PERMAH @ PERUMAL A/L RAMASAMY V. MBF
PROPERTY SERVICES SDN BHD& ANOR
HIGH COURT [KUALA LUMPUR]
[GUAMAN NO: S2-24-155-1997]
31 JULY 1997
KAMALANATHAN RATNAM, JC
JUDGMENT
FACTS
Sometime in 1993 the plaintiff saw an advertisement in the newspapers
regarding the sale of condominiums at a project known as BUKIT OUG-SURIAN
WANGI condominiums (the project) belonging to Sri Keladi Sdn Bhd of which
the 1st defendant was the project manager. He was forthwith attracted to the
said project because it was a term of the contract of sale that he was
required to pay [2] only 10% of the purchase price and not a cent
more until the condominium that he purchased was completed and a Certificate
of Fitness issued. He then purchased one unit condominium in the said
project.
The 1st defendant by way of its letter dated 17.5.93 and titled
"Developer's Undertaking" wrote as follows:
- "We are pleased to inform you that in consideration of you purchasing
the said unit we agree to pay all the interest accrued on your loan
disbursed to pay for the purchase price of the above unit during the
period of construction of the unit and until your loan is fully drawdown
with the Certificate of Fitness being issued. The agreement to pay is not
assignable by you and subject to you complying with the terms and
conditions of your Loan Agreement with your end financier."
Based on the Developer's Undertaking dated 17.5.93 the plaintiff entered
into a sale and purchase agreement with Sri Keladi Sdn Bhd, the vendor. Then
on 25.8.93 the plaintiff entered into a housing loan agreement with the 2nd
defendant.
[3] PLAINTIFF'S CASE
It was the case of the plaintiff that the repayment of the loan would
commence upon the issuance of the Certificate of Fitness. However, by way of
a notice dated 22.1.97 the 2nd defendant demanded from the plaintiff the
instalment due together with interest and together with that, the 2nd
defendant attached a Temporary Certificate for Occupation dated 13.9.96 and
extended for 6 months (Exhibit P-5). It was expressly stated in the said
Temporary Certificate for Occupation that during the period of time that the
Temporary Certificate for Occupation was valid it was necessary for the
vendor to comply with the requirement as stated in Annexure A. However
Annexure A was not annexed by the 2nd defendant to the copy of the Temporary
Certificate for Occupation it had sent to the plaintiff together with the
notice of demand dated 22.1.97. In the circumstances the plaintiff contended
that since the certificate issued was only a Temporary Certificate for
Occupation, the 1st defendant ought to continue to pay the interest until
the Final Certificate for Occupation was issued. The plaintiff therefore
prayed for a declaration that he need not make any payment to the 2nd
defendant until a Final Certificate for Occupation is issued.
[4]CASE FOR THE DEFENDANTS
In reply to the plaintiff's affidavit in support of his originating
summons, one See Kiam Pee @ See Kian Pee, a manager of the 1st defendant,
affirmed an affidavit in reply. He averred that it was the intention of the
1st defendant that the purchasers of the condominiums, including the
plaintiff herein, were not to pay any interest on the loan advanced by the
2nd defendant to the developer, until the purchasers including the
plaintiff, entered into occupation of their respective condominiums. The 1st
defendant contended that the plaintiff could enter into occupation of his
condominium either with a Temporary Certificate for Occupation or a
Certificate of Fitness for Occupation issued by the respective authorities.
The 1st defendant then exhibited another similar Temporary Certificate for
Occupation marked as Exhibit D-5 to the 1st defendant's affidavit. This
Temporary Certificate was dated 9.4.97 and is to expire on 8.10.97. Again
Annexure A was not exhibited. On behalf of the 2nd defendant one Koo Boon
Keong, the Jalan Ipoh branch manager of the 2nd defendant affirmed an
affidavit on almost identical terms to that of the 1st defendant's
affidavit.
COURT'S FINDINGS
The relevant clause in the sale and purchase [5] agreement which
deals with the delivery of vacant possession is clause 23 and it reads as
follows:
"23. Manner of delivery of vacant possession.
- (1) Upon the issuance of a Certificate by the Vendor's Architect
certifying that the construction of the said Parcel has been duly
completed and water and electricity supply has been connected to the said
Parcel and the Vendor has applied for the issuance of the Certificate of
Fitness for Occupation from the Appropriate Authority and the Purchaser
having paid all monies payable under clause 4(1) in accordance with the
Third Schedule and all other monies due under this Agreement and the
Purchaser having performed and observed all the terms and covenants on his
part under this Agreement the Vendor shall let the Purchaser into
possession of the said Parcel.
- PROVIDED THAT such possession shall not give the Purchaser the right
to occupy and the Purchaser shall not occupy the said Parcel until such
time as the
- [6] Certificate of Fitness for Occupation for the said Building
is issued.
- (2) Upon the expiry of fourteen (14) days from the date of a notice
from the Vendor requesting the Purchaser to take possession of the said
Parcel, whether or not the Purchaser has actually entered into possession
or occupation of the said Parcel, the Purchaser shall be deemed to have
taken delivery of vacant possession."
It seems clear from this clause that for vacant possession to be given to
the purchaser, the following conditions must have been performed, namely:
- (a) The architect's certificate is to be issued certifying that
construction has been completed and that water and electricity supply have
been connected to the building in question.
- (b) The vendor has applied for the issuance of a certificate for
occupation from the appropriate authority.
- [7] (c) The purchaser to have paid all monies payable under
clause 4(1) in accordance with the Third Schedule.
- (d) The purchaser to have performed and observed all the terms and
covenants on his part.
The proviso however stipulates that such possession does not give the
purchaser the right to occupy the said building until the Certificate of
Occupation for the said building is issued.
One of the conditions necessary for occupation is that the vendor must
merely apply for the issuance of the said certificate. There is no
requirement for purposes of occupation that the said certificate must be
issued.
It is my judgment that since clause 23(2) is a deeming clause in that
upon expiry of 14 days from the date of a notice from the vendor requesting
the purchaser to take possession of the said building, and whether or not
the purchaser has actually entered into possession or occupation of the
building the purchaser is deemed to have taken delivery of vacant
possession, the mere issuance of a Certificate for Occupation which normally
[ 8] is a Temporary Certificate for Occupation is sufficient to give
the 2nd defendant the right to demand payment. The very fact that it is a
requirement that water and electricity be connected is to my mind an
indicator that occupation is intended; for if there is not to be occupation
but merely taking possession it would make no difference whether water and
electricity had been connected or not. These are the basic amenities of a
household in occupation. Besides, once a Temporary Certificate for
Occupation has been issued for a fixed period, as in this case for 6 months,
and upon the vendor through his architects having complied with the
rectification of any defects as stipulated in the annexure to the Temporary
Certificate for Occupation, the relevant authorities would inevitably issue
a Certificate for Occupation even if it is necessary to issue further prior
Temporary Certificate for Occupation, as in this case.
THE LAW IN QUESTION
The relevant legislation governing the issuance of the Certificate of
Occupation is the Building (Federal Territory of Kuala Lumpur) By-Laws 1985.
By-law 23(1) dealing with the Certificate for Occupation reads:
- "23.(1) Certificate for Occupation of a building [9] shall be
given when -
- (a) the qualified persons during the course of the work have certified
in Form E as set out in the Second Schedule to these By-laws that they
have supervised the erection of the building, that to the best of their
knowledge and belief the building has been constructed in accordance with
these By-laws and any conditions imposed by the Commissioner and that they
accept full responsibility for those portions which they are respectively
concerned with; and
- (b) the Commissioner or an officer authorised by him in writing for
the purpose has inspected the building.
(2) Nothing contained in this by-law shall prevent the Commissioner or
any officer authorised by him in writing for the purpose from inspecting any
building works at any stage thereof and calling attention to any deviation
from the approved plan or non-compliance with any of these By-laws which he
may observe and from giving notice in writing [10] ordering such
deviation to be rectified."
By-law 24 dealing with the Temporary Certificate for Occupation reads:
- "24. Subject to payment of the fees prescribed in the First Schedule
to these By-laws, the Commissioner may in his discretion grant a Temporary
Certificate for Occupation of a building for a period, not exceeding six
months in cases where only minor deviations from the approved building
plans have been made and pending full compliance with the requirements of
the Commissioner before the issue of Certificate for Occupation."
By-law 25 dealing with Partial Certificate for Occupation reads:
- "25.(1) The Commissioner may in his discretion grant a Partial
Certificate for Occupation of any part of a building partially completed
and may impose any conditions that he deems necessary in the public
interest:
- Provided that no such permit shall be granted [11] if -
- (a) no application for Partial Certificate for Occupation has been
made within the period of construction;
- (b) all essential services, including access roads, car parks, drains,
sanitary, water and electricity installations, fire lifts where required,
sewerage and refuse disposal requirements have not been provided; and
- (b) the occupation of such parts of a partially completed building
will prejudice public health or safety.
(2) A Partial Certificate for Occupation once issued shall remain
effective until the whole of the building is completed and a Certificate for
Occupation is issued."
By-law 26 dealing with Occupation Without Certificate for Occupation
reads:
- "26. No person shall occupy or permit to be occupied any building or
any part thereof unless a [12] Certificate for Occupation, a
Partial Certificate for Occupation or a Temporary Certificate for
Occupation has been issued under these By-laws for such building."
It is evident from by-law 24 that a Temporary Certificate for Occupation
is only given for a period not exceeding 6 months, in cases when any minor
deviations from the approved plans have been made and with the hope that
within the 6-month period such deviations would be put right upon which the
Certificate for Occupation would be issued. There is no doubt that in such
circumstances the Certificate for Occupation would follow as a matter of
course. Even at this stage if there is any doubt as to the right of the
owner to occupy upon receipt of a Temporary Certificate for Occupation,
by-law 26 puts paid to any such doubt. This by-law clearly and unambiguously
states that possession of a Temporary Certificate for Occupation would
permit a person to occupy the said building.
Whilst clause 23 of the agreement talks of possession, by-law 26 confirms
the right of occupation with a Temporary Certificate for Occupation. In the
circumstances, it is a wrong assumption of the plaintiff that he is only
entitled to commence payment of the [13] instalments and interest
upon receipt of the Certificate for Occupation and not upon receipt of the
Temporary Certificate for Occupation. The declaration sought must therefore
perforce fail. I therefore had no hesitation in dismissing the application
for declaratory relief with costs.
Dated the 31st day of July 1997.
DATO' KAMALANATHAN RATNAM
JUDICIAL COMMISSIONER
HIGH COURT
KUALA LUMPUR
[Application for declaratory relief dismissed with costs ]
|