LEW YOKE LENG & ORS V. SYKT KAR KING SDN
BHD
HIGH COURT MALAYA, IPOH
JAMES FOONG J
[CIVIL APPEAL NO: 11-72-1999]
7 AUGUST 2000
CONTRACT:
Building contract - Delivery of vacant possession - Water and
electricity, whether must be connected to house - Whether connection of
electricity to substation sufficient - Electricity not connected to house
within contractual period - Whether developer liable to pay liquidated
damages - Certificate of fitness of occupation not obtained within
contractual period - Whether a valid excuse for not connecting electricity
to house
[Appeal allowed.]
JUDGMENT
James Foong J:
Introduction
This is an appeal by the plaintiffs who are dissatisfied with the
decision of the learned magistrate who dismissed their claim for a
liquidated sum of RM5,832.90 being late delivery of a house they purchased
from the defendant, with interest and cost.
Plaintiffs' Claim
By a sale and purchase agreement dated 2 March 1993 (S & P Agreement) the
plaintiffs purchased from the defendant, a developer, a double-storey
terrace house (the house) to be erected by the defendant.
Clause 20(2) of the S & P Agreement states as follows:
If the Vendor fails to hand over vacant possession of the said Building,
together with the connection of water and electricity supply to the said
Building, in time, the Vendor shall pay immediately to the Purchaser
liquidated damages to be calculated from day to day at the rate of ten per
centum (10%) per annum of the purchase price.
"In time" as stipulated under cl. 20(1) of the S & P Agreement means:
The said Building shall be completed by the Vendor and vacant
possession, with the connection of water and electricity supply to the said
Building, shall be handed over to the Purchaser within twenty-four (24)
calender months from date of this Agreement.
Since the S & P Agreement was signed on 2 March 1993 twenty-four months
matured on the 1 March 1995.
Vacant possession of the house was handed over to the plaintiffs on 15
December 1994 but without a certificate or occupation (CF). The authority
only issued CF to the house on 5 January 1996. Upon receiving this, the
plaintiffs proceeded, on the advice of the defendant, to request the
electricity supplier (TNB) to connect electricity to the said house. This
required the plaintiffs to sign an agreement with TNB, and only then on 16
January 1996 electriclty was duly supplied to the house.
Due to this delay in connecting electricity to the house the plaintiffs
claim that cl. 20(2) of the S & P Agreement has not been complied by the
defendant. The defendant was late in delivering vacant possession of the
house with electricity connected thereto by 309 days beginning 1 March 1995
(24 months from date of S & P Agreement) till 16 January 1996 (the date when
electricity was connected to the House).
Defendant's Case
The defendant denied having breached any of the terms in the S & P
Agreement. From facts as it stand, the defendant argued as follows: The
house was practically completed since 15 December 1994, well within the
stipulated period of twenty-four months. Electricity supply was connected to
the housing estate, where the house was erected, since November 1994. As CF
was not granted to the house then, electricity could not be connected to the
House as was the rule and practice by the authorities and the power supply
company. Thus it was not the fault of the defendant for not connecting
electricity supply to the house within the stipulated time. In such
circumstances, cl. 20 in respect of "in the connection of water and
electricity supply to the Building" should be interpreted as: connecting to
the main power supply terminal in the area where the house would tap its
supply from when connected after CF was issued to the house.
Issue
Undoubtedly, the issue in this case centers on the interpretation of cl.
20 in the S & P Agreement of whether vacant possession with electricity
supply to the house means electricity connected to the house or sufficient
when power supply only reached the electrical sub-station in the housing
estate where the house is.
Analysis
To the defendant, this dispute is wrapped in a "chicken & eggs
situation". Without the CF issued no electricity could be connected to the
house even when power was available in the electrical cables in the area.
But his approach was not appreciated by Abdul Malik Ishak J. in Hoya
Holdings Sdn Bhd v. Chia Thin Hing Anor [1994] 4 CLJ 992, where he
decisively, in a factual situation similar to the present case, declared
that "with the connection of water and electricity supply to the said
building" in their plain and ordinary meaning is: there must be water and
electricity supplies actually running through the internal pipes, electrical
and power lines in the dwelling house before the question of whether or not
vacant possession has been delivered could even be considered.
Mr Jagjit Singh, counsel for the defendant, attempts to convince me that
the above decision can be faulted on the ground that the learned judge did
not consider the decision in A-G v. County of London Electric Supply Co
Ltd [1926] Ch. 542 where the term "supply" was decided to mean use or
supply for consumption not at the consumer's terminals but at the
sub-supplier terminals. By this, he implies that the defendant cannot be
found liable for breach of the S & P Agreement since the defendant had since
1994 obtained power supply to the sub-station of the housing estate.
I am not impressed with this argument. The above English case is entirely
distinguishable on facts from our present environment. There it involved a
contest between two power supply companies over territorial jurisdiction for
the supply of power which required the interpretation of an English
enactment - the English Electric Lighting Act 1909 - which is never
applicable in this country. In our case we are not concerned with the
interpretation of any legislation. Here the dispute is over the wordings of
a clause in an agreement entered into by the parties, which interpretation
in accordance with established legal principles must be confined to the four
corners of the agreement itself and not from elsewhere.
After perusing the appeal record and the submissions of the parties, I am
of the opinion that there is no ambiguity in the wordings of cl. 20 of the S
& P Agreement. It means what it says: water and electricity must be
connected to the house before it is considered to be completed with vacant
possession for the purpose of calculating time to hand over the property to
the plaintiffs. Simply put: it means when the plaintiffs entered the house
upon delivery of vacant possession and turned on the lights it will be
illuminated when he affixes a bulb to it. I cannot comprehend it to mean
electricity supply only to a sub-station in the housing estate where the
house is erected, be that terminal near or far.
The contention of the defendant having no control over the time frame in
obtaining CF to facilitate electricity supply to the house is no excuse when
it is an obligation agreed upon by the defendant. It is not a chicken & eggs
situation as the defendant's counsel wish this court to believe. The
defendant could have fulfilled its obligation within the period stipulated
by either completing the house earlier to accommodate adequate time for
inspection by the authorities responsible for the issue of CF, and/or
building the house in accordance to plan and complying with all the
requirements set by the authorities to avoid detection of faults so as to
minimise time taken for rectification after the inspection. These are only
some steps this court can think of that would enable the defendant to
complete the house with water and electricity connected thereto within the
meaning as expressed. The professional developer may have even more
solutions to overcome this hitch, but whatever they are this time frame of
24 months to deliver a dwelling house with water and electricity connected
to the house would certainly drive housing developers
to be more efficient and professional. The Tom, Dick & Harry who possess
little knowledge and experience in this trade and hope to learn the ropes at
the expense of the purchaser would find themselves out of pocket if they are
late in complying such clause as cl. 20 in this S & P Agreement.
By my reasons above, I find that the learned magistrate has erred in the
application of legal principles to the facts. For this I allow this appeal
with cost.
|