NEOH KHOON LYE V. TRANS-INTAN SDN BHD
HIGH COURT MALAYA, PULAU PINANG
TEE AH SING J
[CIVIL SUIT NO: 22-132-2001]
12 APRIL 2002
CONTRACT: Building contract
- Set-off - Whether right of set-off could be excluded by express words
or by implication - Whether claim for set-off proper and not premature -
Whether plaintiff entitled to set-off liquidated damages due to him against
final progressive payment due to defendant
CIVIL PROCEDURE: Injunction - Mandatory injunction - Application
for delivery of vacant possession of land - Balance of convenience - Whether
damages an adequate remedy - Whether there was a serious issue to be tried
- Whether case so "unusually sharp and clear" that injunction should be
granted
This was an application by the plaintiff, who had entered into a sale and
purchase agreement ('the agreement') for property ('the property') with
the defendant, for delivery of vacant possession of the same. The defendant
had demanded the final progressive payment due to it before handing over
the property; the plaintiff, however, claimed that there were liquidated
damages due to him as a result of the delay in the completion of the property
and he was entitled to set-off the liquidated damages against the final
progressive payment due to the defendant. The defendant then averred that
the plaintiff had to make payment of the full purchase price of the property
before he was entitled to vacant possession. The main issue of contention
in this case was whether from the wording of the agreement, there was an
express provision to exclude the right of set-off, or it could be implied
that the parties had intended to exclude the right of set-off.
Held:
[1]The agreement did not provide that payment of liquidated damages by the
defendant was conditional upon full payment of the purchase price nor did
it by necessary implication prohibit a set-off of liquidated damages against
the balance of the purchase price. (p 428 e)
[2]Although the common facilities were still not completed to date, the
plaintiff's right of action for damages for breach of contract accrued on
the date of the breach; therefore, the plaintiff's claim for set-off was
proper and not premature. (p 430 a-b)
[3]The plaintiff's right to liquidated damages was a cross-claim which arose
out of the same transaction as the defendant's right to be paid the balance
of the purchase price and was so closely connected with it that it would
be manifestly unjust to disregard it; the plaintiff had an equitable right
of set-off against the final claim of the defendant. (pp 430 i & 431 a)
[4]Although the plaintiff had settled all outstanding amounts due to the
defendant and was without dispute the legal and beneficial owner of the
said property, the defendant was nevertheless withholding delivery of vacant
possession of the said property to coerce the plaintiff to pay out monies
without taking issue of the set-off of the liquidated damages into consideration.
(p 432 d-e)
[5]The balance of convenience lay in favour of the plaintiff; there would
be little, if any, hardship caused to the defendant if the injunction was
granted. Damages was not an adequate remedy in this case, and the issue
of whether the plaintiff had a right of set-off in respect of the liquidated
damages due to the plaintiff was a serious issue to be tried. This was a
fit and proper case to grant the mandatory injunction as the plaintiff's
case was "unusually sharp and clear". (p 432 f-h)
[Application allowed.]
Cases referred to:
Cheng Hang Guan & Ors v. Perumahan Farlim (Penang) Sdn Bhd & Ors [1988]
1 CLJ 435 (Rep) [1988] 2 CLJ 35; [1988] 3 MLJ 90 (refd)
Ching Yik Development Sdn Bhd v. Setapak Heights Development Sdn Bhd [1997]
1 CLJ 287(dist)
Gibb & Co v. Malaysia Building Society Bhd [1982] CLJ 99 (Rep) ; [1982]
1 CLJ 185; [1982] 1 MLJ 271 (refd)
Insun Development Sdn Bhd v. Azali Bakar [1996] 2 CLJ 753(refd)
Loh Wai Lian v. SEA Housing Corporation Sdn Bhd [1987] 1 LNS 37; [1987]
2 MLJ 1 (dist)
Pembenaan Leow Tuck Chui & Sons Sdn Bhd v. Dr Leela's Medical Centre Sdn
Bhd [1995] 2 CLJ 345(refd)
SEA Housing Corporation Sdn Bhd v. Lee Poh Choo [1982] CLJ 355; [1982] CLJ
(Rep) 305(refd)
For the plaintiff - Daphne Choy; M/s Choy & Assocs
For the defendants - Ong Wee En; M/s Shahrizat & Tan
JUDGMENT
This is an application by summons-in-chambers by the plaintiff for the following
orders:-
(i) that the defendants whether by themselves, directors, servants, agents
or nominees or howsoever do forthwith deliver to the plaintiff vacant possession
of the property known as Parcel No 3, 19 Floor, Block D, Miami Green, Penang
("the property");
(ii) that in the event the defendants fail to deliver vacant possession
of the property within fourteen (14) days from the date of the order herein,
the plaintiff and/or his servants, agents or nominees shall be entitled
to apply reasonable force to enter the said property and the defendants
shall be liable for all costs arising therefrom;
(iii) that the defendants do pay the costs of this application to the plaintiff;
(iv) that there be such further reliefs and/or orders as may be deemed just
and necessary.
By a sale and purchase agreement dated December 21, 1996 entered into between
the plaintiff as the purchaser and the defendants as the vendor ("the agreement")
the defendants agreed to sell the property to the plaintiff for the total
purchase price of RM225,888. The defendants are a housing developer licensed
under the Housing Developers (Control and Licensing) Act 1966.
Subsequent to the execution of the agreement the plaintiff settled each
and every demand for progressive payment made by the defendants.
The defendants had via their letter of February 23, 2001 to the plaintiff
given notice that the final stage of the construction works on the said
property had been completed and demanded the sums of RM33,883.20 and RM11,294.40
being the final progressive payment due to the defendants and the stakeholders
sum due to Messrs Anoop & See respectively under the schedule of payment
in respect of the agreement. The defendants had via another letter of February
23,2001 to the plaintiff given notice that the defendants were ready to
deliver vacant possession of the said property and that the plaintiff was
to forward the sums of RM51,729.57 and RM2,300 to the defendants and to
Belleview Bina Sdn Bhd respectively.
Under Clause 22(1) of the agreement the prescribed date of delivery of vacant
possession of the said property is within 36 calendar months of the date
of signing of the agreement (December 21, 1996) that is on December 21,
1999. So the defendants were ready to hand over vacant possession on February
23, 2001. Thus there was a delay of 431 days from December 21, 1999 to February
23, 2001. The plaintiff calculated the liquidated damages due for 431 days
as amounting to RM26,673.35. So the plaintiff instructed his solicitors,
Choy & Associates, to give notice via their letter of March 12, 2001 to
the defendants that as at February 23, 2001, a sum of RM26,673.35 was due
to the plaintiff as liquidated damages pursuant to Clause 22(2) of the agreement.
Clause 24(1) of the agreement stipulates that the common facilities serving
the housing development wherein the said property is located, are to be
completed by the defendants by December 21, 1999. As at the time of the
defendants' notice of February 23, 2001, the defendants have yet to issue
a certificate of completion of the common facilities.
So there was a delay of 431 days from December 21, 1999 to February 23,
2001.
Although the delay of completion of the common facilities is still continuing,
for purposes of settlement of the final progressive payment the plaintiff
had instructed his solicitors, Messrs Choy & Associates, to give notice
via their letter of March 12, 2001 that as at February 23, 2001, a sum of
RM5,334.67 was due to the plaintiff as liquidated damages for delay pursuant
to Clause 24(2) of the agreement.
The plaintiff after setting off the said sums of RM26,673.3 5 and RM5,334.67
forwarded vide letter dated March 12, 2001 from Choy & Associates, three
cheques for the following sums due:-
(a) OUB cheque 018253 for a sum of RM11,294 made out to Messrs Anoop & See
being the stakeholder's sum;
(b) OUB cheque 018252 for a sum of RM2,300 made out to Belleview Bina Sdn
Bhd being the balance outstanding for an additional package;
(c) OUB cheque 018251 for a sum of RM8,427.15 made out to Trans-Intan Sdn
Bhd, the defendants, being the final progressive payment less the liquidated
damage due to the plaintiff (RM33,883.20 - [RM26,673.35 + RM5.334.67]).
The plaintiff instructed his solicitors to enquire via their letter of March
14, 2001 when the keys to the said property could be collected.
The defendants had replied via their letter dated March 15, 2001 to Choy
& Associates that they were not agreeable to the set-off of the liquidated
damage due to the plaintiff against the final progressive payment, and returned
the plaintiff's OUB cheque 018251 for a sum of RM8,427.15. The defendants
demanded the plaintiff to make full payment.
The plaintiff had on March 15, 2001 instructed his solicitors, Choy & Associates,
to write to the defendants to enquire what provisions allowed the defendants
to refuse the set-off considering that the liquidated damages were due to
him under the agreement. The plaintiff has to date not received a reply
to his solicitor's said letter of March 15, 2001. Instead, the defendants
have via their letter dated March 19, 2001 projected the subject of liquidated
damages as one which requires "a total solution" involving the developer,
contractors, architect and purchasers.
The defendants through their letter dated March 23, 2001 demanded payment
from the plaintiff pursuant to Clause 4 and item 3 and 4 of the Third Schedule
under the agreement.
The plaintiff through his solicitors' letter dated March 27, 2001 once again
sent the said cheque to the defendants. And the defendants vide letters
dated April 27, 2001 and May 2, 2001 returned the said cheque to the plaintiff.
Vide the said letter dated April 27, 2001 the defendants gave notice to
the plaintiff under Clause 9(2) of the agreement that in the event that
the plaintiff did not make full payment within 14 days from the date of
the said letter, the agreement is deemed to have been terminated.
As the defendants refused to accept the plaintiff's said OUB cheque 018251
for the sum of RM8,427.15 the plaintiff paid to the defendant via telegraphic
transfer the sum of RM8,427.15 on May 9, 2001. However according to the
defendants, the plaintiff had on May 9, 2001 made payment by telegraphic
transfer into the account of the defendants without the knowledge and consent
of the defendants.
The defendants also averred in their affidavits that they accept the breach
of the agreement by the plaintiff and intents to terminate the agreement
and refund the sum of RM154,754.92 in respect of all payments made by the
plaintiff less a sum of 20% from the purchase price and interest charged
for late payment pursuant to Clause 8 and 9 of the agreement. The letter
of termination and cheque for a sum of RM154,754,92 has been prepared by
the defendants and is exhibited as Exh "HICC-8". And the defendants have
intention to send the letter and cheque to the plaintiff. But the defendants
are not able to do so because this court had on May 17, 2001 directed that
the status quo be maintained until the hearing of Encl 3 on June 13, 2001.
Both the learned counsels for the plaintiff and the defendants have respectively
put in lengthy written submissions and replies. I have perused all the said
submissions. I shall now deal with the application before me. The relevant
parts of the agreement are as follows:-
4. Schedule of payments
(1) The purchase price shall be paid by the Purchaser to the Vendor by instalments
and at the time and in the manner as prescribed in the Third Schedule hereto.
(2) Every notice referred to in the Third Schedule requesting for payment
shall be supported by a certificate signed by the Vendor's Architect or
Engineer in charge of the housing development and every such certificate
so signed shall be proof of the fact that the works therein referred to
have been completed.
7. Time essence of contract
Time shall be the essence of the contract in relation to all provisions
of this Agreement.
8. Interests on late payments
Without prejudice to the Vendor's rights under clause 9 hereof, if any of
the instalments set out in the Third Schedule hereto shall remain unpaid
by the Purchaser at the expiration of the said period of fourteen (14) days,
interest on such unpaid instalment or instalments shall commence immediately
thereafter and be payable by the Purchaser, such interest to be calculated
from day to day at the rate of ten per centum (10%) per annum.
9. Default by Purchaser and determination of Agreement
(1) If the Purchaser:-
(a) fails to pay any instalments payable under clause 4(1) in accordance
with the Third Schedule hereto or any part thereof and any interest payable
under clause 8; or
(b) commits any breach of the terms or conditions contained in this Agreement
or fails to perform or observe all or any of the Purchaser's covenants herein
contained; or
(c) before payment in full of the purchase price of the said Parcel, commits
an act of bankruptcy or enters into any composition or arrangement with
his creditors or being a company enters into liquidation whether compulsory
or voluntary;
the Vendor may subject to sub-clause (2) hereof, annul the sale of the said
Parcel and forthwith terminate this Agreement and in such an event:-
(i) the Vendor shall be entitled to deal with or otherwise dispose of the
said Parcel in such manner as the Vendor shall see fit as if this Agreement
had not been entered into;
(ii) the instalments previously paid by the Purchaser to the Vendor, excluding
any interest paid, shall be dealt with and disposed of as follows:-
(a) firstly, all interest calculated in accordance with clause 8 hereof
owing and unpaid shall be paid to the Vendor;
(b) secondly, an amount to be forfeited by the Vendor as follows:
(i) where up to fifty per centum (50%) of the purchase price has been paid,
an amount equal to ten per centum (10%) of the purchase price;
(ii) where more than fifty per centum (50%) of the purchase price has been
paid an amount equal to twenty per centum (20%) of the purchase price;
(c) lastly, the residue thereof shall be refunded to the purchaser;
(iii) neither party hereto shall have any further claim against the other
for costs, damages, compensation or otherwise hereunder; and
(iv) each party hereto shall pay its own costs in the matter.
(2) If the Purchaser fails to comply with any of the terms of this Agreement
or if any of such unpaid instalments and interest remain unpaid for any
period in excess of twenty-eight (28) days after its due date, the Vendor
shall give the Purchaser or his solicitors not less than fourteen (14) days'
notice in writing by A.R. Registered post to treat this Agreement as having
been repudiated by the Purchaser and unless in the meanwhile such default
and/or breach alleged is rectified or such unpaid instalments and interest
are paid, this Agreement shall, at the expiration of the said notice, be
deemed to be annulled.
22. Time for handing over of vacant possession
(1) Vacant possession of the said Parcel to which water and electricity
supply are ready for connection shall be handed over to the Purchaser within
thirty-six (36) calendar months from the date of this Agreement;
(2) If the Vendor fails to hand over vacant possession of the said Parcel,
to which water and electricity supply are ready for connection to the said
Parcel, in time, the Vendor shall pay immediately to the Purchaser liquidated
damages to be calculated from day to day at the rate often per centum (10%)
per annum of the purchase price.
23. Manner of delivery of vacant possession
(1) Upon the issuance of a Certificate by the Vendor's Architect certifying
that the construction of the Parcel has been duly completed and water and
electricity supply are ready for connection to the Parcel and the Vendor
has applied for the issuance of the Certificate of Fitness for Occupation
from the Appropriate Authority and the Purchaser having paid all monies
payable under clause 4(1) in accordance with the Third Schedule and all
other monies due under this Agreement and the Purchaser having performed
and observed all the terms and covenants on his part under this Agreement
the Vendor shall let the purchaser into possession of the said Parcel PROVIDED
THAT such possession shall not give the Purchaser the right to occupy and
the Purchaser shall not occupy the said Parcel until such time as the Certificate
of Fitness for Occupation for the said Building is issued.
(2) Upon the expiry of fourteen (14) days from the date of a notice from
the Vendor requesting the Purchaser to take possession of the said Parcel,
whether or not the Purchaser has actually entered into possession or occupation
of the said Parcel, the Purchaser shall be deemed to have taken delivery
of vacant possession.
24. Completion of common facilities
(1) The common facilities serving the said housing development shall be
completed by the Vendor within thirty-six (36) calendar months from the
date of this Agreement.
(2) If the Vendor fails to complete the common facilities in time the Vendor
shall pay immediately to the Purchaser liquidated damages to be calculated
from day to day at the rate often per centum (10%) per annum of the last
twenty per centum (20%) of the purchase price.
I agree with the contention of the plaintiff that the Court of Appeal decision
in Ching Yik Development Sdn Bhd v Setapak Heights Development Sdn Bhd [1997]
1 AMR 89 is distinguishable from the present case as that case does not
deal with the issue of set-off.
The main ground of defence propounded by the defendants is that the plaintiff
is not entitled to unilaterally set-off the liquidated damages due to the
plaintiff against the final progressive payment due to the defendants.
The defendants' contention is that pursuant to Clause 23(1) of the agreement
the plaintiff has to make payment of the full purchase price of the said
property before the plaintiff is entitled to vacant possession. In Pembenaan
Leow Tuck Chui & Sons Sdn Bhd v Dr Leela's Medical Centre Sdn Bhd [1995]
2 AMR 1289, the Supreme Court had held that parties to a building contract
may by express words or "by clear implication" provide for the ouster or
exclusion of the common law right of set-off; in other words, each case
would turn upon the particular wording of the contract. And, in that particular
case the Supreme Court did find that the provisions of that governing PAM-formulated
contract showed an implicit intention of the parties to exclude the right
of set-off.
Thus, the issue for this court to determine is whether from the wording
of the agreement, there is express provision to exclude the right of set-off
or it can be implied that the parties had intended to exclude the right
of set-off. I have perused the whole agreement and in particular Clause
23(1) and I am of the view that the agreement does not provide that payment
of liquidated damages by the defendants is conditional upon full payment
of the purchase price nor does it by necessary implication prohibit a set-off
of liquidated damages against the balance of the purchase price.
In Insun Development Sdn Bhd v Azali Bakar [1996] 2 AMR 2180 His Lordship
Edgar Joseph Jr (delivering the judgment of the Federal Court) at pp 2187-2188
said:
The essential facts may be shortly stated. The agreement was dated December
12, 1984 and by Clause 18 thereof, it was provided as follows:
18. (1) The said building shall be completed by the vendor and vacant possession
delivered to the purchaser within twenty-four (24) calendar months from
the date of this agreement.
(2) If the vendor fails to deliver vacant possession of the said building
in time the vendor shall pay immediately to the purchaser liquidated damages
to be calculated from day to day at the rate of ten per centum (10%) per
annum of the purchaser price.
In giving judgment for the purchaser, the Judge relied heavily on the Malaysian
Privy Council decision in Loh Wai Lian v SEA Housing Corporation Sdn Bhd
[1987] 2 MLJ 1. It follows that the point of central importance to this
appeal is whether the present case is governed by the judgment of the Privy
Council in Loh Wai Lian, as the Judge thought.
And at pp 2193-2194 His Lordship said:
It is obvious from the judgment of the Privy Council in Loh Wai Lian that
but for the unusual language of Clause 17 of the contract of sale, which
had provided a formula for the computation of damages payable by the developer
to the buyer for delay, by defining not merely the terminus a quo (the opening
date) required under Rule 12(r) of the 1970 Rules but also the terminus
ad quem (the closing date) - not required under Rule 12(1)(r) - the case
would have been differently decided, for Their Lordships said this:
If the question is asked 'in the absence of such an express provision when
would the purchaser's right of action for damages for breach of contract
accrue?' the answer is plainly the date on which the breach occurred. But
parties to a contract are, of course, entitled to regulate or modify their
rights in the event of breach in any way that they think fit and the accrual
of any cause of action then becomes a matter of the correct construction
of what they have provided. This appeal raises no point of principle but
simply a question of what is the true construction of the contract in which
the parties entered.
In our view, for the reasons stated Loh Wai Lian is, therefore, readily
distinguishable from the present case and accordingly, the judge was, with
respect, wrong in holding that it was of decisive importance to the question
which arose for decision.
It follows, therefore, that our answer to the crucial question aforesaid
is: because the agreement by Clause 18(2) had provided for a formula for
the calculation of liquidated damages which defined the terminus a quo (the
20 opening date) but not the terminus ad quem (the closing date), the purchaser's
right of action for damages for breach of contract - following the general
rule - accrued on the date of the breach which, in this case, was the day
after the time limited under Clause 18(2) for the delivery of vacant possession,
that is to say, on December 12, 1986. Accordingly, the purchaser, having
commenced proceedings only on July 31, 1993, was more than seven months
out of time. We are thus driven to the inevitable conclusion that the purchaser's
claim was statute-barred under the provisions of s 6(1) of the Limitation
Act 1953.
The learned counsel for the defendants relies on the case of Loh Wai Lian
v SEA Housing Corporation Sdn Bhd [1987] 2 MLJ 1 to support the argument
that as the common facilities are not completed yet, the plaintiffs claim
is premature in that the full sum of liquidated damages due to the plaintiff
cannot be ascertained, and hence the cause of action has yet to arise.
It is clear that the Federal Court has in Insun Development Sdn Bhd v Azali
Bakar (supra) distinguished the decision in Loh Wai Lian v SEA Housing Corporation
Sdn Bhd [1987] 2 MLJ 1. I am of the view that the case of Loh Wai Lian v
SEA Housing Corporation Sdn Bhd (supra) has no application to the present
case before me.
Although the common facilities are still not completed to date, the plaintiffs
right of action for damages for breach of contract following the general
rule accrued on the date of the breach which, in this case, was the day
after the time limited under Clause 24(1) for the completion of the common
facilities; that is to say, on December 22, 1999. So l am of the view that
the claim of the plaintiff for set-off was proper and not premature.
In SEA Housing Corporation Sdn Bhd v Lee Poh Choo [1982] 2 MLJ 31, His Lordship
Suffian LP (delivering the judgment of the Federal Court) at p 33 said:
Three issues arises before us in the appeal:
(1) Is Clause 32 of the agreement valid?
(2) If so, was the learned Judicial Commissioner right in holding that the
acute shortage of cement, etc; did not come within Clause 32 such that the
defendant is not liable for the delay? and
(3) Did the plaintiff in withholding payment of the last instalment due
commit breach of the agreement?
And in p 34 His Lordship said:
As regards the third issue we are of the opinion that the plaintiff did
not breach the agreement when she withheld payment of the money demanded
by the defendant.
The plaintiffs cross-claim and the defendant's claim arises out of the same
transaction and are closely connected with each other. The plaintiff s cross-claim
is so closely connected with the defendant's demand that it would be manifestly
unjust to allow the defendant to enforce payment without taking into account
the plaintiffs cross-claim.
There has been a delay of 431 days in the delivery of vacant possession
of the said property.
The liquidated damages under Clause 22(2) of the agreement amounted to RM26,673.35.
As at the time of the defendants' notice of February 23, 2001, the defendants
have yet to issue a certificate of completion of the common facilities.
For the delay of 431 days the liquidated damages under Clause 24(2) of the
agreement amounted to RM5,334.67.
The plaintiffs right to liquidated damages is a cross-claim which arises
out of the same transaction as the defendants' right to be paid the balance
of the purchase price and is so closely connected with it that it would
be manifestly unjust if I were to order that the plaintiff should pay over
to the defendants the sums of RM51,729.57 and RM2.300 without taking into
account the amount of liquidated damages due to the plaintiff amounting
to RM33.883.20.
I am of the view that the plaintiff has an equitable right of set-off against
the final claim of the defendants. The plaintiff after setting off the said
sums of RM26,673.35 and RM5,334.67 forwarded vide letter dated March 12,
2001 from Choy & Associates, three cheques for the following sums due:-
(a) OUB cheque 018253 for a sum of RM 11,294 made out to Messrs Anoop &
See being the stakeholder's sum;
(b) OUB cheque 018252 for a sum of RM2,300 made out to Belleview Bina Sdn
Bhd being the balance outstanding for an additional package;
(c) OUB cheque 018251 for a sum of RM8,427.15 made out to Trans-Intan Sdn
Bhd, the defendants, being the final progressive payment less the liquidated
damages due to the plaintiff (RM33,883.20 - [RM26.673.35 + RM5,334.67]).
By the aforesaid action the plaintiff has fulfilled his obligations under
the agreement. And I am also of the view that the plaintiff did not breach
the agreement when the plaintiff paid the difference of the defendants'
claim dated February 23, 2001 less the set-off. The defendants have via
their letter of March 15, 2001 and March 19, 2001 evidenced an intention
to repudiate the agreement and refused any longer to be bound by it by refusing
to accept the payment tendered by the plaintiff on the ground that the plaintiff
has no right to set-off. I am of the view that it was the defendants who
wrongly repudiated the agreement by the aforesaid letters.
The learned counsel for the defendants had submitted that the plaintiff
did not aver that he is jobless at present. It was only disclosed subsequently
after the defendants raised this issue. The plaintiff has failed to show
that he has the means to fulfil his undertaking as to damages. The answer
to this can be found in the case of Cheng Hang Guan v Perumahan Farlim (Penang)
Sdn Bhd [1988] 3 MLJ 90 where His Lordship Edgar Joseph Jr J (as he then
was) at p 100 said:
In any event, the court will not generally deny a plaintiff an interlocutory
injunction to which he would otherwise be entitled simply on the ground
that his cross-undertaking in damages would be of limited or of no value.
So, for example, in Allen v Jambo Holdings Ltd [1980] 2 All ER 502 the Court
of Appeal held, when granting a Mareva injunction, that a cross undertaking
was acceptable from the plaintiffs although he was legally aided. The rationale
behind this was that questions of financial ability ought not to affect
the position in regard to what is the essential justice of the case.
The principles of law in respect of an interim mandatory injunction are
succinctly set out in the case of Gibb & Co v Malaysia Building Society
Bhd [1982] 1 MLJ 271.
I agree with the submission of the plaintiff that so long as the strata
title to the said property has not been issued, the plaintiff would be unable
to deal with or dispose of the said property without the consent or knowledge
of the defendants. The plaintiff has paid to the defendants the full purchase
price of the said property less the liquidated damages due to him.
The plaintiff would also be put to the expense and inconvenience of paying
the full sum of the final progressive payment while the defendants would
be allowed to remain indebted to the plaintiff indefinitely in respect of
the liquidated damages.
I also agree with the contention of the plaintiff that while the plaintiff
has settled all outstanding amounts due to the defendants and he is without
dispute the legal and beneficial owner of the said property, the defendants
are nevertheless withholding delivery of vacant possession of the said property
to coerce the plaintiff to pay out monies without taking the issue of set-off
of the liquidated damages into consideration.
This application is urgent as the defendants have by their conduct shown
their intention to terminate the agreement and refuse any longer to be bound
by it notwithstanding that the plaintiff has paid to the defendants the
full purchase price of the said property less the liquidated damages due
to him.
I find that the balance of convenience lies in favour of the plaintiff.
On the other hand, there will be little, if any, hardship caused to the
defendants if the injunction is granted in that the defendants would have
to do little more than to hand the keys to the said property over to the
plaintiff. Damages is not an adequate remedy in this case.
The issue of whether the plaintiff has a right of set-off in respect of
the liquidated damages due to the plaintiff is a serious issue to be tried.
I am of the view that the defence of the defendants that the plaintiff has
no right to set-off will ultimately fail in the trial of this case. The
plaintiff's case is "unusually sharp and clear" which is a fit and proper
case to grant the mandatory injunction.
In view of the aforesaid, I granted orders in terms of prayers (i), (ii)
and (iii) of the application.
Cases
Cheng Hang Guan v Perumahan Farlim (Penang) Sdn Bhd [1988] 3 MLJ 90; Ching
Yik Development Sdn Bhd v Setapak Heights Development Sdn Bhd [1997] 1 AMR
89; Gibb & Co v Malaysia Building Society Bhd [1982] 1 MLJ 271; Insun Development
Sdn Bhd v Azali Bakar [1996] 2 AMR 2180; Loh Wai Lian v SEA Housing Corporation
Sdn Bhd [1987] 2 MLJ 1; Pembenaan Leow Tuck Chui & Sons Sdn Bhd v Dr Leela's
Medical Centre Sdn Bhd [1995] 2 AMR 1289; SEA Housing Corporation Sdn Bhd
v Lee Poh Choo [1982] 2 MLJ 31
Legislations
Housing Developers (Control and Licensing) Act 1966
Representation
Daphne Choy (Choy & Associates) for Plaintiff
Ong Wee En (Shahrizat & Tan) for Defendants
|