HIGH COURT OF MALAYA
LIM EH FAH & ORS
- vs -
Seri Maju Padu
Coram
SURIYADI HALIM OMAR
[CIVIL APPEAL NO: MT(3) 11-3-1999]
12 JULY 2002
LAND LAW: Housing developers - Damages for late delivery -
Agreement to deliver vacant possession within 24 months - Date of
vacant possession - Whether time to commence from date of acceptance
of deposit - Whether contract deemed to have existed on receipt of
deposit
Judgment
Suriyadi Halim Omar, J
-
Three appeals were filed by the purchasers
("the appellants") of immoveable properties called the Desa Maju Padu
Condominium, Kota Bharu, Kelantan from the developer-defendant. The
appeals came about as the learned Magistrate had dismissed the
purchasers' summary judgment applications filed pursuant to Order 26A of
the Subordinate Court Rules 1980. The appellants had claimed damages
against the respondent defendant for late delivery of the immovable
properties.
-
The factual matrix further revealed that the
appellants had much earlier filed three separate actions, later to be
consolidated. For easy appreciation of this consolidated matter, I will
concentrate on the appeal of the first appellant, the outcome of which
will bind the other two cases.
-
To reiterate, the first appellant had bought
one unit of the condominium at a cost price of RM75,300. Pursuant to
that transaction he had deposited RM7,530, being 10% of the purchase
price, with the respondent on July 17, 1992. About three months later
i.e. on October 10, 1992 the first appellant executed a sale and
purchase agreement ("the S&P agreement"), with the respondent pertaining
to that impugned unit.
-
It was agreed upon by the respondent that
vacant possession would be handed to the first appellant within
twenty-four months from the date of the S&P agreement. In the
event of any delay in the delivery of the relevant unit to the
appellant, the respondent was to pay damages to the tune of 10% per year
of the value of the unit. By virtue of a loan agreement and a deed of
assignment, signed on June 12, 1993 the first appellant had assigned his
rights and interest over the impugned property to the fifth appellant
(the bank).
-
In response to the statement of claim, the
respondent in its defence had alleged that countdown in the handing over
of the property, should begin on or before June 12, 1993 and not any
other dates. That being so, the respondent had asserted that it had
fulfilled its part of the bargain within the stipulated time, except for
the fixing of the septic tank and the piping system, which were outside
its control.
-
The first appellant in retort had alleged
that the respondent was contracted to hand over vacant possession on or
before July 17, 1994, but as delivery of vacant possession took place
only on December 1, 1996 a delay of 868 days, he was thus entitled to
damages to the tune of RM17,906.96.
-
The legal poser before me, for purposes of
determining the date of vacant possession in a claim for liquidated
damages, was whether it was the day the deposit was accepted, the day
the S&P agreement was executed or when the deed of assignment was
signed.
-
Counsel for the first appellant ventilated
that the relevant date had to be the date the deposit was paid to the
respondent, which was July 17, 1992 with vacant possession to take place
on or before July 17, 1994 (24 months). The respondent submitted June
12, 1993 i.e. the deed of assignment date, on the premise that the S&P
agreement had to be read with the former. It was further submitted that
the first appellant could not have made payments in accordance with the
schedule, as he had yet to obtain the financial support to finance his
purchase. That being so the appellant could only comply with the
conditions of payments only after he had managed to obtain a loan from
the fifth appellant, the bank. On those grounds, the respondent
contended that June 12, 1993 must invariably take center stage.
-
To really appreciate the issue at hand, it
is quite imperative that I lay down certain portions of the S&P
agreement, in particular those found at pp 40-87.
(i) |
Clause 7
Time shall be the essence of the
contract in relation to all provisions of this agreement. |
(ii) |
Clause 22(1)
The said parcel should be completed by
the developers and vacant possession with the connection of water
and electricity supply to the said parcel shall be handed over to
the purchaser within twenty four (24) calendar months from the
date of this agreement. |
(iii) |
Clause 22(2)
If the developer failed to hand over
vacant possession of the said parcel together with connection of
water and electricity supply to the said parcel in time the
developer shall pay immediately to the purchaser liquidated
damages to be calculated from day to day at the rate of ten per
centum (10%) per annum of the purchase price. |
(iv) |
Clause 23(2)
Upon the expiry of fourteen (14) days
from the date of a notice from the developers requesting the
purchaser to take possession of the said parcel, whether or not
the purchaser has actually entered into possession or occupation
of the said parcel, the purchaser shall be deemed to have taken
delivery of vacant possession. |
-
Having heard the submissions of the
appellant and the respondent, and having intensely scrutinized the
record of appeal, I was satisfied that no triable issue existed which
warranted a full hearing. Based on that view I allowed the appeal and
accordingly allowed the summary application under Order 26A of the
Subordinate Court Rules 1980. I now supply my reasons.
-
As regards the date to take into
consideration for purposes of calculating the damages on the late
delivery of vacant possession, I concluded it to be July 17, 1992 i.e.
the date when the deposit was paid, and not the date of the deed of
assignment. To support my finding, I seek solace from the case of
Faber Union Sdn Bhd v Chew Nyat Shong [1995] 3 AMR 2094 which
factually was on all fours with the current case. There a purchaser had
bought a unit of property from the developer (appellant). A deposit
was paid on February 17, 1984 with the agreement being signed on June
27, 1984. The developer failed to deliver the impugned property within
the agreed thirty-six months, whereupon the buyer claimed liquidated
damages. Following an earlier case of Hoo See Sen v Public Bank Bhd
[1988] 2 MLJ 170, the Supreme Court had decided that the relevant date
for ascertaining when time started to run, to be when the booking fee
was paid. Under held it is clearly authored:
For the purpose of ascertaining the
date of delivery of vacant possession, the relevant date when time
started lo run was the date on which the purchaser paid the
booking fee, and not the date of signing of the sale and purchase
agreement. |
-
Despite the submission that the appellant
could only commence paying pursuant to Clause 4(1) of the S&P agreement,
only after having received financial backing from the fifth appellant
(the bank) and a deed of assignment having been executed, hence the
assertion that time began to run on June 12, 1993, I found that argument
unacceptable. Apart from the above case of Faber Union Sdn Bhd
being crystal clear, in the event of the appellant failing to adhere to
the schedule of payment, there was nothing to stop the respondent from
imposing interest on the late payments. This right is sufficiently
provided for under Clause 8 of the S&P agreement. Any failure on the
part of the appellant, if any, to comply with Clause 4, did not
extinguish the responsibility of the respondent to fulfill the contract
within the stipulated time.
-
One must bear in mind that the date of July
17, 1992 i.e. the deposit payment date, was the date when the contract
was struck, and the very date the respondent assumed responsibility to
fulfill its part of the bargain. If the date of the signing of the S&P
agreement were to be taken as the relevant date, when time started to
run for the delivery of the vacant possession, the respondent could
willy-nilly pick any dates it favoured to execute the S&P agreement,
which would certainly prejudice the interest of the purchaser.
-
Under the Housing Developers (Control And
Licensing) Act 1966 (Act 118) & Regulations 1989 & 1991, s 11(2) reads:
No housing developer shall collect any
payment by whatever name called except as prescribed by the
contract of sale. |
-
In relation to this case, the above
provision explicitly means that the respondent was permitted to accept
deposits so long as it was provided for under the S&P agreement. A
reading of the receipt, found at p 39 of the record of appeal,
highlighted that the payment was a "deposit on apartment No. 6, Floor 2,
Kampong Cina, Kota Bharu, Kelantan". What is the purpose of a deposit if
not to indicate offer and acceptance, each with its respective
responsibilities that must be fulfilled in accordance with the
provisions of the S&P agreement. The main obligation of the appellant
was to pay in full the purchase price of the impugned property (Clause
4), failing which interest may be imposed on any late payments. At the
other end of the agreement, it was the duty of the respondent to build,
deliver and to hand over vacant possession within the agreed period to
the appellant, failing which liquidated damages at the rate of 10% per
annum of the costs of the property must be paid to the appellant.
-
Based on the above reasons I concluded that
the respondent had failed to live up to its bargain to deliver vacant
possession within 24 months, as indicated in the notice of November
17,1996 (pp 132 and 133 of the record of appeal). Evidentially, pursuant
to Clause 23(2) of the S&P agreement, the date of handing over was
supposed to be December 1, 1996 a delay of 868 days (from July 17, 1994
until December 1, 1996). As I had concluded that there was no merit to
the defence of the respondent, I thereupon allowed the appeal with
costs, and accordingly granted the summary judgment application.
Cases
Faber Union Sdn Bhd v Chew Nyat Shong [1995] 3
AMR 2094; Hoo See Sen v Public Bank Bhd [1988] 2 MLJ 170
Legislations
Housing Developers (Control And Licensing) Act
1966 (Act 118) & Regulations 1989 & 1991: s.11(2)
Subordinate Court Rules 1980: Ord.26A
Representation
MS Ong (Raja Eleena Siew Ang & Associate) for
Plaintiff
Jegathesan (C Jegathesan) for Respondent
Notes:-
This decision is also reported at [2002] 4 AMR
4491
|