INSUN DEVELOPMENT SDN. BHD. V. AZALI
BAKAR
SUPREME COURT, KUALA LUMPUR
TAN SRI DATO' LAMIN MOHD YUNUS PCA TAN SRI DATO' EDGAR
JOSEPH JR. FCJ DATO' MOHAMED DZAIDDIN ABDULLAH FCJ
(CIVIL APPEAL NO: 02-348-1994)
CIVIL PROCEDURE:
Action for damages by purchaser for late-delivery of house by developer -
Limitation - When does the purchaser's right to sue for agreed liquidated
damages accrue - Whether purchaser's claim time-barred - Limitation Act 1953
s. 6(1) .
HOUSING DEVELOPERS:Damages for late-delivery - Agreement in the
statutorily prescribed Schedule E form - When does the purchaser's right to
sue for agreed liquidated damages accrue - Construction of clause 18 of the
standard form agreement.
11 MAY 1996
JUDGMENT
Edgar Joseph Jr. FCJ:
This is an appeal from the judgment of the High Court, Johor Bahru,
ordering that judgment should be entered in favour of the plaintiff Azali
bin Bakar, the purchaser (the purchaser) under a sale and purchase agreement
dated 12 December 1984 (the agreement), of a single-storey dwelling house
(the house) to be erected by the defendant Insun Development Sdn. Bhd., the
corporate licensed developer (the vendor). The agreement was in the form
prescribed in the schedule to the Housing Developers (Control & Licensing)
Regulations, 1982 (the 1982 Regulations).
More particularly, the purchaser's claim by way of originating summons,
issued on 31 July 1993, was for a declaration as to entitlement to agreed
liquidated damages for breach of contract, calculated of the rate of 10% per
annum on a daily basis on the purchase price of RM49,725 from 12 December
1986 to date of delivery of possession of the house. Alternatively, the
purchaser's claim was for a declaration as to entitlement to liquidated
damages as aforesaid, under the Housing Developers Act 1966 and the
regulations made thereunder, to wit, the 1982 Regulations. In the event, the
Judge held that the purchaser was entitled to the primary declaration prayed
for and entered judgment in his favour, accordingly.
The essential facts may be shortly stated. The agreement was dated 12
December 1984 and by clause 18 thereof, it was provided, as follows:
- 18(1) The said building shall be completed by the vendor and vacant
possession delivered to the purchaser within twenty-four (24) calendar
months from the date of this agreement.
- (2) If the vendor fails to deliver vacant possession of the said
building in time the vendor shall pay immediately to the purchaser
liquidated damages to be calculated from day to day at the rate of ten per
centum (10%) per annum of the purchase price.
It was common ground that the house was not completed and available for
delivery until 25 March 1994 and that there had thus been a delay from 12
December 1986 until 25 March 1994, on the part of the vendor in delivering
vacant possession of the same.
A demand for agreed liquidated damages by the purchaser having been
refused by the vendor, the former commenced proceedings by way of the
originating summons aforesaid for the declarations aforesaid and for
consequential reliefs.
The vendor's defence was that the purchaser's claim was barred by s. 6(1)
of the Limitation Act, 1953 . More particularly, it was contended that as
the purchaser's claim was founded upon a breach of contract that is to say,
of clause 18, his cause of action accrued on the day following the time
limited under the agreement for completion and delivery of vacant possession
of the house. On this view the purchaser had commenced the proceedings
aforesaid more than seven months out of time and his claim was therefore
barred by limitation.
In giving judgment for the purchaser, the Judge relied heavily on the
Malaysian. Privy Council decision in Loh Wai Lian v. SEA Housing Sdn. Bhd.
[1987] 2 MLJ 1. It follows, that the point of central importance to this
appeal is whether the present case is governed by the judgment of the Privy
Council in Loh Wai Lian, as the Judge thought.
In Loh Wai Lian's case, by a contract in writing dated and
executed on 18 March 1974, the plaintiff/buyer had agreed to purchase and
the defendant/ developer - a corporate licensed housing developer - had
agreed to sell a shophouse to be constructed by the developer. By clause 17
of the contract it was provided as follows:
- Subject to clause 32 hereof and/or to any extension, or extensions of
time as may be allowed by the controller the said building shall be
completed and ready for delivery of possession to the purchaser within
eighteen (18) calendar months from the date of this agreement. Provided
always that if the said building is not completed and ready for delivery
of possession to the purchaser within the aforesaid period then the vendor
shall pay to the purchaser agreed liquidated damages calculated from day
to day at the rate of eight per centum (8%) per annum on the purchase
price of the said property from such aforesaid date to the date of actual
completion and delivery of possession of the said building to the
purchaser.
The applicable legislation in Loh Wai Lian was the Housing
Developers (Control and Licensing) Rules 1970 ("the 1970 Rules") r. 12(l) of
which provided:
- Every contract of sale shall be in writing and shall contain within
its terms and conditions provisions to the following effect, namely: ...
There were then set out twenty-one matters which were required to be
incorporated in the contract of sale, of which the following were relevant
for purposes of the case:
- (o) Provisions specifying the date of delivery of the vacant
possession of the housing accommodation to the purchaser which date shall
be not later than 18 months after the date of signing of the contract of
sale ...
- (r) Provisions binding on the licensed housing developer that he shall
indemnify the purchaser for any delay in the delivery of the vacant
possession of the housing accommodation. The amount of indemnity shall be
calculated from day to day at the rate of not less than eight per centum
per annum of the purchase price commencing immediately after the date of
delivery of vacant possession as specified in the contract of sale ...
For reasons which will appear later, it is important, to note that clause
17 provided a formula for the computation of the agreed liquidated damages
which defined not only its terminus a quo (its opening date) but also
its terminus ad quem (its closing date).
In the event which transpired, there had been a delay in the completion
of the shophouse and it was not until 7 November 1977 that it was in fact
completed. Upon the developer refusing to pay the buyer's demand for
liquidated damages for late delivery, the plaintiff/buyer had commenced an
action against the former for liquidated damages for breach of contract. In
O. 14 proceedings before the Senior Assistant Registrar, the plaintiff/buyer
had succeeded, but on appeal before the Judge in Chambers, the developer's
contention that the plaintiff/buyer's claim was barred by limitation by
virtue of s. 6(1) of the Limitation Ordinance, 1953, was upheld and the
order for summary judgment set aside.
It was next the plaintiff/buyer's turn to appeal to the then Federal
Court, her contention being that regard being had to the provisions of the
proviso to clause 17 of the contract, the cause of action was not complete
until the shophouse was actually completed and vacant possession given to
her and that going by this date, she had commenced proceedings well within
the time limited by the statute.
Before the Federal Court, the plaintiff/ buyer had relied upon the cases
of Turner v. Midland Railway Co. [1911] 1 KB 832, Central
Electricity Generating Board v. Halifax [1962] 3 AER 915, 923, and
Monckton v. Payne [1899] 2 QB 603 , which are authority for the
proposition that where the mode of assessing liquidated damages has been
agreed, time will not run from the date of the breach but from the date when
the damages can be ascertained.
As to the plaintiff/buyer's contention that regard being had to the
provisions of the proviso to clause 17, the cause of action was not complete
until the shophouse was actually completed and vacant possession given to
her, the Federal Court said this:
- Such a proposition would in fact mean that if the respondents did not
complete the shophouse, accrual of cause of action could be postponed
indefinitely. We do not think that the proviso to clause 17 of the
agreement could have that effect on the Limitation Ordinance in an action
founded on contract. A distinction must clearly be recognized between a
cause of action and the relief claimed. The date of completion of the
shophouse was only necessary to quantify the maximum relief under clause
17 which could be done subsequently by evidence. It could not constitute
an impediment to the cause of action being complete. The breach had
occurred on 18 September 1975 giving rise to a complete cause of action,
and the accrual of cause of action would not be postponed by temporary
lack of evidence pertaining to maximum relief claimable resulting from
such breach irrespective of whether the damages claimed were liquidated or
unliquidated. In the circumstances of the present case, we would not agree
to the proposition that the cause of action was not complete until the
shophouse was completed.
As for the cases of Turner, Central Electricity Generating Board
and Monckton, the Federal Court distinguished them as follows:
- Clause 17 itself had provided that such damages were to be calculated
on a day to day basis from the date of breach with the date of actual
completion to be used for the purpose of calculating the maximum days
claimable. Thus, even a day after the date of breach liquidated damages
could be ascertained under clause 17. In any event, if the present
statement of claim had been filed on or before 17 September 1981, no Court
could have struck it out as disclosing no cause of action merely because
the maximum liquidated damages claimable were not quantified. The action
was not an ordinary claim for money due and owing, the sum of which ought
to be ascertained.
Not deterred the plaintiff/buyer pursued her appeal to the Privy Council
[1987] 2 MLJ 1. The Court which comprised Lord Oliver, Lord Bridge, Lord
Templeman, Lord Griffiths and Lord Mackay, unanimously decided in favour of
the plaintiff/buyer and allowed the appeal thereby restoring the order of
the Senior Assistant Registrar giving summary judgment.
The crucial point for decision before their Lordships was, of course,
when did the cause of action accrue, having regard to the particular
contract before them, for it was with effect from that date that time
commenced to run for purposes of the Limitation Act.
In considering this question, their Lordships were of the view, that it
was important, first of all, to identify the true nature of the developer's
obligation. This is how their Lordships put it:
- Mr. Kidwell QC on the other hand, contended that both the trial Judge
and the Federal Court were wrong to approach the case on the footing that
the claim was a simple claim for liquidated damages for breach of
contract. He submitted and their Lordships agree, that the analysis of the
accrual of the appellant's cause of action depends not upon the label
which was put upon the sums which the respondent became obliged to pay but
upon what, on the proper construction of the contract, was the true nature
of the respondent's obligation.
In deciding the question, what was the true nature of the vendor's
obligations, their Lordships laid much stress on the 1970 Rules and the
proviso to clause 17 of the contract of sale. This is how they put it.
- The starting point is that this contract is one the terms of which are
regulated by statute and which therefore falls to be construed in the
light of the statutory provisions to which it was designed to give effect.
Their Lordships then drew attention to the statutory obligation imposed
on the developer in these terms:
- Rule 12(1)(r) imposed on the developer the obligation to indemnify the
purchaser for any delay in delivery of possession and then went on to
provide a formula by which 'the amount of indemnity' was to be calculated.
The use of the word 'indemnity' is significant, for in its natural
meaning, it imports the notion of compensation for a loss already suffered
when the compensation is paid (see, for instance, Yorkshire Electricity
Board v. British Telecom, [1986] 1 WLR 1029, 1034)
Next, touching on the question how r. 12(1)(r), when incorporated had
been modified by the contract of sale, their Lordships said this:
- That rule, when incorporated into the actual contract between the
parties, was modified in two ways. First, the 'indemnity' provided for by
the rule was translated as 'agreed liquidated damages'. Secondly, the
formula for calculation of the indemnity was modified by specifying not
only the terminus a quo as provided in the rule but also the
terminus ad quem, that is to say, the date of actual completion and
delivery of possession.
Their Lordships then went on to make this observation:
- It is, in their Lordships' view, tolerably clear that the only
rational purpose of defining a payment to be made by the vendor, by
reference to what has become a conventional term, as 'agreed liquidated
damages' was to make it clear that the purchaser was not to have any right
to any other payment by way of damages in respect of the delay over and
above what the vendor was undertaking to pay, for there could not sensibly
be any prospect of a sum calculated according to mandatory statutory
provisions being held to be irrecoverable as a penalty.
Their Lordships then went on to caution:
- But the description of the amount as 'liquidated damages' cannot in
any event be determinative of the date on which the sum is to be payable.
The clause has to be reasonably and sensibly construed. The obligation is
introduced by the words 'the vendor shall pay' and there follows the
calculation of the sum which he is to pay carefully defined by its opening
and closing date.
Applying what they considered to be a reasonable and sensible
construction of clause 17 of the contract of sale, their Lordships said
this:
- The whole tenor of the clause is, in their Lordships' view, that the
vendor is assuming as a matter of contract and subject to the occurrence
of the condition precedent that the building remains uncompleted on the
stipulated date, an express contractual obligation to pay a single sum
which cannot become due, because it cannot be ascertained, until the
building has been completed and possession can be delivered.
Their Lordships recognised that the general rule was that a purchaser's
right of action for damages for breach of contract accrues on the date when
the breach occurs. But parties were free to enter into a contract displacing
or modifying the general rule and this is what the parties before their
Lordships had done by the incorporation of clause 17 into their contract of
sale. Their Lordships accordingly concluded:
- In their Lordships' judgment, the only sensible construction of clause
17 is, as Mr. Kidwell has contended, that it imposes an obligation to pay,
in substitution for any other right to damages which the purchaser might
otherwise have, a single sum to be calculated and ascertained at a
particular date and that until that sum has been ascertained it does not
become due and cannot be sued for.
First of all, we must point out, that in the present case, the agreement
is regulated by the 1982 Regulations, which, by reg. 12(1), provides that
every contract for the sale and purchase of housing accommodation shall be
in the standard form prescribed in Schedule E. The agreement with which we
are concerned was, as we have indicated at the outset, exactly in the form
prescribed in Schedule E with no supplementation.
The crucial question is: regard being had to the provisions of clause 18
of the agreement, when did the purchaser's right to sue for the agreed
liquidated damages, for the delay hereinbefore mentioned, accrue?
It is clear law, that in the absence of express contractual provision,
the purchaser's right to sue for damages would accrue on the date of the
breach of contract (See Nasri v. Mesah [1970] 1 MLJ 32, 34 ;
Reeves v. Butcher [1891] 2 QB 509, 511; Gibbs v. Guild [1881] 8
QBD 296, 302). But, the parties to a contract are free to regulate or modify
their rights in the event of breach thereof in such a manner as to postpone
the date of accrual of their right to sue for damages which, of course, was
what had happened in Loh Wai Lian.
In the present context, we have to consider whether there is any, and if
so, what material difference between the contract of sale in Loh Wai Lian
and the agreement here.
The obvious difference between the contract of sale in Loh Wai Lian
and the agreement here, which we consider to be most material, is this:
under the former, the statutory formula for the calculation of the indemnity
was modified by expressly stating not only the terminus a quo (the
opening date) but alsothe terminus ad quem(the closing date),
which was the date of actual completion and delivery, of possession,
whereas under the latter, although there is, by clause 18(2), also a
formula for the calculation of liquidated damages, it only specifies the
terminus a quo but not the terminus ad quem. In our view,
this difference is a matter of critical substance.
It is obvious from the judgment of the Privy Council in Loh Wai Lian,
that but for the unusual language of clause 17 of the contract of sale,
which had provided a formula for the computation of damages payable by the
developer to the buyer for delays, by defining not merely the terminus a
quo (the opening date) required under r. 12(l)(r) of the 1970 Rules but
also the terminus ad quem (the closing date) - not required
under r. 12(l)(r) - the case would have been differently decided for their
Lordships said this:
- If the question is asked 'in the absence of such an express provision
when would the purchaser's right of action for damages for breach of
contract accrue?', the answer is plainly the date on which the breach
occurred. But parties to a contract are, of course, entitled to regulate
or modify their rights in the event of breach in any way that they think
fit and the accrual of any cause of action then becomes a matter of the
correct construction of what they have provided. This appeal raises no
point of principle but simply a question of what is the true construction
of the contract in which the parties entered.
In our view, for the reasons stated, Loh Wai Lian is, therefore,
readily distinguishable from the present case, and accordingly, the Judge
was, with respect, wrong in holding that it was of decisive importance to
the question which arose for decision.
It follows, therefore, that our answer to the crucial question aforesaid
is; because the agreement by clause 18(2) had provided for a formula for the
calculation of liquidated damages which defined the terminus a quo
(the opening date) but not the terminus ad quem (the closing
date), the purchaser's right of action for damages for breach of contract,
following the general rule, accrued on the date of the breach, which in this
case was the day after the time limited under clause 18(2) for the delivery
of vacant possession, that is to say, on 12 December 1986. Accordingly, the
purchaser having commenced proceedings only on 31 July 1993, was more than
seven months out of time. We are thus driven to the inevitable conclusion
that the purchaser's claim was statute-barred under the provisions of s.
6(1) of the Limitation Act, 1953.
The appeal must, therefore, be allowed with costs here and below. The
judgment of the Court below is set aside, and there will be substituted, in
lieu thereof, judgment in favour of the vendor, that is to say that the
purchaser is not entitled to the declarations prayed for or either of
them nor to any other reliefs. The deposit will be refunded.
Our human sympathies are for the purchaser but we are not at liberty to
indulge them.
|