HENG HANG KHIM V. SINEO ENTERPRISE SDN
BHD
HIGH COURT [JOHOR BAHRU]
AZAHAR MOHAMED, J
SAMAN PERMULAAN NO: 24 - 423 - 1999 (4)
6 APRIL 2007
DALAM MAHKAMAH TINGGI MALAYA DI JOHOR BAHRU
DI DALAM NEGERI JOHOR
SAMAN PERMULAAN NO: 24 - 423 - 1999 (4)
Dalam perkara yang diperuntukkan di bawah Seksyen 56 Akta Kontrak
1950
Dan
Dalam perkara yang diperuntukkan di bawah Peraturan 11,
Peraturan-Peraturar Pemaju Perumahan (kawalan & Pelesenan 1989
Dan
Dalam perkara mengenai Perjanjian Jual Beli bertarikh 3.10.1995
untuk pembeliai satu unit kondominium yang dikenal sebagai Unit
#13A-03A5 Type A, Block 2 Skudai Parade, Johor Bahru, Johor
ANTARA
HENG HANG KHIM
- Plaintif
DAN
SINEO ENTERPRISE SDN.BHD.
- Defendan
DI DALAM KAMAR
DI HADAPAN
Y.A DATO' AZAHAR BIN MOHAMED HAKIM
MAHKAMAH TINGGI JOHOR BAHRU
JUDGMENT
This was an appeal to the judge in chambers (encl.33) by the defendant
against the decision of the learned deputy registrar given on 6 June 2006
whereby the defendant was ordered to pay the plaintiff a sum of RM63,800.00
as damages for breach of contract.
To put things in proper context, it is important to set out the factual
background and the sequence of events relevant to this appeal. By the sale
and purchase agreement dated 3 October 1995 (the 'SPA') entered into between
the plaintiff and the defendant, a developer for the sale and purchase of a
condominium known as Unit #13A-03A, Type A, Block 2, Skudai Parade, Johor
Bahru, Johor ('the Condo'), the defendant agreed to sell and the plaintiff
agreed to purchase the Condo unit with a floor area of 1,316.36 sq. ft at
and for the purchase price of RM319,000.00. The SPA was a standard sale and
purchase agreement for undivided building prescribed under the Housing
Developer (Control and Licensing) Regulation 1989. Pursuant to the SPA, 20%
of the purchase price (aggregating RM63,800.00) had been paid by the
plaintiff to the defendant. The defendant had breached the SPA by failing to
deliver vacant possession of the Condo to the plaintiff on or before 3
October 1998 i.e. on or before the expiry of the 36 month period. As a
result thereof, the plaintiff terminated the SPA vide the plaintiffs
solicitors' letter of 3 November 1998. Thereafter the plaintiff brought the
action herein against the defendant claiming, inter alia, the
following:
1. a declaration that the SPA had been terminated;
2. the refund of 20% purchase price paid by the plaintiff to the
defendant under the SPA; and
3. payment of damages to be assessed consequent upon the termination of
the SPA.
On 8 January 2001 the learned judge granted the declaration and also made
the following orders:
1. the defendant was to refund to the plaintiff a sum of RM63,800.00
being the 20% of the purchase price paid;
2. the defendant was to pay general damages as a result of the
termination to be assessed by the registrar.
Soon afterwards the defendant filed an appeal against that decision to
the Court of Appeal. On 25 November 2004, the Court of Appeal allowed, in
part, the defendant's appeal and ordered:
1. the order that the defendant was to refund the sum of RM63,800.00
was set aside;
2. the defendant was to pay to the plaintiff general damages as a
result of the termination, to be assessed by the registrar; and
3. the defendant to pay 1/3 costs of the appeal.
Following the order of the Court of Appeal, the plaintiff afterwards took
out a summons in chambers for the assessment of damages. At the assessment
of damages stage, the plaintiff filed a witness statement and the plaintiffs
bundle of document. The learned deputy registrar awarded damages to the
plaintiff in the sum of RM63,985.00, which included the sum of RM63,800.00
paid to the defendant as part purchase payment.
The defendant being dissatisfied with that decision appealed to this
court. During the argument of the appeal before me, learned counsel for the
defendant submitted that the order of the learned deputy registrar was in
direct conflict with the order of the Court of Appeal. It was said that the
learned deputy registrar was bound by the decision of the Court of Appeal in
that the defendant was not required to refund the sum of RM63,800.00. I now
move on to consider the submission of learned counsel for the defendant. I
could not agree with it. In the first place, it is of significance to note
that as time was provided to be the essence of the SPA (see cl. 7), the
stipulated time period within which the Condo had to be delivered to the
purchaser (see cl. 22(1)) became an essential condition of the agreement.
The stipulated period within which the Condo had to be delivered to the
plaintiff was a covenant so fundamental to the performance of the SPA. The
defendant had failed to complete within time. The defendant's conduct
amounted to a fundamental breach of contract. In view of the fact that the
defendant was in breach of this condition, the plaintiff was at liberty to
elect either to terminate the SPA and sue for damages or to deal with the
agreement as continuing and sue for damages. The plaintiff in this case had
elected to terminate the SPA by the issuance of the notice of termination of
the SPA by his solicitor. He had the right to do so. As an innocent and
non-defaulting party, the plaintiff had the right to terminate it by
recission. The Court of Appeal upheld the decision of the learned judge that
the plaintiff had terminated the SPA due to the breach caused by the
defendant. The Court of Appeal had affirmed the order for damages to be
assessed. It was on the basis of this that the learned deputy registrar
proceeded with the assessment of damages. I would observe that the Court of
Appeal never ruled that the plaintiff was estopped from claiming the sum of
RM63,800.00.
The general principle for the assessment of damages is compensatory. Now,
s. 74 of the Contracts Act 1950 provides that when a contract has been
broken, the party who suffers by the breach is entitled to receive from the
party who has broken the contract, compensation for any loss or damage
caused to him thereby, %hich naturally arise in the usual course of things
from the breach, or which the parties knew, when they made the contract, to
be likely to result from the breach of it. I find it necessary to reproduce
the provision. This is what it says:
Compensation for loss or damage caused by breach of contract.
(1) When a contract has been broken, the party who suffers by the
breach is entitled to receive, from the party who has broken the contract,
compensation for any loss or damage caused to him thereby, which naturally
arose in the usual course of things from the breach, or which the parties
knew, when they made the contract, to be likely to result from the breach
of it.
(2) Such compensation is not to be given for any remote and indirect
loss or damage sustained by reason of the breach.
(3) Compensation for failure to discharge obligation resembling those
created by contract. When an obligation resembling those created by
contract has been incurred and has not been discharged, any person injured
by the failure to discharge it is entitled to receive the same
compensation from the party in default as if the person had contracted to
discharge it and had broken his contract. Explanation - In estimating the
loss or damage arising from a breach of contract, the means which existed
of remedying the inconvenience caused by the non-performance of the
contract must be taken into account Illustration (r) to s. 7 is the most
illustrative. It reads as follows: r) A, a ship owner, contract with B to
convey him from Kelang to Sydney in Ars ship, sailing on the 1st of
January, and B pays to A, by way of deposit, one-half of his
passage-money. The ship does not sail on the 1st of January, and B, after
being, in consequence, detained in Kelang for some time, and thereby put
to some expense, proceeds to Sydney in another vessel, and, in
consequence, arriving too late in Sydney, loses a sum of money. A is
liable to repay to B his deposit, with interest, and the expense to which
he is put by his detention in Kelang, and the excess, if any, of the
passage-money paid for the second ship over that agreed upon for the
first, but not the sum of money which B lost by arriving in Sydney too
late.
I would like to point out that the above illustration uses the phrase
' A is liable to repay B his deposit, with interest" to describe
the kind of the remedy available for the Mamage caused by a breach of
contract. The phrase captures the essence of the point that I want to make.
This was the principle as I saw it. It seems clear to me that recovery of
the sum paid as part purchase payment is allowed under
s. 74 as compensation for loss or damage caused by breach of a contract.
To make this point clear, I should refer to the judgment of Gill J
(as he then was) in
Central Malaysia Development Co. Ltd v Chin Pak Chin [1967] 1 LNS
15 [1967] 2 MLJ 174 where the learned judge had this to say at p 177 on the
subject of
s.74:
It is to be observed that the section is general in its terms, and does
not exclude the case of damages for breach of a contract to sell
immoveable property. In other words, the legislature has not prescribed a
different measure of damages in the case of contracts dealing with land
from the laid down in the case of contracts relating to commodities.
Where, therefore, a purchaser of land claims damages for the loss of his
bargain, the question to be decided is whether the damage alleged to have
been caused to him ''naturally arose in the usual course of things from
such breach ". And further down at p 178 the learned judge said: In the
result the plaintiff's are entitled to recover the sum of $60,000 which
they paid as deposit on the date of the agreement together with a
reasonable rate of interest.
Textbooks authority in general supports the proposition that a breach on
the part of the vendor entitles the purchaser to recover damages for his
deposit and other payments towards the price paid by him. According to
Justice BN Krishnan, Law Of Damages and Compensation (2nd edition) at
p 561:
A breach on the part of the vendor, for whatever cause, entitles the
vendee to a refund of the earnest money paid, or advances towards the
price paid by him, in addition to other damages, if any. See also
Pollock & Mulla, Indian Contract and Specific Relief Acts (12th ed)
Vol. 11, which expressed a similar view at p 1585.
Returning to our present case and applying the foregoing principles to
the facts of the case before me, the crucial point was whether the learned
deputy registrar had rightly assessed the damages as RM63,985.00. To my mind
it was a fair and reasonable award. The 20% of the purchase price paid by
the plaintiff was obviously part of the damages suffered by the plaintiff
consequent upon the breach caused by the defendant. On the facts of the
case, it would to me more commensurate with justice that the plaintiff, the
innocent pa'rty received compensation for the sum of RM63,000.00 that he had
already paid to the defendant as part purchase price. The law should be able
to safeguard the interest of the plaintiff, the non-defaulting party. It
would in my view be wrong and would give rise to injustice to allow a
developer, who failed to deliver vacant possession within the stipulated
period in an agreement where time is of the essence, go scot-free and off
the hook without compensating the purchaser who has already paid to the
developer part of the payment towards the purchase price. That would enable
the developer to gain advantage or benefit of its own fault. One of the
benefits which the defendant, the defaulting party had received under the
SPA, was the payment of the 20% of the purchase price. So I was satisfied
that the defendant's appeal in enclosure 33 was without merit and
unsustainable. To my mind, the learned deputy registrar had rightly
exercised his judicial discretion in awarding the damages in the sum of
RM63,985.00 to the plaintiff. It had not been shown to me that the
discretion of the learned registrar had been exercised on a wrong principle
and should have been exercised in a contrary way or that there had been a
miscarriage of justice. (See:
Vasudevan v Damodaran & Anor[1974] 1 LNS 185 [1981] 2 MLJ 150).
In the result, for the reasons already given, the appeal in enclosure 33
was dismissed with costs. The order of the learned deputy registrar was
quite right and I affirmed it. |