EU SIM CHUAN V. KRIS ANGSANA SDN BHD
HIGH COURT MALAYA, KUALA LUMPUR
[CIVIL SUIT NO: S2(S5)-22-432-1997]
AZMEL MAAMOR J
22 OCTOBER 2006
JUDGMENT
Azmel Maamor J:
[1] In this case, the plaintiffs, who are husband and wife, are
the owners of a property at No. 290A, Lorong Palas, Off Jalan Ampang, 50450
Kuala Lumpur on which is constructed a double storey bungalow house (the
said property). The property is registered in the name of the wife (the 1st
plaintiff) but the purchase of the said property was wholly financed by the
husband the second plaintiff (PW1). Needless to say that the second
plaintiff has beneficial interest of the said property. Both husband and
wife had been living together in the said bungalow house together with their
children until it was damaged by the defendant which led them to bring this
action against the defendant.
Facts Of The Case
[2] Sometime in early March 1997 the defendant began to develop
the land immediately adjacent to the said property to construct two 20
storey condominium blocks. Part of the initial works carried out by the
defendant were piling activities for the construction of basement carparks
which involved excavation and removal of soil. Such activities had caused
movement and settlement of the underground soil which in turn caused damages
to the plaintiffs' bungalow house which developed cracks in various parts of
the building including the compound of the said bungalow. What had caused
the cracks to the said bungalow house was not seriously disputed. In
addition to the evidence of PW1, PW4 and PW5 the cause of cracks to the
plaintiffs' bungalow house was also admitted by DW1, an engineer who had
inspected the plaintiff's bungalow house.
[3] There do not appear to be any action taken by the defendant in
the form of any precautionary or preventive steps and measures before
commencing works on excavation and removal of soil, to ensure that no damage
would be caused to the said bungalow house. None of the 4 witnesses called
by the defence gave any evidence on that issue. Only when cracks had
appeared in the plaintiffs' bungalow after the defendant had commenced
excavation works that the defendant began to get his workers to inspect the
damages to the plaintiffs' bungalow. Yet the defendant continued with its
activities and only forced to stop activities for a while on being given
stop work order by Dewan Bandaraya Kuala Lumpur. Because the cracks
continued to get worse due to the fact that settlement of the underground
soil had not fully stabilised the plaintiffs and their family, on the advice
of their engineer, vacated the said bungalow house to stay in another house
for fear of their safety. On inspection by the plaintiffs' engineer the
bungalow had suffered structural damages particularly the existence of
cracks on the floor area, the walls, column and beam.
Issue Of Negligence
[4] In this action the plaintiffs alleged that the defendant had
been negligent in carrying out the construction works adjacent to their
bungalow house. Para 7 of the plaintiffs' statement of claim stated 7 acts
of negligence of the defendant namely:
(a) Gagal untuk menjalankan sebarang atau apa-apa penyiasatan tanah
yang cukup sebelum memulakan kerja pembinaan termasuk kerja cerucuk;
(b) Gagal untuk mengambil apa-apa langkah yang cukup untuk keselamatan
penghuni/hartanah yang bersempadan dengan kawasan pembinaan;
(c) Gagal untuk memberhentikan dan/atau menangguhkan kerja-kerja
cerucuk/pembinaan walau pun mempunyai pengetahuan mengenai kerosakan yang
ditimpa hartanah tersebut dengan keadaan yang merbahaya kepada jiwa dan
keselamatan Plaintif serta penghuni-penghuni Hartanah tersebut;
(d) Gagal untuk mengamalkan taraf kejuruteraan yang sewajarnya dalam
projek pembinaan tersebut;
(e) Gagal untuk memberi sebarang perhatian atau memberi perhatian yang
secukupnya terhadap amaran-amaran yang diberikan oleh Plaintif;
(f) Gagal untuk mementingkan keadaan Hartanah tersebut dan
penghuni-penghuni yang mendiami rumah-rumah yang bersempadan dengan
kawasan projek tersebut;
(g) Menjalankan kerja-kerja cerucuk/pembinaan dengan cara yang tidak
professional, tidak munasabah tanpa jagaan, perhatian dan kemahiran yang
sewajarnya dan tidak langsung menghiraukan kepentingan orang lain,
khususnya pihak Plaintif.
[5] As the cause of the damage to the plaintiffs' bungalow had not
been disputed and in fact admitted by the defendant the only issue to be
determined is whether there was negligence on the part of the defendant in
carrying out the construction work that led to damages caused to the
plaintiff's bungalow. To do this I need to examine the evidence as regards
the actions of the defendant before commencing the construction works.
According to the evidence of PW1 the defendant only contacted the plaintiff
to request for permission to install "ground anchors" into the plaintiffs'
property to secure the construction on the site. The action was not for the
benefit of the plaintiffs but was in fact done for the benefit of the
defendant's activities. Nothing appeared to have been done by the defendant
to ensure that the said bungalow house would not be damaged by the
activities carried out by the defendant. As the plaintiff had alleged that
the defendant had been negligent in carrying out the construction activities
particularly the excavation and removal of soil from the site it is
therefore incumbent upon the defendant to show that it had done all the
necessary steps to ensure that the plaintiff's bungalow at the adjacent
property would not be damaged. No evidence had been given by any of the 4
witnesses called by the defence.
[6] The plaintiffs had called two engineers (PW4 and PW5) to give
evidence as regards the cause of the damage to the plaintiffs' bungalow.
[7] Purnam Singh (PW4), a practicing engineer, in his statement
said, as regards the most probable causes of the defects to the plaintiffs'
bungalow:
Where buildings, roads or underground services are close to an
excavation the effects of these structures of movements due to excavation
and the construction of adjacent facilities need to be carefully assessed.
The present case of the existing bungalow which is considered close to the
on-going construction of the proposed two blocks of twenty-storey
condominium blocks may be analysed keeping in mind the following:
(i) the possible effects of pumping ground water from excavation can
cause settlement of the ground surface around the excavation.
(ii) settlement surrounding excavated basements may cause settlement
sufficient to cause structural damage to buildings near the excavation
and cracking of drains, perimeter fence and other underground services.
In deep basement excavations, supported by sheet piling system
settlement may be caused by:
(i) a fall of the original water table level surrounding the
excavation due to pumping during construction;
(ii) loss of soil due to erosion and washout of fines;
(iii) possible lateral movements due to elastic deflection of
sheeting members, walings and struts or anchors which support the
surface.
[8] PW4 went on to state his professional conclusion as to the
cause of the damage:
Based on the monitoring results obtained between the first visual
survey of June 1997 and the last survey of December 1997, it can be
conclusively established that the damage to the property in question is
related to the on-going construction works in the adjacent property.
According to interviews with Mr. Jagjit Singh and Mr. Lim Chooi Kui, (PW3
and PW1 respectively), the first signs of damage to the property concerned
were during the piling works in the adjacent property ie, the construction
of the two 20-storey condominium blocks.
It is my conclusion therefore that the cause of damage/defect to the
Property must be due to the ongoing works on the site adjoining the
Property.
[9] Hence in the light of the clear cause of action alleged by the
plaintiff against the defendant for negligent acts particulars of which had
been enumerated in para 7 of the statement of claim the defendant should
prove to the satisfaction of the court that it had taken all the necessary
steps and measures to prevent possible damages to said bungalow adjacent to
the defendant's construction site. No such evidence had been adduced by any
of the defence four witnesses.
[10] Nonetheless the defence counsel submitted that the defendant
could not be held liable for the damages caused to the plaintiffs' bungalow.
He based his argument on the authority of a 19th century case of Acton v.
Blundell [1843] 152 ER 1223. The facts of this case were that the
plaintiff sunk a well in his property for raising water for the working of
his mill. Subsequently, the defendant sunk two coal pits in his land
adjacent to the plaintiff's property. The result was that the supply of
water to the plaintiff's mill was considerably diminished and the plaintiff
sued the defendant for interference with his right of enjoyment over the
water flowing under his land. It was ruled by the court that a man may
abstract water under his land which percolates in undefined channels to
whatever extent he pleases, notwithstanding that this may result in the
abstraction of water percolating under the land of his neighbour and,
thereby, cause injury to him
[11] This principle was adapted by the Singapore case of
Singapore Finance Ltd v. Lim Kah Ngam (Singapore) (Pte) Ltd. and Eugene HL
Chan Associates (Third Party) [1984] 1 LNS 3; [1984] 2 MLJ 202. In this
case the defendants were in the course of erecting a 13-storey building and
passed sheet piles surrounding their land. During that period the owners of
building in the neighbourhood complained that cracks appeared on their
building.
[12] The defendant contended and admitted that ground de-watering
of the plaintiffs' soil had been caused by the defendants excavation works,
but the defendant maintained that such de-watering, that is the flow of
water from the defendants' soil into the excavation hold through
indeterminate or undefined channels, was due to the forces of nature and the
forces of gravity and was neither avoidable nor was it due to any positive
acts done by the defendant their servants or agents. The defendant contended
that the damage to the plaintiffs' building was damnum sine injusia
(damage without legal injury). The court dismissed the plaintiffs' claim.
[13] However there was a subsequent case in Singapore which ruled
the principle of Acton v. Blundellto be no good law to be applied to
modern Singapore and therefore should not be followed. It is the case of
Loh Siew Keng v. Seng Huat Construction Pte. Ltd. [1998] SGHC 197. In
this case the defendant carried out certain sewerage works which included
replacement of an underground sewer line adjacent to the plaintiff's house.
The plaintiff brought an action for negligence and nuisance arising from the
defendant's excavation of the trench next to the plaintiff's house as cracks
penetrated the walls on the 1st and 2nd floor of the plaintiff's house as
well as a continuous crack line on the external floor and at other parts of
the house.
[14] In his judgment Chan Seng Onn JC gave his view on the ruling
of Acton v. Blundell:
The result then is that I have to consider whether the Singapore Courts
should adapt the rule in Acton v. Blundell as a matter of choice.
On careful consideration, I came to the conclusion that it should not be
the law of Singapore. With respect I found myself unable to agree with Lai
Js decision on this point. In Acton v. Blundell the Plaintiff
complained of being cut-off from the water caused by the Defendant's
action; it was not a claim of physical damage to his land caused by loss
of support.
... I do not think that the rule in Acton v. Blundellcan be
justified today. It may be that in old England, the courts had to take
into account the rights of the landowners to extend water percolating
underground for drinking purposes and farmland irrigation. Even if soil
subsidence of adjacent land resulted, I do not think the damage, if any,
would be significant. I think that the rule is clearly ill adopted to
conditions in Singapore, where many areas are densely built up, with
adjacent building very close to, if not adjoining each other, and where
there is hardly anymore open land farming activities being carried out.
Drinking water is no longer drawn from wells sunk into the ground. Water
is supplied by an extensive system of water pipes to distribute water to
all who need it. ... I am not inclined to follow Acton v. Blundellbecause
there is insufficient consideration given to the rights of adjacent
landowners. One has to balance the rights of the landowner to support and
the proprietary right to exploit one's land eg, the right to pump water.
... To conclude that those who abstract percolating water have an
unbridled licence to wreak havoc on their neighbours would be harsh and
entirely out of keeping with the law of torts as it exist today.
[15] I am in full agreement with the views expressed by Chan Seng
Onn JC in the Singapore case of Loh Sim Keng (supra). The drastic
change in the living style of people since ancient England in the 19th
century to those in the 21st century would require a change in the
application of the law. Principles of law that are archaic as the one
propounded in Acton v. Blundell should no longer be applied to modern
society like Kuala Lumpur where, like Singapore, buildings are very close to
each other. And, as observed by Chan JC, drinking water are no longer
obtained from wells. The modern society are supplied with pipe water to
their houses. Hence the factor that one has to bear in mind in doing any
construction works in one's land is to ensure safety and security of one's
neighbour's property especially the house the neighbour lives in. Reasonable
steps and measures must be taken to ensure no damage would cause to one's
neighbour's house before commencing any construction works. Failing to take
such precautionary measures before commencing such construction works would
render one to be actionable for the tort of negligence.
[16] In the instant case in order for the defendant to escape
liability for the tort of negligence the defendant must show sufficient
evidence that it had taken the necessary steps and measures to ensure no
damages were done to the plaintiff's bungalow located immediately adjacent
to the defendant's work site. Having regard to the activities carried out at
the site which included piling works and excavating and removing of soil
that caused damages to the plaintiffs' bungalow the defendant could not and
should be heard to say that it is not liable for the damage to the
plaintiff's bungalow. It is a common knowledge that whenever any activities
of sheet piling, excavating and removal of soil are carried out in any area
it would cause movement of the water level of the land in the surrounding
area. The likely consequence would be that any building constructed on the
neighbouring land would develop cracks depending on the degree of the
piling, the excavation and removal of soil activities being carried out. A
developer like the defendant who employs engineers for carrying out such
construction works must be fully aware that the activities it carried out at
the work site would likely cause damages to the plaintiffs' bungalow house
and should therefore take the necessary steps to prevent damages to the
plaintiffs' house.
[17] But the defendant in the instant case chose not to take any
such preventive measures before commencing the construction works of sheet
piling, excavation and removal of soil. There it is of no surprise that the
defendant's activities had caused major damages to the plaintiffs' bungalow.
[18] The damages to the plaintiffs' bungalow that had been caused
by the activities are so severe that on the advice of the plaintiffs'
engineers it was no longer safe for the plaintiffs to continue to stay in
the house. Not only major and minor cracks to the building had developed the
electrical system had also failed and the water supply had also been
adversely affected due to the damages to the walls where the electrical and
water systems were hidden. It was my finding that the bungalow was no longer
safe for habitation. The plaintiffs were quite right in deciding to vacate
the house for fear of their safety and convenience.
[19] In the light of the facts and circumstances as I have
mentioned above I found the defendant liable for negligence for its failure
to take any reasonable preventive measures to ensure that no damages would
be caused to the plaintiffs' bungalow before commencing its construction
works at the adjacent site.
Issue Of Quantum
[20] After having ruled that the defendant was liable for
negligence I proceeded to hear witnesses from both parties as regards the
issue of quantum of damages payable by the defendant to the plaintiff. The
plaintiff called 5 witnesses some of whom had given evidence earlier when
the case proceeded on determining the issue of liability. The defendant
called 3 witnesses. I also asked counsels for both parties to give their
written submissions. Based on the evidence adduced and submissions of both
counsels before me I arrived at the decision on quantum on the various items
claimed by the plaintiff as follows.
1. Expert and Consultation Fees
I find the plaintiff's claim under this Item is legitimate. And the
amount claimed is reasonable. However the total fees of the engineers,
the valuers and the quantity surveyors should be RM43,828.85 instead of
RM44,828.85.
2. Rental
The plaintiff's claim for rental at the premises No. 1B, Gerbang
Ampang Hilir, 55000 Kuala Lumpur and No. 7. Taman U Thant Dua, 55000
Kuala Lumpur is legitimate. It is also legitimate for the plaintiff to
claim rental charges while staying at No. 1B, Gerbang Ampang Hilir even
though the property was subsequently purchased by the plaintiffs' family
company. The plaintiffs are only claiming the rental and not the
purchase price of the property. The rental of RM12,000 per month is fair
and reasonable, taking into consideration that the rental of the same
premises before purchased by the plaintiff was RM14,000 per month. In
addition, the said premises had been renovated by the plaintiff which
would give an added value to it. The total claim for rental allowed is
RM1,230,246.58.
3. Watchman/Guard Wages
The claim under this item is legitimate. It is only fair for the
plaintiff to employ a watchman of the damaged and unoccupied premises
since the plaintiffs and their family were not staying there, so as to
avoid any vandalism or theft to it. The amount claimed is reasonable. I
allow the claim of RM88,000 under this item.
4. Cost Of Demolishing And Rebuilding Of Property
I agree that based on the facts and circumstances of this case it
would not be safe to continue to stay in the said property. Doing repair
works to the existing building may not be feasible under the
circumstances. I agree with the opinion of plaintiff's expert witness
that it would cause the plaintiff much more if repair works are done
instead of demolishing and rebuilding it. The nature of the soil would
require drastic foundation works to be carried out with proper
reinforcement. The amount of claim for demolition and rebuilding is in
my view fair and reasonable. I therefore allow the claim for RM3,393,167
under this item.
5. Cost Of Moving Back Into The Property
This item is indisputable and the amount claimed is also reasonable.
I therefore allow the claim of RM50,000 under this item.
6. Loss In The Value Of Property
I am inclined to disallow this claim for loss in value of the
property. The subject property has not been sold. Hence the actual loss
has not been realised. As I have allowed the claim for rebuilding the
property it would not be legitimate to claim for any loss in the value
of the property.
7. Theft Of Items From Property On 27 October 1998
I am also not in favour of allowing this item. At the time of theft
the premises was being guarded by the watchman. He did not see the
people entering the premises. It must be due to his negligence that the
Items were stolen.
8. General Damages For Mental Distress, Hardship etc
There are ample evidence that the damage to the property had caused
severe mental distress and hardship to the plaintiffs thereby resulting
in the health conditions of the 2nd plaintiff to deteriorate
drastically. The whole members of the plaintiffs' family had faced great
hardship, getting transferred from one house to another. The 1st
plaintiff, who had personally supervised the construction of the house,
must be feeling very painful and sad to see the house being damaged due
to the acitivities carried out by the defendant. I allow the claim of
RM1,000,000 under this Item.
9. Aggravated And/Or Exemplary Damages Against The Defendant For Their
Conduct In The Matter
On the facts of this case it is quite obvious that the cause of
damage to the plaintiff's property was due to the excavation works
carried out by the defendant at the site adjacent to the plaintiffs'
bungalow. And the damage began to appear during the excavation works
carried out by the defendant. The matter could have been easily settled
if at that time the defendant were to admit liability and agree to do
the necessary repair and ratification works as well as necessary
preventive measures. The defendant refused to admit that they were
liable for its action. Instead the defendant preferred to wait for the
plaintiff to bring court action knowing that this would take years to
complete. The longer the delay the more advantageous would it be to the
defendant. As for the plaintiffs, the longer the delay the more painful
would be their sufferings. This is how the defendant in this case
actually behaved. In addition to that having considered the proximity of
the plaintiffs' property to the excavation site, adequate tests and
precautionary measures should have been taken by the defendant to ensure
that the foundation of the plaintiff's property would not be affected by
their excavation activities. The defendant should have determined the
type of foundation on which the plaintiff's house was constructed
vis-a-vis the nature of the soil found there, and then to take
appropriate steps to ensure that the plaintiff's property would not be
damaged. No such tests or any preventive measures were carried out by
the defendant on the plaintiff's property. Any reasonable person, more
so a developer of the defendant's standing, would have foreseen the
consequence of the excavation works on the plaintiffs' property. This
clearly indicates couldn't care less attitude of the defendant which is
most uncalled for. The sole concern of the defendant was to quickly
complete the construction and reap as much benefits with the minimum
amount of costs incurred. It is a very selfish attitude most undesirable
in a community we Malaysians are used to. The behaviour and attitude of
developers towards their neighbours have been so degrading that
appropriate authorities should take necessary steps to check their
activities to ensure that their neighbours are not adversely affected.
In the light of such behaviour and attitude of the defendant towards the
plaintiff, I allow the claim for aggravated and/or exemplary damages
against the defendant in the sum of RM500,000.
[21] I thereby allowed the plaintiff's claim for damages in the
sum of RM6,306,242.43. I award interest at the rate of 8% p.a. on the amount
awarded from the date of filing of this suit to the date of realisation. I
order that the costs of this action be paid by the defendant to the
plaintiffs. |