CHUNG MAY YEN V. PUNCAKDANA
DEVELOPMENT SDN BHD
HIGH COURT MALAYA, KUALA LUMPUR
AZMEL MAAMOR J
[ORIGINATING SUMMONS NO: S6-24-1604-2001]
20 SEPTEMBER 2002
Contract: Housing
development contract - Breach - Delay in delivering vacant possession of
property - Whether caused by relevant authorities - Defence of waiver -
Whether defendant entitled - Whether purchaser entitled to terminate
agreement
Land Law: Housing developers - Sale and purchase agreement -
Non-delivery of vacant possession - Whether delay caused by relevant
authorities - Whether plaintiff waived right to terminate agreement -
Whether plaintiff entitled to terminate agreement
JUDGMENT
Azmel Maamor J:
By way of an originating summons the plaintiff made an application
seeking answers to the following questions:
1. Whether the plaintiff is entitled to terminate the sale and
purchase agreement in respect of property under Lot No. KKBP1-24,
D'Tinggian Nusa, Kuala Kubu Bahru, Selangor entered between the
plaintiff and the defendant;
2. Whether the defendant is obliged to refund all monies paid by the
plaintiff to the defendant; and
3. If the answers to (a) and (b) are in the affirmative, whether the
defendant is obliged to pay interest on the amount to be refunded to the
plaintiff.
The brief facts of the case are as follows. On 24 October 1996 the
plaintiff entered into sale and purchase agreement with the defendant in
respect of the purchase of a property known as Lot No. KKBP1-24 Kuala Kubu
Bahru, Selangor (the said property). Section 6.04 of the said agreement
stipulates that delivery of vacant possession of the said property to the
plaintiff would be made within 36 months of the signing of the said
agreement, that is on or before 23 October 1999.
Payments in respect of the said property were to be made progressively
in accordance with the 3rd schedule of the said agreement. At the request
for payment by the defendant the plaintiff had so far paid a sum of
RM52.801.95 being the amount for the first five progress payments. No
subsequent progress payment were requested by the defendant. On 23 October
1999 the defendant failed to deliver vacant possession of the said
property to the plaintiff. On 25 May 2000 the plaintiff gave notice of
termination of the said agreement to the defendant. But the defendant
refused to accept the termination of the agreement by the plaintiff.
Almost a year later, on 15 May 2001 the plaintiff commenced this action in
court against the defendant.
The main issue to be determined in this case is whether the plaintiff
had lawfully terminated the said agreement. In disputing the plaintiffs
claim the defendant raised the following defences. Firstly, the defendant
argued that it had not committed any breach of the said agreement. The
defendant claimed that the delay in delivering vacant possession was due
to the delay on the part of the relevant authorities approving the
followings:
(a) delay in securing approval for water supply;
(b) delay in approval of electricity supply;
(c) delay in securing approval for sewerage treatment plant and
piping.
The defendant invoked s. 9.03 of the said agreement, which states:
Section 9.03 Circumstances beyond the Vendor's Control
Notwithstanding any provisions hereinafter contained to the contrary
(if any) it is hereby expressly agreed by the parties hereto that the
Vendor shall not be liable to the Purchaser for any failure on its part
to fulfil any term of this Agreement if such fulfillment is delayed,
hindered or prevented by circumstances beyond the control of the Vendor
including but not limited to force majeure, acts of God, civil
commotion, acts of war, strike or combination workmen, lockout riot,
inclement weather, loss or damage by fire, flood or tempest, delay or
refusal by the Authority to grant any necessary function or approval or
in completing their work in the said Lot other circumstances of whatever
nature beyond the control of the Vendor.
On this ground of defence the plaintiff contended that it was not true
at all that the relevant authorities had caused any delay in giving their
respective approvals. The plaintiff contended that in the case of the
approval from the Jabatan Bekalam Air, Hulu Selangor, the defendant's
application was made on 31 March 1997 and the approval was given on 7 May
1997. As such the approval was quite expeditiously granted. Based on the
above facts I do agree that there was no delay in giving the approval by
the Jabatan Bekalan Air.
In respect of the approval for electricity supply by the Tenaga
Nasional Berhad the plaintiff alleged that the delay in obtaining the
electricity supply was not the fault of TNB but solely due to the
defendant's failure and/or refusal to get the land ready for electricity
supply works. In her written submission, the plaintiff contended that the
defendant's letter dated 17 September 1999 clearly showed that the
defendant and/or its agent's had applied for electricity supply, and the
related reticulation works, to be carried out in April or May 2000. By a
letter dated as late as 25 May 2001 the defendant admitted to only making
payment of the requisite "kos sambungan" on 17 April 2000. This is way
past the date of delivery of vacant possession of the said property. The
chronology of events clearly indicated that notification of readiness of
the defendant's project for electricity supply works and request for
contribution amount (kos sambungan) was only made as late as 17 September
1999. From the above scenario I was quite satisfied that the delay was
caused by the defendant's failure to have the said project ready for
electricity supply works. The delay was not caused by TNB.
In respect of the defendant's allegation of delay in getting the
approval of the sewerage treatment plant plan by Jabatan Perkhidmatan
Pembentungan Kuala Lumpur (JPP) it was also contended by the plaintiff
that the blame should also fall on the defendant and not on the JPP. The
plaintiff explained that the defendant's consultants had submitted its
plans for sewerage treatment plant five times before approval was obtained
on 18 May 2001. The approval had been previously rejected because the
application was not in conformity with the earlier planning approval by
JPP dated 20 June 1997. I was therefore quite satisfied that the delay in
obtaining the approval was due to the defendant's own faults and no blame
should be made against the JPP.
I also wish to point out that if it is true that the said project was
delayed by reason of the occurrence of any event as mentioned in s. 9.03
of the said agreement it would be incumbent upon the defendant to apply
for extension of time to complete the said project to the housing
development department. On legitimate reasons the said department would
allow an extension of time to the defendant to complete the project. In
this case I was unable to see any evidence adduced indicating that such
extension of time had been applied and granted by the said department. In
the absence of such extension of time being granted it must be assumed
that the date of the delivery of vacant possession of the said property
remained the same, that is 23 October 1999.
The 2nd ground relied upon by the defendant was the issue of waiver.
The defendant contended that because the plaintiff did not issue notice of
termination immediately after the date for the delivery of vacant
possession of the said property, the plaintiff had therefore waived her
rights to terminate and as such time would no longer become the essence of
the contract. In support of such contention the defendant relied on the
Court of Appeal case of Hock Huat Iron Foundry v. Naga Tembaga Sdn Bhd[1999]
1 CLJ 89, where YA NH Chan JCA said:
When time is no longer of the essence of the contract and no time for
performance is specified, s. 47 allowed the promise to be performed
within a reasonable time. If there has been unnecessary delay by the
party, the other may give him a notice fixing a reasonable time at the
expiration of which he will treat the contract as at an end.
The plaintiff disputed the defendant's contention that the plaintiff
had waived her right to terminate. However, even assuming that she had
waived her rights the defendant had not done anything between the time she
gave notice of termination to the time she filed this action in court.
The date of delivery of vacant possession was 23 October 1999. The
plaintiff issued notice of termination to the defendant on 25 May 2000.
The defendant disputed the notice and said that the plaintiff had no right
to terminate the said agreement. Subsequently on 15 May 2001 the plaintiff
filed this action in court. Up to this date the defendant had not
completed the works on the said project and had not given any notice to
the plaintiff giving delivery of vacant possession of the said property.
The question that is required to be determined is whether the defendant
is entitled to the defence of waiver in this case. It was contended by the
plaintiff that she had evinced her intention to terminate the said
agreement by sending the letter dated 25 May 2000 to the defendant and
even though the defendant refused to accept the plaintiff's termination of
the said agreement it had knowledge that the plaintiff would take steps to
terminate the said agreement. Hence when the plaintiff filed this action
on 15 May 2001 reasonable time had been given to the defendant to effect
delivery of vacant possession of the said property but the defendant
failed to do so.
In this particular case the plaintiff had issued notice to terminate on
25 May 2000 when contractually the delivery of vacant possession should be
on 23 October 1999. The defendant disputed the plaintiff's rights to
terminate the said agreement. Subsequently the plaintiff filed this action
on 15 May 2001. From the time notice of termination was issued to the time
the plaintiff filed this action in court the defendant still could not
deliver vacant possession of the said project to the plaintiff. In my
view, even though no specific time for delivery had been stated by
plaintiff to ask the defendant to deliver vacant possession, the period of
almost one year was more than sufficient to be given to the defendant to
deliver vacant possession. The period of one year is equivalent to
one-third of the total contract period for the defendant to deliver vacant
possession. It would be most unfair and unjust to allow the defendant to
complete the works eternally. In my view on the peculiar facts of this
case the doctrine of waiver as applied in the case of Hock Huat Iron
Foundry (infra)could not be applied in this case. I find the defendant
in this case guilty of inordinate delay without giving any valid reason to
complete the works on the said project after a notice of termination of
almost 12 months had been issued. In this case if the defendant had
delivered vacant possession of the said property before the plaintiff
filed this action, I would not have decided in favour of the plaintiff.
In the light of the circumstances as I have discussed above, the answer
to the question posed by the plaintiff are as follows:
1. Under the circumstances of this case the plaintiff is entitled to
terminate the said sale and purchase agreement;
2. The defendant is obliged to refund all monies paid by the
plaintiff to the defendant; and
3. Interest at the rate of 8% per annum be paid by the defendant to
the plaintiff from the date of notice of termination to the date of
realisation.
I also ordered that the costs of this action be paid by the defendant
to the plaintiff
|