Max-Benefit Sdn Bhd v Phuah Thean An
& Anor
HIGH COURT (KUALA LUMPUR) - CIVIL APPEAL NO R1-11-188
OF 1999 KC VOHRAH
16 OCTOBER 2000
Civil Law Act
- Assignment - Absolute assignment - Whether there was absolute
assignment - Whether plaintiffs entitled to sue in own names - Civil Law
Act 1956s 4(3)
Land Law
- Housing developers - Damages for late delivery - Delay
in completion - Whether plaintiff could bring action for late delivery damages
- Housing Developers (Control and Licensing) Regulations 1989 Schedule G
The plaintiffs, two joint purchasers of
a property from the defendant, a housing developer had jointly assigned
their rights title and interests in the sale and purchase agreement to Hock
Hua Bank Bhd ('the Bank') in return for a loan from the Bank to purchase
the property. There was late delivery of the property which was a breach
of one of the terms of the sale and purchase agreement. The magistrate's
court gave a summary judgement in favour of the plaintiffs. The defendant
appealed. Two questions were posed to the court: (i) whether the plaintiffs
who had assigned their rights and interests in the property could sue the
defendant; and (ii) whether the plaintiffs could sue for liquidated damages
for late delivery.
Held, dismissing the appeal:
(1) Although the assignment was stated to be absolute,
in effect it was not. The
assignment was purely for the purpose of securing the loan. The implication
is that the assignment of the equitable chose in action would come to an
end and it would revert back to the assignors on one of the events taking
place. The first event is where the loan is fully repaid. The second event
is where the developer has obtained the legal title to the property and
the property is then transferred to the assignors-purchaser with the consent
of the assignee-bank. The assignment of the equitable estate in the property
was thus conditional. Since there was not absolute assignment, the plaintiffs
had locus standi to sue the defendant (see p 556C-G).
(2) By virtue of Schedule G to the Housing Developers
(Control and Licensing) Regulations 1989, the plaintiffs were entitled to
damages for late delivery they had suffered from the time they were supposed
to have been given delivery up to the time they eventually were given vacant
possession (see p557D).
[Bahasa Malaysia summary
Plaintif-plaintif, dua pembeli bersama satu hartanah daripada
defendan, telah bersesama menyerahkan hak hakmilik dan kepentingan dalam
perjanjian jual beli kepada Hock Hua Bank Bhd ('Bank tersebut') sebagai
balasan terhadap satu pinjaman daripada Bank tersebut untuk membeli hartanah
tersebut. Penghantaran lewat hartanah tersebut telah berlaku dan ini merupakan
satu pelanggaran kepada salah satu daripada terma-terma perjanjian jual
beli tersebut. Mahkamah majistret telah memberikan satu penghakiman terus
yang menyebelahi plaintif-plaintif. Defendan telah membuat rayuan. Dua persoalan
telah dikemukakan kepada mahkamah: (i) sama ada plaintif-plaintif yang telah
menyerahkan hak dan kepentingan mereka di dalam hartanah tersebut boleh
menyaman defendan; dan (ii) sama ada plaintif-plaintif boleh menyaman untuk
ganti rugi yang ditetapkan kerana penghantaran lewat.
Diputuskan, menolak rayuan
tersebut:
(1) Walaupun penyerahan hak tersebut telah dinyatakan
sebagai mutlak, sebenarnya ia tidak begitu. Penyerahan hak tersebut adalah
semata-mata untuk tujuan menjamin pinjaman tersebut. Akibatnya ialah penyerahan
hak hakmilik ekuiti yang dipilih dalam tindakan akan tamat dan kembali kepada
penyerah hak dalam salah satu peristiwa yang berlaku. Peristiwa pertaman
adalah di mana pinjaman tersebut telah dibayar semula sepenuhnya. Peristiwa
kedua adalah di mana pemaju telah mendapat Penyerahan hak hakmilik ekuiti
dalam hartanah tersebut adalah bersyarat. Memandangkan tiada penyerahan
hak mutlak, plaintif-plaintif mempunyai locus standi untuk menyaman defendan
(lihat ms556C-G)
2) Menurut Jadual G kepada
Peraturan-Peraturan Pemaju Perumahan (Kawalan dan Pelesenan) 1989, plaintif-plaintif
berhak mendapat ganti rugi kerana penghantaran lewat yang mereka alami daripada
masa mereka telah sepatutnya membuat penyerahan sehingga masa mereka akhirnya
diberikan milikan kosong (lihat ms 557D).]
Notes
For cases on assignment, see 1 Mallal's Digest
(4th Ed, 1998 Reissue) paras 2618-2628.
For cases on housing developers, see 8 Mallal's Digest
(4th Ed, 1999 Reissue) paras 2073-2114.
Cases referred to
Durham Brothers v Robertson
[1898] 1 QB 765 (refd)
Nouvau Mont Dor (M) Sdn Bhd v Faber Development Sdn
Bhd [1984] 2 MLJ 268 (refd)
Legislation referred to
Civil Law Act 1956 s 4(3)
Housing Developers (Control and Licensing) Regulations
1989 Schedule G
Appeal from: Summons No 72-67452-1998
(Magistrate's Court, Kuala Lumpur)
Rajvinder Singh (Dennis Nik & Wong)
for the appellant.
Anthony Kuan (SM Kam & Associates)
for the respondent.
KC Vohrah J:
In this case the plaintiffs, two joint purchasers of a
property from the defendant, a housing developer, had jointly assigned their
rights title and interests in the sale and purchase agreement to Hock Hua
Bank Bhd, in return for a loan from the bank to purchase the property. There
was late delivery of the property which was a breach of one of the terms
of the sales and purchase agreement. Summary judgement in the magistrates'
court Kuala Lumpur was given in favour of the plaintiffs and the defendant
has appealed against the decision of the court.
Two questions have been posed to this court in this
appeal.
The first question is: can the
two purchasers who had assigned their rights and interests in the sales
and purchase sue the developer?
The developer says the purchasers
cannot do so as they had made an absolute assignment of their rights and
interests in their property to the bank within the meaning of s 4 (3) of
the Civil Law Act 1956 and relying on that provision and Nouvau Mont
Dor (M) Sdn Bhd v Faber Development Sdn Bhd [1984] 2 MLJ 268 argue that
only the bank has the right to sue it.
Nouvau Mont dor (M) Sdn Bhd
was decided on the peculiar facts of the
case. Whether or not there has been an absolute assignment is dependent
on what was the aim of the transaction
The recital in the deed of assignment
refers to the fact that the assignors-purchasers had applied for a loan
and that that the bank had agreed to grant to the assignors a loan "in the
principal sum of Ringgit Malaysia two hundred thousand RM200,000 only ('the
Loan') which expression shall include wherever the context so permits any
balance or any part thereof upon the security of the said property
and upon the terms and conditions contained in the bank's letter(s)
of offer to the assignor(s) dated 28 September 1994 and upon the terms and
conditions of a loan agreement of even date. (Emphasis added.)
There is also reference to the
fact that the separate document of title to the property that was purchased
had yet to be issued by the relevant authorities.
The assignment is in the following
terms
IN CONSIDERATION of the Bank
agreeing to the grant, granting and/or continuing to grant to the Assignor(s)
the Loan upon the terms and conditions more particularly set out in the
Loan Agreement, the Assignor(s) hereby
Assign absolutely unto the bank
all the Assignor(s)'s rights title and interests in and to the said Property
by and under the Principal Sale Agreement and all other whatsoever deed(s)
and agreement(s) (if any) mentioned herein and the full benefit and entire
advantage thereof and of all stipulations therein contained and all remedies
for enforcing the same which the bank hereby accepts.
AND PROVIDED ALWAYS
that notwithstanding the Assignment herein contained
or any other provision of this Assignment the Assignor(s) shall and hereby
undertake to continue to observe perform and be bound by all whatsoever
conditions, covenants and stipulations therein on the part of all assignor(s)
expressed and contained in the principal sale agreement and all whatsoever
deed(s) and agreement(s) (if any) mentioned herein.
At the tail end of the assignment
deed appears the consent by the developer to the assignment and there is
expressed by the developer an undertaking to transfer the document of title
of the strata title upon issuance of the title to the purchasers after seeking
the bank's consent.
Although the assignment is stated
to be absolute in effect it is not. The assignment and there is expressed
by the developer an undertaking to transfer the document of title of the
strata title upon issuance of the title to the purchasers after seeking
the bank's consent.
The implication is that the assignment
of the equitable chose in action would come to an end, it would revert
back to the assignors on one of the two events taking place, whichever comes
earlier. The first event is where the loan is fully repaid. The second event
is where the developer has obtained the legal title to the property and
the property is then transferred to the assignors-purchasers with the consent
of the assignee bank.
Thus is is quite obvious that the
assignment of the equitable estate in the property was conditional and was
merely to secure the loan and was not an absolute assignment (see Durham
Brothers v Robertson [1898] 1 QB 765 ). The assignment to the bank was
by way of charge only.
There was no absolute assignment
in this case and the bank has no locus standi in this case. I therefore
hold the purchasers as plaintiffs have locus standi to sue the developer-defendant.
The second question is this: can
the purchasers sue for liquidated damages for late delivery? For late delivery
and liquidated damages cl 22 of the sale and purchase agreement provides
in respect of the parcel of property as between the developer (as vendor)
and the purchasers thus:
(1) The said parcel shall be completed
by the vendor and vacant possession with the connection of water and electricity
supply to the said parcel. shall be handed over to the purchasers within
thirty six (36) calendar months from the date of the agreement.
(2) If the vendor fails to hand
over vacant possession of the said parcel, together with the connection
of water and electricity supply to the said parcel, in time, the vendor
shall pay immediately to the purchasers liquidated damages to be calculated
from day to day at the rate of ten per centum (10%) pa of the purchase price.
Vacant possession as per cl 22(1)
was to have been delivered on 15 September 1997, 36 calendar months from
the date of the sales and purchase agreement.
Vacant possession was handed only
on 22 June 1998.
Clause 22 of the sales and purchase
agreement is a provision which by virtue of Schedule G to the Housing Developers
(Control and Licensing) Regulations 1989 had to be mandatorily inserted
into the Sales and Purchase Agreement, it being a requirement of the prescribed
contract (Regulations) except that while the clause relating to vacant possession
in the Schedule had provided for the property to be handed over in 24 months
(amended as at 1 August 1994) the developer had provided for delivery within
36 months.
Clause 20(1) of Schedule G, a statutory
provision, envisages a purchaser being entitled to damages for the late
delivery he has suffered from the time he was supposed to have been given
delivery up to the time he eventually was given vacant possession and effect
must be given to the statutory provision which quantified the liquidated
damages from day to day at the rate of 10% pa of the purchase price. Clause
22 of the sale and purchase agreement is a mandatory reflection of that
statutory provision and effect must be given to the clause in the agreement.
There is no dispute that the vacant
possession was supposed to have been delivered on 15 September 1997 and
that in fact it was delivered late on 22 June 1998 and the purchasers as
plaintiffs are entitled to the liquidated damages they have claimed.
Appeal dismissed with costs.
Appeal dismissed.
Reported by Jafisah Jaafar
|