LIM YOH V. ASTANA STRATEGI (M) SDN BHD &
ANOR
HIGH COURT MALAYA, MELAKA
AUGUSTINE PAUL JC
[CIVIL SUIT NO: 22-28-96]
27 MARCH 1998
CONTRACT: Time - Time of the essence - Sale and purchase
agreement - Completion date fell on Sunday followed by public holiday -
Balance of purchase price - Defendant unable to pay as office of plaintiff's
solicitors was closed - Whether days in question should be excluded in
computing date of completion of agreement
CONTRACT: Time - Time of the essence - Contracts Act 1950, ss. 51
, 56 - Whether plaintiff had usual hours of business - Section 48 of Act -
Whether plaintiff needed cooperation of another to perform promise - Whether
plaintiff must perform promise on agreed day - Section 38(1) of Act -
Plaintiff's solicitors, appointed agent of plaintiff - Whether should have
made themselves available on agreed day to receive balance of purchase price
- Whether plaintiff was in default of completing agreement - Whether time
was no longer of the essence - Whether notice of termination of agreement by
plaintiff was valid
EQUITY: Contract, for sale of land - Time of the essence -
Plaintiff's solicitors refrained replying 2nd defendant's letter in time -
Whether this showed unwillingness on the part of the plaintiff's solicitors
to complete agreement - Whether this warranted intervention by the court
JUDGMENT
Augustine Paul JC:
When time is of the essence in a sale and purchase agreement and the
completion date falls on a Sunday, is that day to be excluded in computing
the date of completion of the agreement? The answer to this question will
determine the outcome of this proceeding before me.
The plaintiff was one of the 37 co-proprietors of all that piece of land
known as Lot 579 held under Grant No. 2958 (now Geran No. 16359), Mukim Ayer
Panas, Daerah Jasin, Malacca. By a sale and purchase agreement dated 20
January 1996 ('the agreement') she agreed to sell her 11742/335540 undivided
shares therein to the first defendant for a sum of RM245,407.80. Clause 19
of the agreement provides that:
Time whenever mentioned shall in all respects be of the essence of the
contract.
Upon execution of the agreement the first defendant paid the plaintiff a
deposit of RM24,540.78. With regard to payment of the balance the second
schedule to the agreement provides that:
The balance of the purchase price of Ringgit Malaysia TWO HUNDRED
TWENTY THOUSAND EIGHT HUNDRED AND SIXTY SEVEN AND
CENTS TWO (RM220,867.02) only shall be paid by the Purchaser to the
Vendor within three (3) months from the date of this Agreement with an
extension of one (1) month subject to interest payable at the rate of 10%
per annum calculated on a day to day basis on the sum remaining unpaid.
Clause 9 of the agreement deals with the power of the plaintiff to
terminate it if the first defendant fails to pay the balance of the purchase
price. It is in the following terms:
In the event that the Purchaser fails to pay the balance of the purchase
price as stipulated in the Third Schedule hereto the Vendor is entitled to
terminate this Agreement and upon such an event, all monies paid to the
Vendor by the Purchaser or 10% of the purchase price whichever is the lower
shall be forfeited and treated as agreed liquidated damages to the Vendor
absolutely and the balance thereof (if any) shall forthwith be refunded to
the Purchaser by the Vendor without interest and thereafter neither party
shall have further claims against each other.
The second defendant, in its capacity as solicitors for the first
defendant, sought an extension of time to complete the agreement by its
letter dated 23 April 1996 the material part of which reads as follows:
Kindly be notified that we have been instructed to request for an
extension of time of one (1) month subject to interest payable at the agreed
rate of 10% p.a. calculated on daily basis to complete the above Sale and
Purchase.
We have been informed by our client that our client's loan has been
approved, and pending release.
Messrs Lim Soh & Goonting, solicitors for the plaintiff, by their letter
dated 25 April 1996, in granting the extension of time, notified the
defendants of the last date for completion. The material parts of the letter
read as follows:
Our client is agreeable to grant your client an extension of time of one
(1) month until 19 May 1996 to complete the above sale transaction subject
to your client paying interest at the rate of 10% p.a. calculated on daily
basis on the outstanding balance purchase price.
TAKE NOTICE that in the event the balance purchase price amounting to
RM220,867.02 and late payment interest accrued thereon are not deposited
with us within the completion period i.e. on or before 19 May 1996, our
client shall invoke Clause 9 of the Sale and Purchase Agreement dated 20
January 1996 whereby the said agreement shall be terminated and the 10%
deposit shall be forfeited and treated as liquidated damages.
I interpolate to add that 19 May 1996 was a Sunday and the following day,
Monday 20 May 1996, was a public holiday.
Lim Su Heng (DW1), an officer from the first defendant, handed over the
cheque for the balance of the purchase price to Ravinathan Muthiah (DW3),
the sole proprietor of the second defendant in Melaka, on 18 May 1996. DW3
handed the cheque and a covering letter to his clerk Pradeep Kumar (DW2) on
the same day with instructions to deliver them to the plaintiff's solicitors
on 19 May 1996. The material parts of the covering letter read as follows:
We refer to the above matter and your letter dated 25/04196.
We are pleased to forward herewith our client's Hong Leong Bank Bhd
Cheque No 276693 dated 19/05/96 for the balance Purchase Price and interest,
for the amount of RM224,548.14 issued in favour of your goodselves.
Kindly acknowledge receipt by signing and returning the copy of this
letter to bearer hereof.
On 19 May 1996, DW2 went to the office of the plaintiff's solicitors to
effect the payment. However, he found that their office was closed. He then
returned and informed DW3 about it on 21 May 1996. DW3 immediately faxed a
letter to the plaintiff's solicitors in the following terms:
We refer to the above and your letter dated 25/04/96.
We wish to inform you that as per your said letter, our clerk called
over at your office with our client's cheque for the balance of the Purchase
Price and interest on 19/05/96 at about 2.00 p.m., but there was no one
present to accept the said cheque.
In the circumstances we hereby notify you that our clerk shall be
calling over at your office on the 24/05/96 to deposit the said cheque with
your goodselves.
Kindly be present to accept the same.
Upon receipt of this letter Soh Siew Chiang (PW2), a solicitor from the
plaintiff's solicitors' firm, faxed a reply on the same day to the second
defendant saying that the date of completion should be 21 May 1996 by virtue
of the previous two days having been holidays. The material parts of the
letter read as follows:
We refer to your fax letter dated 21 May 1996 which was received by us
at about 1.10 pm today.
As you are aware, 19 May 1996 was a Sunday and 20 May 1996 was a public
holiday, therefore the extended completion date should be on 21 May 1996.
As the balance purchase price is not received by us today, your clients
are in fact in breach of Clause 3 in particular the Third Schedule (b) of
the Sale and Purchase Agreement dated 20 January 1996.
In the circumstances we are awaiting our client's written instructions
confirming acceptance of your payment notwithstanding the said breach by
your clients.
It is of interest to note that this letter was faxed at 6.46 p.m. When
asked why he sent the letter late PW2 said,
I agree that I sent the fax late so as not to give the defendant time to
pay.
Upon being asked by his counsel to clarify this statement PW2 said,
When I said in cross-examination that I agree that the fax was sent late
so as not to give the defendant time to pay is not true.
On 23 May 1996 the plaintiff's solicitor informed the second defendant by
letter that the agreement is terminated and that the deposit of 10% is
forfeited as liquidated damages. On 24 May 1996 DW2 delivered the cheque for
the balance of the purchase price to the plaintiff's solicitors who received
it without prejudice. On the same day the plaintiff's solicitors sent a
second letter of termination to the second defendant and returned the cheque.
In the meanwhile the whole of Lot 579 had been transferred into the name of
the first defendant and a charge on the land was registered in favour of
Southern Finance Company Berhad. This led the plaintiff to commence
proceedings against the two defendants for, inter alia, an order that
the first defendant retransfer the plaintiff's land to her and for damage.
It is pertinent to reproduce paras. 6 and 10 of the statement of claim (as
translated).
Paragraph 6
The last day by which the balance of the purchase price was to be paid
was the 19th day of May, 1996.
Paragraph 10
The 1st Defendants failed to pay the said balance of the purchase price
by the 19th day of May 1996 aforesaid and only purported to make payment of
the same by cheque vide a covering letter dated 23.5.196 which
reached the Plaintiff's solicitors M/s Lim Soh & Goonting on 24.5.1996.
In substance the defence of the defendants is that they are not in breach
of the agreement and accordingly counterclaimed for damages.
I shall first advert to some general principles of law governing the
effect of a contract where time is of the essence. A sale and purchase
agreement is a contract. Generally stated, a contract is an agreement
between two or more persons which creates an obligation to do or not to do a
particular thing. A statement in a contract that time is "of the essence" of
the contract will be sufficient to express an intention to make the time
stipulation to which it applies conditions (see Steedman v. Drinkle
[1916] 1 AC 275; Petrie v. Dwyer [1954] 91 CLR 99; Lombard North
Central Pte v. Butterworth [1987] 1 QB 527). The condition is of primary
importance and the time stipulation must be adhered to (see Peter Ng Teck
Joo v. Vincent Ponniah[1985] 2 MLJ 146). Where there is such a condition
in a sale agreement the vendor must be able, ready and willing to proceed to
completion as agreed (see Moorwell Buildings Ltd v. Barr [1956] 1 Ch
551). The breach of the condition relating to time by one party will entitle
the other party to have an option of treating the agreement either as having
been repudiated and sue for damages or as still subsisting (see
Xavier Kang Yoon Mook v.
Insun
Development Sdn Bhd [1995]2CLJ471 ). Accordingly, where a time for
completion is of the essence, whether by virtue of the contract or of a
notice, failure by either party to complete punctually will give rise
immediately to a right of rescission in the other only if the latter
tendered completion except to the extent of any waiver (see Palmer v.
Lark [1945] Ch 182; Michael Realty Pty Ltd v. Carr [1975] 2 NSWLR
812). In Union Engle Ltd v. Golden Achievement Ltd[1997] 2 WLR 341
the Privy Council held that even a delay of ten minutes after the time for
completion has passed amounted to a breach of contract. It must be observed
that if a vendor has once made time of the essence of the contract and then
allows an extension of time to a fixed date the time remains essential (see
Buckland v. Farmer & Moody[1978] 3 All ER 929;
Siah Kwee Mow & Anor v. Kulim Rubber Plantations Ltd[1979]1LNS93 ).
Do these principles of law exclude Sundays and public holidays when the last
day for completion of an agreement fall on such days?
The answer to the question just posed will have a critical effect on the
outcome of this action. In their submission the defendants did not make any
specific reference to this issue but maintained that the last day to pay the
balance of the purchase price was 19 May 1996 as agreed and as pleaded by
the plaintiff in her statement of claim. In support of this argument they
referred to the letter dated 25 April 1996 from the plaintiff's solicitors
which required the sum due to be paid " ... on or before 19 May 1996....".
In reply the plaintiff referred to Halsbury's Laws of England, 4th
edn, vol 45 para 1138 which reads as follows:
The fact that the last date of a prescribed period is a Sunday, or other
nonjuridical day, does not as a general rule, give the person who is called
upon to act an extra day, it is no excuse for his omission to do the act on
some prior day.
This general rule does not, however, hold good where the effect of it
would be to render performance of the act impossible.
This would be the case if the whole of the prescribed period consisted
of holidays, in which case the act may lawfully be done on the next possible
day.
The starting point for the answer to the problem posed is s. 105(b) of
our Interpretation Acts 1948 and 1967 which provides that in computing time
for the purposes of any written law, unless the contrary intention appears,
if the last day of the period is a weekly holiday or a public holiday (which
days are referred to as excluded days in the section) the period shall
include the next following day not being an excluded day. As the computation
of time in this case does not involve any written law the provision of law
that I have just referred to is inapplicable. It is therefore necessary to
refer to
the Contracts Act 1950 ("the Act") for guidance. Before going into the
relevant provisions in the Act regarding this issue I consider it necessary
to analyse the judgment of the English Court of Appeal in Pritam Kaur (administratix
of Bikar Singh (deceased) v. S Russell & Sons Ltd [1973] 1 All ER 617
(per Lord Denning MR, Karminski LJ and Megarry J) in order to distill some
guidelines which may be of assistance in resolving the problem in this case.
This case is referred to in the footnotes to the passage from Halsbury's
Laws of England referred to by the plaintiff and explains the
significance of the passage relied on. The issue for determination in that
case was the manner of computing time under the Limitation Act 1939 for
bringing proceedings in court when the last day was a Sunday. In his
judgment Lord Denning MR observed that the period of limitation is
prescribed by the statutes and not by rules of court. His Lordship said that
if the time period had been prescribed by rules of court then O. 3 r. 4 of
the Rules of the Supreme Court could be resorted to as it provides that if
the court offices are closed, the time is extended until the next day.
However, this rule does not apply to cases when the time is prescribed by
statute. His Lordship then referred to the arguments of both sides and said
at pp 619 - 620,
The arguments on each side are evenly balanced. The defendants can say:
The plaintiff has three years in which to bring his action. If the last day
is a Saturday or Sunday, or other dies non, he ought not to leave it until
the last day. He ought to make sure and issue it the day before when the
offices are open. The Defendants can rely for this view on the reasoning of
Russell LJ in Hodgson v. Armstrong [1967)1 All ER at 320 and the
cases to which it refers. The plaintiff can say: 'The statute gives me three
years in which I can bring my action. If I go in to the office on the last
day, and find them closed, I ought not to be defeated on that account. I
should be allowed to go next day when the offices are open.
Otherwise, I should be deprived of the three years which the statute
allows me.' The plaintiff can rely for their view on the reasoning of
Sellers LJ in Hodgson v. Armstrong [1967] 1 All ER at 311, 312, and
the cases to which he refers.
His Lordship said that the arguments are so evenly balanced that a
decision can be made either way and concluded at p 620,
The important thing is to lay down a rule for the future so that people
can know how they stand. In laying down a rule, we can look to parallel
fields of law to see the rule there. The nearest parallel is the case where
a time is prescribed by the rules of court for doing any act. The rule
prescribed both in the county court and the High Court is this: if the time
expires on a Sunday or any other day on which the court office is closed,
the act is done on time if it is done on the next day on which the court
office is open. I think we should apply a similar rule when the time is
prescribed by statute. By so doing, we make the law consistent in itself;
and we avoid confusion to practitioners.
So I am prepared to hold that, when a time is prescribed by statute for
doing any act, and that act can only be done if the court office is open on
the day when the time expires, then, if it turns out in any particular case
that the day is a Sunday or other dies non, the time is extended until the
next day on which the court office is open.
Lord Denning MR based his conclusion on Hughes v. Griffiths [1862]
13 CBNS 324 where Erle CJ said at p 333,
Where the act is to be done by the court, and the court refuses to act
on that day, the intendment of the law is that the party shall have until
the earliest day on which the court will act.
Karminski LJ in agreeing with Lord Denning MR also referred to Hughes
v. Griffiths [1862] 13 CBNS 324 where Byles 3 said at p 337,
Consequently, the seventh day must be one upon which the court can be
set in motion; otherwise, the party would not have that which the
legislature contemplated that he should have.
Megarry J analysed an array of authorities and concluded at p 626,
Accordingly, in my judgment the result is as follows. There are a number
of cases which support the general rule that a statutory period of time,
whether general or special, will, in the absence of any contrary provision,
normally be construed as ending at the expiration of the last day of the
period. That rule remains; but there is a limited but important exception or
qualification to it, which may be described from a line of authorities which
include Hughs v. Griffiths (1862) 13 CBNS 324, Mumford v.
Hitchcocks (1863) 14 CBNS 361, the judgment of Sellers LJ in Hodgson
v. Armstrong(1967) 1 All ER 307 and the Scottish cases. If the act to be
done by the person concerned is one for which some action by the court is
requisite, such as issuing a writ, and it is impossible to do that act on
the last day of the period because the offices of the court are closed for
the whole of the day, the period will prima facie be construed as
ending not on that day but at the expiration of the next day upon which the
offices of the court are open and it becomes possible to do the act.
In this appeal, there is nothing in the facts of the case which ousts
the prima facie application of this exception, which accordingly
applies. I therefore concur in allowing the appeal.
One of the Scottish cases that Megarry J referred to in arriving at his
conclusion is M Vean v. Jameson [1896] 23 R (J) 25 where Lord M Laren
said at p 27,
When some step of judicial procedure has to be performed by the litigant
within a definite number of days fixed by statute, and the last day is a
Sunday, our decisions have sanctioned the completion of the step on the
Monday, where the step is one which requires the co-operation of the clerk
of court or other official, as the giving in of a report or document of any
kind ... . But where the act is something which the litigant can do at his
own hand - where he has it in his power to complete the act so far as his
own share in it is concerned without the co-operation of a second party, as
in the case of the notice required - I see no reason why Sunday should be
discounted.
(Emphasis added).
What can be discerned from the passages that I have reproduced thus far
is that a statutory period of time is normally construed as ending at the
expiration of the last day of the period. The exception to the rule arises
where the act becomes impossible to be performed on the last day. Such an
impossibility will arise where the act requires the action of another party,
for example, a court which is closed on the last day being a Sunday. The
exception will not apply to a case where a person can do his share of the
act without the cooperation of another party on the last day which is a
Sunday. In such circumstances the Sunday will not be discounted and must be
treated as the last day for the performance of the act. As we have a
statutory formula for resolving problems of this nature involving any
written law these principles are not relevant in interpreting our statutes.
However, these principles may be relevant in computing time for the
performance of a promise in a contract. I shall refer to these principles in
a later part of the judgment when dealing with the relevant provisions
relating to time in the Act.
I shall now consider some provisions of the Act which deal with this
issue.
Section 38(1) of the Act provides that the parties to a contract must
either perform, or offer to perform, their respective promises, unless the
performance is dispensed with or excused under the Act, or of any other law.
Section 56 of the Act regulates the position when time is of the essence
of a contract. It reads as follows:
56.(1) When a party to a contract promises to do a certain thing at or
before a specified time, or certain things at or before specified times, and
fails to do any such thing at or before the specified time, the contract, or
so much of it as has not been performed, becomes voidable at the option of
the promisee, if the intention of the parties was that time should be of the
essence of the contract.
(2) if it was not the intention of the parties that time should be
of the essence of the contract, the contract does not become voidable by the
failure to do the thing at or before the specified time, but the promisee is
entitled to compensation from the promisor for any loss occasioned to him by
the failure.
(3) if, in case of a contract voidable on account of the promisor's
failure to perform his promise at the time agreed the promisee accepts
performance of the promise at any time other than that agreed, the promisee
cannot claim compensation for any loss occasioned by the non-performance of
the promise at the time agreed, unless, at the time of the acceptance, he
gives notice to the promisor of his intention to do so.
The law embodied in
s. 56 of the Act does not differ from the equitable principle under
English law relating to time in contracts for the sale of land (see
Jamshed Khodaram Irani v. Burjorji Dunjibhai [1916] LR 43 lA 26; Ganam
d/o Rajamany v. Somoo s/o Sinnah [1984] 2 CLJ 268;
Ismail bin Haji Embong v. Lau Kong Han[1970]1LNS40 ; Aiyadurai v.
Lim Hye [1959] MLJ 143). In commenting on this section Gill J (as he
then was) said in
Tan Ah Kian v. Haji Hasnan [1962]1LNS192 at p 404,
These provisions of our law are akin to the distinction in English law
between a condition the breach of which entitles the other party to treat
himself as discharged from liability under the contract and a warranty which
merely gives him a right to damages.
The English law is summarised in paragraph 575 of chitty on Contracts
(22nd edition) as follows:-
Once it has been established that a certain stipulation is indeed a term
of the contract, the question arises as to its comparative importance and
effect. Contracts are normally made up of a number of terms, some of which
may be regarded as of major, and others of minor, importance. In English
law, the breach of any term will normally give a right to the injured party
to claim damages. But his further remedies will depend upon the importance
of the term which has been broken. If the term may be regarded as essential
to the undertaking, it is called a condition. The breach of a condition
entitles the injured party either (i) to treat the contract as at an end, in
which case the contract is said to be discharged by breach, or (ii) to
continue to treat the contract as still binding and to content himself with
damages, which are his remedy in any eyent. If, however, the term is merely
subsidiary or collateral to the main undertaking, the breach of it will not
entitle him to treat the contract as discharged, but to claim damages only.
Such a subsidiary or collateral term is known as a warranty in law'.
Section 51 of the Act provides that the performance of any promise may
be made in any manner, or at any time which the promisee prescribes or
sanctions. The effect of
ss. 51 and
56 of the Act is that a promise must be performed at the time agreed by
the parties. These two sections must be read with
s. 48 of the Act which reads as follows:
When a promise is to be performed on a certain day, and the promisor has
undertaken to perform it without application by the promisee, the promisor
may perform it at any time during the usual hours of business on the day and
at the place at which the promise ought to be performed.
When a promise is to be performed on a certain day this section specifies
the time of the day during which the promise may be performed when the
promisor has undertaken to perform it without application by the promisee.
Under English common law a day is a period of time as from midnight to
midnight, and not a period of 24 consecutive hours (see The Katy
[1895] P 56; Cartwright v. Mac Cormack [1963] 1 WLR 18), unless it is
clear that the latter was intended (see Cornfoot v. Royal Exchange
Assurance Corpn [1904] 1 KB 40). Thus when payment has to be made on a
specified day, it can, in the absence of any custom to the contrary, be made
at any time up to midnight on that day (see Afovos Shipping Co SA v.
Romano Pagnan and Pietro Pagnan[1983] 1 WLR 195). With regard to the
position of Sundays and public holidays as "days" Chitty on Contracts
27th edn, vol says at para 21 - 019,
Usually, 'days' include Sundays and holidays, unless there is a custom
to the contrary, and this is the meaning of the words 'running days' (Nielson
& Co v. Wait James & Co (1885) 16 QBD 67); on the other hand, the phrase
'working days' excludes days when work is not ordinarily done and the terms
of a contract may show that the word 'day' has this meaning (Commercial
SS Co v. Boulton(1875) LR 10 QB 346; Nielson v. Wait supra;
Reardon Smith Line Ltd v. Ministpy of Agriculture (1963) AC 691).
As
s. 48 of the Act provides that the promise may be performed during the
usual hours of business of the day certain problems relating to its
interpretation arise for consideration. Does it refer to the usual business
hours of the public service of the community? Does it refer to the usual
business hours of the private sector? If so, does it vary according to the
business hours of a particular trade? Does it refer only to the business
hours of the promisor? Finally, what is the position if the promisor has no
business hours? In my opinion the clue to the answer to the various
questions posed is provided by the illustration to the section which reads
as follows:
A promises to deliver goods at B's warehouse on the 1st of January.
On that day A brings the goods to B's warehouse, but after the usual
hour for closing it, and they are not received. A has not performed his
promise.
The illustration makes it manifestly plain that the usual hours of
business referred to in the section is a reference only to the usual
business hours of the promisor himself. This is logical as he needs the
co-operation and assistance of his own business enterprise, as in the case
of the warehouse in the illustration to the section, to perform his promise
and not the business hours of some other entity which may have no relevance
or assistance to the performance of his promise. The language employed in
the section only calls for a determation of the time of the agreed day
during which the promise may be performed. The day on which the promise is
to be performed remains as agreed between the parties. Thus if the agreed
day is a Sunday or public holiday and the promisor has his business open on
those days then such days will not be excluded. They will of course be
excluded if he has no hours of business on those days. As the issue of
business hours in the section is peculiar to the promisor himself it follows
that they will not be relevant when a promisor has no such hours. This is
logical as such a person will not need the co-operation or assistance of his
business enterprise, as there is none, to perform his promise. To hold
otherwise would mean that a person who has no business hours will be unable
to perform a promise made by him. Similarly, to equate him with some
non-existent hours of business will be artificial and produce absurd
results. It must be remembered that one of the fundamental principles of
statutory interpretation is to avoid such consequences. In this regard,
Bennion on Statutory Interpretation 2nd edn, says this at p 679.
The Court seeks to avoid a construction that produces an absurd result,
since this is unlikely to have been intended by Parliament.
Here the Courts give a very wide meaning to the concept of 'absurdity',
using it to include virtually any result which is unworkable or
impracticable, inconvenient, anomalous or illogical, futile or pointless,
artificial, or productive of a disproportionate counter-mischief.
The corollary is that
s. 48 of the Act is inapplicable in the case of a person with no hours
of business. The promise must be performed on the agreed day with no
qualification as to the time of the day for the performance of the promise.
It follows that Sundays and public holidays will not be discounted. However,
the position may be different if he needs the co-operation of another person
to complete the promise and that other person has no hours of business on
that day. In that event that day may be excluded.
This interpretation of
s. 48 of the Act is in harmony with the common law principles that I
discussed in an earlier part of the judgment as to when a Sunday can and
cannot be discounted. Some Indian decisions are in support of this line of
thinking. In Kasiram v. Hurnundroy AIR1921 C 809 it was held that in
the absence of any statutory provision or a trade custom or usage to that
effect, the fact that the performance of a contract falls due on a holiday
does not alter the rights of the parties by suspending the transaction of
private business. If; according to the statutory provision or usage, the
contract cannot be performed on the holiday, it may be performed on the next
opening day. Lalchand Balkissan v. John L Kersten [1890] 15 Bom 338
was a case involving a suit for damages against the defendant, a German, for
non-delivery of goods. It was contended that he was not bound to deliver the
goods on Sunday, which was the last day named in the contract for
performance. It was held that the "Lords Day Act" did not apply to India,
and that, in the absence of a custom to the contrary, he was bound to
deliver the goods on that day if they had not already been delivered. In
Motumal v. Ruttanji 24 I C 883 it was held that according to the custom
of Calcutta merchants delivery is to be completed on Saturday if it falls on
Sunday. On the facts of this case there is no statutory provision or
evidence of any hours of business or that the plaintiff needs the
co-operation of another person to complete the promise to discount Sunday in
favour of her. Thus following
s. 38(1) of the Act the plaintiff must perform her promise on the agreed
day as the performance has not been dispensed with or excused under the Act
or by any other law. The result is that she ought to have been able, ready
and willing to complete the agreement on 19 May 1996. That leads rise to a
consideration of the position when the plaintiff has appointed an agent to
perform the promise on her behalf and the agent has his own hours of
business which do not include Sundays.
It is significant to observe that the primary responsibility in
completing the agreement is on the plaintiff herself. This is because the
parties have agreed in the Second Schedule to the agreement that the balance
of the purchase price ".... shall be paid by the purchaser to the vendor
.... ." That, of course, does not preclude the plaintiff from appointing an
agent to act on her behalf in accordance with
s. 41 of the Act . However any agent whom the plaintiff appoints must
also be ready, willing and able to complete the contract as agreed between
the parties. In this regard Chitty on Contracts 27th Edn vol. 1 says
at para 19-046,
A contracting party can in the case of many contracts enter into an
arrangement by which some other person may perform for him, as far as he is
concerned, the obligations of the contract, and the other contracting party
will be obliged to accept that performance if it is performance in
accordance with the terms of the contract. The contracting party will,
however, be liable for any breach that may happen, and the other contracting
party is not bound or, indeed, entitled to sue the substituted person for
breach of contract, although there may, of course, be a remedy in tort, e.g.
where the substituted person negligently damages or causes the loss of goods
entrusted to him. This is technically known as vicarious performance, and it
is 'quite a mistake to regard that as an assignment of the contract; it is
not' (Davies v. Collins [1945] 1 All ER 247).
The rationale for the relationship between a principal and an agent is
anchored on the premise that the agent is merely standing in the principal's
shoes and is not entitled to any special right, privilege or immunity not
enjoyed by the latter. Where a person performs a contract through an agent
he remains liable personally (see Stewart v. Reavell's Garage [1952]
2 QB 544). It is settled law that in no case can the authority of an agent
exceed the power of the principal to act on his own behalf (see
Shrewsbury and Birmingham Rly Co v. North Western Rly Co [1857] 6 HL Cas
113; Montreal Assurance Co v. Mc Gillivray [1859] 13 Moo PCC 87;
Ashbury Railway Carriage and Iron Co v. Riche [1875] LR 7 HL 653). An
agent is a mere instrument and it is the principal who bears the risk of
inadequate representation (see Norwich and Peterborough BS v. Steed
[1993] Ch 116). The agent must comply strictly with the terms of what he has
agreed to do, and is in breach of contract if he exceeds his authority on
the one hand, or fails to carry it out on the other (see Fray v. Voutes
[1859] 1 E & E 839; Butler v. Knight [1867] LR 2 Ex 109; The
Herminone [1922] P 162; Apatu v. Peach Prescott & Jamieson[1985]
1 NZLR 50). It is the duty of an agent to carry out the business he has
undertaken and he must inform his principal promptly if it is impossible to
do so (see Cassaboglou v. Gibb [1883] 11 QBD 797). Where an agent is
employed to carry out any transaction which involves a payment to him on his
principal's behalf, he must not compromise his principal's rights (see
Halsbury's Laws of England 4th edn, vol para 783).
The letter dated 25 April 1996 from the plaintiff's solicitors to the
second defendant shows that the plaintiff has instructed her solicitors to
receive the balance of the purchase price. The letter spells out in clear
and crystalline terms that if the sum due is not deposited with the
solicitors within the completion period, that is to say, on or before 19 May
1996, the agreement shall be terminated. Thus the instruction of the
plaintiff to her solicitors is that the sum due should be received on or
before 19 May 1996 as stipulated by the agreement. There is therefore no
change in the time of performance of the agreement which is a condition by
virtue of time being of the essence of the agreement and which, in any
event, cannot be altered unilaterally. The change is only as to the place of
performance of the agreement. The solicitors are therefore duty-bound to
make themselves available at the relevant time to ensure that the contract
is completed in accordance with the duty of the plaintiff which they have
taken over. Any attempt by them to have this date varied for whatever reason
bearing in mind the fact that there is no legal impediment to their client
completing the agreement on 19 May 1996 is a violation of the express terms
of the agreement thereby resulting in the plaintiff being in breach of the
agreement. Thus their inability to complete the agreement by virtue of their
office being closed at the material time has to be considered as the default
of the plaintiff in completing the agreement as they were her lawfully
appointed agents and as there was no change as to the time of performance of
the agreement. The fact that they were closed on that day and were therefore
unable to complete the agreement is a matter between them and the plaintiff.
So long as the defendants were ready, willing and able to complete the
agreement on that day they are absolved from any fault. The corollary is
that the solicitors appointed by the plaintiff ought to have been available
on Sunday 19 May 1996 to complete the agreement and the question of
extension of the date does not arise. In the premises it is my view that the
completion date of the agreement in this case is Sunday 19 May 1996. That,
incidentally, is precisely what the plaintiff herself has pleaded in her
statement of claim. I interpolate to add that the position may warrant
different consideration if the agreement itself had provided that the
balance of the purchase price is to be paid to the "vendor's solicitors". In
that event the closure of the solicitor's office on the days in question may
require to be taken into account. Notwithstanding the views that I have
expressed the fact that the plaintiff's solicitors have by their letter
dated 25 April 1996 demanded for the balance of the purchase price to be
deposited "... within the completion period i.e. 19 May 1996...." is a
specific direction and includes 19 May 1996 by the expression of a contrary
intention even if that day is to be excluded on general principles.
What now requires consideration is whether the defendants attempted to
complete the agreement on the stipulated day. It is my firm finding of fact,
based on the evidence adduced and the demeanour of the witnesses while
giving evidence, that the second defendant did in fact attempt to pay the
balance of the purchase price to the solicitors for the plaintiff on 19 May
1996. Contrary to the assertion of the plaintiff it is my view that the
covering letter dated 18 May 1996 taken by DW2 to the office of the
plaintiff's solicitors is not a fabrication. DW2 confirmed the evidence of
DW3 on the authenticity of this letter. Additionally, the letter dated 21
May 1996 from DW3 to the plaintiff's solicitors further confirms the defence
version of the sequence of events. The conduct of the plaintiff's solicitors
upon receipt of this letter leaves much to be desired and lends weight to
the case for the defendants. If the solicitors for the plaintiff genuinely
believed that the completion date has in fact been extended to 21 May 1996
they ought to have given an immediate reply to the second defendant's letter
dated 21 May 1996 bearing in mind the fact that the letter speaks of the
attempt made on 19 May 1996 to effect the payment following the intimation
in their letter dated 25 April 1996 that the date for completion is ".... on
or before 19 May 1996 ... " Instead the plaintiff's solicitors sent the
reply late so as not to give the defendants time to pay.
It thus follows that the default in completing the agreement was caused
by the plaintiff. The result is that time was no longer of the essence of
the agreement and the plaintiff must give reasonable notice in order to make
time of the essence (see
Quah Ban Poh v. Dragon Garden Pte Ltd [1985] CLJ 720 (Rep) ). In such
circumstances the giving of an instant notice of termination will be
unreasonable and invalid (see Goh Hooi Yin v. Lim Tong Ghee [1990] 3 MLJ 23;
Plenitude Holdings Sdn Bhd v. Tan Sri Khoo Teck Puat[1992] 3 CLJ 281 (Rep)
). Thus the notice of termination given by the plaintiff's solicitors
pursuant to their letter dated 23 May 1996 is invalid. As the defendants
were and still are willing to complete the agreement the plaintiff ought to
have allowed them to do so. This is in accordance with
s. 40 of the Act which provides that when a party to a contract has
refused to perform, or disabled himself from performing, his promise in its
entirety, the promisee may put an end to the contract, unless he has
signified, by words or conduct, his acquiescence in its continuance.
Notwithstanding what I have said thus far, even if it can be successfully
argued that the defendants did not in fact attempt to complete the agreement
on 19 May 1996 that does not advance the plaintiffs case in any way. A party
who claims to have rescinded for the other party's failure to meet an
essential time bears the onus of proving that he himself was ready, willing
and able to meet it (see Time in the Performance of Contracts by KE
Lindgren 2nd edn p 143). A party to a contract can never in law rely on the
non-performance of a promise by the other party when he himself had waived
performance (see Strong v. Stringer [1889] 61 LT 470). As the
plaintiff was not ready and willing to perform his promise the first
defendant need not perform his promise. This accords with
s. 52 of the Act which reads as follows:
When a contract consists of reciprocal promises to be simultaneously
performed, no promisor need perform his promise, unless the promisee is
ready and willing to perform his reciprocal promise.
Furthermore, the fact that the plaintiff's solicitors refrained from
replying the second defendant's letter dated 21 May 1996 in time so as not
to give the defendants time to pay, shows their unwillingness to complete
the contract and this justifies intervention by the court in the exercise of
its equitable jurisdiction. In this regard I refer to
Yap Hong Too & Anor v. Wong Ah Mei & Anor [1997] 1 CLJ 568 where Peh
Swee Chin FCJ said at p 574,
A court of equity can grant relief against forfeiture when circumstances
justify it. Similarly by extension of this rule, in an action for specific
performance,for a purchaser who comes to Court with clean hands, a Court of
equity can relieve the purchaser against a failure to comply with such a
condition as to time in sale and purchase agreement where circumstances
justify it ...
We find an echo in a relevant passage in Cheshire, Fifoot &
Furmston's Law of Contract11th Ed by Prof Furmston at p 609 as set out
below:
It is clear at least that equity, where warranted by the circumstances,
will relieve the buyer to the extent of giving him further time within which
to complete the contract even though the parties have agreed that time shall
be essential.
In other words, the forfeiture will be suspended, provided that the
buyer expresses himself ready and willing to pay the balance of the price
within the extended time fixed by the Court.
In the upshot I dismiss the plaintiff's claim with costs. I also dismiss
the First Defendant's counterclaim with costs as they have led no evidence
in support of their claim. I further order, on a concession made by the
defendants, that the first defendant do pay the plaintiff the amount due to
her as of 19 May 1996, that is to say, a sum of RM224,548.14 within one
month.
|