This website is
 sponsored.gif

banner.gif

 Welcome    Main    Forum    FAQ    Useful Links    Sample Letters   Tribunal  

MAJOR INDAH SDN BHD V. HOMENG REALTY SDN BHD
:HIGH COURT [KUALA LUMPUR]
MOHD GHAZALI MOHD YUSOFF, J
[GUAMAN SIVIL NO: D1 - 22 - 2415 TAHUN 1999]
19 FEBRUARY 2000


DALAM MAHKAMAH TINGGI MALAYA DI KUALA LUMPUR
(BAHAGIAN DAGANG)

GUAMAN SIVIL NO: D1 - 22 - 2415 TAHUN 1999

MAJOR INDAH SDN BHD (dahulunya dikenali sebagai  SERAMPAI TARAF SDN BHD)
PLAINTIF

DAN

HOMENG REALTY SDN BHD
DEFENDAN


ALASAN PENGHAKIMAN

The dispute between the plaintiff and the defendant arose out of a joint-venture agreement ("the JV agreement") entered into between the parties on 23 April 1999 to develop a housing project known as Sentul Indah comprising of 374 units of apartments and 19 units of shophouses ("the project"). Pursuant to the falling out

between the parties the plaintiff filed this action on 2 September 1999 praying for the following reliefs -

(1) an injunction to restrain the defendant from representing or holding themselves out to be the sole developer of the project to the exclusion of the plaintiff;

(2) an injunction to restrain the defendant from advertising the project for sale to the public or to solicit enquiries from the public by way of advertisements in newspapers, pamphlets, advertisement/signboards or otherwise without the express approval or concurrence of the plaintiff and in this respect to remove or take down any advertisement/signboards if any that may have been erected advertising the project for sale to the public or to solicit enquiries from the public;

(3) an injunction to restrain the defendant from receiving or accepting any payments whether in the form of booking fees, deposit payments or other payments from any purchasers or prospective purchasers or other third parties in respect of the project without the express approval or concurrence of the plaintiff;

(4) an injunction to restrain the defendant from awarding any contract or tender to any third party or from appointing any contractor, engineer, architect, worker or anyone else to commence any work related to the project without the express approval or concurrence of the plaintiff;

(5) an injunction to restrain the defendant from commencing or continuing with any work concerning or related to the project without the express approval or concurrence of the plaintiff;

(6) an order for specific performance of the JV agreement;

(7) damages;

(8) in lieu of specific performance, judgment for the sum of RM944,015-15 together with interest at the rate of 8% per annum from the date of this writ till full payment;

(9) costs.

Simultaneously the plaintiff filed an ex-parte application praying for interlocutory orders in the form similar to prayers

(1) to (5) as laid down above. When the ex-parte application came up before me on 20 September 1999, I ordered that the matter be heard inter-partes. The plaintiff consequently served the cause papers on the defendant. The matter was heard on 20 November 1999 and on that date I allowed the plaintiff's application for the said interlocutory orders. Against that decision the defendant has appealed.

The facts show by a written agreement dated 18 March 1991 ("the first agreement") and entered into between one Region Dynamic Sdn Bhd and the owners of land held under GM No. 1167 Lot No. 4028 and GM No. 1168 Lot No. 4029 both in the Mukim of Batu, Wilayah Persekutuan ("the land"), it was inter alia agreed that Region Dynamic Sdn Bhd would undertake the development of the project to be erected on the land subject to the terms and conditions as contained therein. By another written agreement dated 4 April 1994 ("the second agreement") and entered into between Region Dynamic Sdn Bhd and the

defendant, Region Dynamic Sdn Bhd assigned all its rights, benefits and interests under the first agreement to the defendant subject to the terms and conditions as contained therein. After the execution of the second agreement, the defendant launched the project and sold approximately 96 units of apartment under the project and collected the 10% deposit payable respectively for those units.

By a written joint-venture agreement dated 23 April 1999 and entered into between the plaintiff and the defendant, i.e, the JV agreement, it was, inter alia, agreed that the defendant would jointly with the plaintiff undertake the development of the project subject to the terms and conditions as contained therein. The following are the salient terms and conditions of the JV agreement -

(1) that the plaintiff and the defendant shall jointly undertake the project (clause 1);

(2) that the plaintiff shall pay to the defendant a sum of RM150,000-00 in 3 instalments (clause 2) as follows:-

(a) RM50,000/- to be paid on signing of the agreement, receipt of which the defendant acknowledges;

(b) RM50,000/- to be paid within 30 days after all the squatters/occupants on the land has vacated the premises; and

(c) RM50,000/- to be paid within 30 days upon commencement of piling works;

(3) that all expenses incurred subsequent to the JV agreement shall be borne and paid by the plaintiff until the financier bank releases payment for construction cost under the loan agreement or from progress payments received (clause 5);

(4) that the defendant confirm all the building layout plans have been duly approved by the relevant authorities and currently still valid@ (clause 6);

(5) the basis of the joint development of the project would be 50:50 in respect of costs and net profits (clause 8(a));

(6) the balance payment of compensation to squatters on the land amounting to RM745,000-00 shall be paid by the plaintiff and shall form part of the costs of the project (clause 8(c));

 

(7) that both parties shall jointly undertake the organising and management pertaining to the award of contracts, which shall be based on the lowest tendered price or otherwise as shall be agreed by both parties, as well as the appointment of consultants and other related professionals as well as the administration of the project for its speedy and efficient completion (clause 8(d));

(8) that all payments from the sale of units in the project shall be deposited into the designated project account as required under the Housing Developers (Control and Licensing) Act 1996 and the signatories to the payment approvals and cheques shall be jointly by one representative each from the plaintiff and defendant (clause 8(e));

(9) that the land and the project are Asubject to encumbrances to Sime Bank Bhd@ (clause 11);

(10) that both parties shall not do or permit to be done any acts or matters or things which may adversely affect the development of the project or the interests of the parties thereto (clause 12).

It is the plaintiff's case that their obligation was to finance the project and todate they have spent approximately RM944,015-15 in respect of the project, viz.:-

(a) deposit paid upon execution of the JV agreement - RM50,000/-;

(b) compensation payments made to squatters on the land - RM725,000/-;

(c) monthly payments of RM10,000/- towards the project - RM30,000/-;

(d) interest payment paid to Sime Bank Bhd on behalf of the defendant - RM85,735-15;

(e) deposit and advance rental for sales/administration office at No. 34-3 (3rd Floor), Jalan 14/48A, Sentul Raya Boulevard, 51000 Kuala Lumpur - RM3,600/-;

(f) application fees and deposit paid to Dewan Bandaraya Kuala Lumpur for the erection of an advertisement board together with the fees for making application - RM6,080/-;

(e) refund paid to purchasers of three (3) units sold earlier under the project before the JV agreement - RM43,600/-.

The plaintiff then claim of late they experienced a falling out with the defendant due to the following reasons:-

(1) by Ietter addressed to the plaintiff dated 6 July 1999, the defendant enclosed a notice from Sime Bank which was addressed to the defendant demanding payment of overdue interest in respect of a bridging loan granted to the defendant for the project as well as a notice of acquisition from Danaharta Managers Sdn Bhd (ADanaharta@) dated 10 June 1999 stating that all rights and interests in the credit facilities offered by Sime Bank to the defendant has been acquired by Danaharta; the defendant requested the plaintiff to pay for the said amount of overdue interest;

(2) the plaintiff responded to that letter by way of letter dated 7 July 1999 wherein they expressed dissatisfaction with the defendant's conduct in keeping from them the notices from Sime Bank and Danaharta and contended they cannot be held accountable for the defendant's operations of their bank accounts; nevertheless, the plaintiff, in order to assist the defendant and also in order not to jeopardize the project agreed to pay the outstanding interest of RM85,713-15 to Sime Bank upon receiving verbal confirmation from the defendant that the said credit facilities were still available;

(3) by letter to the plaintiff dated 17 July 1999, the defendant enclosed several notices of payments from several parties and asked the plaintiff to pay the same;

(4) by letter to the defendant dated 20 July 1999 the plaintiff reiterated the relevant clauses in the JV agreement concerning the appointment of contractors and the awarding of contracts relating to the project and insisted they will not be responsible for contracts awarded or contractors appointed without their express concurrence; they also requested that a meeting be held to address the above issue as well as the following matters, namely -

(a) the fact that the development order for the project and hence the buildings plans has long expired and has not been renewed to date;

(b) the defendant's failure todate to supply them with a list of end-purchasers of the project together with receipts,
income and expenditure account relating to the project despite the fact that the same should have been delivered to them within 7 days of the execution of the JV agreement;

(5) by letter addressed to the plaintiff dated 29 July 1999, the defendant made the following allegations:-

(a) the plaintiff had met one Mr Tai from Sime Bank after the execution of the JV agreement wherein it was confirmed that the bridging loan facilities could still be utilised;

(b) that the appointment of one Rencon Construction Works for fencing work at a cost of RM45,000/- was approved by the plaintiff;

(c) that the appointment of one Bumimetro Engineering Sdn Bhd to conduct soil tests has been approved by both parties and no letter of award was required;

(d) that the plaintiff had been given the quit rent and assessment receipts and could pay the same even if the same were missing;

(e) that a copy of the application for the renewal of the development order as well as the architect's letter was given to the plaintiff upon execution of the JV agreement;

(f) that the list of end-purchasers of the project together with receipts, income and
expenditure account, permits and licence relating to the project have been given to the plaintiff upon execution of the JV agreement;

(g) that the land has been handed over to the defendant free from any squatters;

(h) that the decision of the plaintiff not to release any more payment in respect of the project, after the meeting with Danaharta, constituted a breach of the JV agreement;

(6) the plaintiff by letter dated 4 August 1999 replied to the defendant's allegations as follows --

(a) the said Mr Tai of Sime Bank did not give any information as the defendant did not give written authorisation as promised; the responsibility for maintaining the banking facilities with Sime Bank rested solely with the defendant as the same was solely operated by them and its current condition was not disclosed to the plaintiff prior to the execution of the JV agreement;

(b) since the development order has long expired, fencing work on the land would be illegal and that the calling of tenders for fencing work was only to obtain pricing references; further, the defendant appointed the person who quoted the
highest price with used fence sheets as opposed to the others who tendered at lower prices with new fence sheets;

(c) the defendant had failed to approve the draft letter of award for soil testing prepared by the plaintiff and forwarded to the defendant; the plaintiff also deny preventing the contractor from carrying out the work;

(d) the plaintiff deny having been given the quit rent and assessment receipts;

(e) the plaintiff deny they had been given a copy of the application for renewal of the development order as well as the architect's letter upon execution of the JV
agreement; the fact that no development order would mean no project was hidden from the plaintiff prior to the execution of the JV agreement;

(f) the plaintiff deny having been given a list of end-purchasers of the project together with receipts, income and expenditure account, permits and licence relating to the project upon execution of the JV agreement;

(g) the plaintiff has proof that there are still 2 squatter houses remaining on the land.

The plaintiff also raised the following issues in the same letter, namely -

(i) that the advertisement board erected by the defendant on the land advertising the project for sale lists only the telephone number of the defendant;

(ii) that the plaintiff was not consulted regarding the said advertisement board which does not contain material information, eg., developer's name, permit and approved references nor do they agree to the erection of the same;

(iii) that the plaintiff, whilst denying breaching the JV agreement, pointed out that in the absence of a valid development order, the units in the project could not be sold and that this act of the defendant was not only irresponsible but also illegal.

It is the plaintiff's stand that todate the defendant has failed, refused or neglected to agree to a meeting to try and resolve the dispute as requested by them through various letters. By letter dated 11 August 1999 they wrote to the arbitrator named in the JV agreement, namely, one Dato' Toh Hock Chew ("Dato' Toh"), a lawyer with the legal firm of Messrs Amir Toh Francis & Partners, requesting that he call for a meeting with the defendant to try to solve the dispute. Dato' Toh duly sent a notice calling for a meeting between the parties to be held on 19 August 1999 but the defendant proposed a date in September 1999 as that date proposed was unsuitable and simultaneously intimated that they reserve their right to object to the appointment of Dato' Toh as arbitrator notwithstanding clause 16 of the JV agreement which read -

"Any disputes or claims arising out of this Agreement shall, upon failure of an amicable settlement, be settled by arbitration in accordance with the Arbitration Act 1952 and both parties hereby agree and irrevocably appoint Dato' Toh Hock Chew of M/s Amir Toh Francis & Partners to be the arbitrator for the said arbitration."

The plaintiff complain the defendant has proceeded unilaterally to advertise the project for sale to the public by way of erecting the said advertisement board on the land which only contains the telephone number of the defendant and does not make any reference to the JV agreement. Further, the defendant has without the knowledge or approval of the plaintiff appointed one JT Properties as their agent to market the units under the project.

Meanwhile in a letter to the plaintiff dated 20 August 1999 the defendant alleged that the plaintiff has breached the JV agreement. The allegations include the following -

(1) failing to pay the defendant the sum of RM50,000/- within 30 days of the eviction of all squatters from the land as required by clause 2(ii);

(2) failing to pay the monthly sum of RM10,000/- as monthly expenses in respect of office operation cost for the month of August 1999 as required by
clause 3; clause 3 read -

"It is hereby agreed that the Second Party shall advance to the First Party the sum of RM10,000-00 per month (Ringgit Malaysia: Ten Thousand only) as monthly expenses for office operation cost to be commenced from 1st May 1999 and thereafter within the first three (3) days of each month until the practical completion of the Housing Development. "

(3) failing to pay the outstanding interest due on the said facilities and hence breaching clause 5; clause 5 read -

"All expenses incurred subsequent to signing of this Agreement shall be paid by the Second Party until the financier Bank release payment for construction cost under the loan Agreement or progress payment being received.";|
 

(4) failing to pay the following construction cost of the project -
 

(i) the sum of RM10,000/- payable to Wengsan Construction Sdn Bhd in respect of work in clearing the land;

(ii) the sum RM32,409/- payable to Bumimetro Engineering Sdn Bhd in respect of soil tests conducted in respect of the project;

(iii) the sum of RM45,000/- payable to Rencon Construction Works for the fencing works in the project;

(iv) the quit rent and assessment in respect of the said land amounting to RM37,652-53 thereby breaching clause 5.

In the same letter the defendant claimed they have incurred the following actual loss and damage as a result of the breach of agreement, namely -

(a) costs of conducting soil tests - RM 32,409/-;

(b) costs of fencing works - RM45,000/-;

(c) costs of clearing works - RM10,000/-;

(d) costs of disposing rubbish, trees, undergrowth, etc. - RM16,5000/-;
(e) costs of advertising - RM18,880/-;

(f) quit rent and assessment - RM37,652-53.

Subsequently, in another letter to the plaintiff dated 27 August 1999 the defendant purported to accept the "breaches" by the plaintiff and proceeded to forthwith terminate the JV agreement as well as make a claim for loss and damage arising therefrom. That letter, inter alia, read -

"We refer to the above matter and to our letter to you dated 20th August 1999 ("our Letter") which you have yet to reply.

2. We have given you in our Letter notice in detail regarding your many fundamental breaches of the Agreement which have gone to the root of the Agreement ("your Breaches"). Our Letter has also stated in detail the loss and damage suffered by us due to your Breaches and as you are well aware of, our loss and damage directly consequent to your Breaches are still continuing.

3. TAKE NOTICE that we have decided to accept your Breaches and to terminate the Agreement effective from the date of this letter. Our decision to terminate the Agreement is taken primarily to ensure that the Project is not further delayed and jeopardized.

4. TAKE ALSO NOTICE
that we hereby claim against you for all the loss and damage arising from your Breaches ("our Claim").

By letter also dated 27 August 1999 and addressed to the said Dato' Toh, the defendant objected to the appointment of the latter and informed that unless Dato'Toh disqualifies himself, they would proceed to apply to court to do so.

It is the plaintiff's claim that the defendant itself has breached the JV agreement the particulars of which are as follows -

(1) the development order in respect of the project and consequently the building plans of the same has long expired and has yet to be renewed;

(2) by objecting to the appointment of Dato' Toh as arbitrator;

(3) excluding the plaintiff from the day to day running as well as management of the project as well as proceeding to act unilaterally without the consent of or approval of the plaintiff, viz.:-

(a) excluding the plaintiff from a meeting with Danaharta held on 21 July 1999 by not informing them of the said meeting;

(b) appointing JT Properties to market the units under the project without the knowledge or approval of the plaintiff;

(c) proceeding unilaterally to advertise the project for sale to the public by way of erecting an advertisement board on the land;

(d) failing, refusing or neglecting to agree to a meeting with the plaintiff to try and resolve the dispute as requested by the plaintiff through various letters;

(e) unilaterally appointing contractors to carry out work related to the project;

The plaintiff complain the defendant, in purporting to terminate the JV agreement, is trying to exclude or oust them from the project and to deprive them of the potential profits from the sale of the units under the project. The plaintiff in being excluded from the project has not only suffered losses financially but also suffered damage to their reputation and good name due to this debacle. As this is the plaintiff's first major project, the plaintiff's reputation and credibility is at stake should the project be a failure. The unlawful actions of the defendant in relation to the project has also opened up the plaintiff to potential criminal liabilities and civil liabilities to third parties, the plaintiff being a

joint developer of the project vis-a-vis the JV agreement. The plaintiff does not accept the termination of the JV agreement by the defendant as the termination is unlawful and instead reaffirms the JV agreement and state that the plaintiff is ready, able and willing to fulfill their obligations under the JV agreement.

In its affidavit in support of the application for the interlocutory orders, the plaintiff insisted that the defendant had all along been using the plaintiff's ample financial resources to get the project ready for launching by clearing the land of squatters and for paying overdue interest payments to the financier and after the plaintiff had worked to get the project ready for launching, the defendant is now raising frivolous grounds to terminate the JV agreement in an attempt to exclude the plaintiff from enjoying the fruits of their labour, i.e., the profits to be realised from the sale of the units under the project. It is the plaintiff's contention that the defendant's actions are clearly mala fide and calculated to cause loss and damage to them and unless restrained, they will suffer and continue to suffer irreparable harm and damage which cannot be compensated by costs or monetary means.

In its affidavit in opposition, the defendant denied having invited the plaintiff to develop the project together. The deponent to the defendant's affidavit, one Toh Ah Leong, a director, stated he did not know the plaintiff or its directors. It was only sometime in January 1999 that he was introduced to one Hee Jee Pin and one Wee Bing Hock who are the directors of the plaintiff by their lawyer, that is, the said Dato' Toh when both the said directors of the plaintiff offered to invest in the project.

In relation to the various payments alleged to have been paid by the plaintiff, the defendant pointed out that the second instalment of RM50,000/- should have been paid within 30 days after all the squatters have been removed from the land and that the third instalment of RM50,000/- should be paid within 30 days after the commencement of piling works for the project. The defendant also denied that the plaintiff had expended the sum of RM3,600/- as deposit and advance rental for the said sales/administration office. As regards the other payments, the

defendant admits the plaintiff had made those payments but insisted that what induced the defendant to enter into the JV agreement was because the plaintiff had agreed to advance those payments until the bank release the funds under the bridging loan as provided for in clause 5 of the JV agreement. The defendant insist that under the said clause 5 the plaintiff is obliged to make all payments which have been agreed to therein. The defendant then contended as follows -

(1) other than making those payments which they are obliged to make under the JV agreement, the plaintiff did not contribute anything else to the project;

(2) upon the execution of the JV agreement, it was the duty of the said Hee Jee Pin, as instructed by the management committee, to see to the erection of the fencing for the project with used materials but
he failed to carry out his duty after two months had passed as a result of which on 8 July 1999 the said Rencon Construction Works was employed to do the job; however the plaintiff has refused to pay Rencon Construction Works for the said works and instead accused the defendant of appointing them without the approval of the management committee;

(3) the plaintiff has prevented the said Bumimetro Engineering Sdn Bhd from carrying out the soil test on the land notwithstanding that the management committee has approved that that company is to carry out the said work;

(4) the plaintiff caused further delay to the implementation of the project by failing to make payments to the following contractors -

(a) Wengsan Construction Sdn Bhd - RM10,000/-;

(b) Bumimetro Engineering Sdn Bhd - RM32,409/-;

(c) Rencon Contruction Works - RM45,500/-;

(5) the defendant admits the state of relationship between both parties is not cordial but in reply to the averments made by the plaintiff contends, inter alia, as follows -

(a) they deny that they enclosed the notice of acquisition from Danaharta in the said letter to the plaintiff dated 6 July 1999;

(b) they only knew sometime in June 1999 that all rights and interest under the bridging loan facility from Sime Bank had been taken over by Danaharta and this was informed by the said Hee Jee Pin himself who stated that he had been in communication with the said Mr Tai;

(c) they deny having kept from the plaintiff notices from Sime Bank and Danaharta and the monthly statement of accounts;

(d) they deny having conveyed orally to the plaintiff that the credit facility can still be utilised;

(e) they deny having appointed contractors or awarding contracts without the concurrence of the plaintiff;

(f) they concede that the development order for the project has lapsed but insisted that this was due to the presence of squatters of the land; however they have made an application for the extension of the development order and the building plan and the delay in making the application was due to the presence of squatters and this is within the knowledge of the plaintiff;

(g) prior to the execution of the JV agreement the plaintiff knew that the development order and the building plan had lapsed and that the defendant had applied for an extension; furthermore this has been raised at the weekly meetings between both parties;

(h) it is the plaintiff which failed to pay the outstanding payments due under the bridging loan;

(i) it is illogical for the plaintiff to seek confirmation from them on the status of the banking facility as they knew that the facility has been acquired by Danaharta it being a non-performing loan which came about as a result of the plaintiff's failure to pay the outstanding payments due under the bridging loan;

(j) they insist that the plaintiff has been provided with a list of purchasers for the units under the project together with the receipts and statement of accounts in relation to income received and expenditure under the project;

(k) in relation to the allegation of the plaintiff as regards the advertisement board, the defendant's explanation is as follows -

(i) sometime in 1996, prior to the expiry of the development order, about 100 apartment
units under the project were sold and the 10% deposits were collected from the purchasers;

(ii) the project could not progress further due to the presence of squatters on the land;

(iii) since the said purchasers have been making enquiries about the project, for the purpose of pacifying them, the defendant erected the alleged advertisement board giving details of the project not for the purpose of advertisement but merely to inform the purchasers of the location of the project and hence the reason why the developer's name and the advertisement permit number was omitted;

(l) the defendant deny that the units under the project cannot be sold and claim that Dewan Bandaraya Kuala Lumpur has approved their application for an advertisement licence issued pursuant to rule 5(4) of the Housing Developers (Control and Licensing) Rules 1989 and which is effective from 29 December 1998 to 28 December 1999;

(m) in relation to the said Dato' Toh, the deponent state -

(i) it was Dato' Toh, as the plaintiff's lawyer, who introduced the said two directors of the plaintiff;

(ii) Dato' Toh was actively involved in the discussions leading to the JV agreement;

(iii) Dato' Toh's legal firm prepared the sale and purchase agreements for the project;

(iv) Dato' Toh attended and actively participated in the meetings of the management committee;

(v) Dato' Toh has a close relationship with the said directors of the plaintiff and they are from the same hometown;

(n) since the execution of the JV agreement, the defendant never collected any deposits from purchasers;

(o) the said JT Properties has yet to be appointed as the defendant's agent to sell the units under the project;

(p) on or about 16 July 1999 the representatives of the plaintiff had a meeting with Danaharta and the defendant was not informed of the outcome of the meeting in relation to the status of the defendant's loan, i.e., as to whether the defendant can still utilise the said bridging loan or as to whether further conditions have been imposed;

(q) in a meeting with Danaharta on 21 July 1999, Danaharta informed the plaintiff that they have to provide an undertaking to pay all interests due before any proposal in relation to the loan can be considered; up todate the plaintiff has not furnished that undertaking to Danaharta;

(r) when the defendant executed the JV agreement which was prepared by Dato' Toh, the terms and conditions of the contract were not fully explained to them and it was only after its execution that they realised that certain terms were not discussed, inter alia, clause 5(g) which provides that Dato' Toh as solicitor for the plaintiff is given the power to approve and sign cheques to be issued from the project account.

In his submission, counsel for the plaintiff attacked the various contentions of the defendant as forwarded in the latter's affidavits, namely -

(1) the defendant's stand that they did not invite the plaintiff to develop the project is not true as evidenced by the fourth recital of the agreement which read "The First Party has requested and invited the Second Party to jointly develop and the Second Party has agreed to jointly carry out the development of the Housing Development upon the terms and conditions hereinafter contained", the "First Party" referred to therein being the defendant and the "Second Party", the plaintiff;

(2) the defendant deny that the payment relating to the tenancy agreement has been paid, or if paid, was done without their consent whereas a copy of the tenancy agreement which is annexed to the plaintiff's affidavit show that it was the said Toh Ah Leong, i.e., the defendant's director and deponent to the defendant's affidavit, who signed the tenancy agreement;

(3) in their affidavit the defendant admit that the development order has expired and this is contrary to what is expressed by the defendant in clause 6 of the JV agreement which read -

"The First Party hereby confirm that all the building layout plans have been duly approved by the relevant authorities (hereinafter referred to as "the Approved Plans") and currently still valid and that the Assignment of the Agreement and the Joint-Venture Agreement are still valid and subsisting";

(4) the defendant's stand that all squatters have been evicted from the land is not true - a copy of the layout plan and photographs taken on site which are exhibited in the plaintiff's affidavit show there are still squatters on the land;

(5) the defendant's claim that the advertisement board erected on the land was only to inform the previous purchasers is untrue as the price of the units indicated thereon is the new price;

(6) after the execution of the JV agreement there had only been 4 meetings relating to the project held between the parties and not 12 to 15 as claimed by the defendant; the fourth meeting was held on 18 June 1999 and thereafter upon the onset of the dispute between the parties, no more meetings were held although the plaintiff repeatedly requested for the same to resolve the dispute.

The case of American Cynamid Co v Ethicon Ltd [1975] 2 WLR 316 laid down the test to be applied in the granting of an interlocutory injunction, namely, whether there is a serious question to be tried and whether the balance of convenience lies in granting or refusing the injunction. In that case Lord Diplock took the view that there is a serious question to be tried if a claim is not frivolous or vexatious. In Donmar Productions Ltd v Burt & Ors [1967] 2 All ER 338 Ungoed-Thomas J said (at page 339):

"So in an application for the interlocutory injunction the applicant must establish a probability or a strong prima facie case that he is entitled to the right of whose violations he complains and, subject to this being established, the governing consideration is the maintenance of the status quo pending the trial.

It is well established that in deciding whether the matter shall be maintained in status quo regard must be had to the balance of convenience and to the extent to which any damage to the plaintiff can be cured by payment of damages rather than by granting the injunction."

The prerequisites which must be present before a court can determine whether an interlocutory injunction should lie has also been summarised in Alor Janggus Soon Seng Trading SdnBhd & 6 Ors v Sey Hoe Sdn Bhd & 2 Ors [1995] 1 AMR 549 by Mohd Jemuri Serjan CJ (Borneo); he said (at page 568) -

A Firstly, the plaintiffs' case must raise serious issues to be tried. If the plaintiffs fail at that point there is clearly no case for an injunction. Secondly, the trial of the main suit is likely to take place in the sense that the plaintiffs' case shows that they are genuinely concerned to pursue the claim to trial and they are seeking the injunction as a means of holding operation pending the trial. Once it can be established that there are serious questions to be tried then the other guidelines must be invoked. The court has to consider:

(a) Whether damages are an adequate remedy;

(b) Where does the "balance of convenience" and;

(c) Are there any "special factor".

It is not disputed that the development order for the project was issued by the relevant authority on 11 April 1996 and it expired on 10 April 1997. The JV agreement was executed on 23 April 1999

and the defendant has given an undertaking therein that all building plans and development plans are still subsisting. What is clear is when the JV agreement was executed, the development order had expired. The defendant do not dispute that the development order and the building plans have expired but argued since they have applied to renew it, although no renewal has been granted up todate, they can still carry on to advertise the project and sell notwithstanding its expiry.

In his submission, counsel for the defendant stressed that the defendant's main ground in opposing the plaintiff's application for the various interlocutory orders is that the plaintiff's claim is based upon an illegality, namely, the JV agreement was entered into contrary to section 8 of the Housing Developers (Control and Licensing) Act 1966 ("the Act") which read -

"(1) Where a licensed housing developer proposes to enter into an arrangement or agreement to sell, dispose of or reconstruct his business relating to housing development either by amalgamation or otherwise, the licensed housing developer shall as soon as possible notify the Controller of the proposed arrangement or agreement and unless approved by the Controller under subsection (2), the licensed housing developer shall not proceed with that arrangement or agreement."

Counsel for the defendant pointed out no approval from the Controller has been obtained prior to the execution of the JV agreement and this is contrary to the above provision.

It is necessary for a party seeking interlocutory relief to show there is at least a serious question to be tried and to adduce sufficiently precise factual evidence to satisfy the court that he has a real prospect of succeeding in his claim at the trial. A party should not be granted an interlocutory injunction unless he is able to show that if it were not granted he would suffer irreparable damage. Is there a serious

question to be tried in the instant case? From my reading of the various affidavits and the exhibits exhibited therein, I am of the view there are serious questions to be tried at the trial. Whether the JV agreement is void as being contrary to the said section 8(1) of the Act is a serious question to be tried since one of the prayers to the plaintiff's claim is an order for specific performance of the JV agreement. Whether the plaintiff have breached the terms of the JV agreement which would entitle the defendant to terminate the agreement is another serious question to be tried. I am, at this stage of the proceedings, not in a position to make a finding and rule that the plaintiff is entitled to an order for specific performance or rule that the defendant is entitled to treat the JV agreement as void and/or is entitled to terminate the same on the basis that that the plaintiff has committed certain breaches. These are issues to be determined at the trial.

In my view, the plaintiff has shown they have a strong prima facie case in pursuing an order for specific performance of the JV agreement. They may succeed at the trial in establishing that the

defendant has wrongfully purported to terminate the JV agreement. What they are seeking in this application is to preserve the status quo of the JV agreement pending final determination of the suit, i.e., to carry on with what was agreed to in the JV agreement, viz., that the parties would jointly undertake the development of the project and that both parties shall not do or permit to be done any acts or matters or things which may adversely affect the development of the project or the interests of the parties thereto. Under the circumstances, I would think that the balance of convenience would tilt in favour of the plaintiff to grant them the interlocutory orders sought for since what they are seeking is nothing more than to preserve the status quo of the obligations of both parties under the JV agreement.

In allowing the application I had also taken into consideration the conduct of the parties and also as to whether damages instead of an injunction would be an adequate remedy. Looking at the facts, I am of the view that the bona fides of the defendant is suspect. In clause 6 of the JV agreement, the defendant confirm

that "all the building layout plans have been duly approved by the relevant authorities and currently still valid". It is not disputed that those plans had expired on 10 April 1997 and up todate have not been renewed by the relevant authorities. The defendant concede those plans had expired when the JV agreement was executed but in relation to this keep on harping that they have applied for its renewal. Without any valid and subsisting building layout plans, the project cannot go on and this the defendant concede is the current scenario. Without the interlocutory orders sought for, the JV agreement would for all practical purposes come to nought as the defendant, having purported to terminate the JV agreement would now be in a position to, for example, dispose of the project by sale or assignment. That being the reality which may follow, damages may not be an adequate remedy under the circumstances.

The contention of the defendant that the JV agreement is void, it having run foul of section 8 of the Act, to me, do not seem to hold water. The said section 8 provides where a licensed

developer proposes to enter into an arrangement or agreement to sell, dispose of or reconstruct his business relating to housing development either by amalgamation or otherwise, the licensed housing developer shall as soon as possible notify the Controller of the proposed arrangement or agreement and unless approved by the Controller, the licensed housing developer shall not proceed with that arrangement or agreement. Section 19(aa) of the Act provides any housing developer who enters into arrangement or agreement in contravention of section 8, i.e., without first obtaining the approval of the Controller, shall be guilty of an offence and shall, on conviction, be liable to a fine not exceeding RM10,000/- or to imprisonment for a term not exceeding 3 years or to both and shall also be liable to a further fine of RM5,000/- for every day during which the offence is continued after conviction. As to whether the JV agreement falls within the contemplation of section 8 of the Act has not been sufficiently argued by the parties in their submission. Counsel for the defendant who raised this contention has not illustrated how the JV agreement has fallen foul of the said

section 8. Even if the JV agreement is later found to fall within the contemplation of the said section 8, from my reading of that provision, I would think the obligation to notify the Controller and seek his approval prior to the execution of the JV agreement surely lie on the defendant as it is the defendant which is the housing developer and which would be committing the offence under section 19(aa) of the Act if that is the position. Section 8 read together with section 19(aa) has no application to the plaintiff as it is not a housing developer. Furthermore, nowhere is it mentioned in the Act that any arrangement or agreement which fall under section 8 shall be void if the Controller's approval has not been obtained, i.e., there are no provisions in the Act nullifying such an arrangement or agreement.

On the whole I am of the view that the plaintiff has clearly shown that it has a valid cause of action. The plaintiff has also shown it is genuinely concerned to pursue the claim to trial. The facts show after the execution of the JV agreement the plaintiff

expended approximately RM944,000/- in respect of the project in line with clause 5 of the JV agreement. There is nothing to show the plaintiff has done anything which may adversely affect the development of the project. The plaintiff is now seeking interlocutory orders to restrain the defendant from doing acts which may result in the JV agreement being of academic interest only. I am of the view that if those interlocutory orders sought for are not granted, damages would not be an adequate remedy. Further, it would also be difficult to assess the damages in terms of money under the circumstances seeing that the project has not even lifted off the ground.

On a balance of convenience I am of the view that the application should be allowed. I have to act upon the principle of preventing irreparable damage. The purpose of an interlocutory injunction is to preserve the status quo until the rights of the parties have been determined in the action and looking at the plaintiffs' case, the subject matter may no longer be there if the

defendant is not restrained from carrying on with the project on the assumption that the JV agreement has been lawfully terminated. Upon the usual undertaking by the plaintiff as to damages, I allowed the application and ordered that the costs of and incidental to this application to be the plaintiff's costs in the cause.

(DATO HJ MOHD GHAZALI BIN MOHD YUSOFF)

Hakim

Mahkamah Tinggi

Kuala Lumpur

Tarikh: 19 Februari 2000

 

Main   Forum  FAQ  Useful Links  Sample Letters  Tribunal  

National House Buyers Association (HBA)

No, 31, Level 3, Jalan Barat, Off Jalan Imbi, 55100, Kuala Lumpur, Malaysia
Tel: 03-21422225 | 012-3345 676 Fax: 03-22601803 Email: info@hba.org.my

© 2001-2009, National House Buyers Association of Malaysia. All Rights Reserved.