MATRIX MOMENTUM SDN BHD V. SARATOGA SDN
BHD
HIGH COURT MALAYA, JOHOR BAHRU
AZHAR MA'AH J
[CIVIL SUIT NO: 22-20-2001]
10 JANUARY 2002
CIVIL PROCEDURE:Summary judgment - Proper procedure - Mode of
application - Facts deposed in affidavit in Form 18 - Whether derived from
plaintiff's solicitors - Whether facts ought to be within deponent's
personal knowledge - Whether O. 14 r. 2(1) of Rules of the High Court 1980
complied with - Whether deposition could be admitted as evidence
CONTRACT:Sale and purchase of property - Late delivery of vacant
possession - Sale and purchase agreement - Provision for liquidated damages
for late delivery of vacant possession - Whether plaintiff allowed to sue
for damages only - Whether time an essence of agreement - Whether plaintiff
entitled to rescind contract - Contracts Act 1950, s. 56
LAND LAW:Housing developers - Sale and purchase agreement - Late delivery
of vacant possession - Provision for liquidated damages for late delivery of
vacant possession - Whether plaintiff entitled to rescind contract - Whether
time an essence of agreement - Contracts Act 1950, s. 56
JUDGMENT
Azhar Ma'ah J:
This is an appeal by the defendant against the decision of the senior
assistant registrar given on 20 June 2001 in allowing the plaintiff to enter
a final judgment against the defendant under O. 14 r. 1 of the Rules of the
High Court 1980.
Briefly, the facts of the case are these. The plaintiff and the defendant
on 16 March 1996 entered into a sale and purchase agreement whereby the
plaintiff agreed to purchase a unit of condominium particularly known as
2-38-T Polo Park, Johor Bahru which at the material time was under
development by the defendant. The purchase price was RM681,166.
Clause 7 of the said agreement provided that "time shall be the essence
of the contract in relation to all provisions of the agreement". It was also
a term of the agreement that the completion and the handing over of vacant
possession was to take place within 36 months from the date of the agreement
failing which the defendant "shall pay immediately to the plaintiff
liquidated damages to be calculated from day to day at the rate of ten
percent (10%) per annum of the purchase price.
The 36 months period would expire on 16 March 1999. Came 16 March 1999
the defendant was unable to deliver a vacant possession of the said unit to
the plaintiff. By that time the plaintiff had already made various payments
towards the purchase price amounting to RM544,932.80.
As a result the plaintiff by its solicitors wrote to the defendant
demanding delivery of vacant possession of the said unit within 30 days,
failing which the plaintiff would be entitled to terminate or annul the sale
and purchase agreement.
Following the defendant's failure to meet the above demand the plaintiff
by its solicitor's letter dated 13 November 2000 notified the defendant that
the agreement was being terminated and thus demanded for the return of the
money so far paid towards the purchase price together with damages which is
alleged to be payable under the agreement. Failing to get positive response
from the defendant the plaintiff instituted the present action.
Subsequently the plaintiff filed an application for a summary judgment
under O. 14 of the Rules of the High Court 1980. This was allowed by the
senior assistant registrar. Hence, this appeal.
By way of preliminary objection counsel for the defendant argued that the
plaintiff's application for the summary judgment was not properly laid
before the senior assistant registrar by reason of non-compliance of Form
18, the format to be used for an O. 14 application. It was contended that
the plaintiff's affidavit supporting the application did not specifically
state that the defendant at the commencement of the proceedings was justly
and truly indebted to the plaintiff in the sum of RM681,686.91. It was
further contended that whatever facts that were deposed in the supporting
affidavit were not the deponent's personal knowledge but derived from the
advice of the plaintiff's solicitors. As such the deposition should not be
admitted as evidence.
In resisting the above objection it was argued for the plaintiff that the
facts that gave rise to the action by the plaintiff had been comprehensively
set out in the supporting affidavit.
The mode in which an application under O. 14 is to be made is prescribed
under r. 2(1) which states that such application must be supported by an
affidavit in Form 18 verifying the facts on which the claim, or the part of
the claim, to which the application relates is based and stating that in the
deponent's belief there is no defence to that claim. A straight reading of
r. 2(1) will clearly show that what is required in an affidavit supporting
an O. 14 application is a verification by the deponents of facts on which
the applicant's claim and application is based and by reason of that the
deponent believes that the defendant had no defence. It is to be noted that
nowhere in the rule requires that the source of the deponent's belief should
be his personal knowledge. The deponent's belief can also derive from
records or documents that are in his custody or also from advice of
solicitors who have access to such records and documents.
A perusal of the plaintiff's affidavit that supported the application for
summary judgment, showed that the facts that gave rise to the claim against
the defendant had been amply and sufficiently set out. There was no flaw
that was serious enough to override the plaintiff's right to be heard on his
claim.
Legal technicalities should never be allowed to prevail over justice. The
defendant's preliminary objection is thus, dismissed.
Merit Of The Appeal
Learned counsel for the defendant argued that the plaintiff was not
entitled to rescind the contract as the agreement made no provision for such
action. The only remedy that the plaintiff could resort to was to claim
damages for delivery after taking possession of the unit as provided under
cls. 22 and 24 of the sale and purchase agreement.
In ancipation of the plaintiff's counsel's argument that there were
decided authorities (case law) that had allowed the promisee in breached
contracts to terminate such agreements, counsel for the defendant argued
that in all these cases the development projects were abandoned and not
completed as opposed to the present case where all the units were ready for
delivery to the respective purchasers but for the delay. Cases referred to
by the defendant's counsel were Chye Fook & Anor v. The Teng Seng Realty
Sdn Bhd[1989] 1 MLJ 308, Kang Yoon Mook Xavier v. Insun Development
Sdn Bhd[1995] 2 CLJ 471 and Tan Yan Long & Anor v. Newacres Sdn Bhd[1992]
1 CLJ 211; [1992] 3 CLJ (Rep) 666. As the facts of these three cases can be
distinguished from the present case it is contended that the decisions in
the former cannot be related to the latter.
In reply to the above defendant's counsel's argument, counsel for the
plaintiff contended that the plaintiffs action was for money paid as well as
under s. 56 of the Contracts Act 1950. It was submitted further that
although the facts of the above-mentioned cases could be distinguished from
the present case the decisions in those cases did not disentitle the
plaintiff from pursuing his rights under s. 56 of the Contracts Act 1950.
Section 56(1) of the Contracts Act 1950 reads as follows:
when a party to a contract, promises to do a certain thing at or before
a specified time, ... and fails to do any such thing at or before the
specified time, the contract, or so much of it as has not been performed,
becomes voidable at the option of the promisee, if the intention of the
parties was that time should be the essence of the contract.
Then sub-s. 2 of s. 56 provides as follows:
If it was not the intention of the parties that time should be the
essence of the contract, the contract does not become voidable by the
failure to do the thing before the specified time; but the promisee is
entitled to compensation from the promisor, for any loss occasioned to him
by the failure.
It can be seen clearly that the above provisions cover two different
situations. Subsection 1 covers a situation where time is expressed to be an
essence of an agreement and failure to deliver or perform the contract
within the stipulated time, will give the promisee an option to annul the
contract or treat it as subsisting and sue for compensation or damages
whilst sub-s. 2 covers a situation where there is no express provision of
the intention of the parties that time is an essential term of the agreement
and in the event of a party's failure to meet the dateline for the
performance of the agreement the promisee is not entitled to terminate the
contract but can only sue for compensation for any loss occasioned by the
failure.
Now, coming back to the present case by cl. 7 of the sale and purchase
agreement both parties have expressly agreed that "time shall be the essence
of the contract in relation to all provisions of this agreement". The
decision of the courts in the abovementioned cases which incidentally dealt
with cases of abandoned projects do not in any way affect the right of the
aggrieved promisee to exercise the option given to him by the statute. In
the circumstances, on the given facts of the present case the plaintiff is
held to be entitled to terminate the agreement as it did and be returned all
the monies that had been paid towards the purchase price. The plaintiff is
also entitled to damages as provided under the agreement subject to formal
proofs. |