LEONG LAI KUEN V. SENTUL MURNI SDN BHD
HIGH COURT MALAYA, KUALA LUMPUR
[SUMMONS WRIT NO: 22-1008-2002]
JAMES FOONG J
30 SEPTEMBER 2003
CONTRACT: Sale and purchase
of property - Breach - Non-delivery of vacant possession - Claim for liquidated
damages - Whether claim should be based on formulated sum stipulated in
sale and purchase agreement - Whether claim should be a reasonable sum subject
to s. 75 Contracts Act 1950
LAND LAW: Housing developers - Non-delivery
of vacant possession - Purchaser's entitlement to compensation - Whether
compensation should be based on formulated sum stipulated in sale and purchase
agreement - Whether compensation should be a reasonable sum subject to s.
75 Contracts Act 1950
Coram
JAMES CY FOONG J
|
30 SEPTEMBER 2003
|
Judgment
James CY Foong J
INTRODUCTION
-
The plaintiff purchased a unit of condominium (the said
property) from the defendant, who was the developer. As evidence of this
purchase, a sale and purchase agreement (S&P agreement) was executed between
the parties on February 2, 1994. The purchase price was RM99,800. Towards
this, the plaintiff had paid to the defendant, by way of progress payments,
a sum of RM44,910 which represents 45% of the total consideration. The
stage of work specified as completed on the said property is up to "walls
and partitions including floors and window frames". This is evidenced
from the last progress claim made by the defendant on October 6, 1997.
After this, work was abandoned. Dissatisfied with this state of affairs,
the plaintiff gave notice on October 1, 2001 in writing to the defendant
to recommence construction. The defendant did not comply. Consequently,
the plaintiff by letter dated August 21, 2002 terminated the S&P agreement.
This was soon followed by a writ of summons against the defendant where
the plaintiff claims:
(a)
|
a declaration that the defendant had breached the
terms of the S&P agreement and the plaintiff is entitled to rescind
the same on August 21, 2002;
|
(b)
|
that the defendant do refund to the plaintiff a sum
of RM44,910;
|
(c)
|
interest of 8% per annum on the sum of RM44,910 from
date of filing of writ to date of full settlement;
|
(d)
|
the defendant do pay the plaintiff damages of:
(1)
|
RM55,395.84 in accordance to clause 22(2) of
the S&P agreement;
|
(2)
|
RM11,079.16 in accordance to clause 24(2) of
the S&P agreement,
|
both running from February 23, 1997 till August 21,
2002 or such date as the court thinks fit;
|
(e)
|
interest at 8% per annum on both RM55,395.84 and
RM11,079.16 from date of filing to date of full settlement;
|
(f)
|
costs; and
|
(g)
|
and any other relief as this court thinks fit and
suitable to grant.
|
-
The defendant's defence is a plea of frustration of contract
for the following reasons.
-
On April 27, 1994, the High Court at Kuala Lumpur granted
an order for the squatters on the land where the condominium is built
be evicted. Some of these squatters appealed to the Federal Court and
obtained therefrom a stay of execution order pending appeal. The appeal
was heard but it was decided that the merits of the dispute should be
tried.
-
In 1996 the defendant filed another action against four
other remaining squatters. The High Court granted vacant possession to
the defendant on condition that the defendant should pay compensation,
which is to be assessed by an independent valuer, to occupants of the
land. Dissatisfied, the plaintiff appealed to the Court of Appeal against
this decision. This appeal was dismissed on August 28, 1998.
MODE OF TRIAL
-
At the outset both parties agreed that the trial of this
suit be proceeded in the following manner:
-
the dispensation of oral testimony;
-
based on the agreed facts submitted by the parties and
the bundle of documents prepared by them;
-
written and oral submissions.
CONCEDED CLAIMS
-
At the initial stage of the oral submission, Mr. Malcolm
Fernandez, counsel for the defendant candidly conceded to the issue of
liability after this court commented that the court orders, seemingly
in favour of the squatters, did not prevent the defendant from building
on the said land. This is reflected from the defendant's progress claim
on the plaintiff where the defendant declared that the "walls and partitions
including floors and window frames" of the condominium are completed.
If this stage of construction was achieved despite the court orders and
the disputes with the squatters over access to the land then these circumstances
would not justify the defendant for exemption from liability under s 57(1)
and (2) of the Contracts Act - an agreement to do an impossible act.
-
With such concession, the only issue left for discussion
is the quantum of damages. Even on this, Mr. Malcolm Fernandez submits
that the sum of RM44,910 received by the defendant from the plaintiff
ought to be returned. Obviously he must have considered the doctrine of
restitution. Naturally, this comes with the interest of 8% per annum thereon
as prayed for by the plaintiff; an item this court is minded to grant.
DISPUTED CLAIM
-
But Mr. Malcolm Fernandez refused to concede to the plaintiffs
claim for liquidated damages of a sum of RM53,395.84 and RM11,079.16 in
accordance to clause 22(2) and 24(2) respectively in the S&P agreement.
He argued that this is untenable since damages for rescission, according
to him, should be assessed, not based on the formula set out under the
S&P agreement for delay in delivery of vacant possession of the said property.
-
Mr. Leong, counsel for the plaintiff, was adamant on his
view that the law allows the plaintiff to claim such liquidated damages
with interest attached thereto as set out in prayers (d) and (e) above.
He stressed that repudiation of the S&P agreement does not prevent the
plaintiff from claiming such sums formulated on the basis of late delivery
of the said property as set out in the S&P agreement. He cited a number
of authorities in support which I shall deal with shortly in my analysis
of this issue.
-
But before I venture further, it is best to explain why
specific dates and certain provisions of the S&P agreement were selected
by the plaintiff for calculation of her liquidated damages.
-
Under clause 22(2) of the S&P agreement vacant possession
of the said property is to be delivered to the plaintiff within 36 months
from date of agreement. This would put the last date for delivery of vacant
possession to February 1, 1997. The agreed damages stipulated for late
delivery is 10% per annum of the purchase price calculated on daily basis.
-
Under clause 24(2) of the S&P agreement there is a separate
provision for the defendant to complete the common facilities of the condominium.
It is also 36 months from date of agreement and the last date for completion
was February 1, 1997. Any delay will subject the defendant to pay the
plaintiff a penalty of 10% per annum of the last 20% of the purchase price
calculated on daily rest. This 20% amounts to RM18,960.
-
Having set out the facts and figures, I shall now proceed
to analyse whether such claim by the plaintiff should be entertained.
-
Firstly, s 76 of the Contracts Act 1950 provides:
A person who rightly rescinds a contract is entitled
to compensation for any damages which he has sustained through the
non-fulfilment of the contract.
|
-
The principle for the award of compensation is: the injured
party should as far as possible be placed in the same position in terms
of money as if the contract had been performed by the party in default
- see Pollock and Mulla on Indian Contract and Specific Relief Acts, 11th
edn, vol 2 at p 801. But in cases where the breach of the contract consist
in a failure to transfer property, according to McGregor on Damages, 16th
edn at p 25, the basis for ascertainment of loss is the market value of
the property, always deducting the contract price if it has not already
paid to the person in breach. But this is not what the plaintiff wants.
She is asking for damages based on calculation of interest on a day to
day basis for delay in handing over vacant possession of the said property
as specified in the aforesaid provisions of the S&P agreement. Can she
succeed especially when the S&P agreement is rescinded?
-
On the question of her right to claim under the contract
after the same is rescinded the following cases provided the answer in
the positive. In Johnson v Agnew [1979] 1 All ER 883 the House
of Lords accepted this dictum of Dixon J of Australia in the Australian
case of McDonald v Dennys Lascelles Ltd [1933] 48 CLR 457 at 476:
When a party to a simple contract, upon a breach
by the other contracting party of a condition of the contract, elects
to treat the contract as no longer binding upon him, the contract
is not rescinded as from the beginning. Both parties are discharged
from the further performance of the contract, but rights are not
divested or discharged which have already been unconditionally acquired.
Rights and obligations which arise from the partial execution of
the contract and causes of action which have accrued from its breach
alike continue unaffected. When a contract is rescinded because
of matters which affect its formation, as in the case of fraud,
the parties are to be rehabilitated and restored, so far as may
be to the position they occupy before the contract made. But when
a contract, which is not void or voidable at law, or liable to be
set aside in equity, is dissolved at the election of one party because
the other has not observed an essential condition or has committed
a breach going to its root, the contract is determined as far as
it is executory only and the party in default is liable to damages
for its breach.
|
-
Our courts have adopted this proposition through a series
of cases beginning with Chye Fook v Teh Teng Seng Realty Sdn Bhd
[1989] 1 MLJ 308. In this case, the plaintiff was the purchaser of
a house to be built by the defendant. The completion date for the house
was 24 months from the date of signing of the sale and purchase agreement
and failure to comply would subject the defendant to liquidated damages
of 10% per annum of the purchase price calculated on a day to day basis.
The defendant failed to complete within the stipulated date and the defendant
rescinded the agreement. Arguing against the plaintiffs rights to rescind
the contract, the defendant contended that the presence of the default
clause which provided liquidated damages demolishes such recessionary
right of the plaintiff. This did not find favour with the court which
accepted the proposition of Johnson v Agnew, supra.
-
Chye Fook v Teh Teng Seng Realty Sdn Bhd,
supra, was favourably cited in Tan Yang Long v Newacres Sdn
Bhd [1991] 1 MLJ 289 and Xavier Kang Yoon Mook v Insun Development
Sdn Bhd [1995] 1 AMR 667; [1995] 2 MLJ 91.
-
Having established that the plaintiff has a right to claim
damages specified under a rescinded contract, the next issue is whether
she is entitled to the liquidated damages specified in the S & P agreement
for non delivery of possession of the said properly?
-
On this, two cases throw some light. The first is from
the obiter dictum of Abdul Malek J (as he then was) in Chye Fook v
Teh Teng Seng Realty Sdn Bhd, supra:
At this stage of the proceedings, this court was
not asked to determine whether the rescission would result in the
plaintiffs not being able to receive the liquidated damages but
in passing I would say that, as provided by s 76 of the Contracts
Act 1950, a party who rightly rescinds a contract is entitled to
compensation for any damage which he has sustained through the non-fulfilment
of the contact. I had in fact made it clear in my ruling that the
plaintiffs' entitlement to liquidated damages if the developer failed
to complete within 24 months did not in any way take away the rights
of the purchaser to rescind the contract.
|
-
The second is Xavier Kang Yoon Mook v Insun Development
Sdn Bhd, supra. The facts of this case are these: the plaintiff
entered into a sale and purchase agreement for a house to be built by
the defendant developer. The defendant failed to deliver the house within
the stipulated time specified in the agreement. The plaintiff sought to
terminate the agreement by requesting from the court inter alia:
-
a declaration that the agreement is terminated;
-
the return of any sum so paid by the plaintiff under
the agreement;
-
liquidated damages calculated at the rate of 10% per
annum on the purchase price on daily rest from date when vacant possession
of the said house was supposed to be delivered to the plaintiff until
date of rescission of the agreement;
-
in the alternative damages for breach of contract.
The court allowed prayers (a), (b) and (c).
-
Though the facts in Xavier Kang Yoon Mook v Insun Development
Sdn Bhd, supra, is rather similar to our present situation
where the project is abandoned, yet despite allowing a claim for liquidated
damages based on the calculation specified in the contract for late delivery,
which could easily be ascertained on the spot, the learned judge ordered
the senior assistant registrar to assess the same. In our present case,
the exact amount is even spelled out in the statement of claim. By directing
assessment to be conducted by the senior assistant registrar, could the
learned judge in Xavier Kang Yoon Mook v Insun Development Sdn Bhd,
supra, be sharing my fear that such sum under the formula provided
for late delivery may amount to such an enormous sum that it is not equitable
to the developer. Imagine a purchaser of an abandoned project elects to
rescind his contract at a very late date despite having advance knowledge
that the developer is not proceeding with the project. In Xavier Kang
Yoon Mook v Insun Development Sdn Bhd, supra, it was 6 years
from due date of delivery of vacant possession to date of rescission.
In our present case it is approximately 5 years. By such delay in exercising
his rights the purchaser may be taking advantage of the more attractive
benefits set out in the artificial formula for computation for late delivery.
The aggregate may even exceed the total value of the house, if it is completed.
Would this not be defeating the very objective of compensation?
-
Though I agree with the proposition that rescission of
the S&P agreement by the plaintiff does not disqualify her from her entitlement
to liquidated damages spelled out in the said agreement but such formulated
sum to my mind would be subjected to s 75 of the Contracts Act 1950. This
provision provides:
When a contract has been broken, if a sum is named
in the contract as the amount to be paid in case of such breach,
or if the contract contains any other stipulation by way of penalty,
the party complaining of the breach is entitled, whether or not
actual damage or loss is proved to have been caused thereby, to
receive from the party who has broken the contract reasonable compensation
not exceeding the amount so named or, as the case may be, the penalty
stipulated for.
|
-
In this case the contract has been broken, A sum is named
in the contract as the amount to be paid to the plaintiff and this is
derived from a technique or method of calculation. Or alternatively, this
could be considered a penalty. But the plaintiff, under the law is only
entitled to receive from the defendant who has broken the contract "reasonable
compensation not exceeding the amount so named or, as the case may be,
the penalty stipulated for". To determine what is reasonable the court
has to decide. This is a more equitable approach otherwise, as I have
expressed, damages due to purchaser under the artificial formulated method
of calculation stipulated in the agreement may amount to colossal sum
for abandon project where the purchaser refused to rescind or chose to
rescind at a very late stage to continue to enjoy the higher rate for
calculation of compensation.
CONCLUSION
-
For reasons stated, I allow a claim for damages as requested
for in prayer (d) but the amount of reasonable compensation not exceeding
sum so named by the plaintiff in prayer (d) above is to be assessed by
the senior assistant registrar. Once assessed, it will carry an interest
of 8% per annum thereon from date of filing to date of full settlement.
-
As for prayer (a), (b) and (c), there shall be order in
terms. There shall be cost to the plaintiff.
Cases
Chye Fook v Teh Teng Seng Realty Sdn Bhd [1989] I MLJ 308;
Johnson v Agnew [1979] I All ER 883; Mcdonald v Dennys Lascelles Ltd [1933]
48 CLR 457; Tan Yang Long v Newacres Sdn Bhd [1992] 1 MLJ 289; Xavier Kang
Yoon Mook v Insun Development Sdn Bhd [1995] 1 AMR 667; [1995] 2 MLJ 91
Legislations
Contracts Act 1950: s.57(1), (2), s.75, s.76
Authors and other references
McGregor on Damages, 16th edn
Pollock & Mulla, Indian Contract and Specific Relief Acts,
11th edn, vol 2
Representations
CW Leong (Tee, Tan & Partners) for plaintiff
Malcolm Fernandez (Norman Fernandez & Associates) for defendant
Notes:-
This decision is also reported at [2003] 6 AMR 481
|