MAJLIS PERBANDARAN AMPANG JAYA V. STEVEN
PHOA CHENG LOON & ORS
FEDERAL COURT, PUTRAJAYA
[CIVIL APPEAL NO. 01-4-2004 (W)]
STEVE SHIM, CJ (SABAH & SARAWAK); ABDUL HAMID MOHAMAD, FCJ;
ARIFIN ZAKARIA, FCJ
17 FEBRUARY 2006
JUDGMENT
Steve Shim CJ (Sabah & Sarawak):
The Issues
[1] There are two appeals before us - one, an appeal proper by the
appellant, Majlis Perbandaran Ampang Jaya (MPAJ) and the other, a
cross-appeal by the respondents. More specifically, the appellant's appeal
is directed at the decision of the Court of Appeal in affirming the High
Court's finding that the appellant was 15% liable to the respondents for
negligence and nuisance. And the respondents' cross-appeal is aimed at the
Court of Appeal's decision that their cause of action against the appellant
for alleged post-collapse liability lay in the area of public law and not
private law. In effect and in substance, the appeal and cross-appeal can be
said to relate to issues encapsulated in the questions upon which leave to
appeal was granted by this court. These questions are postulated as follows:
1. Where a plaintiff sustains damage and alleges negligence against
various defendants and the tribunal of fact ascribes negligence to the
various defendants and where there is a clear finding that the causa
causans of the plaintiff's damage is the negligence of a particular
defendant, whether in that circumstance, the other defendants who are guilty
of certain negligent acts but whose negligent acts are not held to be the
causa causans can be held liable to the plaintiff as well.
2. Whether
s. 95(2) of the Street, Drainage & Building Act 1974 (Act 133) is wide
enough to provide immunity to a local authority in approving the diversion
of a stream and in failing to detect any damage or defect in the building
and drainage plans relating to the development submitted to the local
authority by the architect and/or the engineer on behalf of the developer.
3. Whether pure economic loss is recoverable under our Malaysian
jurisprudence with reference to (a) negligence and (b) nuisance.
4. In a case involving different acts of negligence by multiple
defendants committed at different times, whether those defendants are joint
tortfeasors.
5. Whether the Court of Appeal erred in providing a distinction between
private law and public law when finding that the appellant was not
responsible to the 1st to 73rd respondents for the appellant's acts and
omissions as determined by the High Court following the collapse of Block 1
of Highland Towers.
The Background Facts
[2] The factual matrix relevant to the issues can be briefly
stated. The Highland Towers consisted of three blocks of apartment known as
Blocks 1, 2 and 3 situated on Lots 494, 495 and 635 Mukim, Hulu Klang. These
apartment blocks were built in front of a steep slope. The hill slope was
originally owned by Highland Properties Sdn. Bhd., the developer who also
developed Highland Towers. Highland Properties initially intended to
construct three apartment blocks on the Highland Towers site and bungalows
on the hill slope. Ultimately, only the three apartment blocks were built.
This was between 1975 and 1978. No bungalows were constructed on the hill
slope. In 1991, Highland Properties transferred ownership of the bungalow
lots on the hill slope to Arab Malaysian Finance Bhd (AMFB) as part of a
set-off for unpaid loans. On the hill slope was a stream which was referred
to at the trial as the "East stream". The East stream originated from land
that was being developed by Metrolux Sdn. Bhd. and MBF Property Services Sdn.
Bhd. This land was referred to as the "Metrolux land". On 11 December 1993,
a landslide occurred resulting in the collapse of Block 1 and the subsequent
evacuation of the respondents from Blocks 2 and 3. The respondents then
filed a suit in the High Court against various parties including MPAJ, the
appellant herein, for negligence and nuisance. After a lengthy hearing, the
learned trial judge found the appellant who was the 4th defendant in the
case to be 15% liable for negligence in respect of the appellant's acts and
omissions prior to the collapse of Block 1 of the Highland Towers. However,
he held that
s. 95(2) of the Street, Drainage & Building Act 1974 (Act 133) operated
to indemnify the appellant of any pre-collapse liability but provided no
protection to the appellant for post-collapse liability. Dissatisfied, both
the appellant and respondents appealed to the Court of Appeal. The Court of
Appeal allowed the appellant's appeal on post-collapse liability. They also
allowed the cross-appeal by the respondents against the order of the High
Court on the indemnity issue under
s. 95(2). Against that decision, the appellant and the respondents have
lodged their appeal and cross-appeal respectively. As I have said, leave to
appeal and cross-appeal were granted.
Causa Causans
[3] The issue relating to the first question is simple enough.
Here, counsel for the appellant MPAJ has submitted that as the learned trial
judge had found the acts and omissions of Arab Malaysian Finance Bhd (AMFB)
were the causa causans of the collapse of Block 1 of Highland Towers,
this would have the effect of precluding the learned trial judge in finding
that the acts and omission of the other defendants had in fact caused harm
to the respondents. In response to this, counsel for the respondents
contends that such a submission amounted to misreading the learned trial
judge's judgment. In my view, the use of the expression "causa causans"
to describe AMFB's acts and omissions as being causative of the Highland
Towers tragedy did not have the effect of excluding the culpability of the
acts and omissions of the other defendants including MPAJ. The relevant
passage in his judgment reads: Mr. Abraham in his submission argues that the
plaintiffs must prove that the acts and/or omissions of the 5th defendant
was or were the effective cause or the causa causans of the collapse
of Block 1 leading to the forced evacuation of the plaintiffs from Blocks 2
and 3. To decide on this, reference must be made to my finding on the cause
of the collapse of Block 1. Since it is already decided that it was due to a
landslide caused primarily by water which emanated from the damage pipe
culvert and the inadequate and unattended drains on the 5th defendant's
land, then the plaintiffs have sufficiently proved the causa causans
of the collapse of Block 1 leading to the forced evacuation of the
plaintiffs from Blocks 2 and 3, was due to the acts and/or omissions of the
defendants in not maintaining those watercourses. The 5th defendant above
refers to AMFB. The expression "causa causans" merely means a cause
that causes: (Smith, Hogg & Company Ltd. v. Black Sea & Baltic General
Insurance Co. Ltd [1940] AC 997, 1003). There may be more than one cause
that causes a particular injury. From the passage cited above, it would
appear that Mr. Abraham was of the view that causa causans merely
meant an effective cause. It has been held that such an expression should be
avoided as the issue of causation does not necessarily turn upon it: (see
Environment Agency (Formerly National Rivers Authority) v. Empress Car Co. (Abertillery)
Ltd [1999] 2 AC 23, 29). Causation is a matter to be determined by
common sense and what the law regards as fair, just and reasonable in the
circumstances of a particular case (see Fairchild (suing on her own
behalf) etc v. Glenhaven Funeral Services Ltd & Ors, etc. [2002] 3 WLR
89; March v E & MH Stramare Pty Ltd & Anor [1991] 99 ALR 423, 429).
The relevant question is whether the acts and/or omissions of a particular
defendant made a material contribution to the harm suffered by the plaintiff
(see Bonnington Castings v. Wardlaw [1956] AC 613, 620, 623;
Nicholsons & Ors v. Atlas Steel Foundary & Engineering Co. Ltd [1957] 1
WLR 631, 624; Fairchild (suing on her own behalf) etc v. Glenhaven
Funeral Services (supra); Chappel v. Hart [1998] 156 ALR 517,
524-524).
[4] When all the relevant authorities are examined in their proper
perspective, the answer to the first question must be in the affirmative.
Scope Of
s. 95(2) Of Act 133
[5] The second question postulated concerns the scope of
s. 95(2) of the Street, Drainage & Building Act 1974 (Act 133) when
examined in the context of the factual circumstances of this case. Here, the
learned trial judge found that the landslide was caused by soil on the hill
slope being saturated with excessive water; that this water triggered the
failure of the high retaining wall within the Highland Towers compound which
in turn caused what was described as a retrogressive landslide on the hill
slope resulting in the collapse of Block 1. The learned trial judge
concluded that water played a significant part in the landslide which
eventually caused the collapse of Block 1. He held that the presence of
water was due to the existence of an inadequate drainage system. This is
clear from the following passage of his judgment which states: As a local
authority, the 4th defendant owes a duty or care to the plaintiffs to use
reasonable care, skill and diligence to ensure that the hillslope and the
drainage thereon were properly accommodated before approving building or
other related plans and during construction stage, to comply with and to
ensure the implementation of the drainage system. Then when CFs were applied
for, there should be proper and thorough inspection on whether the buildings
so built, were safe in all aspect and not just confined to the structure.
And after the Highland Towers was erected, to ensure slope stability -
behind Block 1. Then subsequent to the collapse of Block 1, measures should
have been taken to prevent recurrence of the tragedy to Blocks 2 and 3. The
4th defendant alluded above refers to MPAJ. There is ample evidence to show
that MPAJ and/or its predecessor Majlis Daerah Gombak had required a proper
drainage system to be implemented on the hillslope before and during the
construction of the Highland Towers apartment blocks. Indeed, the Jabatan
Pengairan and Saluran (JPS) had consistently advised MPAJ and/or its
predecessor of this necessity in order to forestall any possibility of
damage to the apartment blocks to be built and thereby avoiding
consequential loss to the owners and occupiers thereof.
[6] On the need by MPAJ and/or its predecessor to maintain the
East stream, the learned trial judge said this: But under
ss. 53 &
54 of the Street, Drainage & Building Act, 1974, the 4th defendant,
being the local authority of the area, has a duty to maintain 'watercourses'
within its jurisdiction. And 'watercourses' under
ss. 53 &
54 of the Street, Drainage & Building Act, 1974 as defined in the case
of Azizah Zainal Abidin & Ors v. Dato' Bandar Kuala Lumpur (supra),
include streams and rivers. Thus, possessed of this duty, Mr. Navaratnam
alleges that the 4th defendant has breached its duty of care when it failed
and/or neglected and is still failing and/or neglecting to maintain this
stream, which was the major factor that caused the collapse of Block 1 and
is an important element in ensuring the instability of the slope behind
Blocks 2 and 3 at the present moment. I am much convinced by this argument
above and based on the facts as disclosed, I find such a duty of care exists
and this duty has been breached by the defendant resulting in damages to the
plaintiffs. From the facts as found by the learned trial judge, it seems
evident that the need by MPAJ and/or its predecessor Majlis Daerah Gombak to
divert the East stream must have been intended to resolve the drainage
problems in the affected areas around the hill slope behind the Highland
Towers. There is no dispute by the respondents that if the drainage was
implemented in accordance with the P34 plan, the possibility of a land slide
causing the collapse of Block 1 would not have occurred. Having required the
diversion of the East stream, as in the P34 plan, it would have been
reasonable to expect the local authority (in this case MPAJ and/or its
predecessor) to ensure its proper maintenance. This would have entailed a
duty on the part of the said local authority to conduct regular inspections
so as to ensure its proper implementation of the said diversion. The learned
trial judge found this to be wanting. Not surprisingly, he found support in
the respondents' contention that MPAJ and/or its predecessor had breached
its duty of care in failing and/or neglecting to maintain the East stream,
which according to him, "was a major factor that caused the collapse of
Block 1 and an important element in ensuring the instability of the slope
behind Blocks 2 and 3".
[7] Now, although the learned trial judge held that MPAJ and/or
its predecessor to be negligent, he took the view that they were protected
from liability by virtue of
s. 95(2) of Act 133. He felt that the immunity provided under the said
section was wide enough to embrace the alleged danger created by MPAJ and/or
its predecessor in diverting the East stream. On appeal, the Court of Appeal
took a different approach. It said as follows:
Mr. Navaratnan learned counsel for the plaintiffs has submitted that the
section does not apply to the facts of the present instance. For, this is a
case which the 4th defendant directed the carrying out of certain works
thereby creating a danger to the plaintiffs' property. Counsel is referring
to the requirement by the 4th defendant that the East stream be diverted
from its natural course. This is a fact as found by the trial court and
amply borne out by the evidence, the relevant parts of which were read to
us. Accordingly, this is not merely a case of - to borrow the language of
the section - inspection or approval of building or other works or the plans
thereof. This is a case where a danger was expressly created at the instance
of the 4th defendant. We are therefore in agreement with learned counsel for
the plaintiffs that the judge went wrong on the indemnity point. The Court
of Appeal went on to extrapolate on the common law duty of care a local
authority such as the 4th defendant owed to a third party citing a number of
cases including Kane v. New Forest District Council [2001] 3 All ER
914. The court then states: If the local authority in Kane v. New Forest
District Council (supra) could not wash its hands off the danger in the
footpath it required to be constructed, we are unable to see how the 4th
defendant could possibly escape liability in the present case of requiring
the diversion of the East stream. Accordingly, we set aside the indemnity
granted to the 4th defendant by the trial judge. The consequence is that the
4th defendant is liable to the plaintiffs in the tort of negligence. We
would add for good measure that the kind of harm that was foreseeable by the
5th defendant was equally foreseeable by the 4th defendant. Upon the
evidence on record and applying it to the relevant principles already
referred to earlier in this judgment, it is clear that the 4th defendant
must as a reasonable local authority have foreseen the danger created by
diverting the East stream would probably cause a landslide of the kind that
happened and that in such event, resultant harm, including financial loss of
the kind suffered by the plaintiffs, would occur. We would in the
circumstances uphold the apportionment of liability as against the 4th
defendant Essentially, the position taken by the Court of Appeal is that the
appellant (who is a local authority) had created a danger by requiring or
approving the diversion of the East stream on the hill slope behind Highland
Towers. Now,
s. 95(2) reads: The State Authority, local authority and any public
officer or employee of the local authority shall not be subject to any
action, claim, liability or demand whatsoever arising out of any building or
other works carried out in accordance with the provision of this Act or any
by-laws made thereunder or by reason of the fact that such building works or
plans thereof are subject to inspection and approval by the State Authority,
local authority or such public officer or employee of the State Authority or
the local authority and nothing in this Act or any by-laws made thereunder
shall make it obligatory for the State Authority or the local authority to
inspect any building, building works or materials or the site of any
proposed building to ascertain that the provisions of this Act or any
by-laws made thereunder are complied with or that plans, certificates and
notices submitted to him are accurate. In this connection, counsel for the
respondents has submitted that
s. 95(2) does not give local authorities any power to act negligently or
create a nuisance. He contends that as an essential principle of statutory
interpretation, statutory powers granted to local authorities must be
exercised without negligence and without committing avoidable nuisances,
citing in support cases such as David Geddis v. Proprietors of Bana
Reservoir [1878] 3 AC 430, 447; Allen v. Gulf Oil Refining Ltd
[1981] AC 1004, 1011; Capital & Countries Plc. v. Hampshire County
Council [1997] GB 1004, 1045. As a general principle, I agree that is
the correct approach. However, it has been held that although a statute
should be interpreted as far as possible to ensure it does not permit a
tortfeasor to escape the wrongful consequences of his acts and omissions,
nevertheless a statutory body can be granted immunity from liability for
such consequences if and only if the words granting such immunity are clear
and explicit: (see Boulting v. Association of Cinematograph, Television &
Allied Technicians [1963] 2 QB 606, 643-644; Capital & Countries Plc.
v. Hampshire County Council (supra). The issue before us is whether
s. 95(2) grants such an immunity, Here, the respondents have taken the
position that when the factual matrix of this case is examined in the
context of
s. 95(2), they do not afford MPAJ and/or its predecessor any protection
whatsoever. Counsel for the respondents contends that there are 3 limbs to
s. 95(2). According to him, the first limb only protects local
authorities from liability for building or other works carried out in
accordance with
Act 133; the second limb merely states that local authorities shall not
be under any liability simply because building works and building plans are
subject to inspection and approval; and the third limb states that local
authorities shall not be under any obligation to inspect buildings and
building works to ascertain that they comply with
Act 133.
[8] Counsel for the respondents seems to have placed much emphasis
on the first limb in
s. 95(2), contending that MPAJ and/or its predecessor, by creating a
danger, had failed to carry out its duty in accordance with
Act 133, drawing particular attention to
ss. 54 &
55 thereof and therefore not subject to any protection under the said
s. 95(2). With respect this argument is quite misconceived. As I
indicated earlier, the Court of Appeal had accepted the factual finding of
the learned trial judge that MPAJ and/or its predecessor had created a
danger when it required or approved the diversion of the East stream and
subsequently failing or neglecting to maintain the said diversion or to
ensure its proper maintenance. As the learned trial judge has pointed out,
proper maintenance would have involved regular and effective inspections to
be conducted by MPAJ and/or its predecessor. He held that such failure or
neglect constituted a breach of the duty of care on the part of MPAJ and/or
its predecessor. In effect, the finding of the learned trial judge as to the
creation of the danger in the diversion of the East stream relates
essentially to approval and inspection by MPAJ and/or its predecessor. Thus,
when the facts as found by the learned trial judge which were accepted by
the Court of Appeal are examined in the context of the specific provision
under
s. 95(2), in particular the second and third limbs thereof, they fall
squarely within its ambit. In my view, MPAJ and/or its predecessor Majlis
Daerah Gombak are fully protected from liability under the said section. For
the reasons stated, the Court of Appeal has therefore erred in holding
otherwise. It is in this context that the second question postulated has to
be answered.
Pure Economic Loss
The third question postulated the consideration of whether pure economic
loss is recoverable under the Malaysian jurisprudence in negligence and
nuisance. In the law of negligence, there is no immutable rule that pure
economic loss is not recoverable. All major Commonwealth jurisdictions
recognize that pure economic loss is recoverable in negligence. Under
English law, the general duty of care test enunciated in Caparo
Industries Plc. v. Dickman [1990] 2 AC 605 is applicable to all
negligence claims, including claims for pure economic loss. Pursuant to this
test, 3 questions have to be addressed, namely, whether the damage suffered
by the plaintiff is reasonably foreseeable; whether there is a relationship
of proximity between the plaintiff and defendant; and whether it is fair and
reasonable that the defendant should owe the plaintiff a duty of care. The
English courts have adopted a dual approach in applying the Caparo
test (see Marc Rich & Co. AG v. Bishop Marine Co. Ltd [1996] 1 AC
211). The first concerns the "categorization approach". Here, the English
courts would determine if the plaintiff's claim falls into a recognized
category of liability. In cases of pure economic loss, the recognized
categories include the following scenarios ie, (1) where a defendant has
assumed a particular responsibility towards the plaintiff. For example, in
White v. Jones [1995] 2 AC 207, where a solicitor was found to have
assumed a responsibility towards the beneficiary under a will when drafting
the will pursuant to a testator's instructions; (2) where a defendant has
exposed a plaintiff to a particular danger (see Harris v. Evans
[1998] 1 WLR 1285) and (3) where there is a recognized legal relationship
between the plaintiff and defendant. For example, in Phelps v. Hillingdon
London Borough Council [2001] 2 AC 6019, 667, it was found that a
teacher-pupil relationship might place a teacher under a duty of care not to
cause pure economic loss by teaching pupils the wrong syllabus. The second
concerns the "open-ended approach". Here, if the facts of a particular case
do not come within a recognized category of liability, a court could go
further to look at the facts closely to determine if a duty of care should
nevertheless be owed by the defendant to the plaintiff. Recent statements by
the English courts confirm that the "open-ended approach" can be used to
recognize duties of care in new situations: (see Spring v. Guardian
Assurance Plc. [1985] 2 AC 295.)
[10] In the instant case, the Court of Appeal held that under the
Atkinian doctrine, loss of any type or description is recoverable provided
that it is reasonably foreseeable; that it is not the nature of the damage
itself, whether physical or pure financial loss, that is determinative of
remoteness and the critical question is whether the scope of the duty of
care in the circumstances of the case is such as to embrace damage of the
kind that the plaintiff claims to have sustained, whether it be pure
economic loss or injury to person or property. The Court of Appeal relied on
the English case of Murphy v. Brentwood District Council [1991] 1 AC
398.
[11] Now, Murphy v. Brentwood (supra) merely involved an
application of the Caparo test to the facts of that case. There, the
defendant council had powers to inspect buildings and other foundations to
ensure that they complied with the building by-laws. The plaintiff's home
suffered from defective foundations. He sued the defendant council alleging
that it failed to detect the defects during the course of construction. On
the previous authority of Anns v. Merton London Borough Council
[1978] AC 728, the plaintiff ought to have succeeded. He however failed in
the House of Lords. The majority of their Lordships (ie, Lords Mackay,
Keith, Bridge and Jauncey) adopted the following reasons in denying relief
to the plaintiff:
(1) That Donoghue v. Stevenson [1932] AC 562 only dealt with the
situation whether a defective chattel or building caused personal injury or
harm to property that was distinct and separate from the defective chattel
itself. If a plaintiff sought recovery for the cost of repairing or
replacing a defective chattel or building before it caused personal injury
or damage to other property, such a claim would be one for pure economic
loss;
(2) That recovery for pure economic loss in the law of negligence was
restricted to circumstances where there was reliance on another person's
advice or conduct as was the case in Hedley Byrne & Co. v. Heller &
Partners Ltd. [1964] AC 465;
(3) That a builder was not liable for the pure economic loss of
correcting defects in a building before they caused harm to other property
or personal injury unless reliance in the sense envisaged in Hedley Byrne
was shown to exist. Similarly, the defendant council could not be made
liable for the cost of correcting such defects;
(4) That it was not fair, just and reasonable to recognize liability on
the part of the defendant council for failing to detect errors in buildings
in the course of exercising its statutory powers of inspection under the
Defective Premises Act 1972 (UK). It is perhaps important to note, from the
analysis of the various speeches of the law Lords in Murphy v. Brentwood
(supra) that pure economic loss is recoverable in negligence in English
law on the two alternate bases, namely the "categorization approach" and the
"open-ended approach" alluded to earlier. I may add that the two approaches
do not exist in strict water tight compartments. It is possible for them to
overlap: (see Kane v. New Forest District Council (supra).
[12] In Australia, it is accepted that pure economic loss in the
law of negligence is not restricted to particular categories or approaches.
The High Court of Australia in Perre & Ors v. Apand Pty Ltd [1999]
164 ALR 606 seems to have adopted the "open-ended approach" in assessing
claims for pure economic loss in the law of negligence. Although the various
members of the High Court have expressed differing views, they all agree
that claims for pure economic loss in the law of negligence are not
precluded and will depend on the facts of individual cases. The New Zealand
courts have also adopted the "open-ended approach" to claims for pure
economic loss: (see South Pacific Manufacturing Co. Ltd v. New Zealand
Security Consultants & Investigations Ltd [1992] 2 NZLR 282.) In
Singapore too, the courts have recognized the "open-ended approach". In
RSP Architects Planners & Engineers (Reglan Squire & Partners F.E.) v.
Management Corporation Strata Title No. 1075 [1999] 2 SLR 449, the Court
of Appeal has held that whether a defendant owes the plaintiff a duty of
care not to cause the particular type of loss depends on the circumstances
and facts of that case. This view has been confirmed in the recent case of
Man B & W Diesel S E Asia Pte Ltd & Anor v. P.T. Bumi International
Tankers & Another Appeal [2004] 2 SLR 300, 318 where the Court of Appeal
also expresses the view that the principle in Donoughue v. Stevenson
[1932] AC 562 was still evolving and could offer redress for loss suffered
by the plaintiff as a result of defendant's acts and omissions in
circumstances where a remedy for such losses would not otherwise exist.
[13] Having had the benefit of reading the various authorities on
this subject, I am more inclined to accept the positions taken by the courts
in Australia and Singapore. In adopting the sentiments and observations
expressed by the Singapore Court of Appeal in PT Bumi International
Tankers (supra) I would also endorse the view that caution should be
exercised in extending the principle in Donoghue v. Stevensen to new
situations. Much would depend on the facts and circumstances of each case in
determining the existence or otherwise of a duty of care.
[14] The Court of Appeal in the instant case is correct in
adopting the view expressed by Lord Oliver in Murphy v. Brentwood (supra)
that the critical question is not the nature of the damage itself, whether
physical or pecuniary, but whether the scope of the duty of care in the
circumstances of the case is such as to embrace damage of the kind which the
plaintiff claims to have sustained. The decision in Murphy involves,
as I have mentioned earlier, the application of the Caparo test which
takes into account the elements of foreseeability, proximity and the
additional requirement of justice, fairness and reasonableness.
[15] Now, the exposition above relates to pure economic loss in
the law of negligence. What is the position in the law of nuisance? Here, I
need only rely on the speech of Lord Lloyd in Hunter v. Canary Wharf Ltd
[1997] 2 WLR 684, a case also cited with approval by the Court of Appeal in
the instant case. Therein, Lord Lloyd has said this: It has been said that
an actionable nuisance is incapable of exact definition. But the essence of
nuisance is easy enough to identify, and it is the same in all three cases
of private nuisance, namely, interference with land or the enjoyment of
land. In the case of nuisances within class (1) or (2), the measure of
damages is, as I have said, the diminution of the value of the land. Exactly
the same should be true of nuisances within class (3). There is no
difference in principle. The effect of smoke from a neighbouring factory is
to reduce the value of the land. There may be no diminution in the market
value. But there will certainly be loss of amenity value so long as the
nuisance lasts. If that is the right approach, then the reduction in amenity
value is the same whether the land is recognized by the family man or the
bachelor. The three classes of private nuisance referred to by Lord Lloyd
are (1) nuisance by encroachment on a neighbour's land; (2) nuisance by
direct physical injury to a neighbour's land; and (3) nuisance by
interference with a neighbour's quiet enjoyment of his land. On the
authority in Hunter v. Canary Wharf Ltd (supra), which I accept to be
correct, it seems clear that pure economic loss is recoverable for any of
the forms of nuisance recognized by law. Indeed, the fact that damages for
diminution in value in land are recoverable in nuisance has been recognized
by the Federal Court in
Liew Choy Hung v. Shah Alam Properties Sdn Bhd. [1997] 2 CLJ 601.
[16] Before us, both the appellant and respondents are on common
ground that recovery for pure economic loss is permitted in the law of
negligence. However, they disagree on their application to the facts of the
instant case. For the respondents, it is submitted that they should be
allowed to recover economic loss against MPAJ and/or its predecessor Majlis
Daerah Gombak. They advanced the following grounds: First, the danger posed
by the concept of diverting the East stream across the hill slope behind
Highland Towers was reasonably foreseeable. It was recognized by existing
engineering codes. Secondly, the drainage requirements for the hill slope
imposed by JPS were the result of its concerns for the safety of the
Highland Towers apartment blocks, which were in close proximity to the hill
slope. There was therefore a direct link between the need for a safe
drainage scheme on the hill slope and the Highland Towers apartment blocks
below it. Thirdly, the Highland Towers tragedy rocked the nation and the
world. Forty-eight people died and many were made homeless. It has been
urged upon this court that public policy would only accord with common sense
and public perception if MPAJ and/or its predecessor were held liable for
requiring or approving the diversion of the East stream without ensuring its
proper maintenance. On the grounds so advanced, negligence would have been
attributed to MPAJ and/or its predecessor. But, for the reasons already
stated, they are however immunized against any liability under
s. 95(2) of Act 133.
Joint Tortfeasors
[17] The issue here is whether defendants are joint tortfeasors in
a case involving different acts of negligence by multiple defendants
committed at different times. In my view, the answer to this question can be
found in the Supreme Court case of
Malaysian National Insurance Sdn Bhd v. Lim Tiok [1997] 2 CLJ 351,
375 wherein Edgar Joseph Jr. FCJ said: To recapitulate, at common law, if
each of several persons, not acting in concert, commits a tort against
another person substantially contemporaneously and causing the same or
indivisible damage, each tortfeasor is liable for these same damages.
[18] Counsel for the respondents has cast doubt on the correctness
of this proposition which adopts the stand taken by Choor Singh, J in
Oli Mohamed v. Keith Murphy & Anor [1969] 1 LNS 122; [1969] 2 MLJ
244, 245, who in turn cited in support the following passage of a speech by
Delvin, LJ in Dingle v. Associated Newspapers Ltd. & Ors [1961] 2 QB
162: Where injury has been done to the plaintiff and the injury is
indivisible, any tortfeasor whose act has been a proximate cause of the
injury, must compensate for the whole of it. As between the plaintiff and
the defendant, it is immaterial that there were others whose acts also have
been a cause of the injury and it does not matter whether those others have
or have not a good defence. These factors would be relevant in a claim
between tortfeasors for contribution, but the plaintiff is not concerned
with that; he can obtain judgment for total compensation from anyone whose
act has been a cause of his injury. If there are more than one of such
persons, it is immaterial to the plaintiff whether they are joint
tortfeasors or not. If four men, acting severally and not in concert, strike
the plaintiff one after another and as a result of his injuries he suffers
shock and is detained in hospital and loses a month's wages, each wrong-doer
is liable to compensate for the whole loss of earnings. If there were four
distinct physical injuries, each man would be liable only for the
consequences peculiar to the injury he inflicted, but in the example I have
given, the loss of earnings is one injury caused in part by all the four
defendants. It is essential for this purpose that the loss should be one and
indivisible; whether it is so or not is a matter of fact and not a matter of
law According to counsel, Choor Singh J, in citing the above passage, has
erred in suggesting that the acts of different defendants must be
sufficiently contemporaneous before there can be concurrent liability in
tort. He submits that the passage cited above shows clearly that the
imposition of joint and several liability on defendants as concurrent
tortfeasors is not premised on the contemporaniety of their actions but is
determined by deciding whether their separate actions caused the plaintiff
indivisible harm. With respect, counsel is misconceived. In my view, the
first sentence in that passage is sufficiently clear. I would repeat it for
emphasis - "where the injury has been done to the plaintiff and the injury
is indivisible, any tortfeasor whose act has been a proximate cause of the
injury, must compensate for the whole of it." When the words underscored
above are examined in their proper perspective, particularly in the light of
the illustration given in the same passage, there can be little doubt that
the statement of Edgar Joseph Jr. FCJ represents the correct reflection of
the position taken by Lord Delvin in Dingle. In the circumstances, the
attempt by counsel for the respondents to revisit Malaysian National
Insurance (supra), in terms of his proposition, has no basis whatsoever.
Private Law And Public Law
[19] The fifth question seeks a consideration of whether the Court
of Appeal has erred in holding that the respondents' cause of action lay in
the area of public law and not private law. The complaint of the respondents
seems to be directed at the following passage of its judgment: Now, assuming
that there was a duty on the 4th defendant to act in a particular manner
towards the property of the plaintiff's post collapse, such duty must find
its expression in public law and not private law. Accordingly, if there had
been a failure on the part of the 4th defendant to do or not to do something
as a public authority, the proper method is to proceed by way of an
application for judicial review - see Trustees of Dennis Rye pension Fund
& Anor v. Sheffield City Council [1997] 4 All ER 749. Further, the
substance of the order made against the 4th defendant appears to demand
constant supervision and though this may no longer be a complete bar to the
grant of a mandatory order, it is nevertheless a relevant consideration that
must be kept in the forefront of the judicial mind. In the circumstances of
this case, we are unable to see how such a duty as alleged to exist may be
enforced in private law proceedings. It follows that this part of the
judge's judgment cannot stand. It is set aside. I think the brief facts in
Trustee of Dennis Rye Pension Fund relied on by the Court of Appeal ought to
be stated. There, the plaintiffs were served with a repair notice under the
Housing Act (UK) requiring work to be carried out to certain houses to
render them fit for human habitation. They then applied to the Sheffield
City Council for improvement grants under the Local Government & Housing
Act. The council approved the application but subsequently refused to pay
the grants on the grounds, inter alia, that the works had not been
completed to its satisfaction. The plaintiffs' commenced private law actions
against the council claiming the sums due under the grants. The council
contended that if the plaintiffs had any grounds of complaint (which it did
not accept), the only appropriate procedure was an application for judicial
review and not an ordinary action. It accordingly applied to strike out the
plaintiff's claims under RSC O. 18 r.19 and the inherent jurisdiction of the
court. The district judge struck out the claims; but the judge allowed the
plaintiffs' appeal and dismissed the council's application. The council
appealed to the Court of Appeal.
[20] The Court of Appeal presided by Lord Woolf MR held that when
performing its role under the Local Government & Housing Act (UK) in
relation to the making of grants, a local authority was in general
performing public functions which did not give rise to private rights; but
once an application for a grant had been approved, a duty to pay it arose on
the applicant fulfilling the statutory conditions and that duty would be
enforceable by an ordinary action. The court further emphasized that
although, in the case before it, there was a dispute as to whether those
conditions had been fulfilled, any challenge to the local authority's
refusal to express satisfaction would depend on an examination of issues
largely on fact - that furthermore, the remedy sought for the payment of a
sum of money was not available on an application for judicial review. The
court concluded that an ordinary action was the more appropriate and
convenient procedure and consequently that the plaintiff's actions were not
an abuse of process. The appeal was therefore dismissed.
[21] It is clear that when the speeches by Lord Woolf MR and Pill,
LJ are read in their proper perspective, they explicitly recognize that
remedies for protecting both private and public rights can be given in
private law proceeding and an application for judicial review. It is
pertinent to note the observations made by Lord Woolf MR in explaining the
seminal decision in O'Reilly v. Mackman [1983] 2 AC 237 when he said
as follows:
Where does that leave O'Reilly v. Mackman and what can be done to
stop this constant unprofitable litigation over the divide between public
and private law proceedings? What I could suggest is necessary to begin by
going back to first principles and remind oneself of the guidance which Lord
Diplock gave in O'Reilly v. Mackman. This guidance involves
recognizing (a) that remedies for protecting both private and public rights
can be given in both private law proceedings and on an application for
judicial review; (b) that judicial review provides, in the interest of the
public, protection for public bodies which are not available in private law
proceedings (namely the requirement of leave and protection against delay).
Another significant case referred to by Lord Woolf MR was Roy v.
Kensington & Chelsea and Westminster Family Practitioner Committee
[1992] 1 All ER 705, where it was held before a strong bench of law Lords
comprising Lords Bridge, Emslie, Griffiths, Oliver and Lowry that although
an issue which depended exclusively on the existence of a purely public law
right should, as a general rule, be determined in judicial review proceeding
and not otherwise, a litigant asserting his entitlement to a subsisting
private law right, whether by way of claim or defence, was not barred from
seeking to establish that right by action by the circumstance that the
existence and extent of the private right asserted could incidentally
involve the examination of a public law issue. It seems apparent from Roy
that claims in negligence against local authorities could be brought by way
of writ action if the claims depend on ordinary tort principles: (see also
Davy v. Spelthorne Borough Council (184) A (262).
[22] It is in the light of the established principles stated above
that the respondents in our case maintain that the Court of Appeal has erred
in holding that their only cause of action against MPAJ lay in the area of
public law for post-collapse liability. The respondents have relied on
ordinary tort principles for their claims of negligence. In this, they are
amply supported by established authorities. They should be entitled to file
their claims against MPAJ by way of writ action. In this connection, I think
it is significant to draw attention to the findings of the learned trial
judge on the issue of post-collapse liability. This is reflected in the
following passage of his judgment: To consider whether the 4th defendant is
liable for the acts and/or omissions committed post-collapse, it is
necessary to disclose some events that transpired after the collapse of
Block I. After the Highland Towers calamity there were efforts by the 4th
defendant to stabilize the hillslope on Arab Malaysian land to ensure that
no accident of the kind that caused the collapse of Block I would occur to
Blocks 2 & 3. In January 1995, there was a briefing called by the 4th
defendant which was attended by the 5th defendant and some others. They were
told by the 4th defendant that a master drainage plan for the entire area to
accommodate all landowners in the vicinity of Highland Towers would be
prepared. It was announced that the consultant engaged by the 4th defendant,
M/s EEC would be ready with the master drainage plan within three months
from the date of briefing. It was obvious that any master drainage plan for
the area must cater for the East Stream. It was substantially due to this
East Stream not properly attended to that Block I collapsed. In fact, this
concern of the East Stream, from the chronology of events as set out, was
highlighted by JPS from the very beginning of the development of the
Highland Towers project. Thus, the task to incorporate the East Stream into
the comprehensive master drainage plan falls upon the 4th defendant who is
the body in charge of this watercourse. But after a period of one year,
there was no sight or news of this plan. After numerous reminders by the 5th
defendant of such a plan, the 4th defendant on 29 March 1996 held another
briefing. This time, the 4th defendant informed the attendees that a new
firm of consultant by the name of KN Associates, was engaged to replace the
previous. Again, the 4th defendant gave an assurance that a comprehensive
drainage plan of the area would be forth coming with this replacement of
consultant. Sad to say, until the time when all evidence for this case was
recorded by this court, no comprehensive master drainage plan for the
Highland Towers and its surrounding area was adduced by the 4th defendant.
In fact, this 4th defendant offered no explanation as to why its promise was
not met. These delays had affected the 5th defendant who insist that without
a master drainage plan of the area approved and implemented by the 4th
defendant, and the retaining walls on their land as well as those on
Highland Towers site are corrected or rectified, then very little can be
done by anyone to secure the stability of the slope behind Blocks 2 & 3. It
seems clear that after the collapse of Block I, MPAJ had promised or assured
the respondents that a master drainage plan for the affected area on the
hill slope behind Highland Towers would be formulated and implemented so as
to ensure the stability and safety of the adjacent Blocks 2 & 3 occupied by
the respondents. The respondents waited in vain for this promise or
assurance to materialize. It never came. Their disappointment was echoed by
the learned trial judge who said: Despite this pressing need and the obvious
knowledge of the urgent requirement for a master drainage plan (for
otherwise the 4th defendant would not have initiated steps to appoint
consultants for this work soon after the collapse of Block I) to secure the
stability of the slope so as to ensure the safety of the two apartment
blocks, the 4th defendant did nothing after the respective consultants were
unable to meet their commitments. The plaintiffs and all other relevant
parties are kept waiting because of the 4th defendant. Quite obviously,
there was a failure on the part of MPAJ to formulate and implement the
promised master drainage plan. This persisted at the time of the trial
before the learned trial judge. Certainly no settlement agreement was in
sight at the material time. Not surprisingly, the learned trial judge found
negligence on the part of MPAJ. Given the factual circumstances, I tend to
agree with him. In my view, MPAJ could not seek shelter in
s. 95(2) of Act 133 because this is a case of negligence in failing to
formulate and implement certain works or plans and not negligence in
carrying out those works or plans. There was an assumption of responsibility
by MPAJ to do what it had promised to do. The respondents alleged that its
failure to do so had exposed MPAJ to liability for negligence. The
negligence involved a complete absence or failure of works or plans to be
done or effected and not with the manner in which the works or plans were
being carried out or with the approval and inspection of those works or
plans which would have immunized MPAJ from liability for negligence under
s. 95(2) aforesaid.
[23] The failure by MPAJ to formulate and implement the master
drainage plan had resulted in damages incurred by the respondents who had to
evacuate their apartments in Blocks 2 & 3. The elements of forseeability and
proximity are clearly discernible from the established facts. Moreover, I do
not think it would be in the public interest that a local authority such as
MPAJ should be allowed to disclaim liability for negligence committed beyond
the expansive shelter of
s. 95(2) or other relevant provisions of Act 133 nor would it be fair,
just and reasonable to deprive the respondents of their rightful claims
under the law. The respondents' claim for negligence by way of writ action
is perfectly proper in law. In my view, the Court of Appeal has erred in
holding that the respondents' only recourse against MPAJ lay in the area of
public law by way of judicial review. I may add that at the time the
respondents filed this present action, the public law remedy of judicial
review under
O. 53 of the Rules of the High Court 1980, did not permit the recovery
of damages. Hence, it is not inappropriate for the respondents to proceed by
way of writ action which they did. It is therefore in the context discussed
above that the question postulated should be answered.
The Settlement Agreement
[24] Before us, the appellant MPAJ has relied on a settlement
agreement which was effected between AMFB (the 5th defendant) and the
respondents as having the effect of extinguishing its liability to the
respondents. It is clear that the proceedings before the High Court and the
Court of Appeal were confined to the issue of liability for negligence and
nuisance. The High Court found MPAJ to be 15% liable and this was upheld by
the Court of Appeal. The said settlement agreement was never part and parcel
of the proceedings in the lower courts. As such, it has no bearing on MPAJ's
liability to the respondents. It is therefore not relevant for the purpose
of this appeal.
Conclusion
[25] Given the answers to the questions postulated and for the
reasons stated, it is appropriate to conclude that the appeal by MPAJ is
allowed and the cross-appeal by the respondents is also allowed. Costs to
the appellant and respondents accordingly. Deposits to be refunded to the
successful parties. Finally, let me say, in postscript, that I am greatly
indebted to counsel for the parties concerned for their detailed and
in-depth research work. They have contributed much to a better understanding
and appraisal of the complex issues before the court.
Abdul Hamid Mohamad FCJ:
[26] I have the advantage of reading the judgment of the learned
Chief Judge (Sabah & Sarawak). It saves me from having to narrate the
background facts as well as having to deal with all the issues raised in the
appeal. As I agree with the learned Chief Judge (Sabah & Sarawak) on other
issues, I shall only deal with the issue of "post collapse" liability of the
appellant ("MPAJ").
[27] However, before going any further there is one point that I
would like to make and, that is, regarding the provision of
s. 3(1) of the Civil Law Act 1956 which provides:
3. (1) Save so far as other provision has been made or may hereafter be
made by any written law in force in Malaysia, the Court shall:
(a) in West Malaysia or any part thereof, apply the common law of England
and the rules of equity as administered in England on the 7th day of April
1956;
(b) in Sabah, apply the common law of England and the rules of equity,
together with statutes of general application, as administered or in force
in England on the 1st day of December 1951;
(c) in Sarawak, apply the common law of England and the rules of equity,
together with statutes of general application, as administered or in force
in England on the 12th day of December 1949, subject however to subsection
(3)(ii): Provided always that the said common law, rules of equity and
statutes of general application shall be applied so far only as the
circumstances of the States of Malaysia and their respective inhabitants
permit and subject to such qualifications as local circumstances render
necessary.
[28] That provision was legislated, if I may so, by the British
one year before the then Malaya obtained her independence and remains the
law of this country for half a century now. Whatever our personal views
about it, it is the law and no court can ignore it.
[29] That provision says (I am only referring to common law) that
the court shall apply the common law of England as administered of England
on the given dates provided that no provision has been made or may hereafter
be made by any written law in force in Malaysia. Even then, it is further
qualified that it is only applicable so far only as the circumstances of the
States of Malaysia and their respective inhabitants permit and subject to
such qualifications as local circumstances render necessary.
[30] Strictly speaking, when faced with the situation whether a
particular principle of common law of England is applicable, first, the
court has to determine whether there is any written law in force in
Malaysia. If there is, the court does not have to look anywhere else. If
there is none, then the court should determine what is the common law as
administered in England on 7 April 1956, in the case of West Malaysia.
Having done that the court should consider whether "local circumstances" and
"local inhabitants" permit its application, as such. If it is "permissible"
the court should apply it. If not, in my view, the court is free to reject
it totally or adopt any part which is "permissible", with or without
qualification. Where the court rejects it totally or in part, then the court
is free to formulate Malaysia's own common law. In so doing, the court is at
liberty to look at other sources, local or otherwise, including the common
law of England after 7 April 1956 and principles of common law in other
countries.
[31] In practice, lawyers and judges do not usually approach the
matter that way. One of the reasons, I believe, is the difficulty in
determining the common law of England as administered in England on that
date. Another reason which may even be more dominant, is that both lawyers
and judges alike do not see the rational of Malaysian courts applying
"archaic" common law of England which reason, in law, is difficult to
justify. As a result, quite often, most recent developments in the common
law of England are followed without any reference to the said provision.
However, this is not to say that judges are not aware or, generally
speaking, choose to disregard the provision. Some do state clearly in their
judgments the effects of that provision. For example, in
Syarikat Batu Sinar Sdn. Bhd. & 2 Ors. v. UMBC Finance Bhd. & 2 Ors.
[1990] 2 CLJ 691; [1990] 3 CLJ (Rep) 140 Peh Swee Chin J (as he then
was) referring to the proviso to
s. 3(i) said: We have to develop our own Common law just like what
Australia has been doing, by directing our mind to the "local circumstances"
or "local inhabitants".
[32] In
Chung Khiaw Bank Ltd. v. Hotel Rasa Sayang [1990] 1 CLJ 675; [1990] 1
CLJ (Rep) 57 the Supreme Court, inter alia, held: (4) Because the
principle of common law has been incorporated into statutory law as
contained in
s. 24 of the Contracts Act 1950, the trend on any change in the common
law elsewhere is not relevant. Any change in the common law after 7 April
1956 shall be made by our own courts.
[33] In the judgment of the court in that case, delivered by
Hashim Yeop A. Sani CJ (Malaya), the learned Chief Justice (Malaya), said:
Section 3 of the Civil Law Act 1956 directs the courts to apply the
common law of England only in so far as the circumstances permit and save
where no provision has been made by statute law. The development of the
common law after 7 April 1956 (for the States of Malaya) is entirely in the
hands of the courts of this country. We cannot just accept the development
of the common law in England. See also the majority judgments in
Government of Malaysia v. Lim Kit Siang ([1988] 1 CLJ 63 (Rep);
[1988] 1 CLJ 219; [1988] 2 MLJ 12 - added).
[34] That case is an example where our statute has made specific
provisions incorporating the principles of common law of England. However,
it shows the effect on the application of the common law in England. In the
instant appeal, we are dealing with a situation where no statutory
provisions have been made.
[35] In
Jamal bin Harun v. Yang Kamsiah & Anor [1984] 1 CLJ 215; [1984] 1 CLJ
(Rep) 11 (PC) a "running down" case in which the issue of itemization of
damages was in question, Lord Scarman, delivering the judgment of the Board,
inter alia, said: Their Lordships do not doubt that it is for the
courts of Malaysia to decide, subject always to the statute law of the
Federation, whether to follow English case law. Modern English authorities
may be persuasive, but are not binding. In determining whether to accept
their guidance the courts will have regard to the circumstances of the
states of Malaysia and will be careful to apply them only to the extent that
the written law permits and no further than in their view it is just to do
so.
[36] As early as 1963, this provision had been criticised.
Professor L.C. Green, in an article "Filling Lacunae in the Law"
[1963] MLJ xxviii, commented: Apart from any problem that might arise from
the fact that this legislation attempts, to some extent at least, to
introduce a supplementary English common law or equity which may have become
out of date and which may no longer be applicable in England, the situation
in Malaysia and Singapore is today different from what it was at the time of
the enactment of the Ordinances. In view of the increased political stature
of the two territories, an in anticipation of further changes likely to be
effected with the establishment of Malaysia, it is now perhaps evidence of
an out of date attitude as well as contrary to national prestige to make
provisions for the supplementation of the local law in the event of lacunae
by means of reference to any "alien" system, whether it be that of the
former imperial power or not.
[37] It is not the function of the court to enter into arguments
regarding the desirability or otherwise of the provision. That is a matter
for Parliament to decide. As far as the court is concerned, until now, that
is the law and the court is duty bound to apply it. In so doing, the
provision is clear that even the application of common law of England as
administered in England on 7 April 1956 is subject to the conditions that no
provision has been made by statute law and that it is "permissible"
considering the "circumstances of the States of Malaysia" and their
"respective inhabitants". That is not to say that post_7 April 1956
developments are totally irrelevant and must be ignored altogether. If the
court finds that the common law of England as at 7 April 1956, is not
"permissible", it is open to the court to consider post-7 April 1956
developments or even the law in other jurisdictions or sources.
[38] The point I am making, if I may borrow the words of Hashim
Yeop A. Sani, Chief Justice (Malaya) in Chung Khiaw Bank Ltd. (supra)
is that "We cannot just accept the development of the common law of
England". We have to "direct our mind to the "local circumstances" or "local
inhabitants"," to quote the words of Peh Swee Chin J in
Syarikat Batu
Sinar Sdn. Bhd. & 2 Ors (supra)
Claim For Post-collapse Economic Loss
[39] As I agree with the Chief Judge (Sabah & Sarawak) that
s. 95(2) protects MPAJ from claims for pre-collapse period, it is not
necessary for me to discuss the issue. So, I shall confine myself to the
post-collapse period.
[40] The High Court had found MPAJ liable for the post-collapse
period and that
s. 95(2) of the Street, Drainage & Building Act 1974 ("S, D & B Act 1974")
does not cover MPAJ. The Court of Appeal reversed that finding purely on the
ground that it is a matter under public law and not private law. The learned
Chief Judge (Sabah & Sarawak) disagreed with the Court of Appeal and held
that the claim could be made under private law as well. While I agree with
his finding of law, in my view, since the Court of Appeal merely "assumes"
that MPAJ was liable for post-collapse period, this Court should go one step
further and decide whether on the facts, MPAJ should be held liable for the
pure economic loss suffered by the respondents/plaintiffs. In this respect,
I shall confine my discussions to the liability of MPAJ, a local authority,
for economic loss suffered by the respondents for its failure to take
remedial actions after the collapse of Block 1.
[41] The judgment of the High Court on this point is rather brief.
This is what the learned judge said: To consider whether the 4th (MPAJ -
added) defendant is liable for the acts and/or omissions committed
post-collapse, it is necessary to disclose some events that transpired after
the collapse of Block 1. After the Highland Towers calamity there were
efforts by the 4th defendant to stabilize the hill slope on Arab Malaysian
Land to ensure that no accident of the kind that caused the collapse of
Block 1 would occurred (sic) to Block 2 & 3. In January 1995, there
was a briefing called by the 4th defendant which was attended by the 5th
defendant and some others. They were told by the 4th defendant that a master
drainage plan for the entire area to accommodate all landowners in the
vicinity of Highland Towers would be prepared. It was announced that the
consultant engaged by the 4th defendant, M/s EEC would be ready with the
master drainage plan within 3 months from date of the briefing. It was
obvious that any master drainage plan for the area must cater for the East
Stream. It was substantially due to this East Stream not properly attended
to that Block 1 collapsed. In fact this concern of the East Stream, from the
chronology of events as set out, was highlighted by JPS from the very
beginning of the development of the Highland Towers Project. Thus the task
to incorporate the East Stream into the comprehensive master drainage plan
falls upon the 4th defendant who is the body in charge of this watercourse.
But after a period of 1 year there was no sight or news of this plan. After
numerous reminders by the 5th defendant of such a plan, the 4th defendant on
the 29.3.1996 held another briefing. This time, the 4th defendant informed
the attendees that a new firm of consultant, by the name of K.N. Associates,
was engaged to replace the previous. Again the 4th defendant gave an
assurance that a comprehensive drainage plan of the area would be forth
coming with this replacement of consultant. Sad to say, until the time when
all evidence for this case was recorded by this Court, no comprehensive
master drainage plan for the Highland Towers and its surrounding area was
adduced by the 4th defendant. In fact this defendant offered no explanation
as to why its promise was not met. These delays had affected the 5th
defendant who insists that without a master drainage plan of the area
approved and implemented by the 4th defendant, and the retaining walls on
their land as well as those on Highland Towers Site are corrected or
rectified, then very little can be done by anyone to secure the stability of
the slope behind Block 2 & 3. Despite this pressing need and the obvious
knowledge of the urgent requirement for a master drainage plan (for
otherwise the 4th defendant would not have initiated steps to appoint
consultants for this work soon after the collapse of Block 1) to secure the
stability of the slope so as to ensure the safety of the 2 apartment blocks,
the 4th defendant did nothing after the respective consultants were unable
to meet their commitments. The plaintiffs and all other relevant parties are
kept waiting because of the 4th defendant. This is certainly inexcusable and
definitely a breach of the duty of care owed by the 4th defendant to the
plaintiffs for not even fulfilling its obligation towards maintenance of the
East Stream. For this I find the 4th defendant liable to the plaintiffs for
negligence. Lastly, the plaintiffs have also alleged that the 4th defendant
failed to take any action against the Tropic in clearing the 5th defendant's
land. I shall be elaborating in detail the acts of Tropic when I analyze the
position of the 5th defendant and Tropic. For the present moment, suffice me
to say that I do not consider the 4th defendant liable to the plaintiffs in
respect of the action committed by Tropic. As for the claim of the
plaintiffs on the 4th defendant for failing to prevent vandalism and theft
to Block 2 & 3, I allow it and my reasons will be intimated in the later
part of this judgment.
Analysis - Nuisance
By the acts and/or omissions of the 4th defendant elaborated above, I
also find that the 4th defendant is an unreasonable user of its land in
failing to maintain the East Stream post collapse which is under its care.
Its acts and or omissions are foreseeable to cause a damage to the
plaintiffs - its neighbour. For this, I find the 4th defendant is also
liable to the plaintiffs for nuisance.
[42] The sum total of it all is the failure of MPAJ to fulfill its
promise to come up with and implement the master drainage plan. As found by
the learned judge, there were efforts made by MPAJ to stabilize the hill
slope on Arab Malaysian Land to ensure that no accident of the kind that
caused the collapse of Block 1 would occur to Blocks 2 & 3. A consultant was
engaged to prepare a master drainage plan. After a year and no such plan was
produced, a new consultant was appointed to prepare the same. Yet it never
materialized. It is for this reason that the learned Judge found MPAJ liable
for negligence to the plaintiffs.
[43] It must be clarified that here I am only concerned with the
failure or delay on the part of MPAJ to come up with and to implement a
master drainage plan in an effort to stabilize the hill slope on the Arab
Malaysian Land.
[44] The question is, does this failure or delay amount to
actionable negligence against a public authority, the MPAJ, for pure
economic loss?
[45] Let us now look at cases decided by Malaysian courts on pure
economic loss. First the case of Kerajaan Malaysia v. Chuah Fong Shiew
[1993] 2 MLJ 439. In that case, the plaintiff claimed damages resulting from
the negligence of the defendants in superintending and supervising buildings
constructed for the plaintiff by Sri Kinabalu Sdn. Bhd. All the defendants
were employees or agents of the consultant firm, Sigoh Din Sdn. Bhd., which
was responsible for superintending and supervising the construction. The
plaintiff alleged that all the three defendants had failed to carry out
their duties to superintend and supervise the construction, causing the
plaintiff to suffer substantial losses in repairing the buildings in order
to make them safe for occupation. The third defendant applied to strike out
the plaintiff's action under
O. 18 r. 19 of the Rules of the High Court 1980 ("RHC 1980"). The senior
assistant registrar struck out the action against the third defendant. The
plaintiff appealed to the judge-in-chambers. The learned judge dismissed the
appeal.
[46] Very interesting arguments were forwarded by learned counsel
for both parties including the effect of
s. 3 of the Civil Law Act 1956, the issue of public policy and exception
to Hedley Byrue & Co. Ltd. & Partners Ltd. [1964] 2 All ER 575.
[47] Unfortunately, the judgment proper is rather brief. On
economic loss, the learned judge merely said: (3) Kerugian yang dialami oleh
plaintif adalah kerugian atau kehilangan ekonomi tulen (pure economic
losses), dan defendan ketiga tidak boleh dikenakan tanggungan (liability) di
bawah tort di atas kerugian yang dialami oleh plaintif dalam kes ini oleh
kerana tiada siapapun yang cedera atau tiada harta kepunyaan orang lain
rosak akibat daripada perbuatan atau salahlaku oleh defendan ketiga.
Keputusan yang dibuat oleh Dewan Pertuanan (House of Lords) dalam kes
Murphy v. Brentwood DC dan lain-lain kes lagi yang membuat keputusan
yang sama, adalah sangat munasabah, berpatutan dan sepatutnya diterima
sehingga bila-bila masapun. Mahkamah di negara ini menerima keputusan dan
pendapat itu dan tiada kemungkinan membuat pendapat yang berlainan, walaupun
apa yang dikatakan oleh peguam pihak plaintif bahawa keadaan di Malaysia
berlainan dengan keadaan di United Kingdom. Hakim dalam kamar ini juga
berpendapat bahawa adalah tidak berpatutan dan tidak munasabah jika
pekerja-pekerja, termasuk juga pekerja-pekerja mahir yang bekerja di bawah
seseorang atau syarikat pemborong binaan, bertanggungan (liable) kepada tuan
ampunya bangunan yang berkenaan di atas kecuaian yang membawa kepada
ketidaksempurnaan bangunan yang berkenaan asalkan ianya tidak menyebabkan
kecederaan kepada diri seseorang atau harta benda orang lain.
[48] Two years later, as a High Court Judge, I had occassion to
decide the case of
Nepline Sdn. Bhd. v. Jones Lang Wootton [1995] 1 CLJ 865. In that
case, a firm of registered real estate agents and chartered valuer was sued
for damages for failure to disclose the fact to the appellant (tenant) that
the premises was subject to "a foreclosure proceeding then pending in
court". The court made an order for sale of the said premises and the
appellant demanded the return of the deposit. The respondent contended that
it was a case of mere omission and not a positive statement made by the
respondent and that the claim was for pure economic loss. It is in that case
that I took the approach mentioned earlier in this judgment. I then tried to
determine the common law of England on the subject as on 7 April 1956, and
then considered the provision to
s. 3(1) of the Civil Law Act 1956. This is what I had said then: I
therefore ask the question whether local circumstances would require the
respondent, an estate agent, a professional who advertised premises for
rent, who knew that the premises was a subject matter of a pending
foreclosure action, to owe a duty of care to the appellant, who answered to
the advertisement and subsequently entered into a tenancy agreement for a
period of two years, to disclose the fact that the premises was subject to a
pending foreclosure action?
I do not have the slightest doubt that the answer should be in the
affirmative.
This is not a case of a friend telling another friend that there is a
house for rent. This is a case of a professional firm, holding out to be a
professional with expertise in its field, earning its income as such
professional. They know that people like the appellant would act on their
advice. Indeed, I have no doubt that they would hold out to be experts in
the field and are reliable. It would be a sad day if the law of this country
recognises that such a firm, in that kind of relationship, owes no duty of
care to its client yet may charge fees for their expert services.
In the circumstances, I think I am fully justified in taking the view
that the defendant in this case owed a duty to the plaintiff to disclose
that there was a foreclosure proceeding pending. I think the provision of
s. 3 of the Civil Law Act 1956, especially the proviso thereto, allows
me to do so.
Learned Counsel for the respondent, referring to numerous texts and
authorities, stressed the need for some control mechanism narrower than the
concept of reasonable foreseeability to limit a person's liability for pure
economic loss. He argued, correctly I must says, that subsequent to Anns's
case there are a number of cases, including Caparo which steered clear of it
and were termed as the "retreat from Anns's cases."
First, I must say that I agree with him that the claim in the present
case (for the refund of the deposit paid) is for pure economic loss. It is
not for an injury to person or property.
Secondly, generally speaking, I also agree that there is a need to limit
recoverability of damages for pure economic loss.
The reasons for judicial reluctance to impose liability in such cases are
conveniently listed by R.P. Balkin and J.L.R. Davis in the Law of Torts
from pp. 421 to 424. These are:
(i) the fear of indeterminate liability;
(ii) disproportion between defendant's blameworthiness and the extent of
his liability;
(iii) interrelationship between liability in tort and contract;
(iv) the need for certainty; and
(v) the effect of insurance.
Considering these factors, it is a wise policy to limit liability in pure
economic loss cases, generally speaking.
However, I am of the view that such fears do not arise in this case. Here
the amount claimed is definite. It is a definite amount which had been paid
by the appellant. It is that amount only which the appellant now seeks to
recover. So, even using the two tests which learned counsel for the
respondent urged me to apply, I think, on the facts of this case, the
respondent is liable.
[49] My record shows that appeal to the Court of Appeal (Court of
Appeal Civil Appeal No. 4-90-95) was dismissed on 6 January 1997.
Unfortunately there is no written judgment of the Court of Appeal.
[50] In the same year
Teh Khem On & Anor v. Yeoh & Wu Development Sdn. Bhd. & Ors. [1996] 2
CLJ 1105 was decided by Peh Swee Chin J (as he then was). In that case,
the plaintiffs claimed against the first defendant ("the builder") in
contract for defective works in the construction of the house purchased by
the plaintiffs. They also claimed against the second defendant ("the
architect") and the third defendant ("the engineer") for damages in
negligence. The learned judge found the builder liable for breach of
contract but dismissed the claim against the architect and the engineer with
whom the plaintiffs had no contractual relationship, the claim being for
pure economic loss. The learned judge discussed at length the development in
England (and mentioning also the attitude of the courts in Australia and New
Zealand) up to Murphy v. Brentwood District Council [1990] 2 All ER
908.
[51] In
Pilba Trading & Agency v. South East Asia Insurance Bhd & Anor [1999]
8 CLJ 403, the appellant ("the insured") sent a damaged car for repair
at a workshop appointed by the respondent ("the insurer"). There was a long
delay at the workshop. As a result, the insured incurred expenses in hiring
an alternative vehicle for which the insured claimed in tort of negligence.
Muhammad Kamil J dismissed the claim on the ground, inter alia, that "the
alleged loss was pure economic loss. It was a financial or pecuniary loss
and did not involve any physical damage or danger of physical damage to the
property of the appellant. It was quite distinct from cases of economic loss
involving physical damage. The established legal position in regard to this
is to preclude such claims even where foreseeable. The courts have always
been reluctant to extend the law of negligence to claim of foreseeable
economic loss."
[52] The learned judge also reviewed judgments of the courts in
England right up to Caparo Industries plc v. Dickman & Ors. [1990] 1
All ER 568
[53] In 1996, James Foong J (as he then was) decided the case of
Dr. Abdul Hamid Abdul Rashid & Anor v. Jurusan Malaysia Consultants (sued
as a firm) & Ors. [1999] 8 CLJ 131. In that case, the plaintiff had
hired the first defendant, an engineering firm, to construct a double storey
house. The plans were signed by the fourth defendant, the proprietor of the
first defendant who was a registered engineer. The building plans were
approved by the second defendant, the local council. About three and a half
years after the handing over of the house to the plaintiff the house began
to collapse due to landslide and the plaintiff had to evacuate the house.
The plaintiffs claims against the first, fourth and fifth defendants were
founded on contract and tort. Their claim against the second defendant (the
local council) was based on negligence and breach of statutory duties. The
cause of action against the third defendant was based on negligence,
nuisance and the rule of Rylands v. Flether.
[54] The court allowed the plaintiffs' claim against the first,
third and fourth defendants but dismissed the claim against the second and
fifth defendants. The learned judge, inter alia, held: (3) A claim
for pure economic loss can be entertained in an action for negligence.
Non-allowance of such claim would leave the entire group of subsequent
purchasers in this country without relief against errant builders,
architects, engineers and related personnel who are found to have erred. If
there is any fear that this approach may encumber the local authorities to
pay out substantial claims due to their negligence in granting approvals or
inspecting building works, there is
s 95 of the Street, Drainage and Building Act 1974 which prohibits such
authorities to be sued.
[55] The learned judge, in his judgment, reviewed judgments of the
courts in England, Australia, New Zealand, Canada and Singapore besides the
judgment of Peh Swee Chin J mentioned earlier. The learned judge
distinguished Murphy (supra), followed the Canadian case of
Winnipeg Condominium Corp. No. 36 v. Bird Construction Co. Ltd. & Ors
[1995] 121 DLR (4th edn.) 193, the Australian case Sutherland Shire
Council v. Heyman & Anor [1985] 157 CLR 424; 60 ALR 1, the Singapore
case of RSP Architects Planniners & Engineers v. Ocean Front Pte Ltd. &
Anor Appeal [1996] 1 SLR 113, but did not follow Pek Swee Chin's
judgment in Teh Khew On & Anor (supra).
[56] However, this case (Dr. Abdul Hamid Abdul Rashid, supra)
was overruled by the Court of Appeal in the instant case.
[57] So, we see that, so far, there had only been a few judgments
of Malaysian courts and all are at High Court level. In three of the cases,
Kerajaan Malaysia (supra), Teh Khew On (supra) and Pilba Trading
(supra), the learned judges appear to have dismissed the claims for pure
economic loss because there were no injuries to person or property. Of the
two that allowed the claim, I had in Nepline Sdn. Bhd. (supra)
allowed it after resorting to the proviso to
s. 3(1) of the Civil Law Act 1959, following and indeed extended
Hedley Byrue (supra) on the basis that there was fiduciary relationship
between the parties. James Foong J, in Dr. Abdul Hamid Abdul Rashid
(supra), appears to base his decision to allow economic loss on his
concern that otherwise "the entire group of subsequent purchases in this
country (would be left) without relief against errant builders, architects,
engineers and related personnel who are found to have erred." However, this
case was overruled by the Court of Appeal in the instant case.
[58] So, it appears that until today Nepline Sdn. Bhd. (supra)
is the only case in which the Court of Appeal has confirmed the judgment of
the High Court in a claim for economic loss, though without a written
judgment.
[59] Now, reflecting on my own judgment in Nepline Sdn. Bhd.
(supra) delivered ten years ago, I am afraid I am still of the same view
regarding the approach that the court has to take in view of
s. 3(1) of the Civil Law Act 1956, the effect of the provision and the
proviso thereto and the decision to accept claims for pure economic loss in
negligence in limited cases, considering the local circumstances. However, I
shall not venture to say where the line should be drawn. It may be said that
this will lead to uncertainly in the law. The answer to that is that this
whole area of common law itself is fraught with uncertainty.
[60] I shall now return to the issue under discussion in the
instant appeal: whether MPAJ is liable for the economic loss suffered by the
plaintiffs for failure (so far) to do what it had promised to do to
alleviate the loss suffered by the respondents after the collapse of Block 1
and evacuation of Blocks 2 and 3. We are actually dealing with the failure
on the part of MPAJ to promptly and effectively carry out the drainage
master plan that it promised to do. And, we are dealing with a local
authority. I am confining my judgment to that factual situation alone.
[61] Even the Privy Council, sitting in England hearing an appeal
from New Zealand had in mind the "local policy considerations" in applying
the common law of England. This can be seen in Invercargill City Council
v. Hamlin [1996] 1 All ER 756, a case concerning the duty of care of the
local authority in New Zealand over the negligence of its Inspector in
approving defective foundations causing damage to the house in question. The
headnote summarises the views of the Privy Council as follows:
Held - The appeal would be dismissed for the following reasons:
(1) The New Zealand Court of Appeal was entitled to develop the common
law of New Zealand according to local policy considerations in areas of the
common law which were developing, not settled. The law of negligence in
relation to a local authority's liability for the negligence of a building
inspector was particularly unsuited to a single solution applicable in all
common law jurisdictions regardless of differing local circumstances. The
perception in New Zealand was that community standards and expectations
demanded the imposition of a duty of care on local authorities and builders
alike to ensure compliance with local byelaws and the Court of Appeal had,
in common with other common law jurisdictions, built up a line of authority
based on the linked concepts of control by the local authority of building
works through the enforcement of its byelaws and reliance on that control by
purchasers. The present case had been decided in accordance with that line
of authority and therefore on the duty of care issue the Board would indorse
in relation to New Zealand the approach taken by the New Zealand courts,
notwithstanding House of Lords authority to the contrary (see p 764 h to p
765 a, p 766 j to p 767 c f g, p 768 c and p 773 c, post); dictum of Lord
Diplock in Cassell & Co. Ltd. v. Broome [1972] 1 All ER 801 at 871
applied; Bowen v. Paramount Builders (Hamilton) Ltd [1977] 1 NZLR 394
and Kamloops (City) v. Nielsen [1984] 10 DLR (4th) 641 followed; D
& F Estates Ltd v. Church Comrs for England [1988] 2 All ER 992 and
Murphy v. Brentwood DC [1990] 2 All ER 908 not followed.
[62] In that case, the court in New Zealand went even further than
the courts in England on the issue of duty of care of a local council. Yet,
the Privy Council declined to interfere considering the "local policy
consideration" and "differing local circumstances" in New Zealand.
[63] We will also remember the views expressed by the Privy
Council in relation to Malaysia quoted earlier.
[64] So, it is in this light that I shall consider the issue now
under discussion.
[65] I shall not enter into the discussion whether the
"categorization approach" or the "open-ended approach" should be accepted by
the courts in this country. That has been sufficiently dealt with by the
learned Chief Judge (Sabah & Sarawak). After all, as correctly stated by
learned Chief Judge (Sabah & Sarawak), the two approaches do not exist in
strict water tight compartments. It is possible for them to overlap.
[66] Even if we accept that the question is not the nature of the
damage itself, whether physical or percuniary, but whether the scope of the
duty of care in the circumstances of the case is such as to embrace damage
of the kind suffered by the plaintiffs, there is the additional factor to be
considered ie, whether it is fair, just and reasonable to impose such a
duty. This is where public policy and local circumstances come into
consideration: In Caparo Industries plc v. Dickman [1990] 1 All ER
568 (HL) at p. 573 to 574, Lord Bride said: What emerges is that, is
addition to the foreseeability of damage, necessary ingredients in any
situation giving rise to a duty of care are that there should exist between
the party owing the duty and the party to whom it is owed a relationship
characterised by the law as one of 'proximity' or 'neighbourhood' and that
the situation should be one in which the council considers it fair, just
and reasonable that the law should impose a duty of a given scope on the
party for the benefit of the other. (emphasis added).
[67] The question then is, considering the public policy and local
circumstances, is it fair, just and reasonable to impose a liability on MPAJ,
a local authority, for pure economic loss to the plaintiffs for its failure
(so far) to come up with and implement the promised drainage master plan or
to stabilize the hill slop on Arab Malaysian Land to ensure that no accident
of the kind that caused the collapse of Block 1 would occur to Blocks 2 and
3?
[68] A local council is establish with a host of duties to
perform, from providing and maintaining recreational areas and collecting
garbage to providing public transport, homes for the squatters, temporary
homes in case of disasters, natural or otherwise, and so on. Indeed, the
list is endless. The expectations of residents are even more. These are
public duties to all residents or ratepayers within the council's
geographical limit. To finance all their activities, local authorities
depend mainly on assessment rates and fees for licences. In a democracy as
in Malaysia and the kind of attitude of the people, we know too well how
difficult it is to increase the rates or the fees even by a few percent.
With limited resources and manpower, even if it tries its best (and
generally speaking, I say they do) to provide the infrastructure and
services, it will not satisfy everybody. People's demands far outweigh their
contributions. When services are provided or as a result of infrastructural
improvements, the value of their properties goes up, as usually happen, it
is taken for granted, as their rights, their good fortune or business
acumen. Then there is the attitude of the public from littering and
vandalism to resorting to irresponsible means in order to maximise profits,
as we see in the facts of this case as narrated by the learned High Court
Judge.
[69] With limited resources and manpower local councils would have
to have their priorities. In my view, the provision of basic necessities for
the general public has priority over compensation for pure economic loss of
some individuals who are clearly better off than the majority of the
residents in the local council area. Indeed, the large sum required to pay
for the economic loss, even if a local council has the means to pay, will
certainly deplete whatever resources a local council has for the provision
of basic services and infrastructure. Projects will stall. More claims for
economic loss will follow. There may be situations where a local council,
which may only be minimally negligent, may be held to be a joint tortfeasor
with other tortfeasors, which may include irresponsible developers,
contractors and professionals. There is no way to execute the judgments
against them. Out of necessity or for convenience, the judgment for the full
amount may be enforced against the local council. The local council may go
bust. Even if it does not, is it fair, just and reasonable that the
taxpayers' money be utilised to pay for the "debts" of such people? In my
view, the answer is "No".
[70] I do not think that we can compare the "local circumstances"
in New Zealand, for example, with the "local circumstances" in Malaysia now,
be it in terms of development (many Malaysian, though it may not in the MPAJ
locality, are still without water supply and electricity), civic mindedness
of, and compliance with laws and bylaws by the general public or, as we see
in this case, even by developers, and others. I do not think that, in the
present circumstances, on the facts and in the circumstances of this case,
it is fair, just and reasonable to impose such a burden on MPAJ or other
local councils in this country in similar situations.
[71] For the same reasons too, the claim for loss due to vandalism
and theft by the respondents which was allowed by the learned trial judge
should not be allowed. Vandalism follows every disaster, natural or
otherwise, in undeveloped, developing or most developed countries. Recent
event shows that even the most powerful military and the best equipped
police force in the richest and most developed country in the world were
also unable to prevent it. Even we ourselves cannot ensure that our own
houses will not be broken into. I do not think it is fair, just and
reasonable to hold MPAJ liable for it.
[72] The discussion in this judgment covers nuisance as well.
[73] So, while I agree with the answers given by the learned Chief
Judge (Sabah & Sarawak) on other questions, on pure economic loss, my answer
to question No. 3 is as follows:
[74] While economic loss under limited situations may be allowed,
Malaysian courts will have to consider the effects of
s. 3 of the Civil Law Act 1956 and, considering the "public policy" and
the "local circumstances", whether it is fair, just and reasonable to allow
it on the facts and in the circumstances of the case.
[75] I would therefore allow MPAJ's appeal with costs here and in
the courts below and order that the deposit be refunded. Regarding the
cross-appeal by the respondents, even though, as a matter of law, I agree
with the learned Chief Judge (Sabah & Sarawak) who disagrees with the Court
of Appeal on the question of the dichotomy between public law and private
law, in the light of my judgment on the pure economic loss issue, I would
dismiss it. However, on the cross-appeal, I would order that each party pays
its own costs and that the deposit be refunded to the respondents.
Arifin Zakaria FCJ:
[76] I have had the advantage of reading in draft the judgments of
the learned Chief Judge (Sabah & Sarawak) and that of my learned brother
Abdul Hamid Mohamad, FCJ and for the reasons he gives I agree with the
learned Chief Judge (Sabah & Sarawak) on all the issues before this court
except on the issue of "post collapse" liability. On the "post collapse"
liability, for the reasons he gives, I agree with the view of my learned
brother Abdul Hamid Mohamad, FCJ.
[77] In the circumstances, I would therefore allow the appeal by
Majlis Perbandaran Ampang Jaya with costs here and in the courts below and
order that the deposit be refunded. On the cross appeal by the respondents I
would dismiss the same but order that each party bears its own costs and the
deposit be refunded to the respondents.
|