MAWAR AWAL (M) SDN BHD V. KEPONG
MANAGEMENT SDN BHD & ANOR
HIGH COURT MALAYA, KUALA LUMPUR
[SUIT NO: S6-22-2014-2003]
ABDUL MALIK ISHAK J
15 SEPTEMBER 2005
CONTRACT:
Specific performance - Sale and purchase Agreement - Breach of terms of
Agreement - Failure to grant power of attorney to plaintiff - Whether a
mandatory obligation - Whether sale and purchase Agreement extinguished by
Deed of assignment and another Agreement of a later date - Allegation of
novation - Whether improbable - Whether just and equitable for court to
grant specific performance
CONTRACT: Sale and purchase Agreement - Specific performance,
application for - Breach of terms of Agreement - Failure to grant power of
attorney - Whether a mandatory obligation - Whether sale and purchase
Agreement extinguished by Deed of assignment and another Agreement of a
later date - Allegation of novation - Whether improbable - Whether just and
equitable for court to grant specific performance
CONTRACT: Remedies - Specific performance, application for - Breach
of terms of Agreement - Failure to grant power of attorney to plaintiff -
Whether a mandatory obligation - Whether just and equitable for court to
grant specific performance
This was the plaintiff's application by way of a summons in chambers in
encl. 7 for summary judgment in an action for specific performance of a
contract for the sale and purchase of a piece of land ('the land'). By a
sale and purchase agreement dated 2 April 1999, the first defendant agreed
to sell and the plaintiff agreed to purchase the land. Under the term of the
sale and purchase agreement by cl. 3.3 it was agreed that the first
defendant would grant a power of attorney to the plaintiff for the purpose
of developing the land. On 8 April 1999, the first defendant and the second
defendant entered into a deed of assignment whereby the former agreed to
assign all the proceeds arising from the sale and purchase agreement to the
second defendant in consideration of the sum of RM15 million paid by the
second defendant to the first defendant. There was also an agreement dated 8
April 1999 between the plaintiff and the second defendant where the latter
had agreed to accept from the plaintiff payment of proceeds under the sale
and purchase agreement in the manner as set out in the assignee agreement.
In compliance with its obligations under the sale and purchase agreement and
the assignee agreement, the plaintiff had proceeded to apply for and
obtained approvals for all the relevant plans for the development of the
land. However, the plaintiff was unable to proceed further when it could not
apply for the developer's licence and the advertising permit without the
power of attorney from the registered proprietor of the land, namely, the
first defendant.
By way of a letter dated 17 November 2003, the plaintiff demanded that the
first defendant grant/or execute a power of attorney in favour of the
plaintiff in compliance with the said cl. 3.3 of the sale and purchase
agreement within seven days from the said letter. The first defendant failed
and neglected to do so. It was the stand of the plaintiff that it had
suffered losses and incurred damages. Furthermore, by reason of the
aforesaid, the plaintiff was unable to fulfill its obligations under the
assignee agreement towards the second defendant. The plaintiff submitted
that it was entitled to specific performance of the sale and purchase
agreement that was executed between the plaintiff and the first defendant
dated 2 April 1999 pursuant to O. 81 of the Rules of the High Court 1980 ('RHC').
The defendants, however, alleged that there was novation in law wherein the
sale and purchase agreement had been discharged or replaced by the said deed
of assignment dated 8 April 1999 and said agreement dated 8 April 1999.
Held (order in terms of encl. 7)
[1]Clause 3.3 of the sale and purchase agreement dated 2 April 1999 states
that the first defendant 'shall grant' to the plaintiff a power of attorney
to be prepared, stamped and registered at the High Court; this was, in fact,
a mandatory obligation posed on the first defendant. The wording of cl. 3.3
of the sale and purchase agreement was clear and unequivocal and the court
must give effect to it because the said clause could be specifically
enforced without the need of supervision for its performance. Damages would
not be an adequate remedy since cl. 3.3 of the sale and purchase agreement
involved the rights over an immovable property and that the plaintiff was
ready and willing to perform its obligation under the sale and purchase
agreement. (pp 311 b & d-f)
[2]The defendants' allegation that it need not perform any obligations under
the sale and purchase agreement since it had been extinguished by the deed
of assignment and agreement dated 8 April 1999 was a fallacy. The terms and
conditions of these three legal documents were not mutually exclusive. They
supplemented each other and they effectively vary some of the terms agreed
upon between the parties. It was unconscionable for the defendants to now
allege that none of them was obliged to perform the first defendant's duties
under the sale and purchase agreement. The defendants' allegation of
novation was so inconsistent with contemporaneous documents and was so
improbable. The deed of assignment dated 8 April 1999 and the agreement
dated 8 April 1999 did not extinguish the liabilities and obligations of the
first defendant under the sale and purchase agreement dated 2 April 1999.
(pp 314 d-h & 315 a, e-g)
[3]The sale and purchase agreement did not provide for any condition
precedent to be fulfilled by the plaintiff before the first defendant
granted the power of attorney to the plaintiff. There was also no
requirement that the plaintiff must first produce proof to justify the need
for a power of attorney. The first defendant had no discretion to decide
whether or not to execute and deliver the power of attorney. (p 317 a-b)
[4]It was just and equitable for this court to grant specific performance of
the sale and purchase agreement because the plaintiff had expended a
substantial amount of money on the land based on the defendants' promise to
comply with its obligations under the sale and purchase agreement in
particular its obligation to execute a power of attorney in the plaintiff's
favour. The court thus granted summary judgment to be entered for specific
performance of the sale and purchase agreement as prayed for in encl. 7. (p
320 d-f)
[5]In the alternative, the plaintiff had prayed for damages in lieu of
specific performance against the first defendant. In this connection,
reference to cl.9 of the sale and purchase agreement should be made. That
clause stipulated that in the event of default the purchaser (referring to
the plaintiff) may in lieu of specific performance elect to sue for damages
for breach of contract from the vendor (referring to the first defendant).
The first defendant was aware at all material times that construction works
would be delayed and that the plaintiff would suffer losses and damages if
the power of attorney was not granted. Consequently it was just and proper
that the first defendant indemnified the plaintiff on any claims/demands
which the second defendant may bring against the plaintiff under the
agreement dated 8 April 1999 entered between the plaintiff and the second
defendant. (p 322 c-f)
Cases referred to:
Alloy Automotive Sdn Bhd v. Perusahaan Ironfield Sdn Bhd
[1986] 1 CLJ 2; [1986] CLJ (Rep) 45 SC(refd)
Bank of Tokyo Ltd v. Mohd Zaini Arshad (Maria Pragasam, Intervenor) [1991] 2
CLJ 989; [1991] 2 CLJ (Rep) 341 HC(refd)
Bigg v. Boyd Gibbins Ltd [1971] 2 All ER 183 (refd)
Brinks Ltd v. Abu-Saleh & Ors (No 1) [1995] 4 All ER 65 (refd)
Chan Kin & Anor v. Chareen Realty Development Sdn Bhd [1988] 1 LNS 166;
[1989] 1 MLJ 62 (refd)
Chin Yew Loy Holdings Sdn Bhd lwn. Au Metalvest (M) Sdn Bhd [2002] 6 CLJ 141
HC (refd)
Chappell v. Times Newspappers Ltd [1975] 1 WLR 482 (refd)
Chong Hoong & Anor v. Wong Yuen Sang [1975] 1 LNS 13; [1976] 1 MLJ 282 (refd)
Chow Yoong Hong v. Tai Chet Siang [1959] 1 LNS 20; [1960] 1 MLJ 130 (refd)
Codd v. Delap [1905] 92 LT 510 (refd)
Cud v. Rutter [1720] IP Wms 570 (refd)
Harvela Investments Ltd v. Royal Trust Co of Canada [1985] 2 All ER 966 (refd)
Keet Gerald Francis Noel John v. Mohd Noor Abdullah [1995] 1 CLJ 293 CA (refd)
Lamare v. Dixon [1873] LR 6 HL 414 (refd)
Lee Hoy v. Chen Chi [1970] 1 LNS 57; [1971] 1 MLJ 76 (refd)
Lim Sin Oo v. Cheah Tjeng Siong [1989] 1 CLJ 953; [1989] 2 CLJ (Rep) 68
HC(refd)
LYL Hooker Sdn Bhd v. Tevanaigam Savisthri & Anor [1987] 1 CLJ 356; [1987]
CLJ (Rep) 179 SC(refd)
M Ratnaval v. S Lourdenadin [1988] 2 MLJ 371 (refd)
Masalam Sdn Bhd v. Ngah Embong & Anor [1998] 2 CLJ 817 CA(refd)
Milward v. Earl of Thanet [1801] 5 Ves 720 (refd)
Narayanan Chettiar Raman Chettiar v. Samuel Jivamoney Dass Chelliah [1986] 1
CLJ 579; [1986] CLJ (Rep) 547 HC(refd)
Nik Mohamed Salleh v. Tengku Besar Zabidah [1969] 1 LNS 121; [1971] MLJ 73 (refd)
Perkapalan Shamelin Jaya Sdn Bhd & Anor v. Alpine Bulk Transport New York
[1998] 1 CLJ 424 CA(refd)
Polygram Records Sdn Bhd v. The Search [1994] 3 CLJ 806 HC(refd)
Quadrat Visual Communications Ltd v. Hutchison Telephone UK [1993] BCLC
442(refd)
Rainbow Estates Ltd v. Tokenhold Ltd [1998] 2 All ER 860 (refd)
Ruby Construction Sdn Bhd v. Sun Metal Works Sdn Bhd [1997] 3 CLJ Supp
183(refd)
Sekemas Sdn Bhd v. Lian Seng Co Sdn Bhd [1989] 2 CLJ 142; [1989] 1 CLJ (Rep)
154 SC(refd)
Stickney v. Keeble [1915] AC 386 (refd)
Storer v. Manchester City Council [1974] 3 All ER 824 (refd)
Syed Azman Syed Mohamed v. Lian Seng (KL) Construction Co Sdn Bhd [1992] 4
CLJ 2194; [1992] 3 CLJ (Rep) 625 HC(refd)
Tan Sri Khoo Teck Puat v. Plenitude Holdings Sdn Bhd [1995] 1 CLJ 15 FC (refd)
Tito v. Waddell (No 2) [1977] Ch 106 (refd)
Vambadi Vairapperumal v. Sinniah Sellamuthu [1998] 1 LNS 609(refd)
Wilson v. Northampton and Banbury Junction Rly Co [1874] 9 Ch App 279 (refd)
Yap Mong Siew & Ors v. Leong Hum [1998] 3 CLJ Supp 513(refd)
Yeong Ne Hong lwn. Bumida Engineering and Construction Sdn Bhd [1995] 1 LNS
307; [1996] 4 MLJ 350 (refd)
Zaibun Sa Syed Ahmad v. Loh Koon Moy [1982] CLJ 457; [1982] CLJ (Rep) 58
PC(refd)
Zainab Mohamed v. Syarikat Permodalan Johor (PP) Sdn Bhd [1998] 4 CLJ Supp
262(refd)
Legislation referred to:
Contracts Act 1950, s. 63
Rules of the High Court 1980, O. 14, O. 81 rr. 1(2), 3
Specific Relief Act 1950, ss. 11(1), 18
Other source(s) referred to:
ICF Spry, The Principles of Equitable Remedies, 5th edn, p 78
PV Baker & PSTJ Langan, Snell's Principles of Equity, 28 edn, pp 569, 570
RP Meagher, WMC Gummow & JRF Lehane, Equity Doctrines and Remedies, 3rd edn,
para 2004
For the plaintiff - Leong Wai Hong (Claudia Cheah Pek Yee & Sharon Tan Geok
Bee); M/s Skrine
For the defendants - Ringo Low Kim Leng; M/s Ringo Low & Assoc
Reported by Suhainah Wahiduddin
[As ordered.]
JUDGMENT
Abdul Malik Ishak J:
Introduction
This was the plaintiff's application by way of a summons in chambers in
encl. 7 for summary judgment in an action for specific performance of a
contract for the sale and purchase of a piece of land held under GM 1530 and
known as Lot 798, Mukim of Batu, District of Kuala Lumpur, Wilayah
Persekutuan measuring approximately 13,516.5 square metres in area
(hereafter referred to as the "land"). Everything revolved on the sale and
purchase of that land. This judgment focussed on
O. 81 of the Rules of the High Court 1980.
Facts Of The Case
By a sale and purchase agreement dated 2 April 1999, the first defendant
agreed to sell and the plaintiff agreed to purchase the land at the total
consideration of RM15 million. It was a term of the sale and purchase
agreement that the land would be developed into a mixed residential and
commercial development by the plaintiff. And under the term of the sale and
purchase agreement it was agreed that the first defendant would grant a
power of attorney to the plaintiff for the purpose of developing the land.
This was clearly set out in cl. 3.3 of the sale and purchase agreement which
reads as follows:
3.3 At the request of the purchaser, the vendor will remain the
registered proprietor of the said land notwithstanding the completion of
this agreement as stipulated in clause 3.3 hereof provided the vendor shall
grant to the purchaser a power of attorney to be prepared stamped and
registered at the High Court at the purchaser's expense to sign and execute
all lawful deeds documents and agreements which are related to:
(a) the application for the approval of the buildings and other plans
connected with the construction of the buildings and the commercial lots and
the development of the project;
(b) the application for the sub-division and issuance of separate strata
titles of the buildings and the commercial lots;
(c) the sale and transfer of the buildings to the end purchasers thereof
in compliance with the Housing Developer's (Control and Licensing) Act 1966
and the sale and transfer of the commercial lots to the purchasers thereof;
and
(d) the assignment (if necessary) of the buildings and the commercial
lots by the aforesaid end purchasers in favour of their respective
end-financiers by way of security for any facility granted by the
end-financier to the said purchasers to finance the purchase of the said
buildings and commercial lots.
The other relevant terms of the sale and purchase agreement would be cl.
9. That clause states as follows:
9.1 In the event of any breach of this agreement by the vendor or the
vendor shall wilfully fail or refuse to complete this transaction, the
purchaser shall be entitled to take such action as may be available to the
purchaser at law to enforce specific performance of this agreement against
the vendor or in lieu thereof to elect to sue for damages for breach
of contract from the vendor without prejudice to any rights which the
purchaser may be entitled against the vendor in respect of the antecedent
breach of this agreement.
Two other clauses of the sale and purchase agreement must be mentioned.
They are cls. 12 and 13 and they are worded as follows:
12. It is hereby agreed that the vendor may at its absolute discretion
assign all its rights interests and benefits under this agreement to a third
party and the purchaser will upon the request of the vendor endorse its
consent thereto.
13. Time wherever mentioned shall be of the essence of this agreement.
There was a deed of assignment dated 8 April 1999 entered between the
first and the second defendants. By this deed of assignment, the first
defendant agreed to assign all the proceeds arising from the sale and
purchase agreement to the second defendant in consideration of the sum of
RM15 million paid by the second defendant to the first defendant. Reference
to term 2 of the deed of assignment should be made. There it provides that
the second defendant covenanted and undertook with the first defendant to
observe, discharge and carry out all the duties, responsibilities,
covenants, undertakings, stipulations and obligations on the part of the
first defendant as contained in the sale and purchase agreement.
There was also an agreement dated 8 April 1999 between the plaintiff and
the second defendant. By this agreement the second defendant agreed to
accept from the plaintiff payment of proceeds under the sale and purchase
agreement in the manner as set out in the assignee agreement.
In consideration of the acceptance of the proceeds in kind by the second
defendant, the plaintiff has undertaken various obligations under the
assignee agreement towards the development of the land. Under cl. 10 of the
assignee agreement, time wherever mentioned therein shall be the essence of
the agreement.
In compliance with its obligations under the sale and purchase agreement
and the assignee agreement, the plaintiff has proceeded to apply for and
obtained approvals for all the relevant plans including the layout plans,
buildings plans, earthwork plans and approvals from the Foreign Investment
Committee. Furthermore, the plaintiff has even proceeded with the
development on the land in that it has erected hoarding around the land,
mobilised its plant, equipment, machinery and labour force thereon and has
completed test piling and commenced earthworks thereon.
But, all said and done, the plaintiff was unable to proceed further with
the development in that it was unable to apply for the developer's licence
and the advertising permit without the power of attorney from the registered
proprietor of the land, namely, the first defendant. This constituted the
breach of contract by the first defendant, so submitted the plaintiff.
Incidentally, there was also a deed of indemnity dated 2 April 1999
between the plaintiff, the first defendant and Pilecon Engineering Berhad.
By this deed of indemnity, Pilecon Engineering Berhad agreed to indemnify
the first defendant in respect of a banking facility executed by the first
defendant over the said land.
Now, despite the plaintiff's numerous oral and written requests by way of
a letter from Pilecon Engineering Berhad to Messrs Hamzah Sulaiman &
Partners, solicitors for the first defendant dated 18 July 2003 and the
plaintiff's letters dated 27 February 2003, 16 April 2003, 24 April 2003, 12
May 2003, 29 May 2003 and 27 June 2003 requesting the first defendant to
grant and/ or execute a power of attorney to the plaintiff, the first
defendant has in breach of the sale and purchase agreement in particular cl.
3.3 thereof failed, refused and/or neglected to do so. By way of a letter
dated 17 November 2003 from the plaintiff's solicitors Messrs Skrine to the
first defendant's solicitors Messrs Hamzah Sulaiman & Partners, the
plaintiff demanded that the first defendant grant and/or execute a power of
attorney in favour of the plaintiff in compliance with cl. 3.3 of the sale
and purchase agreement within seven (7) days from the date of the said
letter. But the first defendant again failed refused and/or neglected to do
so. It was the stand of the plaintiff that it had suffered losses and
incurred damages in that it had incurred substantial sums for the
development of the land. Furthermore, by reason of the aforesaid, the
plaintiff was unable to fulfill its obligations under the assignee agreement
towards the second defendant. It was the stand of the plaintiff that it was
entitled to be indemnified by the first defendant against any claim or
demand that may be brought against the plaintiff by the second defendant
under the assignee agreement.
The obligations of the second defendant under the deed of assignment may
be stated in this way. That the second defendant having agreed under the
deed of assignment to observe, discharge and carry out all the duties,
responsibilities, covenants, undertakings, stipulations and obligations on
the part of the first defendant as contained in the sale and purchase
agreement, was obliged to secure the granting of the power of attorney by
the first defendant in favour of the plaintiff. However, despite numerous
oral and written requests by way of two letters both dated 27 June 2003 from
the plaintiff, the second defendant has failed, refused and/or neglected to
procure the granting of the power of attorney by the first defendant to the
plaintiff (see exh. "A7" of encl. 6 that exhibited these two letters). The
stand of the plaintiff was this. That it was ready and willing, at all
material times, to continue to perform its obligations under the sale and
purchase agreement dated 2 April 1999 as well as the assignee agreement
dated 8 April 1999.
The Prayers Sought For In encl. 7 By The Plaintiff
By way of encl. 7, the plaintiff sought for the following prayers:
Against the First Defendant
(1) an Order pursuant to Order 81 of the Rules of the High Court 1980 for
the specific performance of the Sale and Purchase Agreement dated 2nd April
1999 that was executed between the Plaintiff and the first Defendant;
(2) the specific performance of Clause 3.3 of the said Sale and Purchase
Agreement dated 2nd April 1999 that is referred to in the Writ and Statement
of Claim and that is mentioned in the terms of the Minutes enclosed herein;
(3) an Order that at the First Defendant's refusal to execute the Power
of Attorney pursuant to Clause 3.3 of the Sale and Purchase Agreement dated
2nd April 1999 between the Plaintiff and the First Defendant within seven
(7) days from the date of this Order, the Registrar of this Court be given
the power to execute the Power of Attorney;
(4) damages for the breach of contract in lieu of specific performance;
(5) damages in addition to specific performance;
(6) repayment of the deposit to the plaintiff that was paid to the First
Defendant under the Sale and Purchase Agreement in the amount of
RM100,000.00 with interest at 8% per year from 2-3-1999 until the date of
full payment;
(7) a lien on the said Land in favour of the Plaintiff for repayment of
the amount of RM100,000.00; damages, interest and costs awarded in this
action against the First Defendant; (and)
(8) a declaration that the First Defendant indemnifies the Plaintiff on
any claims or demands that might be brought against the Plaintiff by the
Second Defendant under the Agreement dated 8th April 1999 between the
Plaintiff and the Second Defendant.
Against the Second Defendant
(9) A declaration that the Plaintiff is not liable to the Second
Defendant for any loss or damage in relation to the Agreement dated 8th
April 1999 between the Plaintiff and the Second Defendant.
Against the First and Second Defendants
(10) interest at the rate of 8% per year on any amount awarded by this
Court to the Plaintiff from 28th July 2000 until the date of full payment;
(11) costs to be paid by the First Defendant and Second Defendant; (and)
(12) any order, direction or other relief whatsoever as this Honourable
Court deems just and reasonable.
The grounds in support of encl. 7 were simply that the plaintiff was
entitled to specific performance of the sale and purchase agreement that was
executed between the plaintiff and the first defendant dated 2 April 1999
pursuant to
O. 81 of the Rules of the High Court 1980 ("RHC").
Order 81 of the RHC relates to the procedure for summary judgment and it
applies to any action begun by writ indorsed with a claim. It has the same
procedural objective as
O. 14 of the RHC in that it provides for a speedy mechanism for
obtaining summary judgment without proceeding to a trial. It is certainly
effective in an action for specific performance for the sale and purchase of
a piece of land where there is no defence to the action at all. It must be
borne in mind that an application for summary judgment under
O. 81 of the RHC may be filed notwithstanding the fact that the
defendant has not entered an appearance (Alloy
Automotive Sdn. Bhd. v Perusahaan Ironfield Sdn. Bhd. [1986] 1 CLJ 2;
[1986] CLJ (Rep) 45 and
O. 81 r. 1(2) of the RHC). It is also ideal to note that an application
under O. 81 of the RHC must relate to the whole action at hand. Of course,
the remedy for specific performance is enshrined in the Specific Relief Act
1950 and it is entirely discretionary (Sekemas
Sdn Bhd v. Lian Seng Co Sdn Bhd [1989] 2 CLJ 155; [1989] 1 CLJ (Rep)
154, SC; and
Yeong Ne Hong lwn. Bumida Engineering and Construction Sdn Bhd [1995]
1 LNS 307; [1996] 4 MLJ 350) and it is also ideal to enforce an
agreement, whether in writing or not, for the sale and purchase of a
property as exemplified in
Bank of Tokyo Ltd v. Mohd Zaini bin Arshad (Maria Pragasam, Intervenor)
[1991] 2 CLJ 989; [1991] 2 CLJ (Rep) 341;
Chong Hoong & Anor. v. Wong Yuen Sang [1975] 1 LNS 13; [1976] 1
MLJ 282;Chan
Kin & Anor v. Chareen Realty Development Sdn Bhd [1988] 1 LNS 166;
[1989] 1 MLJ 62; andMasalam
Sdn Bhd v. Ngah bin Embong & Anor [1998] 2 CLJ 817, CA. Specific
performance too is effective in ordering the delivery of strata title as
seen in the case of
Syed Azman bin Syed Mohamed v. Lian Seng (KL) Construction Co Sdn Bhd
[1992] 4 CLJ 2194; [1992] 3 CLJ (Rep) 625. It has often been said that
an order for summary judgment under
O. 81 of the RHC should only be made in a plain case and where there is
no necessity for a trial (Bigg v. Boyd Gibbins Ltd [1971] 2 All ER
183 at 184, [1971] 1 WLR 913 at 915, CA). Such a procedure is also ideal
where the defence put forward is obviously "frivolous and practically
moonshine" (Codd v. Delap [1905] 92 LT 510 at 511, HL per Lord
Lindley). The court is empowered after hearing an
O. 81 application to give judgment to the plaintiff (r.
3 of O. 81 of the RHC) unless the defendant succeeds in satisfying the
court that there is an issue or question in dispute which ought to be tried
or that there ought for some other reason to be a trial of the action (r.
3 of O. 81 of the RHC).
Specific Performance
The relief of specific performance is liberally and generously granted so
long as the circumstances warrant it. There is no necessity on the part of
the plaintiff to show:
(a) that the plaintiff has in the past strictly and literally complied
with all its obligations under the contract; or
(b) that the defendant has committed a breach of the contract.
In support of this proposition of the law, reference should be made to
the write-ups in the following text books:
(1) Snell's Principles of Equity, 28th edn by P.V. Baker and
P.ST.J. Langan at p. 569:
(c) No breach required. Although in most cases no action for specific
performance will be commenced until a breach of the contract has occurred, a
breach is not an essential part of the cause of action in equity. Whereas
the breach is of the essence of an action for damages at law, an action for
specific performance is based on the mere existence of the contract, coupled
with circumstances which make it equitable to grant a decree (Hasham v.
Zenab [1960] AC 316; and see [1960] 76 LQR 200).
(2) Equity Doctrines and Remedies, 3rd edn by RP Meagher, WMC
Gummow, and JRF Lehane at para. 2004;
[2024] It is, however, established that these principles do not require
the plaintiff, in order to succeed in his suit for specific performance, to
show that he has in the past strictly and literally complied with all his
obligations under the contract (see Fuller's Theatres Ltd v. Musgrove
[1923] 31 CLR 524) or that he is ready and willing to perform strictly and
literally his obligations in future (Bahr v. Nicolay (No 2) [1988]
164 CLR 604 at 619-20). The position is explained by the High Court in
Mehmet v. Benson [1965] 113 CLR 295. The plaintiff was a purchaser of
land under a terms contract. Payments due by him under the contract were,
and had for some years been, substantially in arrears, yet he obtained a
decree of specific performance. Barwick CJ said at 307-8:
The question as to whether or not the plaintiff is ready and willing to
perform the contract is one of substance not to be resolved in any technical
or narrow sense. It is important to bear in mind what is the substantial
thing for which the parties contract and what on the part of the plaintiff
in a suit for specific performance are his essential obligations. Here the
substantial thing for which the defendant bargained was the payment of the
price; and, unless time be and remain of the essence, he obtained what he
bargained for if by the decree he obtains his price with such ancillary
orders as recompense him for the delay in its receipt. To order specific
performance in this case would not involve the court in dispensing with
anything for which the vendor essentially contracted. ... But it is the
essential terms of the contract which he must be ready and willing to
perform. He seeks a transfer of the interest in land, the subject of the
contract: the counterpart obligation is the payment of the price. In
consideration the question of the plaintiff's readiness and willingness in
this respect in this case there are many factors. His default in paying the
instalments of the price, whilst not conclusive, is amongst these factors.
... In my opinion, not-withstanding the defaults of the plaintiff in the
payment of the instalments of price, he was not unready or unwilling to
perform the contract in its essential terms, specific performance ought to
have been granted. (See also Besant v. Woo [1879] 12 Ch D 605;
Dyster v. Randall [1926] Ch 932; Hill v. Barclay [1811] 18 Ves
56; 34 ER 238; Swain v. Ayers [1888] 21 QBD 289; Telegraph
Despatch & Intelligence Co v. McLean [1873] LR 8 Ch 658; and Powell
v. Whyte [1968] Qd R 255).
Nor is it necessarily fatal that the plaintiff asserts a wrong view of
the contract which he believes to be correct, provided that the view is not
untenable and that the plaintiff is willing to perform the contract
according to what transpires to be its true tenor. Thus in Green v.
Sommerville [1979] 141 CLR 594, the High Court held the principle
applied in favour of a plaintiff who had insisted on an oral variation of
the contract which the Court determined against her.
(3) The Principles Of Equitable Remedies by I.C.F. Spry, 5th edn
at p. 78:
So it has been said that 'proceedings for the specific performance of a
contract which is of such a kind that it can be specifically enforced can be
commenced as soon as one party threatens to refuse to perform the contract
or any part thereof or actually refuses to perform any promise for which the
time of performance has arrived.' (Turner v. Bladin [1951] 82 CLR 463
at p. 472. In Hasham v. Zenab [1960] AC 316 at p. 329 it was said,
'In equity all that is required is to show circumstances which will justify
the intervention by a court of equity).' This principle may be applied even
though the term of which the breach is threatened is conditional and the
condition has not yet been fulfilled. (Where an obligation is conditional an
order of specific performance may be made in a conditional form and by
ancillary orders the defendant may be enjoined from performing acts that are
inconsistent with his positive obligations). Further, it is not essential
that there should have been an explicit threat not to perform the material
obligation. They must be more than a theoretical or remote possibility of a
breach, but otherwise a greater or lesser probability that there will be a
failure to perform may be found to be sufficient in the general
circumstances; and in particular the degree of probability of a future
breach that must be shown before the court will intervene depends on the
extent of hardship that the plaintiff may suffer if the breach occurs and on
any other such matters that bear on the justice or injustice of granting
relief immediately.
The bottom line is this. That even if the plaintiff was said to be in
breach of any of the agreements as alluded to earlier or that it has not
complied strictly and literally with all its obligations thereunder (which
the plaintiff vehemently denied), the court could still order the first
defendant to specifically perform its obligations under the sale and
purchase agreement dated 2 April 1999. Furthermore, even if the court were
to find that the plaintiff has failed to show any breach of contract on the
part of the defendants, the relief of specific performance was still open to
the plaintiff.
I must exercise my discretion in favour of granting the relief of
specific performance. It is trite law that specific performance would be
ordered where damages is not an adequate remedy as envisaged under
s. 11(1) of the Specific Relief Act 1950. There is a statutory
presumption in
s. 11(2) of the Specific Relief Act 1950 that damages is not an adequate
remedy in a contract to transfer immovable property. The burden to rebut
this presumption lies on the defendants.
Section 11(2) of the Specific Relief Act 1950 enacts as follows:
Unless and until the contrary is proved, the court shall presume that the
breach of a contract to transfer immovable property cannot be adequately
relieved by compensation in money, and that the breach of a contract to
transfer movable property can be thus relieved.
It was rightly submitted that the statutory presumption under
s. 11(2) of the Specific Relief Act 1950 applies in favour of the
plaintiff and that it has not been rebutted by the defendants. In Snell's
Principles of Equity, the learned authors wrote at p. 570:
2. Contracts relating to land.The commonest case in which the
court specifically enforces a contract is where the contract is for the sale
of land or for the granting of a lease. Contracts relating to land differ
greatly from contracts respecting most goods, because the land may have a
peculiar value to the purchaser or lessee. Where the necessary conditions
are satisfied, the court will therefore almost invariably decree specific
performance of a contract regarding land, even if the interest to be granted
is no more than a licence of short duration (Verrall v. Great Yarmouth
B.C. [1981] QB 202 (use of meeting hall for two days)); and where the
contracting parties are within the jurisdiction this willingness to decree
specific performance extends even to land out of the jurisdiction (Penn
v. Lord Baltimore [1750] 1 Ves. Sen. 444; 1 W. & T.L.C. 638).
I have in
Zainab Mohamed v. Syarikat Permodalan Johor (PP) Sdn Bhd [1998] 4 CLJ
Supp 262 at p. 280 to p. 281 set out the law in regard to specific
performance in these words:
Simply put, specific performance is an equitable relief given by the
court to enforce against a defendant the duty of doing what he agreed by
contract to do. The plaintiff may obtain judgment for specific performance
even though there has not been, in the strict sense of the word, any default
by the defendant before the issue of the writ (Hasham v. Zenab [1960]
AC 316, [1960] 2 WLR 374 PC; Oakacre Ltd v. Claire Cleaners (Holdings)
Ltd [1982] Ch 197, [1981] 3 All ER 667). It can be seen that the remedy
of specific performance is in sharp contrast with the remedy by way of
damages for breach of contract - where the court orders pecuniary
compensation for failure to carry out the terms of the contract. The remedy
of specific performance is both special and extraordinary in character, and
the court has a discretion either to grant it or to leave the parties to
their rights at law (Re Scott and Alvarez's Contract, Scott v. Alvarez
[1895] 2 Ch 603 at 612, 615 CA; and Jobson v. Johnson [1989] 1
All ER 621, [1989] 1 WLR 1026 CA). The judge, as I said, must exercise his
discretion in a judicial manner (Revell v. Hussey [1813] 2 Ball & B
280 at 288; and Conlon v. Murray [1958] NI 17). The contract must be
within the category of contracts of which specific performance will be
granted, a striking example of contracts outside the scope of the remedy
would be Robertson v. St. John [1786] 2 Bro CC 140, where a promise
to renew a lease in consequence of money already laid out was held nudum
pactum and specific performance was refused. I might as well point out
that for the remedy of specific performance to be invoked the following
conditions must be fulfilled:
(1) the contract is valid in form; and
(2) has been made between competent parties; and
(3) is unobjectionable in its nature and circumstances.
It is correct statement of the law to say that specific performance is
granted as a matter of course (Hall v. Warren [1804] 9 Ves 605 at
608) and this is so even though the judge feels that it is favourable to one
party and not the other (Haywood v. Cope [1858] 25 Beav 140). The
defendant, however, is not left without legal recourse for if the defendant
can rely on one of the recognised equitable defences then the defendant can
avoid the contract. It may be inequitable to enforce the contract if there
is delay, acquiescence, breach on the plaintiff's part or for that matter
some other circumstance outside the contract (Clowes v. Higginson
[1813] 1 Ves & B 524 at 527; Leech v. Schweder [1874] 9 Ch App 465 n
at 467 n; and Re Terry and White's Contract [1886] 32 Ch D 14 at 27,
CA).
In my judgment, in the context of the present case, there was a concluded
contract binding in law as all the formalities had been observed. In
particular, the parties have agreed on all the essential terms of the
contract with the terms sufficiently certain and precise so that this court
can order and easily supervise the performance of that contract.
I will now briefly examine the conditions as set out in Zainab Mohamed
to the facts of the present case, in particular to encl. 7.
The First Condition: That The Contract Is Valid In Form
It cannot be doubted and it was not disputed that the contract that was
sought to be specifically enforced by the plaintiff - referring to the sale
and purchase agreement dated 2 April 1999, is valid in form. In actual fact,
the existence and the terms of the sale and purchase agreement were admitted
by the defendants in their defence. Moreover, the terms sought to be
enforced by the plaintiff in particular cl. 3.3 of the sale and purchase
agreement were phrased and framed in a precise and clear language. It
categorically stated that the first defendant "shall grant" to the plaintiff
a power of attorney.
The Second Condition: That The Contract Has Been Made Between
Competent Parties
Without a doubt, both the plaintiff and the defendants are competent
parties under the law. This condition has been fulfilled to the hilt.
The Third Condition: That The Contract Is Unobjectionable In Its
Nature And Circumstances
There was nothing objectionable about the sale and purchase agreement
dated 2 April 1999. It was a concluded contract for the sale and purchase of
a piece of land for a mixed residential and commercial development. It was a
legally enforceable contract giving rise to obligations for the parties
thereto. In Storer v. Manchester City Council [1974] 3 All ER 824 at
828, Lord Denning aptly said:
In contracts you do not look into the actual intent in a man's mind. You
look at what he said and did. A contract is formed when there is, to all
outward appearances, a contract.
Indeed there was a concluded contract here and there was nothing
objectionable in ordering the first defendant to specifically perform its
obligation under the sale and purchase agreement, in particular to grant a
power of attorney to the plaintiff for the development of the land.
Analysis
At the outset, I must categorically say that the defendants have not
raised any triable issues in their affidavits. This was certainly a clear
cut case for summary judgment for the following reasons:
(1) clause 3.3 of the sale and purchase agreement dated 2 April 1999
states in plain language that the first defendant "shall grant" to the
plaintiff a power of attorney to be prepared stamped and registered at the
High Court; this was, in fact, a mandatory obligation imposed on the first
defendant;
(2) despite the plaintiff's repeated requests and reminders, the first
defendant has refused to grant the power of attorney to the plaintiff;
(3) the fact of the matter is this - that until today cl. 3.3 of the sale
and purchase agreement has not been performed by the first defendant;
(4) the defendants' say that they saw no need for the power of attorney,
but with respect, this was not a relevant consideration;
(5) the wording of cl. 3.3 of the sale and purchase agreement is clear
and unequivocal and the court must give effect to it because the said clause
can be specifically enforced without the need of supervision for its
performance;
(6) that damages would not be an adequate remedy since cl. 3.3 of the
sale and purchase agreement involves the rights over an immovable property;
and
(7) that the plaintiff was and still is ready and willing to perform its
obligations under sale and purchase agreement.
The arguments advanced by the defendants were designed to confuse the
facts even though the facts were fairly clear. Factually speaking, I must
state the following salient points:
(1) that the sale and purchase agreement dated 2 April 1999 sets out in
detail the rights, benefits and obligations of both the parties pertaining
to the sale of the land and one of the obligations of the first defendant
includes the obligation to grant the plaintiff a power of attorney over the
land;
(2) by way of a deed of assignment dated 8 April 1999 between the first
defendant and the second defendant, the first defendant assigned all the
proceeds arising from the sale and purchase agreement to the second
defendant;
(3) the "assignment" mentioned in the deed of assignment relates to the
proceeds under the sale and purchase agreement which the first defendant was
entitled to receive;
(4) that the proceeds under the sale and purchase agreement were the
rights of and the benefits to be received by the vendor - referring to the
first defendant, and they were not an obligation imposed on the first
defendant; consequently, only the rights and benefits of the first defendant
under the sale and purchase agreement were assigned to the second defendant
by way of the deed of assignment;
(5) that the deed of assignment does not provide for the assignment of
the obligations of the first defendant under the sale and purchase agreement
to the second defendant but it does contain a covenant given by the second
defendant to the first defendant that the second defendant would "observe
discharge and carry out all the duties responsibilities covenants
undertakings stipulations and obligations on the part of the assignor or as
contained in the sale and purchase agreement;
(6) that the covenant to perform is entirely a matter between the first
and the second defendants only;
(7) that the obligations of the first defendant towards the plaintiff
under the sale and purchase agreement including the obligation to grant the
power of attorney to the plaintiff under cl. 3.3 of the sale and purchase
agreement remain with the first defendant; and
(8) if the first defendant fails to perform its obligations under the
sale and purchase agreement the plaintiff is entitled to sue the first
defendant; it does not matter that the first defendant had procured a
promise from the second defendant to the effect that the second defendant
would carry out the first defendant's obligations under the sale and
purchase agreement on its behalf because that arrangement is entirely an
arrangement between the first defendant and the second defendant - it has
nothing to do with the plaintiff.
At this juncture, it would be appropriate to consider the other issues
raised by the defendants not in its order of importance.
The Alleged Delay In Filing The Summons In Chambers In Encl. 7
It was rather unfortunate that the defendants had never raised the issue
of delay in any of the affidavits filed earlier. As a consequence thereto,
the plaintiff did not answer the allegation of delay, if any, by way of an
affidavit.
The law is clear. That delay, if any and the plaintiff does not admit it,
does not per se defeat any application for summary judgment. The defendants
relied heavily on the case of
Ruby Construction Sdn Bhd v. Sun Metal Works Sdn Bhd [1997] 3 CLJ
Supp 183, a High Court decision that was decided on 25 October 1996 by
the learned Judicial Commissioner and that decision has been superceded,
with respect, by the Court of Appeal decision of
Perkapalan Shamelin Jaya Sdn Bhd & Anor v. Alpine Bulk Transport New York[1998]
1 CLJ 424; [1998] 3 MLJ 818 with a coram of Gopal Sri Ram, NH Chan and
Mahadev Shankar JJCA which decided that delay per se will not defeat
an application for summary judgment and the headnotes of the Court of Appeal
decision merit reproduction (see p. 818 of the report):
Held, dismissing the appeal.
[1] (Per Gopal Sri Ram JCA) There is nothing to suggest that an
application for summary judgment may be defeated solely on the ground that
there has been a delay in moving the court. In this case, as the judge was
of the opinion that the issues raised by the appellants were a sham, he
would have been entitled to enter judgment for the respondent. However, in
the exercise of discretion, he had decided to grant conditional leave. If
the trial judge erred in granting conditional leave instead of judgment for
the respondent, the error was one that prejudiced the respondent, not the
appellants. The present case therefore did not warrant appellate
interference (see pp 821D, I and 822A); Comptroller-General of Inland
Revenue, Malaysia v. Weng Lok Mining Co Ltd [1969] 2 MLJ 98 and
McLardy v. Slateum [1890] 24 QBD 504 followed.
[2] (Per NH Chan JCA) An application for leave to sign judgment under
O. 14 r. 1 of the Rules of the High Court 1980 need not necessarily be
made before the defendant has delivered his defence. A defendant may show
cause by 'affidavit or otherwise' and the term 'or otherwise' allows the
defendant to do so by delivering a defence. Therefore, delay in applying for
O. 14 is no ground for defeating the plaintiff's right to summary
judgment under
O. 14 when there is no real defence disclosed (see p 822E, F, G);
McLardy v. Stateum [1890] 24 QBD 504, Comptroller-General of Inland
Revenue, Malaysia v. Weng Lok Mining Co Ltd [1969] 2 MLJ 98, Jacobs
v. Booth's Distillery Co [1901] 85 LT 262 and Krishnamurthy & Anor v.
Malayan Finance Corp Bhd [1986] 2 MLJ 134 followed; Societe des
Etains de Bayas Tudjuh v. Who Heng Mining Kongsi [1978] 2 MLJ 267 not
followed.
In
Yap Mong Siew & Ors v. Leong Hum [1998] 3 CLJ Supp 513, the High
Court Judge correctly held that the delay in that case did not constitute a
triable issue nor did delay per se prevent the plaintiffs there from
securing summary judgment against the defendant there.
In my opinion, the avoidance of a trial should be the primary
consideration in a summary judgment application. And that the delay in
filing, no matter how long, is irrelevant and is of no consequence at all.
In Brinks Ltd v. Abu-Saleh and Others (No 1) [1995] 4 All ER 65, on
the issue of delay, Jacob J aptly said at p. 68 to p. 69 of the report:
But otherwise I can see no objection to a late application for judgment
under Ord 14. Indeed, in some cases, and I think this is one, its use may be
commendable as saving both the extra costs and time involved in a full
trial. If these defendants truly have no defence it is worse and pointless
for them to be present at the trial, which will be complex enough without
them. The plaintiffs are right to clear the decks as far as possible before
trial.
Using these authorities as authoritative guidelines, the upshot of it all
would be this. That even if there was a delay in the filing of encl. 7, it
did not per se preclude the plaintiff from obtaining summary judgment
because, clearly on the evidence, there was no defence to this action and
that there was no issue which ought to be tried.
Novation And The Extinguishment Of The Sale And Purchase Agreement
The defendants alleged that there was novation in law wherein the sale
and purchase agreement has been discharged or replaced by the deed of
assignment dated 8 April 1999 and the agreement dated 8 April 1999. The
defendants pointed out that the parties need not perform any obligations
under the sale and purchase agreement since it has been extinguished. To say
the least, it was a fallacy to hold onto this notion. The terms and
conditions of these three legal documents are not mutually exclusive. Rather
they supplement each other and they effectively vary some of the terms
agreed upon between the parties in this way:
(1) that the sale and purchase agreement governs the sale of the land by
the first defendant to the plaintiff and lays down the rights and benefits
and obligations of both the vendor - referring to the first defendant, and
the purchaser - referring to the plaintiff, pertaining to the sale of the
land;
(2) that the deed of assignment governs the assignment of the rights and
benefits of the first defendant in relation to the proceeds under the sale
and purchase agreement to the second defendant; and
(3) that the agreement dated 8 April 1999 governs the method in which the
proceeds under the sale and purchase agreement should be delivered by the
plaintiff to the second defendant in that the proceeds are no longer in
monetary terms but rather by way of units, car parks, and the net saleable
areas of commercial units amounting to 35% from the development.
It cannot be the parties' intention to extinguish the sale and purchase
agreement by way of the deed of assignment or by way of the agreement. In
fact and in reality, the sale and purchase agreement was referred to many
times in both the deed of assignment and the agreement. Evidential wise,
recital 2, cl. 2, cl. 3 and cl. 4 of the deed of assignment would bear this
out. Even recital 1 and recital 2 of the agreement would bear witness to
this. In addition to all these, even the second defendant in its own letter
made reference to the sale and purchase agreement and informed the plaintiff
that it would carry out the duties of the first defendant under the sale and
purchase agreement. The second defendant further admitted that the sale and
purchase agreement was merely varied by the agreement dated 8 April 1999.
The second defendant's letter dated 7 May 2003 to the plaintiff as seen at
exh. "WJJ3" of the defendants' affidavit dated 19 July 2004, at para. 2 of
the letter merits reproduction and it was worded in this way:
It is within your knowledge that the sale and purchase agreement have
been assigned by Messrs Kepong Management Sdn Bhd to us with your consent
whereby we shall carry out the duties of Messrs Kepong Management Sdn Bhd
under the sale and purchase agreement dated 2.4.1999. The aforesaid sale and
purchase agreement have been varied by the agreement dated 8.4.1999 made
between you and us.
Approaching encl. 7 with circumspection, I must say that it is
unconscionable for the defendants to now allege that none of them is obliged
to perform the first defendant's duties under the sale and purchase
agreement because the sale and purchase agreement is no longer in existence.
A submission along these lines would certainly be in error. I am of the
considered view that the defendants' allegation of novation is so
inconsistent with contemporaneous documents and they are so inherently
improbable that it should be rejected by this court outright. The case of
LYL Hooker Sdn. Bhd. v. Tevanaigam Savisthri & Anor. [1987] 1 CLJ
356; [1987] CLJ (Rep) 179, SC relied upon by the defendants does not,
with respect, assist the defendants at all. On the contrary, it supports the
plaintiff's stand that there is no novation in this case at all. There
Salleh Abas LP, said:
Referring to the second objection, there seems to be a confused thinking
here. What was transferred from the assignor to the respondents in so far as
the matter in issue is concerned, was not liability but a right to have
vacant possession of the house delivered within eighteen months from the
date of the sale and purchase agreement. The appellant company's liability
to deliver vacant possession within that period remained with the appellant
company and was not transferred to any one else, though in the discharge of
this obligation it has to deliver it to the respondents instead of to the
assignor (the original purchaser). This is what the assignment is all about.
Moreover, for the deed to amount to a novation, the appellant company must
show that there was consideration moving between them and the respondents.
Here they fail to do so.
Novation is a new contract. It extinguishes rights and obligations under
the old contract for which the new contract is made. Being a new contract,
there must be consent by all parties and there must be consideration, and
rights and obligations under it are not those transferred from the old
contract which is already extinguished. (See Chitty on Contract, Vol.
2, 1983 edition at paragraphs 1315 and 1316).
Looking at the deed we fail to find anything which suggests
extinguishment of rights and obligations under the sale and purchase
agreement. There is nothing either to show any consideration moving between
the appellant company and the respondents, which is a vital requirement for
a novation.
We therefore hold that the deed of assignment dated November 29, 1978 was
an assignment. This appeal is dismissed with costs. We order that the appeal
deposit be paid to the respondents towards taxed costs.
It is ideal to mention that
s. 63 of the Contracts Act 1950 on novation is of wider import. Indeed
this was the view held by Visu Sinnadurai J in
Polygram Records Sdn Bhd v. The Search[1994] 3 CLJ 806; [1994] 3
MLJ 127, [1994] 3 AMR 2060 and I certainly share his view. His Lordship Visu
Sinnadurai J in that case aptly said:
Section 63 is not limited in its scope to novation as it is understood
under English Law alone, but also covers situations where the parties have
rescinded the earlier contract, by substituting a new one. If there is an
intention on the part of both the parties to substitute a new contract, the
old need not be performed, even if the new merely alters certain terms of
the old. The test basically is this: if a new contract is entered into by
the parties, whatever its terms, the old contract is extinguished. It does
not, however, cover a situation where the terms of the old contract are
merely altered or varied, without a new contract in substitution of it being
entered into. In such a case, the old contract, as altered or varied,
remains in force.
The upshot of it all would be this. That the deed of assignment dated 8
April 1999 and the agreement dated 8 April 1999 did not extinguish the
liabilities and obligations of the first defendant under the sale and
purchase agreement dated 2 April 1999.
The Allegation That The Request For The Power Of Attorney Is Not In
Accordance With The Sale And Purchase Agreement
Clause 3.1 of the sale and purchase agreement basically provides that the
first defendant will still remain as the registered proprietor of the land
even if the entire sale and purchase agreement has been completed in
accordance with cl. 3.1 thereto. It does not mandate the completion of the
entire sale and purchase agreement as a condition precedent for the granting
of the power of attorney.
In fact, the sale and purchase agreement does not provide for any
condition precedent to be fulfilled by the plaintiff before the first
defendant grants the power of attorney to the plaintiff. There is also no
requirement that the plaintiff must first produce proof to justify the need
for a power of attorney. Clause 3.1 of the sale and purchase agreement
provides in clear and unequivocal terms that " the vendor shall grant to the
purchaser a power of attorney " It is therefore couched in a mandatory term
thereby imposing a mandatory obligation on the part of the first defendant.
The first defendant has no discretion to decide whether or not to execute
and deliver the power of attorney (Chin
Yew Loy Holdings Sdn Bhd lwn. Au Metalvest (M) Sdn Bhd [2002] 6 CLJ 141).
At any rate, the defendants have been very inconsistent in their stand.
On the one hand, the defendants say that the sale and purchase agreement had
been discharged and replaced. On the other hand, the defendants want to rely
on the provision of the sale and purchase agreement in regard to the
"condition" for the power of attorney. Such inconsistent stand merely
reinforced the fact that the defendants have nobona fide defence to
this action. To say the least this alleged issue merely constituted a
red-herring to distract this court's attention from the facts at hand.
The Plaintiff's Request Does Not Fit In Any Situations Provided In cl.
3.3(a) To (D) Of The Sale And Purchase Agreement
Since the prayer sought for by the plaintiff is for specific performance
of cl. 3.3 of the sale and purchase agreement, there is no question of
whether or not the power of attorney would fit into any of the situations
provided for in cl. 3.3 of the sale and purchase agreement.
No Evidence Of Any Rule Of Law Or Of Any Fact That The Ministry Of
Housing Insisted For The Production Of The Power Of Attorney As A
Pre-requisite For Obtaining The Developer's Licence And The Advertising
Permit
I say that this issue is not a defence to the plaintiff's claim at all.
The contemporaneous documents would show and did show that the plaintiff did
earnestly and consistently seek to proceed with the development in obtaining
the approvals of the building and all the other plans connected with the
construction. It must be emphasised that the plaintiff sent numerous letters
to the first defendant to provide the power of attorney. By way of evidence,
I shall allude to the following documents:
(a) Faxes from the plaintiff dated 21 June 2000, 11 July 2000 and 28 July
2000 issued under the letterhead of Pilecon Engineering Bhd to the first
defendant's previous solicitors, namely, Messrs Hamzah Sulaiman & Partners
regarding the power of attorney in favour of Mawar Awal (see pp. 21 to 23,
25 and 26 of exh. "B3" of encl. 12).
(b) Letter from the plaintiff to the first defendant's previous
solicitors, namely, Messrs Hamzah Sulaiman & Partners dated 27 February 2003
and that letter was worded,inter alia, like this (see p. 3 of exh.
"A5" of encl. 6):
We would appreciate it if you could kindly forward to us a copy of the
duly executed power of attorney to enable us to obtain the necessary
approval from the Ministry of Housing to proceed with the development of the
said land.
(c) Letter from the plaintiff to the first defendant dated 16 April 2003
as per pp. 44 and 46 of exh. "A5" of encl. 6 worded in this manner:
We wish to emphasise that we are earnestly trying to launch the project
and have even mobilised equipment onto the site with intention to proceed
with foundation works.
We write to remind and again respectfully request from you the power of
attorney to execute all deeds documents and agreements relating to the
project which you are obliged to grant pursuant to clause 3.3 of the sale
and purchase agreement dated 24th April 1999 to enable us to proceed further
in obtaining the DL and AP.
We thank you in anticipation and hope to receive the power of attorney
within a week from the date of this letter
(d) Letter from the plaintiff to the first defendant dated 24 April 2003
(see paras. 2 and 3 at p. 47 of exh. "A5" of encl. 6) and it was worded
thus:
We wish to remind you that we have yet to obtain the power of attorney
from your goodself
In view of the rising cost of building material such as steel, timber,
cement and their related products, we will appreciate that the power of
attorney is released to us as soon as possible to enable us to proceed with
the development of the project concerned; as it is, construction cost has
increased and we do not wish to incur cost overrun if construction is
further withheld.
(e) Letter from the plaintiff to the first defendant dated 30 April 2003
as seen at paras 2 and 3 of p. 26 at exh. "B3" of encl. 12 and it was worded
as follows:
We wish to emphasise that your non-issuance of the power of attorney to
us (as stipulated under clause 3.3 of the sale and purchase agreement) has
prevented us from obtaining the necessary approvals from the authorities
thus leading to a delay on the launch of the project.
As discussed, we stress that we are at all material times ready, able and
willing to mobilise our machineries to the site for the propose of
construction and launch of the project
(f) Letter from the plaintiff's previous solicitors, namely, Messrs Edwin
Lim & Suren to the defendants' previous solicitors, namely, Messrs Hamzah
Sulaiman & Partners dated 12 May 2003 and it was worded like this (see p. 49
of exh. "A5" of encl. 6):
We shall be grateful if you will be kind enough to prepare the power of
attorney for our approval.
(g) Letter from the plaintiff's previous solicitors, namely, Messrs Edwin
Lim & Suren to the defendants' previous solicitors, namely, Messrs Yip Kum
Foo & Associates dated 29 May 2003 and it was worded as follows (see para. 3
of p. 50 of exh. "A5" of encl. 6):
Our clients are however anxious to proceed with and complete the project
as soon as possible for mutual benefit. It would be most appreciated if you
are able to obtain your client's favourable response
(h) Letter from the plaintiff to the first defendant dated 27 June 2003
as seen at p. 52, exh. "A5" of encl. 6 and that letter was worded thus:
We enclosed herewith for your execution a copy of the power of attorney.
Please execute and return to us for stamping and filing with the High
Court.
Now, all these letters categorically show that the plaintiff was, at all
material times, anxious, ready and willing to proceed to obtain the
approvals of the plans connected with the development of the project but was
impeded from doing so by the defendants. At this juncture, it is germane to
refer to the case of
Chow Yoong Hong v. Tai Chet Siang [1959] 1 LNS 20; [1960] 1 MLJ
130. There, the Privy Council in the context of a sale of a house held that,
on the evidence as a whole, the plaintiff there was in fact at all times
ready and willing to complete the purchase and accordingly it was held that
he was entitled to the recovery of his deposit. Another case worth referring
to would be the case of
Vambadi a/l Vairapperumal v. Sinniah s/o Sellamuthu [1998] 1 LNS 609,
where I allowed the purchaser's application for summary judgment for
specific performance against the defendant who breached the sale and
purchase of a piece of land by refusing to perform his end of the bargain.
In
Yap Mong Siew & Ors v Leong Hum [1998] 3 CLJ Supp 513, RK Nathan
J granted summary judgment for specific performance since the defendant
there refused to cooperate with the plaintiffs in obtaining consent from the
Ruler-in-Council in regard to the transfer of the land.
The Plaintiff Was Said To Be In Breach Of The Agreement Dated 8 April
1999
This allegation was totally irrelevant to the plaintiff's claim for
specific performance of the sale and purchase agreement dated 2 April 1999.
It was, to say the least, a red herring to cloud the facts at hand. I must
ignore this issue entirely.
Is It Really Just And Equitable For The Relief To Be Granted?
The answer is in the positive. It is certainly just and equitable for the
relief to be granted. This court should grant specific performance of the
sale and purchase agreement because the plaintiff has expended a substantial
amount of money on the land based on the defendants' promise to comply with
its obligations under the sale and purchase agreement in particular its
obligation to execute a power of attorney in the plaintiff's favour. As
alluded to earlier the plaintiff had, inter alia, mobilised its plant
and started piling and construction work on the land. I have no hesitation
to grant summary judgment to be entered for specific performance of the sale
and purchase agreement as prayed for in prayers (1) to (3) of encl. 7.
An order for specific performance has the effect of ordering a
contracting party to do what he has undertaken to do. It is an equitable
remedy. It cannot be asked for as of right. It is a discretionary remedy and
the discretion is not to be arbitrarily or capriciously exercised. It is
certainly governed by fixed rules and principles (Lamare v. Dixon
[1873] LR 6 HL 414 at p. 423). Certain factors that may affect the court's
discretion have been set out by other judges before me, notable among them
would be:
(1) whether there has been a delay in asking for specific performance (Milward
v. Earl of Thanet [1801] 5 Ves 720);
(2) whether the person seeking specific performance is himself prepared
to perform his side of the contract (Chappell v. Times Newspapers Ltd
[1975] 1 WLR 482);
(3) the court will certainly weigh, on a balance, the difference between
the benefit one party will gain from specific performance and the cost of
performance to the other party and if the cost is disproportionate to the
benefit then this is a factor against the making of an order of specific
performance (Tito v. Waddell (No: 2) [1977] Ch 106 at p. 326); and
(4) it must be noted that the parties cannot fetter the court's
discretion in their contract (Quadrant Visual Communications Ltd v.
Hutchison Telephone UK [1993] BCLC 442).
In Lamare v. Dixon (supra), a contract had been entered for the
lease of some cellars. But before the execution of the contract, the owner
promised that he would make them dry. The promise was not a term of the
contract and it was not regarded as a misrepresentation since it related to
the future. Nevertheless, the owner's failure to make the cellars dry led to
the refusal of specific performance.
These authorities serve as useful guidelines in adjudicating enclosure
7
Here, factually speaking, the plaintiff has expended a substantial amount
of money on the land based on the defendants' promise to comply with its
obligations under the sale and purchase agreement. It is certainly different
from the facts in Lamare v. Dixon (supra).
Damages In Addition To Specific Performance
Pursuant to
s. 11 of the Specific Relief Act 1950, the plaintiff may also ask for
compensation for breach of contract in addition to or in substitution of its
performance. Gareth Jones and William Goodhart in their book entitled
"Specific Performance" stated that one may seek damages in addition to
specific performance in order to compensate the loss suffered.
It was submitted on behalf of the plaintiff that the plaintiff should be
granted damages in addition to specific performance for the loss suffered
due to the first defendant's delay in granting the power of attorney to the
plaintiff. I readily subscribe to these salient submissions.
In Rainbow Estates Ltd v. Tokenhold Ltd [1998] 2 All ER 860 it was
held that specific performance "should be available when damages are not an
adequate remedy or, in the more modern formulation, when specific
performance is the appropriate remedy" (see p. 868 of the report). But the
question of whether damages will be an adequate remedy for a breach of
contract is often put in terms of whether the injured party would be able to
purchase a substitute performance if given the remedy of damages. Thus, a
contract for the sale of shares which are freely available on the market
will not be specifically enforced. The injured party would be able to secure
a substitute by buying other shares in the market (Cud v. Rutter
[1720] I P Wms 570). But in a situation where the replacement shares will
not be readily available then specific performance might be ordered. A
classic example would be the case of Harvela Investments Ltd v. Royal
Trust Co of Canada [1985] 2 All ER 966 where the contract relates to
shares that determine the controlling interest in a company. In sharp
contrast would be the case pertaining to a transaction involving a piece of
land. The courts seem to assume that any piece of land, no matter what it is
wanted for, is always unique and that damages will always be an inadequate
remedy. In the context of adjudicating encl. 7, as I said in the early part
of this judgment, everything revolved on the land in question.
Damages In Lieu Of Specific Performance
In the alternative, the plaintiff prays for damages in lieu of
specific performance against the first defendant. In this connection,
reference to clause 9 of the sale and purchase agreement should be made.
That clause stipulates that in the event of default the purchaser (referring
to the plaintiff) may in lieu of specific performance elect to sue
for damages for breach of contract from the vendor (referring to the first
defendant).
Prayer (8) Of encl. 7
It cannot be denied that the first defendant was and is aware, at all
material times, that construction works would be delayed and that the
plaintiff would suffer loss and damages if the power of attorney is not
granted. In this connection, there was certainly ample documentary evidence
which was alluded to somewhere in this judgment. Consequently, it is just
and proper that the first defendant indemnifies the plaintiff on any
claims/demands which the second defendant may bring against the plaintiff
under the agreement dated 8 April 1999 entered between the plaintiff and the
second defendant.
Prayer (9) Of encl. 7
It must be borne in mind that the second defendant had expressly admitted
that it agreed to carry out the duties of the first defendant (see the
letter dated 7 May 2003 written by the second defendant to the plaintiff).
Unfortunately, till to date, the second defendant has failed, refused and/or
neglected to procure the power of attorney for the plaintiff.
It was the stand of the plaintiff that the second defendant has acted in
bad faith when it refused to procure the power of attorney for the plaintiff
thereby causing delay to the development works. It is unconscionable for the
second defendant to insist that the plaintiff should strictly comply with
the time frame for the development works as set out in the agreement dated 8
April 1999 entered between the plaintiff and the second defendant. In the
circumstances, it would be just and proper for this court to grant a
declaration that the plaintiff is not liable to the second defendant for any
loss or damage in relation to the agreement dated 8 April 1999 entered
between the plaintiff and the second defendant as prayed for in prayer (9)
of encl. 7.
Why Must Specific Performance Be Decreed In This Case?
It is to do justice. It is according to Lord Selborne in Wilson v.
Northampton and Banbury Junction Rly Co [1874] 9 Ch App 279 at 284,
that:
The court gives specific performance instead of damages, only when it can
by that means do more perfect and complete justice.
And according to Lord Parker in Stickney v. Keeble [1915] AC 386
at 419:
Indeed, the dominant principle has always been that equity will only
grant specific performance if, under all the circumstances, it is just and
equitable so to do.
Section 18 of the Specific Relief Act 1950 is of great utility. It enacts
as follows:
Power to 18. (1) Any person suing for the specific performance of a award
contract may also ask for compensation for its breach either in compensation
addition to, or in substitution for, its performance. in certain cases.
(2) If in any such suit the court decides that specific performance ought
not to be granted, but that there is a contract between the parties which
has been broken by the defendant and that the plaintiff is entitled to
compensation for that breach, it shall award him compensation accordingly.
ILLUSTRATION
A contracts to sell a hundred gantangs of rice to B. B brings a suit to
compel A to perform the contract or to pay compensation. The court is of
opinion that A has made a valid contract and has broken it, without excuse,
to the injury of B, but that specific performance is not the proper remedy.
It shall award to B such compensation as it deems just.
(3) If in any such suit the court decides that specific performance ought
to be granted, but that it is not sufficient to satisfy the justice of the
case, and that some compensation for breach of the contract should also be
made to the plaintiff, it shall award him such compensation accordingly.
ILLUSTRATION
A contracts with B to sell him a house for RM 1,000, the price to be paid
and the possession given on the 1st January. A fails to perform his part of
the contract, and B brings his suit for specific performance and
compensation, which is decided in his favour. The decree may besides
ordering specific performance, award to B compensation for any loss which he
has sustained by A's refusal.
(4) Compensation awarded under this section may be assessed in such a
manner as the court may direct.
(5) The circumstance that the contract has become incapable of specific
performance shall not preclude the court from exercising the jurisdiction
conferred by this section.
ILLUSTRATIONS
(a) A, a purchaser, sues B, his vendor, for specific performance of a
contract for the sale of a patent. Before the hearing of the suit the patent
expires. The court may award A compensation for the non-performance of the
contract, and may, if necessary, amend the plaint for that purpose.
(b) A sues for the specific performance of a resolution passed by the
directors of a public company, under which he was entitled to have a certain
number of shares allotted to him, and for compensation for the
non-performance of the resolution. All the shares had been allotted before
the institution of the suit. The court may, under this section, award A
compensation for the non-performance.
And I must give effect to s. 18 of the Specific Relief Act 1950.
According to Lee
Hoy v. Chen Chi [1970] 1 LNS 57; [1971] 1 MLJ 76, the court may not
award compensation under s. 18 of the Specific Relief Act 1950 if the
plaintiff did not ask for specific performance in the first place. Indeed,
s. 18 of the Specific Relief Act 1950 is important. It concerns the award of
damages either in addition to, or in substitution for, specific performance.
According to Edgar Joseph Jr FCJ in
Tan Sri Khoo Teck Puat v. Plenitude Holdings Sdn Bhd [1995] 1 CLJ 15
that:
Section 18 of the Specific Relief Act 1950 is based on section 19 of the
Indian Specific Relief Act 1877, which in turn, has its roots is section 2
of the Lord Cairns' Act and Jacques v. Millar [1877] 6 Ch D 153.
Then there is s. 19 of the Specific Relief Act 1950 which states that a
contract which is otherwise specifically enforceable may be enforced
notwithstanding the fact that there is contained within the contract a
liquidated damages clause (Nik
Mohamed Salleh v. Tengku Besar Zabidah [1969] 1 LNS 121; [1971] MLJ
73 at 76;
Zaibun Sa bte Syed Ahmad v. Loh Koon Moy [1982] CLJ 457; [1982] CLJ
(Rep) 58, [1982] 4 PCC 49 at 54; M Ratnavale v. S. Lourdenadin
[1988] 2 MLJ 371, [1988] 2 SCR 161 at 175;
Lim Sin Oo v. Cheah Tjeng Siong [1989] 1 CLJ 953; [1989] 2 CLJ (Rep)
68; Sekemas Sdn Bhd v. Lian Seng Co Sdn Bhd (supra), [1989] 1 SCR
385 at 391; and Keet Gerald Francis Noel John v. Mohd Noor bin Abdullah[1995]
1 CLJ 293).
I too took into account the case of
Narayanan Chettiar s/o Raman Chettiar v. Samuel Jivamoney Dass s/o
Chelliah [1986] 1 CLJ 579; [1986] CLJ (rep) 547 which held that
where an order for specific performance would breach the principles of
natural justice then damages would be the more appropriate remedy.
All said and done, in adjudicating encl. 7, I have vigorously applied all
these principles. They certainly serve as useful guidelines.
Conclusion
For the reasons as adumbrated above, I gave an order in terms of encl. 7.
|