANCE
BERHAD V ZAINAL BIN OSMAN T/A PUTERA FOTOT STUDIO
HIGH COURT (SHAH ALAM)
GUAMAN NO MT3-22-1615-1998
LOW HOP BING J
30 AUGUST 2001
JUDGMENT
I. BACKGROUND AND APPEAL
This is a writ action commenced by the plaintiff against the defendant to
recover the sum of RM443,773.51 as at 4 September 1998, interest at 13.85%
(i.e. 1.5% p.a. above the base lending rate of 12.35% at monthly rests on
the balance outstanding from 5 September 1998 until full realisation) and
costs.
The writ together with the statement of claim had been duly served on the
defendant on 10 April 1999. The defendant did not file any memorandum of
appearance and so judgment in default of appearance ('the judgment') was
entered for the plaintiff on 21 April 1999. The judgment was served on the
defendant on 9 June 1999. The defendant on 1 July 1999 filed an application
by way of summons in chambers in enclosure (8) to set aside the judgment and
to file the statement of defence. Enclosure (8) was heard on 12 May 2000 by
the learned senior assistant registrar who had dismissed it on the same day.
Against the registrar's aforesaid decision, the defendant had on 16 May 2000
filed this appeal in enclosure (13). In this appeal, for ease of reference,
I shall refer to the parties as plaintiff and defendant respectively.
II. SUBMISSION FOR DEFENDANT
Encik James Dominic Culaz, learned counsel for the defendant, submitted that
this is a charge action and so leave is required under O.83, r.4(1) of the
Rules of the High Court 1980 to enter the judgment. He said that the
decision in Public Finance Bhd v Soo Hock Siong [1987] 1 LNS 95; [1988] 3
MLJ 352 is distinguishable.
He proceeded to contend that there is defence on the merits in that the
plaintiff before releasing the progress payments under clause 1.08 of the
fixed term loan agreement ('loan agreement') has failed to be satisfied that
the state of the building to be erected thereon justified the advance and
that the architect's certificate was produced. He argued that the repayment
of the loan commences only upon the principal sum having been disbursed in
full in accordance with the loan agreement and the charge documents. He
added that the plaintiff, by failing to ensure that the progress payments
are justified by the state of the building as required under the said clause
1.08, should not be allowed to demand repayment of the loan.
In his view, there was no connection of water and electricity, in which
event the defendant was unable to utilise the building to generate any form
of income to make the relevant repayment and he relied on Lew Yoke Leng &
2 Ors v Syarikat Kar King Sdn Bhd [2000] 4 CLJ 184; [2000] 4 AMR 3911 in
support of this proposition.
He alleged that the plaintiff has been negligent in releasing the progress
payments without studying the architect's certificate and cited MBf
Property Services Sdn Bhd & Anor v Balasubramaniam A/L K Arumugam [2000] 2
CL 230; [2000] 2 AMR 1542 as the supporting authority.
III. PLAINTIFF'S RESPONSE
Cik L.T. Tan, learned counsel for the plaintiff, submitted that this writ is
founded on the loan agreement and that there is no dispute that the parties
herein are bound by their respective obligations. She added that there is
also no dispute that the principal sum has been disbursed in accordance with
the loan agreement and so the defendant's obligation to repay arises
thereafter. She referred to the defendant's affidavit in enclosure (7)
clause 9 wherein the defendant admitted that he needed more time to fulfil
his obligation to repay the loan. She said that there is a clear event of
default by the defendant and that it is a writ action based on the
defendant's contractual breach of the loan agreement. She added that it is
therefore not a charge action, in which case, no leave is necessary to enter
the judgment.
On the defence of merits, plaintiff's learned counsel replied that there is
no express clause in the loan agreement which imposes an obligation on the
plaintiff to inspect physically the state of the building to ensure water
and electricity supply to the building before the release of the loan sum,
and that it is not within the plaintiff's expertise to make sure that
delivery of vacant possession was effected. It was contended for the
plaintiff that the plaintiff could release progress payments so long as
there are some forms of certification by an architect and that the plaintiff
could not be faulted for the absence of water and electricity supply to the
property in question, otherwise it would amount to insertion of clauses
which were not in the agreement. Plaintiff's learned counsel said that the
defendant's remedy, if any, is against the architect or the developer.
Hence, she concluded that there are no merits in the defence.
IV. DECISION OF THE COURT
1. DOES O.83, R.4(1) APPLY?
The action filed by the plaintiff in this case is plainly a writ action. The
question that has to be determined by the court is whether O.83, r.4(1) of
the Rules of the High Court 1980 applies here. O.83 r.4(1) provides as
follows:
'Notwithstanding anything in Order 13 or Order 19, in a charge action begun
by writ judgment in default of appearance ...... shall not be entered except
with the leave of the Court.'.
The answer to the aforesaid question would depend on the conclusion as to
whether the action herein is a charge action begun by writ. Under O.83,
r.1(1), a charge action may be begun by a writ or an originating summons. A
charge action is an action in which there is a claim for, inter alia,
payment of moneys secured by the charge: O.83, r.1(1)(a). In the context of
the instant case, to constitute a charge action, the cause of action must be
founded on the charge documents registered [Page 9] under the National Land
Code 1965. If a cause of action is not based on a charge, but merely on a
breach of e.g. a loan agreement, then it would not be a charge action.
The cause of action herein is founded on the averments contained in the
plaintiff's statement of claim. Para 3 thereof avers that by the loan
agreement, the plaintiff agreed to extend and the defendant agreed to accept
a fixed term loan, on the terms and conditions expressed therein, including
the interest and monthly instalment payment of RM4,969.00 for 144 months,
which the defendant has defaulted in payment as averred in para 6 thereof.
After serving the necessary notices of demand due to the defendant's
repeated defaults, the present writ action was commenced against the
defendant. The essence of the plaintiff's claim is wholly and exclusively
based on the loan agreement which is one of the 3 forms of security which
the plaintiff may elect to enforce, the other 2 being a charge on the
property in question registered under the National Land Code 1965 while the
third form of security is constituted by a letter of guarantee given by
Credit Guarantee Corporation Malaysia Berhad: see clause 1.02 with the
caption 'SECURITY FOR THE FIXED LOAN' in the loan agreement. This writ
action undoubtedly arises out of the defendant's defaults in the repayment
of the loan sum and is anchored on the loan agreement, independent of the
other 2 aforesaid forms of security viz. charge and letter of
guarantee. That being the case, it is my specific finding that this is a
writ action commenced by the plaintiff by reason of the contractual breach
by the defendant of the loan agreement. There is no averment in the
plaintiff's statement of claim in relation to the enforcement of plaintiff's
right pursuant to the charge. Therefore it is, in my view, not a charge
action and so the provisions of O.83, r.4(1) have no application. Hence, no
leave of the court is required to enter the judgment. I hold that the
judgment is a regular judgment. Support for my view may be found in Pulic
Finance Bhd v Soo Hock Siong, supra, where the facts are almost on all
fours with those in the present action, except that judgment in default of
defence was entered for the plaintiff there while in the instant case,
judgment in default of appearance was entered for the plaintiff. Anuar, J
(later CJ(M)) held that the plaintiff's action being based on the
plaintiff's letter of offer granting and the defendant's acceptance of a
loan, is a simple action to recover a debt, to which O.83, r.4(1) does not
apply.
2. DEFENCE ON MERITS
In an application to set aside a regular judgment in default of appearance,
the burden is on the defendant to show a defence on the merits: Kwong Yik
Bank Bhd v Sa'Adiah Bte Mastan [1994] 3 CLJ 781; [1994] 2 MLJ 830 ;
Evans v Bartlam [1937] AC 473. It is therefore incumbent on the
defendant to show in his affidavit that he has a defence on the merits. The
defendant's affidavit in support is to be found in enclosure (7) wherein
para 3 refers to the sale and purchase agreement which he has executed with
the developer to purchase the property in question, while para 4 specifies
the mode of progress payment under the sale and purchase agreement. The loan
for the purchase of the said property was obtained from the plaintiff (para
5). Paras 6 and 7 relate to the annexure to the charge. It is to be noted
that these 2 paras do not refer to or rely on the loan agreement which is
the basis of the plaintiff's cause of action herein. Para 8 alleges that the
failure on the part of the developer to connect water and electricity supply
to the property, as a result of which the defendant states in para 9 that he
was unable to commence his business and he needed more time to repay the
loan. In para 10, he says that he has lodged a complaint with the Menteri
Besar of Negeri Sembilan and also Bank Negara. He was advised by his lawyer
that the plaintiff should not have made progress payments pursuant to the
sale and purchase agreement and so the plaintiff is not able to recover the
repayment of the loan pursuant to the charge (para 11) and not, be it noted,
the loan agreement. He alleges in para 12 that the plaintiff has been
negligent in doing so. In para 13, the defendant argues that this action is
premature and does not reflect the true intention of the parties as
expressed in the annexure to the charge. On these allegations of fact, he
urges the court to hold that he has a defence on the merits.
After a very careful analysis of each and every allegation of fact as
deposed to in the plaintiff's affidavit, it is my specific finding that the
defendant has proceeded on the basis that this action is a charge action
under O.83 and hence it is not surprising that he has affirmed his affidavit
based on that ground alone and not the loan agreement which is the
substratum of the plaintiff's claim. Without any doubt whatsoever, there is
nothing in the affidavit to show any defence on the merits in relation to
the plaintiff's cause of action founded on the loan agreement. Since there
was no allegation in the defendant's affidavit to rebut the plaintiff's case
based on the loan agreement, the plaintiff's allegations of fact in that
respect are deemed to have been admitted by the plaintiff: Ng Hee Thoong
& Anor v Public Bank Bhd [1995] 1 CLJ 609; [1995] 1 MLJ 281 , where the
Court of Appeal held, inter alia, that 'in evaluating affidavit evidence,
where one party makes a positive assertion upon a material issue, the
failure of the opponent to contradict it is usually treated as an admission
by him of the fact so asserted.'. Therefore, where, as in this case, the
defendant's affidavit discloses no defence on the merits or for that matter
no triable or arguable issue, the application to set aside a judgment in
default should be dismissed: Government of Malaysia v Sim Soe Hoe [1990]
2 CLJ 72 (Rep); [1990] 1 MLJ 379 . In the circumstances, I am of the
view that the learned registrar has properly exerised his discretion in
dismissing the plaintiff's application in enclosure (8) with costs. I
therefore hereby uphold and affirm that decision and accordingly dismiss
this appeal in enclosure (13) with costs.
By way of an exercise of extra caution, in the event that I have erred in my
conclusion above, I shall now proceed to consider the argument and
authorities cited by learned counsel for the defendant.
First, the plaintiff's release of the loan pursuant to the architect's
certificate under the sale and purchase agreement entered into between the
defendant as purchaser and the developer as vendor. Clause 1.08 of the loan
agreement reads as follows:
'RELEASE OF LOAN
1.08. The loan is to be released progressively as and when the Lender is
satisfied that the state of the Building to be erected thereon justified the
advances and upon production of the necessary Architect's Certificate
certifying the state of completion and after the legal documents are duly
completed and the difference between the purchase price and the Loan is
firstly paid by the Borrower.'.
As a matter of fact, the progress payments were disbursed or released by the
plaintiff pursuant to each and every certificate issued by the relevant
architect who has certified the state of the building to be erected thereon.
There is no evidence of any non-compliance by the plaintiff with the said
clause 1.08.
Lew Yoke Leng & 2 ORS v Syarikat Kar King Sdn Bhd, supra, relied on
by the defendant in relation to the connection of water and electricity to
the building in question, did not determine the issue concerning the
obligation or liability of a banker to release the progress payment under
the loan agreement in the instant case. James Foong, J clearly identified
the issue in that case as one which 'centres on the interpretation of clause
20 in the S & P agreement of whether vacant possession with electricity
supply to the house means electricity connected to the house or sufficient
when power supply only reached the electrical sub-station in the housing
estate where the house is.' I fail to see how the defendant's learned
counsel is able to derive any support therefrom for his contention as I have
stated above.
The next and final point raised for the defendant is the alleged negligence
in releasing the progress payments without studying the architect's
certificates. The loan agreement does not appear to contain any obligation
which requires the plaintiff to go behind the architect's certificate.
Architects have the special professional skill and competence to certify the
state of the building and the plaintiff is perfectly entitled to rely on
these certificates issued by architects in order to justify the
disbursements of the relevant progress payments, and that is precisely what
the plaintiff has done in this case.
MBF Property Services Sdn Bhd & Anor v Balasubramaniam A/L K. Arumugam,
supra, is not a case which deals with the alleged negligence of a banker
in releasing the relevant progress payments. It was an appeal concerning the
construction of an agreement entered into between the first appellant and
the respondent. The respondent there took out an originating summons against
the appellants asking for a declaration that he need not make any payments
to the second appellant (the end financer) until the issuance of the
certificate of fitness for occupation. This application was allowed by the
High Court and the Court of Appeal. That case does not concern any
allegation of negligence on the part of the financier and in my view, cannot
lend any support to the defendant's argument. As a matter of fact, the
architect's certificate dated 9 December 1997 exhibit SA-2 in
enclosure (12) in the instant case expressly states that the defendant was
given vacant possession with water and electricity supply ready for
connection to the said building. In the ultimate analysis, there can be no
doubt in my mind that the defendant has not shown any defence on the merits
and so from whatever angle one looks at the entire case before me, the
result is the same and the defendant's appeal still fails.
|