ARCHLAW DEVELOPMENT SDN BHD V.
SAW EWE LEONG
HIGH COURT MALAYA, PENANG
[ORIGINATING SUMMONS NO: 22-298-2002]
RK NATHAN J
16 OCTOBER 2002
JUDGMENT
RK
Nathan J:
Facts
The plaintiff is a housing
developer and was at all material times developing a housing project known
as Rumah Pangsa Kos Rendah on Lots 1518, 1521, 816 and 824, Mukim 12, S.W.D.,
Daerah Barat Daya, Permatang Damar Laut, Pulau Pinang.
Plaintiff's Case
It is the case of the plaintiff
that the defendant had at all material times agreed to undertake the task of
Consultant Mechanical and Electrical Engineering, in the most professional
manner. The plaintiff accepted the defendant in that capacity by a letter
dated 12 December 1995 and appointed him the Project Consultant for
Mechanical and Electrical Engineering Works. The plaintiff contended that it
was a term of the agreement between the parties that the defendant's work in
relation to the said project included works relating to:
(A) Electrical & Telephone
1) Internal Lighting
Distribution System
2) Internal Telephone
Distribution System
3) External TNB
Infrastructure
4) External Telecom
Infrastructure
5) Street Lighting &
Compound Lighting
6) Stanby Genset System
7) MATV
(B) Fire Protection System
(C) Lifts
The defendant also undertook the
following duties:
1) to investigate available
data for information relating to the project and which are relevant to the
works and collaborating with other professional advisers appointed by the
client.
2) to negotiate and arrange
for incoming electrical supply from Tenaga Nasional Berhad.
3) to liaise with the fire
department regarding fire fighting requirements and obtaining approval.
4) to liaise with telecoms
regarding telephone lines and obtaining approval.
5) to prepare and draw up such
designs, drawings and specifications as may be necessary for placing
contracts for the execution of the works. These drawings are the 'tender
drawings' to be completed in such detail as to enable competitive tenders
to be obtained.
6) to examine and report on
tenders or estimates and advising the acceptance by the client of any
tender.
7) to provide periodical
supervision of the installation and administration of the contract.
8) to obtain clearance for O.C./C.F.
The plaintiff pleaded that it
was also a term of the said agreement that the plaintiff would pay the
defendant 3% of the total mechanical and electrical costs upon completion of
the said project. It is the plaintiff's case that the defendant breached the
terms of the said agreement and as a result of which the plaintiff was
unable to complete the project on time and thereby suffered loss. For the
purposes of the present issue before me there is no need to reproduce the
numerous breaches the plaintiff had enumerated in the statement of claim.
One of the major complaints of the plaintiff related to purchase and
installation of the lifts. The plaintiff contended that the defendant had
failed to prepare or with due care to prepare the tender documents relating
to the 'lift contract' so that competitive tenders could be proceeded with
as agreed in cls. 5 and 6 of the said agreement. The plaintiff also accused
the defendant of failing to call for tenders relating to the lift contracts
relating to the purchase and installation of the said lifts. Because of the
defendant's breaches the plaintiff had to on its own, accept an offer from
one Harden Elevators Sdn. Bhd (Harden) for the sale and installation of the
said lifts. Various other particulars of breaches were leveled against the
defendant for failing to supervise and advice the plaintiff in respect of
the works carried out by Harden. Because of the shoddy works of Harden in
the installation of the lifts, the plaintiff was forced to terminate the
contract with Harden. The plaintiff was then forced to look for a fresh
supplier to supply and instal new lifts and this the plaintiff contended
hampered its project further. Further, the plaintiff contended that the
defendant failed to arrange for the mandatory inspection by the Fire
Department, the Machinery Department, the Telecoms Department, Tenaga
National Berhad, in relation to the installation of the said lifts. The
defendant had also failed to obtain the letter of clearance pursuant to cl.
8 of the said agreement. As a result of all the above professional
misconduct of the defendant, the plaintiff contended that it sustained loss
by not completing the project in time and thus had to answer to the
purchasers as the certificates of fitness were delayed.
The plaintiff was however
surprised that notwithstanding all these breaches on his part, the defendant
had sent the plaintiff a s. 218 Companies Act 1965notice claiming a sum of
RM35,777.21 being his fees for professional services rendered. The plaintiff
however disputed the said sum. The plaintiff also contended that the
defendant had not shown that the plaintiff did not intend to pay the said
sum if it became due. The plaintiff however made an offer to settle the
defendant's claim without first verifying the claim by three instalments on
condition the defendant instructed its solicitors to withdraw the impending
action. However when the plaintiff subsequently verified the defendant's
claim, the plaintiff realised that the defendant had failed to take into
account the sums due to the plaintiff from the defendant.
The plaintiff contended that
serving such a notice based on the facts so far available, clearly meant
that the defendant was pressuring the plaintiff and forcing it to submit to
the demands of the defendant and to pay the sum which the plaintiff
contended the defendant was not entitled to. As the plaintiff would suffer
irreparable damages to its reputation as a developer if the defendant was
allowed to proceed to present the winding up petition, the plaintiff sought
an injunction to restrain the defendant from filing the winding-up petition.
Having filed the writ the plaintiff then took out an ex partesummons
in chambers with an affidavit in support (encl. 3) and prayed for the
following orders:
1. An injunction to restrain
the defendant or his servants or agents from presenting a winding-up
petition under s. 218 of the Companies Act 1965in respect of a sum of
RM35,777.21 which he had claimed pursuant to a s. 218 notice dated
15.5.2002 and which was received by the plaintiff on the same day.
2. That in the event such a
petition had been presented then the defendant or his servant or agents
be prevented from proceeding with the said petition by advertising the
said winding up proceedings until the said writ filed herein be heard
and a decision given.
3. Costs.
4. Such further or other
relief that this Court would deem fit and proper.
I heard the ex partesummons
and granted an order in terms and fixed a date for the hearing of the
inter partes. At the hearing of the inter partes, the plaintiff
contended that because of the defendant's breaches it had to pay 392
purchasers various sums for late delivery and that the said payments
totalled to about RM4 million. The plaintiff contended that he was still in
the process of settling with the various purchasers. The plaintiff argued
that whilst the defendant was aware of these facts, the defendant had with
mala fidesserved the s. 218 notice on the plaintiff for a mere
RM35,777.21. The plaintiff averred that it was solvent and was still
carrying on housing development projects. The plaintiff exhibited its
Housing Development Account which is a mandatory account it has to keep
pursuant to s. 7A of the Housing Developers (Control and Licensing) Act
1966which reads as follows:
(1) Subject to subsection (9),
every licensed housing developer shall open and maintain a
Housing Development Account with a bank or finance company for each
housing development undertaken by the licensed housing developer .
In the account the plaintiff
showed that it had a sum of RM907,947.03 as of April 2002. The plaintiff
contended that the defendant's action in seeking to wind-up the plaintiff
was malicious and an abuse of the process of the court. The plaintiff
pointed out that since it has a running account in relation to this
development pursuant to s. 7A of the Housing Developers (Control and
Licensing) Act 1966, any attempt to wind-up the plaintiff over such a small
sum would cause much mischief and disrupt the plaintiff's business. The
plaintiff argued that its credit-worthiness and reputation would be
tarnished by a winding-up petition and that such an act would cause
irreparable loss to its reputation which cannot be compensated with damages.
The plaintiff therefore urged the court to maintain the injunction until the
hearing of this suit.
Case For The Defence
At the outset the defendant
raised a preliminary objection in its affidavit in reply by stating that
there was no personal service. The defendant argued that the plaintiff could
not apply to restrain him from filing a winding-up petition pursuant to s.
218 of the Companies Act 1965. Referring to the letter written by the
plaintiff in which the plaintiff agreed to pay the said sum in three monthly
instalments, the defendant contended that the plaintiff had in fact admitted
to the debt. Denying that he had breached any of the terms of the agreement
the defendant contended that his claim was made bona fide. The
defendant expressly admitted that his fees of 3% of the "total Mechanical
and Electrical Cost," was to be paid upon completion of the entire project.
The defendant also specifically
denied that it was his duty to call for tenders in respect of the project
works and for the purchase and installation of the lifts. His job was merely
to provide designs, drawings and specifications, when called upon to do so
called "tender drawings". He contended that because the plaintiff had failed
to pay the initial contractors for the purchase and installation of the
lifts and the said initial contractors having ceased to complete the works
relating to the lifts, the plaintiff was thus compelled to retain the
services of Harden. The defendant maintained that he had always acted
professionally. He also averred that it was possible that because the
plaintiff had failed to pay Harden, Harden too must have therefore
terminated its services. As for the delay in the completion of the project
the defendant averred that the said delay was occasioned by the plaintiff's
own carelessness in failing to make prompt payments to the various
contractors in respect of the installation of the lifts. The defendant also
averred that the reason the plaintiff had to pay compensation to the
purchasers for late delivery was because of the plaintiff's own negligence.
The defendant also contended that the plaintiff ought to have exhibited its
bank statement to show its solvency. The defendant also averred that the
Housing Development Account was a client's account and that the plaintiff
had no access to it.
The Plaintiff's Reply
In reply the plaintiff averred
through its director that when the Court's Process Server attempted to
effect personal service on the defendant, the defendant attempted to run
away and evade service. The Court Process Server's affidavit exhibited
showed that he drew the defendant's attention to the summons and the ex
parteorder and to all other relevant cause papers before leaving it in
front of him. The plaintiff contended that the denial of the defendant of
personal service was scandalous and an affront to the integrity of the
Court's Process Server and thereby affecting the integrity of the court.
Referring to the defendant's
denial that he had breached conditions of his contract by failing to provide
periodical supervision the plaintiff referred to cl. 7 of the said agreement
which specifically required that the defendant do "provide periodical
supervision of the installation and administration of the contract". The
plaintiff argued that it was the duty of the defendant to have maintained
such periodic supervision and by his failure to do so, he had indeed
breached inter aliacl. 7 of the said agreement.
In respect of the defendant's
denial that it was his duty to call for tenders to enable competitive
tendering and thereby enabling the plaintiff to select the most competitive
tenderer, the plaintiff referred to cls. 5 and 6 of the agreement which
state as follows:
Clause 5
Preparing and drawing up such
designs, drawings, and specifications as may be necessary for placing
contractors for the execution of the works. These drawings are the Tender
Drawings completed in such detail as to enable competitive tenders to be
obtained.
Clause 6
Examining and reporting on
tenders or estimates and advising the acceptance by the client of any
tender.
In respect of this the plaintiff
referred to a letter dated 15 June 1996 which reads as follows:
ARCHLAW DEVELOPMENT SDN. BHD.
(Co. No
299022-A)
(Units 3 & 4,
7th Floor Canton Square, 56 Cantonment Road,
10250 Penang)
Tel:
(04)
229-229-0430 Fax: (04) 229-2187)
Your Ref: SAA 95(11/7)
Our Ref: AY/D1/GEN/41/96/PN
Date: 15th June 1996
Messrs Saw & Associates,
318, 1st Floor
Jalan Jelutong
11600 PENANG
BY MAIL
Dear Sis,
RE: INVITING TENDERS FOR
DESA JELITA PHASE I
We refer to your offer letter
dated 7th November 1995 which was duly accepted by us and our appointment
letter dated 14th May 1996. We would be pleased if you could make
available to us a copy each of tender drawings for the various aspects of
the job for our record, as considerable time has been lost and let us know
at least 14 days ahead of time when you intend to invite tenders on our
behalf.
We would like to stress here
the importance of holding the tender exercises early as time is cost to
us.
Yours faithfully
ARCHLAW DEVELOPMENT SDN BHD
sgd. Allan K.L. Yoon
MANAGING DIRECTOR
In respect of the defendant's
averment that it was he who obtained the letters of clearance to enable the
plaintiff to get the Certificates of Fitness for the project, the plaintiff,
whilst denying this, contended that it was the plaintiff's director who had
affirmed the affidavits in support, who personally obtained the letters of
clearance and who had handed the same to the architect. The architect
himself has affirmed an affidavit (encl. 14) to this effect and specifically
denied in that affidavit that it was the defendant who was responsible for
obtaining the letters of clearance. The plaintiff was quick to point out
that it was the duty of the defendant and not its duty to obtain the letters
of clearance. (See item 8 under duties of defendant as stated earlier.)
In response to the defendant's
reference to the letter whereby the plaintiff agreed to settle the sum
claimed by three instalments the plaintiff averred that whilst agreeing to
pay, the plaintiff reserved its right to challenge the veracity of the claim
subsequently. It was the plaintiff's case that it was compelled by
circumstances to agree to pay in the manner suggested, to register its
disagreement on its liability to pay.
In respect of the defendant's
allegation that the "Housing Developers Account" is a client's account, the
plaintiff denied the same and pointed out that the plaintiff is entitled to
withdraw monies from the account for the cost of the project pursuant to r.
7 of the Housing Developers (Housing Development Account) Regulations
1991made pursuant to s. 24 of the Housing Developers (Control and Licensing)
Act 1966. Rule 7 lists 15 grounds under which money from the Housing
Development Account can be withdrawn and it would seem clearly that the
plaintiff would be entitled to withdraw from this account, for the cost of
the project.
The Defendant's Response
In response the defendant now
raised a further new preliminary objection in his affidavit (encl. 16) which
was that the plaintiff had failed to comply with O. 29 r. 1(2A) of the Rules
of the High Court 1980(the RHC). In response to the process server's
affidavit the defendant averred that since the process server was not in
uniform and since he was accompanied by the plaintiff's director and
representative he thought he was going to be assaulted for sending the s.
218 notice and so he ran.
Findings Of The Court
On the date fixed for the
hearing of the inter partes application Cik Kanagavalli for the
plaintiff informed the court that she was only served with encl. 16 a few
minutes before the inter partes hearing. She asked for the matter to
be stood down for her to see if she needed to request for an adjournment to
respond or whether she could proceed without a reply. After a short
adjournment by which time she had read encl. 16 and had taken client's
instructions, she informed the court that she was prepared to proceed with
her inter partes application. Mr Kwang for the defendant then
informed the court that he was not proceeding with the first preliminary
objection of non-personal service. As regard to the second preliminary
objection he contended that the plaintiff had failed to comply with O. 29 r.
1(2), (2A)(c) of the RHC which reads as follows:
Rule 1(2A)(c)
1. (1) xxx
(2) Where the applicant is
the plaintiff and the case is one of urgency such application may be
made ex parte by summons supported by an affidavit but, except as
aforesaid, such application must be made by summons.
(2A) The affidavit in
support shall contain a clear and concise statement:
(a) xxx
(b) xxx
(c) of the facts relied on
as justifying application ex parte, including details of any
notice given to the defendant or, if none has been given, the reason
for giving none.
It was the defendant's
preliminary objection that the plaintiff had not, in its affidavit in
support of the ex parte application, given reasons for not giving the
notice.
The plaintiff contended that
even though it was willing to settle the sum in instalments under protest,
and the defendant having refused to accept the offer of settlement, sending
a notice of its intention to take out the injunction, would have tipped off
the defendant into proceeding to do precisely what the plaintiff did not
want the defendant to do without this trial. The plaintiff also pointed out
that since the defendant had issued out a s. 218 notice which would take
effect exactly 21 days from the date the notice was issued and that any
failure to pay within the 21 days would result in the plaintiff being
forthwith liable to be wound-up, the plaintiff averred that it was urgent
and imperative that it proceeded to get an ex parteorder since the 21
days had expired on 5 June 2002 and the defendant could at any time take out
winding-up proceedings.
I was satisfied with the
explanation given by the plaintiff and held that the plaintiff had
sufficiently complied with O. 29 r. 1(2A)(c) of the RHC.
In any case the said rule
applied to ex parteapplications only. To a question from the court
Mr. Kwang readily conceded that his client had not filed any application to
set aside the ex parteorder. I therefore held that having failed to
apply to set aside the ex parteorder and having filed affidavits in
reply, the defendant was now estopped from relying on O. 29 r. 1(2A)(c) of
the RHCwhich applied to ex parteapplications. Based on this and
together with the fact that I had accepted the plaintiff's explanation, I
rejected the defendant's preliminary objection.
Having read all the affidavits I
then considered whether there were serious questions to be tried since the
plaintiff had averred that notwithstanding its agreement to settle the small
claim of the defendant by three instalments, yet on subsequent perusal and
vetting of the defendant's accounts the plaintiff had discovered that the
amount demanded is neither in fact nor in law payable.
Serious Questions To Be Tried
The facts narrated clearly show
that there are serious questions of facts in dispute. The main issue relates
to the purchase and installation of lifts. It is the plaintiff's case that
it was the duty of the defendant as the expert in the mechanical and
engineering field to provide designs, drawings and specifications called
tender documents when called upon to do so, so that competitive tendering
for the purchase and installation of the lifts could be opened, to enable
the plaintiff to chose the best contractor and at the best price. The
defendant's case is that, that is not his job. Looking at the letter of
offer of the plaintiff dated 7 November 1995 and which letter of offer was
accepted by the defendant and the plaintiff's subsequent letter dated 15
June 1996 which I have reproduced, cl. 5 seems to suggest that the plaintiff
has merit in what it contends with regard to the defendant's duties. At this
stage this court is not to make any findings or arrive at any decisions. All
this court has to do is to see if the plaintiff has raised sufficient
triable issues. The affidavit evidence of the plaintiff and denied by the
defendant shows that there are serious questions to be tried and it
therefore becomes necessary to consider the balance of convenience issue.
Besides, in contending that the plaintiff had to pay its purchasers for late
delivery because of the plaintiff's own negligence, other than making a bare
statement that the plaintiff was negligent, the defendant failed to
substantiate with facts. Accusing the plaintiff of negligence without
stating the particulars, is unacceptable. Having at the forefront of my mind
the guidelines set in Keet Gerald Francis Noel John v. Mohd Noor Abdullah
& Ors[1995] 1 CLJ 293CA I find that the facts of this case bear
similarities to my decision in Pengkalen Securities Sdn Bhd v. Leow Li
Lain[1997] 5 CLJ 440where I held like in this case that there was a
bona fidedispute as to the alleged debt and that a s. 218 statutory
notice of demand was an abuse of process and that the defendant ought to
have filed a writ and summons-in-chambers to determine the issue of
liability to pay. I also held in that case that the justice of the case lay
in granting the injunction as the debt was clearly in dispute and to wind-up
the plaintiff would cause tremendous hardship and that the balance of
convenience favoured the grant of the injunction to maintain status quo.
Public policy would also dictate the grant of the injunction in this case as
the plaintiff is a housing developers and any frivolous winding-up
proceedings against a housing developers would cause adverse chain
reaction and ultimately the demise of the company itself. At a time when all
efforts are being made to boost the economy and to give every opportunity
for businesses to remain afloat and vibrant to generate liquidity, simply
applying to wind-up large companies including housing developers for small
sums must be discouraged, more so when the alleged small debts are
strenuously resisted.
The other reason in my view for
granting the injunction is the fact that damages would not be an adequate
remedy for the plaintiff because if the defendant is not injuncted and if he
obtains the winding-up order, it would be practically impossible for this
court to make any remedial orders later because there would be so many
irreversible changes flowing from the winding-up order. Accordingly it is my
judgment that the balance of convenience lay in favour of making the orders
sought by the plaintiff. Besides, the reputation of a housing developers is
his best advertisement. To drag a housing developers through a
protracted winding-up proceeding more so when the alleged debt is hotly
disputed, is akin to raking the developer through a horse-manured field. He
might vindicate himself finally but the foul smell of a seedy reputation
will linger on. His reputation is what is sacrosanct to a developer.
I therefore granted the
plaintiff an order in terms of Prayers (1), (2) and (3). |