LIM TECK KONG V. DR ABDUL HAMID ABDUL
RASHID & ANOR
COURT OF APPEAL, PUTRAJAYA
[CIVIL APPEAL NO: B-02-757-98]
MOKHTAR SIDIN, JCA ; HAIDAR MOHD NOOR, JCA ; ABDUL KADIR
SULAIMAN, JCA
28 SEPTEMBER 2005
JUDGMENT
Mokhtar Sidin JCA:-
[1] Sometime in January 1990, the respondents issued a writ of
summons and a statement of claim against the appellant and four others. This
writ and statement of claim was amended on 27 December 1990. In the amended
writ and the statement of claim the 1st defendant was Jurusan Malaysia
Consultants (sued as a firm), the 2nd defendant was Majlis Daerah Gombak,
the 3rd defendant was Mighty Corporation Sdn Bhd, the 4th defendant is the
appellant in the present appeal and the 5th defendant was an individual by
the name of Leow Kim Sang. After hearing the case, the High Court, Shah Alam
on 15 December 1996 made an order that the 1st, 3rd and 4th defendants do
pay the sum of RM364,173 to be apportioned as follows:-
(1) The 1st defendant and/or 4th defendant to pay the plaintiffs (the
respondents in this appeal) the sum of RM218,503.80 representing 60%
liability.
(2) The 3rd defendant the sum of RM145,669.20 representing 40%
liability.
[2] The claim of the respondents as against the 2nd defendant was
dismissed with costs. As against the 5th defendant, the learned judge found
that he was a clerk in the 1st defendant's firm, although he represented
himself as a partner in the 1st defendant's firm. No order was made against
him.
[3] In order to understand the roles played by the parties, we
have to refer to the statement of claim and the statements of defence. We
will refer to the parties as they were in the High Court. In their amended
statement of claim, the plaintiffs claimed that sometime in early 1984, they
wanted to build a double-storey bungalow (hereinafter referred to as "the
bungalow") on Lot No. 3007, Mukim of Ulu Kelang, Gombak, Selangor, belonging
to them and the bungalow was intended to be their residential home. The
plaintiffs then engaged the services of the 1st defendant, a firm of civil
and structural engineers who was then practicing at 201-A (1st floor), Jalan
Imbi, Kuala Lumpur. The plaintiffs claimed that when they went to the office
of the 1st defendant, the 4th and 5th defendants claimed to be the partners
of the 1st defendant's firm. During the trial it was established that the
5th defendant was only a clerk and a draughtsman of the firm and not a
partner. At the recommendation of the 1st defendant, the plaintiffs entered
into a written agreement (the building contract) with one Yap Foot Ching
(hereinafter referred to as "the contractor") to build the bungalow. One of
the terms and conditions of the building contract was the contractor was to
perform the works shown in the drawings and the specifications prepared by
or under the direction of the 1st defendant. It is not disputed that the
bungalow was duly completed and the plaintiffs and their family moved into
the said building when the contractor handed over vacant possession to the
plaintiffs on 11 April 1985.
[4] The claim of the plaintiffs against the 2nd defendant (a
corporate body established under the Local Government Act 1976) was that the
2nd defendant being the District Council where the bungalow was situated has
legal duties which amongst others include:-
(a) to do or cause to be taken or done such steps or acts so as to
prevent matters which are likely to endanger public safety or cause damage
to property within the local authority area including and not limited to
the proper supervision and examination of proper and safe drainage and
flow of water within the area and the removal of any dangers arising
therefrom;
(b) the supervision and approval of, inter alia, building plans
in respect of buildings and other structures proposed to be built or
erected within local authority area.
[5] In or about the middle of 1987, the 3rd defendant commenced
construction works on Lot 3008 which was a lot adjoining Lot 3007 to erect
another residential building. During the course of construction on Lot 3008
a meeting was held between the owner of Lot 3008, a representative of the
3rd defendant and the 1st plaintiff whereby the 3rd defendant was alerted
that construction works carried out by the 3rd defendant on Lot 3008 posed a
potential danger to the neighbouring lots including Lot 3007 because Lot
3008 stood on higher ground. The 3rd defendant's representative assured the
parties that adequate steps would be taken to prevent obstruction and water
collection and ensure free flow and drainage of water passing through the
vicinity of Lot 3007.
[6] Between the night of 17 September 1988 and the early morning
of 18 September 1988, the rear portion of the bungalow collapsed and as a
result the bungalow became uninhabitable. The plaintiffs thus suffered
losses, damages and expenses. In the statement of claim the plaintiffs
claimed that the damages to the bungalow and Lot 3007 were due to breach of
duty by all the defendants either jointly or severally. The damages and
losses suffered by the plaintiffs are particularised in the schedules to the
statement of claim.
[7] The 1st, 4th and 5th defendants filed their statement of
defence. In the statement of defence the 4th and 5th defendants admitted
they were the partners of the 1st defendant's firm. (During the trial
evidence was adduced to show that the 5th defendant was not a partner but
only a clerk in the firm). They denied that they were in breach of duty and
put the plaintiffs to strict proof. The defendants further claimed that they
had fully discharged their legal and/or contractual duties by adopting the
normal engineering practices. They also claimed that in constructing the
bungalow they had adopted the following measures:-
(a) conducted pre-design assessment and evaluation of the site
conditions of Lot 3007;
(b) supported the new buildings on Lot 3007 on a piled foundation based
on correct design considerations.
[8] This was based on their experience in development of building
site and housing infrastructure. The defendants averred that the cause of
the collapse was due to the failure to maintain by an ignorant owner of an
initially stable slope which was increased by overburden to the slope and
erosion.
[9] The 2nd defendant in their statement of defence denied that
they own any legal duty as averred by the plaintiffs in their re-amended
statement of claim. The 2nd defendant further stated in their defence that
pursuant to the Local Government Act, the 2nd defendant merely had the power
to execute works of such general advantage to the inhabitants of the local
authority areas and to do all things necessary or conducive to the public
safety, health and convenience. The 2nd defendant also stated that they were
not responsible for any alleged loss, damage or expense incurred or suffered
by the plaintiffs.
[10] The 3rd defendant admitted that they did construction works
on Lot 3008, but denied that the construction works caused the damages and
losses on Lot 3007 as claimed by the plaintiffs. The 3rd defendant also
denied that a meeting between the representative of the 3rd defendant, the
1st plaintiff and the owner of Lot 3008 ever took place as alleged by the
plaintiffs. The 3rd defendant claimed that they had carried out and
completed the construction of the building on Lot 3008 in accordance with
the contract drawings and specifications and also the directions of the
architects and civil and structural engineers employed by the owner of Lot
3008. The 3rd defendant further averred that they had taken all reasonable
measures and steps at all material times to avoid dangers and/or causing any
damage to the neighbouring lots such as implementing run-off drains and that
there were no unfilled trench on Lot 3008 during and after the construction
of the building on Lot 3008. The 3rd defendant further claimed that the
bungalow's collapse was caused and/or contributed to by the plaintiffs'
failure to exercise reasonable care in not engaging a competent consultant
civil and structural engineers to prepare, design, drawings and plans and
all other necessary works in connection with the building of their family
house. Alternatively, the 3rd defendant contended that the collapse of the
bungalow was caused by and/or contributed to by the breach of the 1st
defendant.
[11] The learned trial judge in his judgment found the following
facts as proved either by documents or oral evidence adduced during the
trial. Sometime in 1984 or 1985, the 1st plaintiff went to the 1st
defendant's office. When he was inside the office he was attended to by the
5th defendant who gave an impression that he was also an engineer. The plan
for a double-storey house was drawn and signed by the 4th defendant. It was
not disputed that the 4th defendant was a registered engineer with the Board
of Engineers at the material time but he was struck off at the time when the
trial took place as a result of his admission to the regulatory body that he
had breached the rules by operating two firms at the same time, one of which
was the 1st defendant. That was the reason why the 5th defendant (who was
only a clerk and a draughtsman) claimed to be an engineer and a partner in
the 1st defendant's firm. The 1st defendant then prepared the building plans
in respect of the bungalow and submitted the plans to the 2nd defendant for
approval. The 2nd defendant approved the plans. The contractor approved by
the 4th defendant then commenced construction of the bungalow and completed
it in 1985 and handed over vacant possession of the bungalow to the
plaintiffs.
[12] On 18 September 1988, at about 3am the plaintiffs were
awakened by a loud noise. The 1st plaintiff looked out of his bedroom window
and saw the concrete deck and the boundary brickwall which were erected on
his land had tilted and collapsed. The plaintiffs and their family then
rushed out of the house. At about 5am, the 1st plaintiff heard shattering
sounds of glass coming out from his house. By about 6am the plaintiffs
returned to the house and found that half of the house on the side of the
river had collapsed. The incident was reported to the relevant authorities
including the 2nd defendant. On the instigation of the 2nd defendant, the
plaintiffs appointed Kumarasivam Tan Ariffin Sdn Bhd (KTA), an engineering
consultant, to determine the cause of the collapse. A report was issued on 3
April 1989. In that report it was stated the causes of the collapse were:-
(1) the slope on which the said building was built was steep with a
gradient of about 45 degrees;
(2) engineers advising on the building and construction of the house
took little consideration in assessing the stability of the slope;
(3) an excavation that was carried out on a neighbouring land known as
Lot 3008 at the material time by the 3rd defendant who were the
contractors engaged in erecting a double-storey bungalow thereon;
(4) heavy rainfall; and
(5) toe erosion at the river banks bordering Lot 3007.
[13] The learned trial judge found that the 4th defendant was the
proprietor of the 1st defendant. The 5th defendant was only a clerk and a
draughtsman working with the 1st defendant and not the co-proprietor as
alleged by the plaintiffs. The learned trial judge then dismissed the
plaintiffs' claim against the 5th defendant. The learned judge found that
the claim by the plaintiffs against the 2nd defendant is based on negligence
and breach of statutory duties. The learned trial Judge found that the
plaintiffs failed to establish the specific provisions in the statute where
the 2nd defendant had breached except may be the following provisions:-
(1) Section 101(ee) of the Local Government Act relates to "the local
authority shall have the power to divert, straighten, define and canalise
the course of any stream, channel or watercourse";
(2) Section 53(1) of Act 133 requires local authority to maintain and
keep in repair watercourses under the control of the local authority;
(3) Section 70A of Act 133 empowers the local council to order
cessation of earth works where the safety of life or property is affected
or is likely to be affected;
(4) By-law 8(3) and 17 Uniform Building By-Laws 1984 confer powers on
local authority to disapprove building and structural plans submitted for
its approval;
(5) By-law 10 of the Uniform Building By-Laws 1984 sets out requirement
for building plans submitted to the local authority must contain complete
lines of surface water discharge to the proposed drains, which the
plaintiffs claim is absent in the site plans for their lot submitted by
the 1st and/or 4th defendants;
(6) By-law 25(2) of the Uniform Building By-Laws requires that "all
.... open spaces in and around buildings shall be suitably protected
against soil erosion", of the 2nd defendants have failed to ensure
relevant steps to protect this.
[14] The learned trial judge dismissed the claim against the 2nd
defendant on the following grounds:-
Firstly, whether the pleadings of the plaintiffs have sufficiently
disclose material facts to support the plaintiffs' claim for breach of
statutory duty against the 2nd defendants. In order to succeed under a
cause of action for breach of statutory duty the plaintiffs must show that
they came within the class of person intended by an Act or regulation to
be protected, that the statutory provision was broken, and that they
suffered damage and that this damage was caused by the breach of the
provision ... In essence the entire claim based on breach of statutory
duty depends on the provision of the statute or by-laws being alleged to
be breached. The affected legal provision has thus become a material fact
that needs to be disclosed, for failure to do so the defendant will be
caught by surprise and be prejudiced in their defence.
Secondly, the Uniform Building By-Law 1984 in which various provisions
are said to have been breached did not come into force in the State of
Selangor until 1.1.1986. The building plans of the house was submitted
around 1984 and the completed house was handed over for possession to the
plaintiffs on 11.4.1985. Therefore any allegations for breach of statutory
duties which involve the 2nd defendants in respect of this piece of
legislation before it came into force cannot be sustained, there being no
enacted statute at the material time to be breached. Though the 2nd
defendants may have relied on this by-law as a guideline in the course of
their duties before the enactment of this statute in the State of Selangor,
but in a claim for breach of statutory duty reliance must be on a lawful
enactment and not on a piece of legislation that has no force of law in a
particular area.
Thirdly, by virtue of section 95 of Act 133:-
The State Authority, local authority and any public officer or
employee of the local authority shall not be subjected to any action,
claim, liabilities of demand whatsoever arising out of any building or
other works carried out in accordance with the provisions of this Act or
any by-laws made thereunder or by reason of the fact that such building
works or plans thereof are subject to inspection and approval by the
State Authority, or such public authority and nothing in this Act or any
by-laws made thereunder shall make it obligatory for the State Authority
or the local authority to inspect any building, building works or
material or the site of any proposed building to ascertain that the
provisions of this Act or any by-laws made thereunder are complied with
or that plans, certificates and notices submitted to him are accurate.
[15] The plaintiffs did not appeal against that decision.
[16] As against the 3rd defendant, the plaintiffs' claim was for
unnecessarily allowing infiltration or seepage of water into the ground
and/or allowing it to overflow onto the plaintiffs' land causing saturation
in the soil resulting in the landslide which brought down the bungalow. The
learned judge was of the view that there are four main allegations of fault
against the 3rd defendant:-
(a) inserting a pipe into the public drain fronting Lot 3009 which
caused rainwater to overflow onto Lot 3009, Lot 3008 and Lot 3007;
(b) blocking the public drain fronting Lot 3008 with plastic sheets and
wooden debris thereby causing rainwater to overflow onto Lot 3008 and Lot
3007;
(c) excavating a trench measuring 60' x 10' x 3' on Lot 3008, causing
it to collect a concentration of rainwater which seeped and infiltrated
into the ground;
(d) leaving transverse drains built along the slope of Lot 3008 to end
three quarter of the way down the slope instead to the river.
[17] In his judgment, the learned judge found that the plaintiffs
failed to prove the first two allegations, but succeeded in proving the last
two allegations. In his judgment he said:-
The cause of action against the 3rd defendants is based on nuisance,
negligence and the rule of Rylands & Fletcher. As for liability in respect
of water it is best stated in Clerk & Lindsell on Tort 13th Edition
at page 851, of which was adopted by the Federal Court in Seong Fatt
Sawmill Sdn Bhd v. Dunlop Malaysia Industries Sdn Bhd [1984] 1 MLJ
286. It reads as follows:-
Liability in respect of water depends on whether the water is
naturally on the land or whether it is artificially accumulated or
interfered with in some way. The owner of land on a lower level cannot
complain of water naturally flowing or percolating to his land from a
higher level. Nevertheless the higher proprietor is liable if he
deliberately drains his land onto his lower neighbour's land and this
appears to be so if the water is caused to flow in a more concentrated
form than it naturally would, as the result of artificial alterations in
the levels and contours of the higher land.
When water appears upon the surface of the land in a diffused state,
with no regular course, and then disappears by percolation or evaporation,
Justice Winderyer J in an Australian case of Gartner v. Kidman
(1961-62) 108 CLR 12 has this to add;
The higher proprietor: He is not liable merely because surface water
flows naturally from his land on to lower land. He may be liable if such
water is caused to flow in a more concentrated form than it naturally
would. It flows in a more concentrated form than it naturally would if, by
the discernible work of man the levels or conformations of land have been
altered and as a result the flow of surface water is increased at any
particular point. If a more concentrated flow occurs simply as the result
of the "natural" use of his land by the higher proprietor, he is,
generally speaking, not liable. What is a natural use is a question to be
determined reasonably having regard to all the circumstances, including
the purpose for which the land is being used and the manner in which the
flow of water was increased, as for example whether it is agricultural
land cleared for grazing, whether it is a mining tenement, or is used for
buildings and so forth. ....
In this case, the 3rd defendants had artificially accumulated the
rainwater with the excavation which was an alteration to the nature of the
land. They had also interfered with the rainwater by constructing transverse
drains ending three quarter way down the slope of Lot 3008. All these had
affected the natural flow of the water resulting in its concentrated and
increased infiltration into the land thereby causing destructive effect to
Lot 3007. By such deeds the 3rd defendants have breached their duty of care
towards the plaintiffs in respect of negligence, caused nuisance to the
plaintiffs, as well as being liable in part under the rule of Rylands and
Fletcher.
Though the 3rd defendants did claim contributory negligence from the
plaintiffs, but from the evidence so tendered this Court finds no support
for it. The plaintiffs have built a house according to plans advised, drawn
and designed by the 1st and/or 4th defendants. They have even taken
cautionary steps to place piles along their slopes and sand bags at the toe
of both Lots 3008 and 3007. They had also advised the 3rd defendants to take
precautionary measures in their construction on Lot 3008. These were
positive actions which cannot be interpreted as having contributed to the
3rd defendants' negligence.
[18] Based on the above, the learned judge found that the 3rd
defendant was 40% liable for causing nuisance and negligence which
contributed to the collapse of the bungalow. Apparently, the 3rd defendant
did not appeal against that decision nor did the plaintiffs.
[19] The appeal before us is only the appeal by the 4th defendant.
Though there is no appeal by the 1st defendant. it is clear from the
evidence that the 4th defendant was the sole proprietor and the alto ego of
the 1st defendant and the decision against the 4th defendant (the appellant)
is a decision against the 1st defendant. It appears that when this matter
came up for hearing in the court below, the 4th defendant had been struck
off from the Register for committing an offence of running two engineering
firms at two different places. We are not sure whether the 1st defendant is
still in existence when this matter came up for hearing before us in view of
the fact that the 4th defendant, being the sole proprietor of the 1st
defendant, had been struck off from the Register.
[20] In his judgment, the learned trial judge found that the 1st
defendant was an engineering firm solely owned by the 4th defendant (the
appellant). In his judgment, the learned judge made it clear that any
reference to the 1st defendant would be reference to the 4th defendant. In
his judgment the learned judge said:
The contractual relationship between the plaintiffs and the 1st
defendants, which is basically the 4th defendant derives from a letter of
appointment tendered as exhibit P12. In it, the 1st defendants agree "as
your (the plaintiffs) consultant engineers to prepare the civil and
structure drawings and calculations and to submit to the respective
authorities". These drawings and calculations, as the heading in exhibit
P12 specifies are for the plaintiffs' house. Other than this brief
declaration of obligation and another two short paragraphs which devotes
to the amount of professional fees charged and the mode of its payment, no
other terms are elaborated.
By the nature of the plaintiffs' claim on contractual liability, the
contentions are as follows:-
(a) the 1st and/or 4th defendants failed to exercise reasonable care
and skill in carrying out all aspects of the engagement having regard in
particular to the primary objective of the plaintiffs;
(b) the 1st and/or 4th defendants failed to properly and adequately
implement and examine Lot 3007, its soil condition and surroundings to
ascertain the suitability of the slope for the proposed house to be built
thereon.
As these contentions are not within any express and specific condition in
the written contract, the only basis the plaintiffs can rely on to succeed
is within the legal concept of they being implied terms.
The principle of implied terms to be read into any contract is well
accepted in our Courts, and for it to be applicable certain conditions must
be fulfilled. On these, Lord Simon in the Privy Council case of B.P.
Refinery (Western-port) Pty Ltd v. Shire of Hasting [1978] 52 ALJR 20
had spelled them out as follows:
In their (their Lordships) view, for a term to be implied, the
following conditions must be satisfied; it must be reasonable and
equitable; it must necessary to give business efficacy to the contract, so
that no term will be implied if the is effective without it; it must be so
obvious that 'it goes without saying', it must be capable of clear
expression, it must not contradict any express term of the contract.
In the circumstances of this case, the contract between the plaintiffs
and the 1st and/or 4th defendants is one of performance of services by
professionals who have described themselves as "consulting Civil and
Structural Engineers". Any persons declaring themselves to be such must
reasonably and equitably be expected to take reasonable care and skill in
the performance of their craft. If this be not the case, why then should a
layman engage and pay a price for their services. This term of the expected
reasonable care and skill is so obvious in the 1st and/or 4th defendants'
appointment that this Court finds it to come within the ambit of "it goes
without saying". Further, this term is clear in expression and contradicts
no other terms in exhibit P12. For these, it qualifies to be accepted as an
implied term of the contract between the plaintiffs and the 1st and/or 4th
defendants.
[21] Perusing the memorandum of appeal, the 4th defendant accepted
the above ruling by the learned judge. In his memorandum of appeal the 4th
defendant raised 15 grounds which could be simplified into two broad issues,
ie, the contractual liability and the causation.
[22] Before us, the learned counsel conceded that the learned
judge was correct in his conclusion in respect of the contractual liability.
The 4th defendant contended that the plaintiffs in their statement of claim
failed to plead duty of care, particulars of negligence and causation in
respect of the collapse. Anyway, the learned counsel for the 4th defendant
submitted that the contractual liability could be narrowed to: (i) whether
the duty of care had been breached; and (ii) the causation.
[23] The learned trial judge in his judgment stated:-
In respect of the soil, he took some samples from the exposed layer on
the land in his hand, examined it visually, and concluded it to be a silty
sand soil. To him this soil "has good drainage properties, it drains very
fast".
As regards to the house, piling was recommended and carried out just
before the slope so that the structure of the house would "not place too
much weight on the slope."
All these evidence of the 4th defendant, considered in the light of the
expert opinions of KTA's report and that of Dr. Toh's reveal fundamental
weaknesses. Firstly, as admitted by this defendant himself under
cross-examination, "I cannot ascertain the soil by simply looking at it". By
just looking and feeling the soil he agrees that the sheer strength of the
soil cannot be determined. Yet, it is an accepted fact by the two expert
engineers and to a large extent by the 4th defendant himself, that the
determination of this sheer strength of the soil was one of the vital
factors in deciding slope stability. Exhaustive tests were conducted by both
Dr. Ramli and Dr. Toh in the laboratory on the nature and strength of the
grain found on Lot 3007, but with this professional, the 4th defendant, his
judgment depended on only visual and feel. Further, though silty sand soil
has good drainage properties but as the 4th defendant also admits, "water
also enter (into such soil) very fast, and water do not drain out
immediately. There would be a period when the water will be held in the
soil". If this is his theory then suction in the soil will be saturated,
effecting its stress effectiveness to be reduced to a point where the total
sheer strength resistance would fail resulting in a landslide. So essential
is the need for an engineer to determine the soil condition to a high degree
of certainty, particularly on a gradient such as Lot 3007, that a failure to
do so must be accepted as a breach of implied term of his appointment to
take reasonable care.
[24] The 4th defendant submitted that the learned judge was in
error in coming to the conclusion that the 4th defendant did not do enough
to ensure that the building that he built on Lot 3007 was safe. In his
submission, the 4th defendant stated that construction of the bungalow was
completed in 1985 and handed over to the plaintiffs on 11 April 1985. It was
only on 17 September 1988 that the bungalow collapsed. The 4th defendant
submitted further that the house on Lot 3008 which was situated above Lot
3007 (the bungalow) was constructed later. It was also submitted that the
bungalow collapsed two weeks after the 3rd defendant (who was the contractor
building the house on Lot 3008) did some excavation to construct a trench
60' x 10' x 5'. This trench collected water which caused weakening to the
wall and caused the bungalow to collapse. The 4th defendant claimed that
stability of 1.53 was enough and that was an accepted engineering fact. The
4th defendant referred to exh. P20 (pp. 775-878 of the appeal record at pp.
775-784) the expert opinion submitted by the 4th defendant.
[25] As to causation, the learned counsel for the 4th defendant
submitted that there was no finding on causation by the learned judge. In
the court below, two separate reports prepared by two experts were tendered
as evidence. The first report from the firm KTA prepared by Dr. Ramli was
tendered by the plaintiffs while the second report prepared by Dr. Toh was
tendered by the 4th defendant. The two reports are basically evidence in
respect of causation of the collapse. In addition, both Dr. Ramli and Dr.
Toh gave evidence in court in support of their reports. The 4th defendant
contended that the learned trial judge was in error when he preferred the
evidence of Dr. Ramli.
[26] The learned judge in his judgment explained why he preferred
to accept the finding (opinion) of Dr. Ramli as against the finding of Dr.
Toh:-
The 4th defendant through the vehicle of the 1st defendants had
professed to be a consultant civil and structural engineer. His
specialized craft was to advise and design structures adequate and safe
for a particular purpose. Why then did the house collapse, and was it due
to the 4th defendant failing to exercise his skill to the standard of a
man professing similar professional craft? To examine this, one would have
to refer to the reports by the experts. One is prepared by KTA with Dr.
Ramli's testimony in Court to elaborate on it. The other is a report
prepared by Dr. Toh on the 27.4.1995 - exhibit D20 done almost 6 years
after the collapse of the house, at the request of the 1st and/or 4th
defendants.
Basically, in KTA's report, the collapse of the house was attributed
to slope failure caused by the lateral movement of the earth supporting the
foundation of the house. This was due to infiltration of water, such as
rainfall which increased saturation of the soil causing a rise in water
table and a reduction in the soil suction. "This result in a decrease in the
effective stress and therefore soil sheer strength, to a point where the
total sheer resistence along the potential failure surface is insufficient
to sustain equilibrium of the slope". In KTA's opinion, though "it is
extremely difficult to predict the relationship between suction and rainfall
intensity for a particular soil profile, a conservative analysis could be
made by assuming sheer strength parameters for saturated soil. This, coupled
with a reasonable assumption of piezometric heads within the slope, would
give a conservative indication of the factor of safety against failure of
the slope. Such an analysis, based on sheer strength and other data as
shown in Drg. RBM-FR-89-2, gives a safety of about 1, indicating that the
slope was of doubtful stability.
Dr. Toh, though questioned the high water table grafted in KTA's
report is basically in agreement with the theory of the movement of soil.
The main difference between his own and that of KTA's is that he attributes
the failure of the slope not so much on the high water table but more on the
toe failure of the slope near to the river which substantially supported the
original slope.
Now lets examine what the 4th defendant said and did. According to him,
"dealing with soil is like taking our daily meal". Firstly, he had a visual
inspection. From this he said, "one will be able to determine whether there
is a need to machine bore to obtain the subsoil. When boring is necessary,
the extracted soil will be sent to the laboratory for test". For Lot 3007
however, no subsoil was extracted for laboratory examination. Instead, the
4th defendant just had a visual examination of the slope and came to a
conclusion that the slope, being a cut slope as compared with a filled
slope, extraction by machine bore to obtain the subsoil was not necessary.
He also observed that the slope was well done with a safe gradient. Though
he did notice the river at the bottom of Lot 3007, he felt that it was a
distance away from where the house was to be erected. He also added that, "I
did not worry about the river because there was drainage contribution by the
original developer under usual state authority requirement and this is for
the maintenance of the river by channeling it. I took it for granted that
the government will channel it".
In respect of the soil, he took some samples from the exposed layer on
the land in his hand, examined it visually, and concluded it to be a silty
sand soil. To him this soil "has good drainage properties; it drains very
fast".
As regards to the house, piling was recommended and carried out just
before the slope so that the structure of the house would "not place too
much weight on the slope".
All these evidence of the 4th defendant, considered in the light of
the expert opinions of KTA's report and that of Dr. Toh's reveal fundamental
weaknesses. Firstly, as admitted by this defendant himself under
cross-examination, "I cannot ascertain the soil by simply looking at it". By
just looking and feeling the soil he agrees that the sheer strength of the
soil cannot be determined. Yet it is an accepted fact by the two expert
engineers and to a large extent by the 4th defendant himself, that the
determination of this sheer strength of the soil was one of the vital
factors in deciding slope stability. Exhaustive tests were conducted by
both Dr. Ramli and Dr. Toh in the laboratory on the nature and strength of
the grain found on Lot 3007, but with this professional, the 4th defendant,
his judgment depended on only visual and feel. Further, though silty sand
soil has good drainage properties but as the 4th defendant also admits,
"water also enter (into such soil) very fast, and water do not drain out
immediately. There would be a period when the water will be held in the
soil". If this is his theory then suction in the soil will be saturated,
effecting its stress effectiveness to be reduced to a point where the total
sheer strength resistence would fail resulting in a landslide.
So
essential is the need for an engineer to determine the soil condition to a
high degree of certainty, particularly on a gradient such as Lot 3007, that
a failure to do so must be accepted as a breach of implied term of his
appointment to take reasonable care.
The level of the existence of the water table on the said land before
the landslide is a hotly debated issue between Dr. Ramli and Dr. Toh. Both
their assumptions on where this water table was, is based on facts after the
slope had failed. Nevertheless, despite this differences of opinion, both
agree that it plays an important part in the determination of slope
stability. If the water table is high, then the slope is more vulnerable.
This is only elementary and yet, according to the 4th defendant, a qualified
engineer he felt that, "at the time I (he) looked at the site and drew my
plans, I (he) did not make an assumption of where the water table was". This
certainly is a clear breach of professional duties.
The presence of the river cannot be ignored. Though it may provide scenic
beauty to the owner of the land above but its potential of threat to the
land was, but apparent. This, the Court had the opportunity of observing
this during a visit to the site. The 4th defendant had also made similar
observation and conclusion where, besides what he uttered earlier adds, "I
cannot say the river pose absolutely no danger but I assumed that the
general development would have taken into consideration the river". This
assumption together with his belief that since the owner pays drainage
contribution, the government will channel the river are mere presumptions,
taken for granted by him, and not substantiated or investigated as a
professional in this field would have done. As a qualified engineer on civil
and structural matters, with a slope as steep as that found in Lot 3007
coupled with a river of swift flowing water, the 4th defendant should have
taken serious and indepth consideration of its presence when recommending,
planning and finally building a house above. Presumptions have no place in
this trade particularly when structures to be erected thereon must be able
to withstand and accommodate natural and existing forces. Though financial
costs can overcome any slope instability in a situation such as this, but at
the very least the same should be made known to the owner. In this case this
was not even presented.
Faced with a sharp gradient as that in Lot 3007, and a river at its
bottom little care and attention seemed to have been concentrated on the
slope which practically engulfed two thirds of land in Lot 3007. In the
opinion of this Court, an engineer of such qualification and skill as the
4th defendant should have taken these matters into more serious
consideration to design and devise plans that would have made the house
erected thereon safe for habitation. Instead, a casual attitude was adopted
without much care and skill practiced. Such work is indeed a far cry from
that expected of a professional in a similar field. As KTA's report
prepared also by a firm of consulting engineers has remarked at p. 10, "it
is evident that no systematic attempt to assess the stability of the slope
based on established engineering techniques" were adopted. Again this seems
to be the view of Dr. Toh, a qualified engineer by his first degree and the
1st and/or 4th defendants own witness when he opinioned that "The engineers
should have taken a duty on all these factors, ie, water table level plus
wetting area before building a house on such a terrain". Under these
circumstances, this Court hereby finds the 1st and/or 4th defendants liable
to the plaintiffs for breach of contract. (emphasis added)
[27] Perusing the two reports, it is clear to us that the learned
trial judge had come to the right conclusion. We are of the view that the
learned judge took great pains to study the two reports. The learned judge
found the views expressed by Dr. Ramli and Dr. Toh to be almost similar
except for the collapse. In his evidence, Dr. Ramli stated that the cause
was due to water saturation on Lot 3007 while Dr. Toh stated the cause was
due to the slope near the river. The reason given by the learned judge in
preferring the view of Dr. Ramli was the fact that Dr. Ramli carried out the
investigation soon after the collapse when the instability of the ground
could still be seen. Dr. Toh, on the other hand, carried out his
investigation six years after the collapse which, in our view, the ground
had stabilised and the water saturation on Lot 3008 caused by the trench
might not be there anymore and whatever water on Lot 3007 could by then have
been drained out. In our view, the learned judge is justified in taking up
that view.
[28] In the passage we cited above (in particular the last
paragraph), the learned judge found the 4th defendant was liable on the
ground that the 4th defendant, as an engineer, should have taken more
serious considerations of the ground and its vicinity in designing and
devising plans that would make a house erected on Lot 3007 safe for
habitation. In this the evidence of both Dr. Ramli and Dr. Toh complement
each other in that the 4th defendant failed to do a thorough test of the
soil and ground on Lot 3007. The 4th defendant only did visionary and
feeling tests which the learned judge found not acceptable.
[29] The 4th defendant contended that the trial judge was in error
when he accepted the evidence of Dr Ramli and rejected the evidence of Dr.
Toh. After reading the judgment of the learned judge, we find that this is
not true. The learned judge did consider the evidence of both but at the end
preferred the evidence of Dr. Ramli on the ground that the investigation
carried out by Dr. Ramli was closer to the time when the incident took
place. Further, the evidence of Dr. Ramli was supported by the 4th defendant
himself when he admitted that he did not do a thorough testing of the soil
where the bungalow was built. This is negligence on the part of the 4th
defendant. There is no fault on the part of the learned trial judge.
[30] The learned judge also found that the 3rd defendant was also
partly to be blamed when he constructed a trench near the boundary of Lot
3007. The trench retained and collected water. The water collected saturated
the ground mostly on Lot 3007. This was a contributory factor to the
collapse. For that the learned judge found the 3rd defendant to be 40%
liable. The 4th defendant was apportioned 60% liability on his failure to
exercise his skill and duty as an engineer and consultant in constructing
the bungalow.
[31] The 4th defendant's only other ground of appeal is found in
para. 4 of the memorandum of appeal where it is stated that the learned
judge had erred in giving judgment on "pure economic loss" based on tortious
liability. In his judgment the learned judge stated as follows:-
This Court shall now move on to consider the plaintiffs' claim for
negligence. Basically they allege that the 1st and/or 4th defendants have
breached a duty of care in failing to take into serious consideration the
stability of the slope on which the house was built. Against this, Mr.
Ngeow, counsel for both these defendants immediately maintains that this
claim is for pure economic loss, the collapsed house being the defective
product. With this defence, this Court is forced to move into an arena of
fierce legal embattlement now being raged throughout the entire Common Law
practicing nations, and to take a legal stand.
To understand this "loaded" term of pure economic loss or economic loss
one has to move backwards in time, to the creation of the principles of
negligence in the case of Donoghue v. Stevenson [1932] AC 562.
There Lord Atkin expounded the principle of where there is a duty to
exercise care, reasonable care must be taken to avoid acts or omissions
which can reasonably foreseen to be likely to cause physical injury to
person or damage to his property other than the damaged property itself.
By this proposition, a person without contractual relationship can claim
from another damages for injury suffered by him or damage to his property,
other than the defective product itself. Any claim to this defective
product either in the manner of making good or replacement thereto, is a
claim for pure economic loss. This can be better explained in the context
of the facts in Donoghue v. Stevenson itself. There the consumer of
a bottle of ginger beer which contained the dead snail was successful in
her claim against the manufacturer of negligence for injuries to her
health and damage to her property (if any) other than the contaminated
bottle of ginger beer, it being the defective product.
This principle has been applied to different but analogous factual
situation for a substantial period of time since first established, but
often the last condition of this proposition was not seriously considered in
respect of defective houses until the case of Dutton v. Bognor Regis
Urban Council [1972] 1 QB 373. In this case the plaintiff was the second
purchaser of a house and soon after she moved in found serious defects in
the internal structure of the building. Investigation revealed that this was
caused by inadequate foundation due to the fact that it was constructed on
the site of a rubbish tip. She sued the local council whose building
inspector was negligent in failing to detect the defect at an early stage of
the building works. The only issue before the Court of Appeal in consequent
to an award of damages to the plaintiff by the Court of first instance for
the estimated cost of repairs of the house and the surveyor fees was,
whether the council was liable to the plaintiff for pure economic loss. Pure
economic loss being the claim on the defective product ie, the defective
house itself. The Court of Appeal dismissed the appeal and found in favour
of the plaintiff. By this, it means a departure from the principle that
defective product itself cannot be claimed. This gives rise to a case of
recovery of economic loss which was not consequent on any injury to person
or damage to property.
Dutton's case was approved by the House of Lords in Anns and
Ors v. London Borough Council of Merton [1978] AC 728. Here again the
plaintiff who took a long lease in a block of flats found cracks in the
wall. The cause was due to inadequate foundation. The builder was sued and
so was the local council. The latter for allowing the builder to construct
the building on inadequate foundation or in failing to carry out necessary
inspection or approving the foundation. The House of Lords held that the
council owed a Common Law duty of care to the plaintiffs. This again is a
claim based on the defective product itself and thus pure economic loss can
be recovered.
Though the above two authorities involve the liability of the local
council, the House of Lords in Junior Books Ltd v. Veither Co. Ltd
[1983] 1 AC 520 dealt directly with the builder's liability to the owner of
the building with whom he had no contractual relationship with. They too
were found liable for negligence on a claim for economic loss.
In 1989, this legal proposition in motherland of Common Law took a
drastic change, and retreated from the broad view they took earlier. In the
case of D & F Estates Ltd & Ors v. Church Commissioners for England & Ors
[1989] AC 177, the House of Lords dismissed the Court of Appeal decision
basically on the following grounds:
(1) any duty owed by a contractor to a home owner with respect of
quality of the construction must arise in contract and not tort;
(2) that to allow the recoverability for the cost of repairing defects
in the building would have the effect of creating a non-contractual
warranty of fitness;
(3) the contractor can only be held liable in tort to subsequent
purchaser on negligence which caused physical injury or damaged to other
property other than the damaged property.
Once again the facts in this case are virtually similar to the cases
referred to earlier. The defendants were main contractors hired by the owner
to build a block of flats. A sub-contractor was engaged by the main
contractor to carry out plastering work which they performed negligently.
The plaintiff, a leasee to a flat in this block discovered that the plaster
on the ceiling and wall were loose. He repaired it and sued the original
contractor for the cost of repairs and estimated cost of future remedial
works.
The decision of D & F Estates Ltd was fortified by the latest case
of Murphy v. Brentwood District Council [1990] 2 All ER 908, in which
the House of Lords expressly departed from Anns. Here the defendant's
council approved the design on the foundation of a house which was found by
a subsequent purchaser to be defective. The highest court of appeal in the
United Kingdom ruled that the defendant's counsel owed no duty of care to
the plaintiff in respect of the damage of the kind sustained. The reasons,
as Lord Keith put:-
To start with, if such a duty (of care) is incumbent on the local
authority a similar duty must necessarily be incumbent also on the builder
of the house. If the builder is so subject there can be no grounds in logic
or in principle for not extending liability on like grounds to the
manufacturer of the chattel. That would open on an exceedingly wide field of
claims, involving the introduction or something in the nature of a
transmissible warranty of quality. The purchaser of the article who
discovered that it suffered from a dangerous defect before that defect had
caused any damage would be entitled to recover from the manufacturer the
cost of rectifying the defect, and, presumably, if the article was not
capable of economic repair, the amount of loss sustained through discarding
it. Then it would be opened to question whether there should be a right to
recovery where the defect renders the article not dangerous but merely
useless. The economic loss in either case would be the same. There would
also be a problem where the defect causes the destruction of the article
itself, without causing any personal injury or damage to other property. A
similar problem could arise, if the Anns principle is to be treated as
confined to real property, where the building collapse when unoccupied.
In another part of his judgment Lord Keith proceeded with:-
so far as policy consideration is concerned it is no doubt the case
that extending the scope of the tort of negligence may tend to inhibit
carelessness and improve standard of manufacturer and construction on the
other hand, overkill may present its own disadvantages.
Unfortunately these sentiments do not seem to be shared by the
Commonwealth counter-parts. Starting with New Zealand, the case of
Invercargill City Council v. Hamlin [1996] 1 All ER 756 refused to
follow Murphy. Ironically this is an appeal heard before the Privy Council
which affirmed the decision of the New Zealand Court of Appeal for upholding
the trial judge's finding that the City Council were liable for negligence
to the plaintiff based on the following facts. The plaintiff contracted a
builder who sold him the land to construct a house thereon. In the course of
construction a building inspector from the City Council inspected and
approved the work as in accordance with the Council's by-laws. Years later
cracks appeared in the house leading to this plaintiff's claim against the
City Council. The reasons forwarded by the Privy Council for not adopting
D & F Estates Ltd & Murphy appear to be:-
(a) New Zealand Court of Appeal is entitled to develop the Common Law
of New Zealand according to local policy consideration in areas of Common
Law which are developing;
(b) And the perception in New Zealand is that the community standards
and expectation demanded the imposition of a duty of care on local
authorities and builders alike to ensure compliance of by-laws, and the
Court of Appeal of New Zealand has built up a long line of authority based
on link concept of control by the local authority of building works
through the enforcement of its by-laws, and reliance on that control by
the purchaser.
Next comes Canada in Winnipeg Condominium Corp No. 36 v. Bird
Construction Co. Ltd & Ors [1995] 121 DLR (4th edn.) 193. Here a
developer entered into a contract with a general contractor called Bird
Construction Ltd (Bird) to construct an apartment block. Works were carried
out according to plans drawn by the architects - Smith Carter. As for the
external cladding, it consisted of slabs of stones which were installed by a
sub-contractor. The plaintiff becoming the subsequent owner of the apartment
had to repair a section of the cladding which fell. He claimed from Bird,
Smith Carter and the sub-contractor cost of repairs due to their negligence.
Bird applied to strike the plaintiff's claim disclosing no reasonable cause
of action. The Court of first instance disallowed this application which was
upheld by the Canadian Supreme Court. La Forest J delivering the judgment of
the Supreme Court is of the following views:-
The underlying rationale for this conclusion is that the person who
participates in the construction of a large house and permanent structure
which, if negligently constructed, has the capacity to cause serious damage
to other persons and property in the community, should be held to a
reasonable standard of care.
He then continues:-
This is important because, in my view, the unfortunate result of the
reasoning in D & F Estates is that it leaves its subsequent
purchaser with no remedy against the contractor who construct the building
with substandard materials and substandard workmanship and thereby puts
subsequent purchasers at considerable risk.
In Australia, initially in the case of Sutherland Shire Council v.
Heyman & Anor (1984-1985) 157 CLR 424 found that the Council was not
guilty of negligence for approving plans which subsequently showed
inadequate footings. However in their latest landmark decision in Bryan
v. Maloney [1995] 128 ALR 163, the High Court of Australia by a
majority supported the trial judge's ruling that the Council was liable
for negligence to a subsequent owner of the property who was put to loss
by the defective house. In their judgment, the High Court of Australia has
this to say:-
The relationship between them (the subsequent purchaser and the
builder) is marked by proximity in a number of important respects. The
connecting link of the house is itself a substantial one. It is a
permanent structure to be used indefinitely and, in this country, is
likely to represent one of the most significant, and possibly the most
significant, investment which the subsequent owner will make during his or
her lifetime. It is obviously foreseeable by such a builder that the
negligent construction of the house with inadequate footings is likely to
cause economic loss, of the kind substantiated by Mrs. Maloney, to the
owner of the house at the time when inadequacy of the footing first become
manifest.
Closer home in Singapore, this similar type of issue appeared in the
case of RSD Architects Planners & Engineers v. Ocean Front Pte Ltd
[1996] 1 SLR 113. LP Thean, Judge of the Court of Appeal practically
combed the entire Common Law countries for enlightenment as to whether the
plaintiff, a management corporation of a condominium can sue the
developers and the architects for pure economic loss arising out of faulty
construction of the common property in the building. Ultimately, the Court
of Appeal of Singapore elected not to follow Murphy and D & F
Estates and found that the builders and architects can be liable for
negligence.
At home two High Court decisions are made on this subject. The first is
the case of Kerajaan Malaysia v. Cheah Foong Chiew & Anor [1993] 2
MLJ 439. Justice Wan Mohamed presided as follows:-
Kerugian yang dialami oleh plaintif adalah kerugian atau kehilangan
ekonomi tulen (pure economic losses), dan defendan ketiga tidak boleh
dikenakan tanggungan (liability) di bawah tort di atas kerugian yang
dialami oleh plaintif dalam kes ini oleh kerana tiada siapapun yang cedera
atau tidak harta kepunyaan orang lain rosak akibat daripada perbuatan atau
salahlaku oleh defendan ketiga. Keputusan yang dibuat oleh Dewan Pertuanan
(House of Lords) dalam kes Murphy v. Brentwood DC dan lain-lain kes
lagi yang membuat keputusan yang sama, adalah sangat munasabah, berpatutan
dan sepatutnya diterima sehingga bila-bila masa pun.
Justice Peh Swee Chin FCJ sitting as a High Court judge in a more recent
case of Teh Khem
On & Anor v. Yeoh & Wu Development Sdn Bhd & 3 Ors [1996] 2 CLJ 1105;
[1995] 2 AMR 1558 had the opportunity to confront this issue. He adopted the
decisions in Murphy and D & F Estates. Though not directly
stating the reason for his preference, this Court is of the view that it was
founded in the fear of extending the scope of liability "for an
indeterminate amount for an indeterminate time to an indeterminate class".
It is rather unfortunate that we are deprived of Justice Peh's further
elaboration and indepth reasonings for which he is highly acclaimed,
particularly when "there are many cases which are not mentioned in the
judgment and which allowed for recovery of pure economic loss in an action
for tort", but he felt that "this is neither the place nor the time to
discuss all of them".
In Teh Khem On the purchasers purchased a house from the
vendor/builder. After taking possession they found cracks on the wall, the
ground was uneven and the upstairs bathroom was leaking. This was repaired
by the vendor/builder but subsequent defects appeared. This lead to a series
of claims and counter-claims between the purchasers, the vendor/builder and
the architects and engineers who were involved in the design and drawing of
the said house. The architects and engineers contended that the purchasers'
claim being for pure economic loss is not recoverable in negligence. To this
Justice Peh agreed when he said:-
The decision of D & F Estates in the House of Lords, in so far
as it concerns the non-recoverability of such pure economic loss as
described above by an owner of the house against the builder in tort ie,
by way of negligence: was confirmed twice by the House of Lords in
Murphy v. Brentwood District Council, supra and Department of
Environment v. Thomas Bates & Sons Ltd [1990] 1 All ER 943.
In the light of the substantial persuasive authorities on this
conflicting claims and without any determination from our appellate courts,
this Court is impelled upon to decide whether to allow a claim for pure
economic loss or to reject the same. For this, it is essential to unearth
from the cited authorities the rational the courts expounded in arriving at
their decisions.
For those against allowing the claim for pure economic loss, it is
primarily to avoid the creation of liability "for an indeterminate amount
for an indeterminate time to an indeterminate class", to quote Cardozo CJ in
the American case of Utramares v. Trouche [1931] 255 NY 170,
otherwise it would "open an exceedingly wide field of claims" or creating
"endless indeterminate liability" or "the overkill may present its own
disadvantage." On the opposing camp in favour one has, "community's
expectation and demand" of third parties to exercise due care and compliance
with relevant by-laws, or the deprivation of relief would not justify the
economic loss suffered on the defective product, or the moral duty of third
party to exercise care.
Of all the reasons against allowing pure economic loss, the fundamental
rational is still to prevent the creation or extension of liability to "an
indeterminate amount for an indeterminate time to an indeterminate class."
But these could be a misconception and unallied fear. Interpreting through
the circumstances of all the cases cited, the amount of damages so claimed
is not an indeterminate amount. They are the expenses and costs involved in
repairing, making good or replacing the defective product, or cost that may
be involved in ensuring the defective product is of the condition that it
should be in the first place. As for indeterminate time, it may be true that
liability to a subsequent owner might be greater than the first owner but as
the High Court in Australia in Bryan v. Maloney (supra) states, it
can "limited by the element of reasonableness both in the requirement that
the damage be foreseeable and in the content of the duty of care." In
respect of indeterminate class, this Court feels that it is best put in the
High Court Justices Bryan v. Maloney as follows:-
The similarities between the relationship between the builder and the
first owner and the relationship between builder and subsequent owner as
regards the particular kind of economic loss are of much greater
significancy than the differences to which attention has been drawn,
namely the absence of direct contact or dealing and the possibly extended
time in which liability might arise. Both relationships are characterised,
to a comparable extent by the assumption of responsibility on the part of
the builder and likely reliance on the part of the owner. No distinction
can be drawn between the two relationship in so far as the foreseeability
of a particular kind of economic loss is concerned: it is obviously
foreseeable that loss will be sustained by whichever of the first or
subsequent owners happens to be the owner at the time when the inadequacy
of the footing becomes manifest.
With these arguments forwarded, one wonders why there is such
limitation imposed upon a claim for pure economic loss, for after all the
entire concept of negligence is to extend liability beyond the borders of
privity. To impose such a restriction is highly inequitable particularly
in cases where the duty of care and the breach of such duty are found to
be substantiated. There should be no fear that carelessness will be
inhibited and the standard of manufacturing and construction section will
be improved by the abolition of this so call limitation to a claim for
pure economic loss, for after all, it is not this value that society from
one generation to the next strive to achieve. To adhere to old principle
and leaving it to Parliament to resolve the issue is by no means a
solution, since the principle of negligence itself is founded on Common
Law, and it is Common Law of the United Kingdom that has a change of
heart. Possibly this could be a policy decision in that country as can be
reflected in Lord Keith's judgment in Murphy when he said;
Anns has the effect of imposing on the builders generally a liability
going far beyond that which Parliament thought fit to impose on house
builders alone by the Defective Premises Act 1972, a statute very material
to the policy of the decision but adverted to in it.
In Malaysia we do not possess this piece of legislation. To adopt the
decisions of Murphy and D & F Estates which are based on a
foreign policy of no application here would leave the entire group of
subsequent purchasers in this country without relief against errant
builders, architects, engineers and related personnel who are found to have
erred. If there is any fear that this approach may encumbered upon the local
authorities to pay out substantial claims due to their negligence in
granting approvals or inspecting building works, there is section 95 of the
Street Drainage and Building Act which prohibits such authorities to be
sued.
This legal principle for accepting a claim for economic loss is obviously
not only confined to defective buildings and structures. It has far greater
impact on all situations by analogy and if limited by the limitations
imposed as in Murphy and D & F Estates it would be grossly
inequitable with justice not being served. For these reasons it is the
opinion of this Court that a claim for pure economic loss can be entertained
in a claim in negligence.
Now that this Court has found a claim for pure economic loss can be
entertained, we shall return to the circumstances of our case. The legal
principles to be applied in this claim of negligence against the 1st and/or
4th defendants must certainly be that of Bolam v. Friern Hospital
Management Committee (supra) since this is a claim based on professional
negligence. As this principle is similar to that as found under the cause of
action for breach of contract which has been elaborated earlier, and since
the facts are also identical there is no necessity for this Court to
re-examine on them. Based on similar grounds as those stated earlier under
the cause of action for breach of contract this Court hereby finds the 1st
and/or 4th defendants liable to the plaintiffs for negligence.
[32] The learned trial judge chose to depart from the High Court
decisions which were cited earlier. He was of the opinion that the decisions
of Murphy and D & F Estates which were followed by the two
High Court decisions were outdated in view of the decisions of the courts
within the Commonwealth except England where the decisions of Murphy
and D & F Estates are still binding.
[33] The learned counsel for the 4th defendant submitted that the
learned judge was in error when he did not follow the decisions in
Kerajaan Malaysia v. Cheah Fong Chiew & Anor [1993] 2 MLJ 439 and Teh Khim On &
Anor v. Yeoh & Wu Development Sdn Bhd & 3 Ors [1996] 2 CLJ 1105;
[1995] 2 AMR 1558, the decisions of emminent judges of this country. It is
obvious that the decisions in those cases followed the House of Lords'
decision in Murphy v. Brentwood District Council [1990] 2 All ER 908.
In the present appeal, the learned trial judge was fully aware of the
decisions in the two Malaysian cases. This can be seen from his judgment
where he had referred to the two cases. As can be seen the judgments were
the judgments of two High Court Judges. The learned trial judge in the
present appeal was also a High Court Judge (as he then was) and as such he
was not bound by the decisions of those two cases. As such, we find no merit
in the submission of the 4th defendant's counsel that the learned judge did
not follow the other two decisions of the Malaysian High Courts.
[34] In our view, the learned judge was within his right to award
damages on pure economic loss. We have been too long in the shadow of the
House of Lords' decisions of Murphy and D & F Estates. We are
of the view that it is time for us to move out of that shadow and move along
with other Commonwealth countries where damages could be awarded on pure
economic loss. In the media we have seen how consumers suffer due to shoddy
and haphazard manner the developers and contractors in putting up buildings
with so many defects and in most cases, delay. The legislature and the
government are fully aware of this and for those reasons a special tribunal
has been set up to cater for complaints in respect of houses. As such the
courts should also play their part in this.
[35] Anyway, in the present appeal, we are of the view that the
losses by the plaintiffs were not pure economic losses. The evidence shows
that the damages suffered by the plaintiffs were the loss of the bungalow
which collapsed a few years after it was built on that site where the 1st
defendant failed to conduct thorough tests on the site, whether it was safe
to build a building as designed by the 1st defendant on that site. It was
the duty of the 1st defendant as consultant employed by the plaintiffs to
ensure that it was safe to build the building on that site. The evidence
shows that the 1st defendant failed to carry a thorough test of the soil
when they recommended the building to be built on the said land to the
plaintiffs. For the said reasons, we are of the view that the learned judge
came to the correct conclusion that the 1st defendant was also negligent and
liable.
[36] For the above reasons, we find that there is no merit in the
appeal and the appeal is hereby dismissed with costs. The order of the
learned judge is hereby affirmed. The deposit is to be paid to the account
of taxed costs.
[37] My learned brother, Abdul Kadir bin Sulaiman, JCA has seen
this judgment in the draft and has expressed his agreement. |