LOH WAI LIAN V.
S.E.A. HOUSING CORP. SDN. BHD.
HIGH COURT MALAYA, KUALA LUMPUR
MOHAMED DZAIDDIN J
[CIVIL SUIT NO. F 210 OF 1982]
29 SEPTEMBER 1983
JUDGMENT
Mohamed Dzaiddin J:
This is an appeal by the defendant against the decision of the Registrar in
giving leave to the plaintiff to enter final judgment under O. 14 of the
Rules of the High Court for liquidated damages for a breach of contract.
The facts are as follows. On 18 March 1974, the respondent executed a sales
and purchase agreement with the appellant to purchase a 3 1/2 storey terrace
house at the price of RM175,000. The agreement provides that the house was
to be completed and vacant possession to be delivered to the respondent not
later than eighteen months from the date of agreement, i.e. on or before 18
September 1975. However, the house was not completed until 7 November 1977.
It is a term of the said agreement that the appellant should pay liquidated
damages at the rate of 8% per annum on the purchase price for any delay in
the completion of the said house up to the date of actual completion and
delivery of possession. Since November 1977, nothing had taken place between
the respondent and the appellant until 21 April 1980 when the respondents
through the solicitors wrote to the appellant alleging a breach of the
agreement and demanded payment of RM29,972.01 being liquidated damages.
Then, on 7 September 1982, the respondent filed a civil action for
liquidated damages for breach of contract. On 10 December 1982, the
appellant entered a defence; and paragraph 3 of the said defence states as
follows:
... the Plaintiff's alleged cause of action did not accrue within six (6)
years before the commencement of this action and therefore any claim against
the Defendant herein, which is not admitted, is time barred under the
Limitation Ordinance, 1953.
It appears from the record that the appellant has abandoned other defences
in view of the Federal Court decision in S.E.A. Housing Corporation Sdn. Bhd.
v. Lee Poh Choo [1981] 1 LNS 25.
On 14 October 1982, the respondent applied for summary judgment and the
matter was heard by the learned Registrar on 14 April 1983 who held that "In
this situation, the action brought by the plaintiff is still within the six
year period and hence, I have allowed the plaintiff to enter judgment
against the defendant".
This appeal is centred on just one question: when did the respondent's cause
of action accrue?
Counsel for the appellant submitted that the cause of action in this case
accrued on the day when vacant possession was supposed to be delivered, i.e.
on or before 18 September 1975, because the cause of action accrued on the
breach of the agreement.
The respondent, on the other hand, contended that time started to run from
the date of actual delivery of vacant possession (7 November 1977).
Therefore, she was still within time when she filed the action on 7
September 1982.
Section 6 (1) of the Ordinance provides that in the case of actions founded
on a contract, the period of limitation shall be six years from the date on
which the cause of action accrued. It has been said in Chitty on Contracts
that the ascertainment of this date is often the question of some
difficulty. There is no definition of the term "cause of action" in the
Ordinance. There are, however, a few English authorities on this point. In
Nasri v. Mesah [1970] 1 LNS 85, Gill FJ (as he then was) stated as follows:
A `cause of action' is the entire set of facts that gives rise to an
enforceable claim; the phrase comprises every fact which, if traversed, the
plaintiff must prove in order to obtain judgment (per Lord Esher MR in Read
v. Brown). In Reeves v. Butcher Lindley LJ said:
This expression, `cause of action', has been repeatedly the subject of
decision, and it has been held, particularly in Hemp v. Garland, decided in
1843, that the cause of action arises at the time when the debt could first
have been recovered by action. The right to bring an action may arise on
various events; but it has always been held that the statute runs from the
earliest time at which an action could be brought.
In Board of Trade v. Cayzer, Irvine & Co. Viscount Dunedin described "cause
of action" as that which makes action possible. Now, what makes possible an
action founded on a contract is its breach. In other words, a cause of
action founded on a contract accrues on the date of its breach. Similarly,
the right to sue on a contract accrues on its breach. In the case of actions
founded on contract, therefore, time runs from breach (per Field J in Gibbs
v. Guild). In the case of actions founded on any other right, time runs from
the date on which that right is infringed or there is a threat of its
infringement (see Bolo's case). It would seem clear, therefore, that the
expressions "the right to sue accrues", mean one and the same thing when one
speaks of time from which the period of limitation as prescribed by law
should run.
In the above case, the appellant claimed for specific performance of an
agreement whereby the respondent agreed to sell to him certain land. The
appellant had paid the agreed price for the land but no document of transfer
was executed because of the moratorium then in force. After the expiration
of the moratorium, the appellant approached the respondent on several
occasions and requested her to execute a transfer of the land. Eventually,
the appellant commenced the action. The High Court dismissed this action on
the ground of limitation. On appeal, the Federal Court in allowing the
appeal held:
(1) in this case whether the action was for specific performance of an
agreement for the sale of land or for a declaration of title to land, it was
essentially an action to recover land, and the period of limitation
therefore would be twelve years;
(2) time begins to run for the purposes of limitation from the date of any
infringement or threat of infringement of the appellant's right under the
agreement. A cause of action on a contract accrues on the date of breach and
in the case of actions founded on contract, therefore, the time runs from
the breach.
The learned Registrar in her grounds of judgment, referred to the decision
of Bolo v. Koklan & Ors. LR 57 IA 325, a Privy Council case in which it was
said at page 331:
There can be no `right to sue' until there is an accrual of the right
asserted in the suit and its infringement, or at least a clear and
unequivocal threat to infringe that right, by the defendant against whom the
suit is instituted.
In my opinion, the principle in Bolo's case is not applicable to the present
case. Here, the `right to sue' is established upon a breach under the
agreement and a breach is committed on the expiry of the eighteen months
period from the date of the signing of the agreement. In my judgment, time
runs from the date of the breach which is immediately after the date of
delivery of vacant possession under the agreement, i.e. six years from 18
September 1975. In such circumstances, the respondent's action which was
filed on 7 September 1982 is statute-barred.
I allow this appeal with costs (including costs of O. 14 proceedings) to the
appellant.