SALMAH SULAIMAN
& ANOR. V. METROPLEX DEVELOPMENT SDN. BHD.
COURT OF APPEAL, KUALA LUMPUR
ZAKARIA YATIM JCA NH CHAN JCA MAHADEV SHANKAR JCA
[CIVIL APPEAL NO: W-04-31-94]
10 SEPTEMBER 1996
CONTRACT: Building contract - Vacant possession, delivery of -
Delay - Whether purchaser entitled to damages for late delivery from
developer - Determination of period of delay
CONTRACT: Building contract - Housing Developers (Control &
Licensing) Rules 1970, r 12(1)(1) - Water and electricity, delay in supply
of - Whether developer liable for delays caused by public authorities -
Scope of developer's responsibilities - Whether purchaser entitled to
damages for delay in supply of water and electricity
The appellants in the instant appeal were the administrators of the estate
of one Ahmad Ibrahim ('the deceased') while the respondent was a housing
developer under the Housing Developer (Control & Licensing) Act 1966 . On 4
April 1981, the deceased entered into a sale and purchase agreement ('the
S&P') with the respondent for the purchase of a house from the latter. Under
the S&P, the respondent was to deliver vacant possession of the house to the
deceased not later than 3 October 1982.
The appellants alleged that the respondent only delivered the keys to the
house on 25 July 1984 and that there was no supply of water and electricity
until January 1985. Thus, the appellants alleged that the respondent had
breached the S&P and proceeded to claim liquidated damages for late delivery
calculated as from 4 October 1982 to 25 January 1985. It was the appellants'
argument that vacant possession of the house was delivered only when water
and electricity were supplied to the house.
The respondent contended that the internal water and electricity mains of
the house were connected to the external mains on 31 March 1983 and, hence,
vacant possession of the house was delivered to the appellants on that very
same day. The respondent further contended that the appellants were only
entitled to claim liquidated damages for late delivery and not for any
delays in the supply of water and electricity. The Sessions Court accepted
the respondent's contentions and, on appeal, the High Court confirmed the
decision of the Sessions Court. The appellants appealed.
Held:
Per Zakaria Yatim JCA
[1]Rule 12(1)(1) of the Housing Developers (Control & Licensing Rules 1970
('the Rules') only requires the housing developer to connect the external
electricity and water mains of the appropriate public authorities to the
internal mains within the house. The housing developer is not under an
obligation to ensure the flow of water and electricity into the house.
[2] In the instant appeal, the S&P explicitly provided that the respondent
shall not be responsible or liable for any delays on the part of the
relevant authorities in supplying water and electricity. Consequently,
vacant possession of the house was delivered on 31 March 1983, and the
appellants were not entitled to damages in respect of the delay in the
supply of water and electricity.
[Appeal dismissed.]
Legislation referred to:
Housing Developers (Control and Licensing) Act 1966
Housing Developers (Control and Licensing) Rules 1970, r. 12(1)(1) [Appeal
from High Court Malaya, Kuala Lumpur; Civil Appeal No: R2-12-10-94]
For the appellants - Won Walter Pereira (Kemkumar S. Lopez with whim); M/s.Kamarudin
& Partners
For the respondent - Tan Ming-Li; M/s. Allen & Gledhill
[Appeal dismissed.]
JUDGMENT
Zakaria Yatim JCA:
The appellants are the administrators of the estate of Ahmad bin Ibrahim
(deceased). The defendant is a housing developer within the meaning ascribed
to it under the Housing Developers (Control and Licensing) Act 1966 .
By a sale and purchase agreement ("the said agreement") entered into between
the late Ahmad bin Ibrahim and the defendant on 4 April 1981, the said Ahmad
bin Ibrahim purchased from the defendant a house and land known as Lot No.
1338, Type B3, Taman Muda, Ampang, under the title H.S.(D) 2544 to 2552 for
Lot Nos. 10093 to 10101, Mukim of Ampang, District of Ulu Langat for the
purchase price of RM92,950.00. By cl. 18 of the said agreement, the
defendant agreed to deliver vacant possession of the said house to the said
Ahmad bin Ibrahim not later than 3 October 1982. The appellants alleged in
the statement of claim that the defendant, in breach of the agreement,
delivered the keys to the house on 25 July 1984 but there was no supply of
water and electricity until January 1985. The appellants therefore claimed
liquidated damages for late delivery calculated from 4 October 1982 to 25
January 1985 in the sum of RM17,398.20 together with interest and general
damages.
The defendant, contended that the house was delivered to the appellants on
31 March 1983 and the delay was only for 179 days and not as alleged by the
appellants. The defendant said under the agreement, the appellants were only
entitled to claim for liquidated damages for delay in delivery of vacant
possession by the defendant but did not include any delay caused by the
relevant authorities to supply water and electricity to the said house.
The learned Sessions Judge decided that damages for late delivery was to be
calculated from 3 October 1982 to 31 March 1983 for the delay of a period of
179 days. On appeal to the High Court, Siti Norma Yaakob J (as she then was)
confirmed the decision of the learned Sessions Judge. In her grounds of
Judgment, she said,
There is no evidence to show otherwise although as at 31 March 1983, the
house was not yet supplied with water and electricity. As the supply of such
amenities is not the responsibility of the respondent, I consider that
delivery of vacant possession had been validly effected on 31 March 1983,
for as at that date, the respondent had fulfilled all their statutory and
contractual obligations both under the Rules and under the agreement. The
fact that water and electricity were supplied very much later is due very
much to the delay of the relevant authorities, for which the respondent
cannot be faulted and for which they had been exempted by clause 18 of the
agreement.
On that finding, I have no reason to disturb the decision of the Sessions
Court and I had accordingly dismissed the appellants' appeal with costs.
The respondent contended that it had delivered vacant possession of the
house on 31 March 1983. Miss Tan Ming-Li submitted that the internal mains
were connected to the external mains on 31 March 1983. The connected to the
external mains on 31 March 1983. The appellants said that on that date the
house was not supplied with electricity. Mr. Walter Pereira, Counsel for the
appellants argued that under cl. 18 of the said agreement vacant possession
of the house was delivered when there was flow of water and electricity into
the house. He said that electricity was supplied to the house only on 16
February 1985. It was also the appellants' contention that water was
supplied to the house in January 1985.
It is now necessary to examine the relevant provision of the law and the
relevant clause in the agreement. Rule 12(1) (1) of the Housing Developers
(Control and Licensing) Rules, 1970 states as follows:
(1) provisions binding on the licensed housing developer that he shall at
his own costs and expenses cause of connection of electricity, water and
sewerage mains of the Appropriate Authority or public authority with the
internal electricity, water and sewerage mains of the housing accommodation
erected for the purchaser"
We agree with Siti Norma Yaakob J that the Rule speaks of connection of the
electrical and water mains and that the respondent's obligation was only to
connect electricity and water mains to the internal electricity and water
mains and not the flow of water and electricity.
Clause 18 of the agreement states as follows:
(18) Subject to cl. 33 hereof and/or to any extension or extensions of
time as may be allowed by the controller the said building shall be
completed and ready for delivery of possession to the purchaser within
eighteen (18) calendar months from the date of this agreement save that the
Vendor shall not be responsible or liable for any delay on the part of the
relevant authorities to supply water and/or electricity to the said
building.
Provided always that if the said building is not completed and ready for
delivery of possession to the purchaser within the aforesaid period, delay
cause by circumstances set out in cl. 33 hereof or delay on the part of the
relevant authorities to supply water and/or electricity excepted, then the
vendor shall pay to the purchaser agreed liquidated damages calculated from
day to day at the rate of eight per centum (8%) per annum on the purchase
price of the said property from such aforesaid date to the date of actual
completion and delivery of possession of the said building to the purchaser.
The above clause is consistent with r. 12(1)(1). The clause explicitly
provides that the developer shall not be responsible or liable for any delay
on the part of the relevant authorities to supply water and electricity.
We agree that vacant possession was delivered to the appellants on 31 March
1983.
In our view, the above Rule and cl 18 of the agreement, clearly state that
the duty of the developer is only to connect the electricity and water mains
to the internal mains. The supply of water, and electricity are the
responsibility of the relevant authorities.
For the reasons stated above we dismiss the appeal with costs.
|