HWA CHEA LIN & ANOR V MALIM JAYA (MELAKA)
SDN BHD
HIGH COURT [MELAKA]
CIVIL SUIT NO 22–49–1988
SURIYADI J
19 JANUARY 1996
Suriyadi J
On 11 September 1984, the plaintiffs entered into an agreement with the
developer (the 'defendant') for the purchase of a single-storey terrace
house identified as No 126, Jalan Zahir 18, Taman Malim Jaya, Jalan Malim,
75250 Melaka ('the said building') on Lot PT No 1279, HS (M) 1015/82, Mukim
Bacang, District of Melaka Tengah, Melaka. The purchase price was RM62,950
only. Under cl 18 (B1–11), the said building was to be completed by the
vendor and vacant possession delivered to the purchasers within 24 calendar
months from the date of the agreement. The defendant later served a notice
dated 3 June 1986 (B79) to the plaintiffs to take delivery of vacant
possession even though the supposed delivery date was 7 September 1986. The
plaintiffs, sometime in 1987, orally complained to the defendant as to the
defects found in the building. Remedial works were done in the same year
albeit unsatisfactorily. The plaintiffs undeterred further complained to one
Mr Ng, who was the manager of the defendant, and was assured that further
repairs would be carried out after the Chinese New Year in 1988. The
defendant kept their words but the plaintiffs were still dissatisfied with
the repairs done. Unhappy with the situation, the first plaintiff complained
vide letter dated 4 April 1988 (B83). From the evidence, it was adduced that
the plaintiffs subsequently employed certain experts, amongst them an
engineer who visited the site in 1988 who later prepared the relevant report
in September 1988 and an architect. On 28 May 1988, the plaintiffs through
their solicitors sent P1, ie a letter rescinding the contract. On 18
November 1988, the plaintiffs filed this action. Evidentially it is not
disputed that the defendant literally tore down four rows of houses
including the said building sometime in February 1990 and completed the
rebuilding at the end of 1991.
The plaintiffs alleged in para 7 of the statement of claim that there was
a fundamental breach of the agreement as the house they received on 3 June
1986 was not what they had bargained for and therefore the rescission was
correct in law. The plaintiffs, therefore, prayed for the refund of all the
monies already paid inclusive of interest and certain other reliefs.
The defendant in the statement of defence asserted that at all material
times the defendant had carried out the construction of the said single-
terrace house in a good and workmanlike manner and in accordance with the
specifications described in the second schedule to the said agreement. The
defendant also alleged that the plaintiffs could not have rescinded the
agreement as they had acquiesced to the contract. Aside from that, there was
no evidence of the requirements of s 40 of the Contracts Act 1950 ('the
Act') being fulfilled, namely that the defendant had refused or was
incapable of fulfilling the contract. In para 5 of the amended statement of
defence and counterclaim, the defendant had averred that the massive cracks,
foundation faults, sinking and other major structural defects alleged by the
plaintiffs were beyond the control of the defendant as the defects
complained of were entirely that of the act of nature but no evidence was
adduced to support this contention. In fact, the defendant had persisted on
the defence that the rescission was bad and that the contract was still
good.
To support the plaintiffs' case four witnesses were called, namely PW1
the first plaintiff himself, PW2 an architect, PW3 a neighbour of the
plaintiffs who was in the same predicament as the plaintiffs and PW4 an
engineer. PW1 in his evidence admitted that on 3 June 1986 he received B79,
a notice requesting him to take vacant possession. He did not take the keys
as the house was in an unsatisfactory state. He subsequently informed Mr Ng
of the state of the house and he in return promised that remedial works
would be done later. The remedial works were completed in 1987 but were
still not up to the mark and PW1 lodged a similar complaint. Repairs were
again undertaken after the Chinese New Year in 1988 but with the same
negative results. Bitter with the situation, he voiced out his unhappiness
vide a letter dated 4 April 1988 (B83) which contained among others his
complaints regarding cracks, sinking and other defects in the house. He
asserted that the defects were major defects involving the structure and
foundation of the building. Aside from recording his extreme dissatisfaction
in the manner in which the house was constructed, he ventilated his fears of
his personal safety, hence causing him not to be able to occupy the house.
PW1 also said before his lawyer's rescission letter was forwarded to the
defendant he did request from Mr Ng a new house as a replacement. He also
gave evidence that a few years later the said building was literally torn
down and rebuilt.
PW2, an architect by profession who investigated into the condition of
the said building, evinced that he saw first hand on 9 August 1988 that the
ground on which the building was built had sunk at different parts. The
substantial differential settlement on the land led to the cracks and tear
of the building. He concluded that the construction was no longer safe for
habitation and therefore required a major repair to be undertaken. PW4, a
qualified engineer on instruction of PW1, inspected the said building on 31
January 1988. He too found many sink holes when the repairmen hacked the
concrete leaving a void wherever the earth had subsided. In fact, he found
that the ground floor slabs had not followed the British Code of Practice
emulated by the Malaysian practices as the ground floor slab was a mere 11ú2
in and not 4in. The cement content was low and piling had not been properly
carried out. He similarly concluded that overall the workmanship was poor
and the house was unsafe to stay in.
PW3, who is the neighbour of PW1, was one of the purchasers of the lot of
houses built by the defendant. His house is immediately to the right of
PW1's house as one faces away from the row of buildings. He moved in into
his unit in September 1987 but moved out in February 1990 when the house was
dismantled. He confirmed that the plaintiffs' house too was rebuilt and
completed at the end of 1991.
Aside from the evidence adduced from these witnesses, photographs were
tendered which lucidly highlighted the poor condition of the relevant
building. The pictures spoke for themselves. Besides highlighting the
serious defects, they confirmed the subsequent actions of the defendant
after 1990 when the defendant literally tore down and rebuilt the building.
The defendant in their submission admitted of the literal rebuilding but
justified the necessity of the dismantling of the walls and the roof in
order to redress the foundation and the structure of the building.
The relevant questions begging to be considered by the court, inter alia,
would be:
(1) whether cl 23 which provided for a defect liability period is
relevant in this case;
(2) whether there was a fundamental breach which justified a rescission
on the part of the plaintiff; and
(3) whether there was a good rescission when the plaintiffs through his
lawyer sent the letter of rescission on 28 May 1988 (P1).
To have a better understanding of the above problems and before
disseminating in detail the legal intricacies involved, perhaps it would not
be inappropriate to touch briefly on the contention of the defence. The
defendant submitted that since vacant possession had taken place on 3 June
1986 and a year had passed, the plaintiffs could not now invoke cl 23. This
clause provided a mere one year for the defect liability period. Further,
the plaintiffs could not have rescinded the contract as there was no
evidence that the defendant had refused or was unable to perform the
contract what with the conduct and attitude of the plaintiffs before or
after 28 May 1988 showing acquiescence to contract.
The plaintiffs have asserted that they had rescinded the contract on the
solitary ground of fundamental breach on the part of the defendant. To fully
understand the plaintiffs' stance perhaps it would be better if I discuss
the expression of 'fundamental breach of contract' briefly. 1 Chitty on
Contracts (24th Ed) at p 367 elucidated:
The expression 'fundamental breach of contract' is used in two quite
different senses. In one sense, it denotes a breach by one party which is
sufficiently serious to entitle the other party, not merely to claim
damages, but to elect to treat himself as discharged from further
performance under the contract … In another sense, however, fundamental
breach expresses a supposed principle of law that there are certain
breaches of contract which are so totally destructive of the obligations
of the party in default that liability for such a breach cannot be limited
or excluded by means of an exemption clause.
In Suisse Atlantique Societe D'Armement Maritime SA v NV Rotterdamsche
Kolen Centrale [1967] 1 AC 361, the House of Lords held that even though
there was a breach that went to the root of the contract but as they had
affirmed the contract 'they cannot escape from the consequences of the
demurrage clause, unless as a matter of construction, they can show that it
has no application to the events of this case' (per Lord Upjohn). Therefore,
if the innocent party had elected to affirm the contract he would thus be
bound by the terms of the contract including the exemption clause. If the
innocent party had elected to treat the breach as discharging himself from
further performance of the contract 'the whole contract has ceased to exist
including the exclusion clause, and I do not see how that clause can be used
to exclude action for loss which was suffered by the innocent party after it
has ceased to exist …' (per Lord Reid at p 398B; see also Chua Ngah Chin
v Ng Kie En [1986] 1 MLJ 267 ).
Pearson LJ on this point in UGS Finance Ltd v National Mortgage Bank
Of Greece and National Bank of Greece [1964] 1 Lloyd's Rep 446 at p 450
had this to say:
As to the question of 'fundamental breach,' I think there is a rule of
construction that normally an exception or exclusion clause or similar
provision in a contract should be construed as not applying to a situation
created by a fundamental breach of the contract … This is … a rule of
construction based on the presumed intention of the contracting parties …
This rule of construction is not new in principle but it has become
prominent in recent years in consequence of the tendency to have standard
forms of contract containing exception clauses drawn in extravagantly wide
terms, which would produce absurd results if applied literally.
In George Mitchell v Finney Lock Seeds [1983] 1 All ER 108, the
court too was of the view that exclusion clauses which purported to exclude
all liability were to be construed more narrowly than those which sought to
limit liability.
In another landmark case but many years earlier, the court in Harbutts
'Plasticine' Ltd v Wayne Tank and Pump Co Ltd[1970] 1 QB 447 affirmed
that where a fundamental breach occurred and further performance of the
contract was impossible and the plaintiff had no option but to treat the
contract as at an end, the defendant was precluded from relying on the
exemption clause limiting his liability.
In Malaysia, the terminology of fundamental breach, which is a concept of
the common law, though not in exact term terms has become a creature of
statute (seeChoo Yin Loo v Visuvalingam Pillay(1930) 7 FMSLR 135).
The relevant provision which is now enshrined in s 40 of the Act reads:
When a party to a contract has refused to perform, or disabled himself
from performing, his promise in its entirety, the promisee may put an end
to the contract, unless he has signified, by words or conduct his
acquiescence, in its continuance.
For the innocent party to rescind, two situations must prevail, namely
that the offending party had refused to perform or disabled himself from
performing his promise. (The relevant contract as indicated by para 3 of the
statement of claim comes under the Housing Developers (Control and
Licensing) Act 1966.) The defendant's counsel had consistently argued that
there was absolutely no evidence that the defendant had refused or had
disabled itself from performing its promise. On the contrary, the defendant
was not only willing but was in the process of fulfilling its obligation as
provided by s 47 of the Act. The defendant further submitted that the
plaintiffs by conduct or words had acquiesced in the continuance of the
agreement. This point will be discussed in detail later. Now is the right
time to decide whether a fundamental breach or a non-performance of the
contract as envisaged by s 40 of the Act had occurred which entitled the
plaintiffs to rescind. (Henceforth, I shall maintain the terminology of
'fundamental breach' since I am fully satisfied that the provision of s 40
is the direct descendant of the common law concept.) Further, even if the
court is satisfied that a fundamental breach had occurred the further
question to be answered is whether the plaintiffs had elected to discharge
the contract or had acquiesced to the contract. From the evidence adduced, I
must conclude that a fundamental breach had occurred as the building that
was delivered to them in 1986 was not what they had bargained for (see
Pollock & Mulla on Indian Contract and Specific Relief Actsat p 397). On
perusal of the sale and purchase agreement dated 11 September 1984 (B1-B11),
the vendor agreed to sell the plaintiffs a single-storey terrace house with
the details provided in the second and third schedules. The evidence adduced
during the hearing clearly showed that the said building when delivered to
the plaintiffs was in a terrible shape that required massive remedial works
and eventually had to be rebuilt. Since what was delivered was not what had
been agreed upon surely the breach was a breach that went to the root of the
contract. I also find solace in the writings of Cheshire and Fifoot's Law
of Contract(8th Ed) at p 566 which reads:
Of what nature, then, must a breach be before it is to be called
'fundamental?' There are two alternative tests that may provide the
answer. The court may find the decisive element either in the importance
that the parties would seem to have attached to the term which has been
broken or to the seriousness of the consequences that have in fact
resulted from the breach. We have already suggested that the former is the
happier approach to the matter …
According to this test, the governing principle is that everything
depends upon the construction of the contract in question. The court has
to decide whether, at the time when the contract was made, the parties
must be taken to have regarded the promise which has been violated as of
major or of minor importance. In the words of Bowen LJ:
'There is no way of deciding that question except by looking at the
contract in the light of the surrounding circumstances, and then making up
one's mind whether the intention of the parties, as gathered from the
instrument itself, will best be carried out by treating the promise as a
warranty sounding only in damages, or as a condition precedent by the
failure to perform which the other party is relieved of his liability.'
Since the plaintiffs did not get delivery of a house in the accepted
sense clearly a fundamental breach had occurred. Case law too has clearly
come to the forefront to affirm that in a contract with builders for the
purchase of a house to be erected there is an implied warranty by the
vendors that the house would be built in an efficient and workmanlike
manner, and with proper materials and fit for habitation (seeMiller v
Cannon Hill Estates Ltd[1931] 2 KB 113; Teh Khem On & Anor v Yeoh &
Wu Development Sdn Bhd & Ors [1995] 2 MLJ 663 ; Hancock & Ors v
Brazier (BW) (Anerley) Ltd[1966] 2 All ER 901).
I now come to another related issue, namely whether on a proper
construction of cl 23 this defect liability period clause did exclude a
fundamental breach. Clause 23 reads:
(23) Any defect, shrinkage or other faults in the building which shall
become apparent within a period of 12 calendar months after the date of
delivery of vacant possession to the purchaser and which are due to
defective workmanship or materials or the said building not having been
constructed in accordance with the said specifications and plans as
approved by the appropriate authority (amended or unamended as the case
may be) shall be repaired and made good by the vendor at his own cost and
expense within one month of its having received written notice thereof
from the purchaser and if the said defects, shrinkage or other faults in
the said building have not been made good by the vendor, the purchaser
shall be entitled to recover from the vendor the costs of making good the
same and the purchaser may deduct such costs from any sum which has been
held by the vendor's solicitor as stakeholder for the vendor.
Having perused this clause on a plain interpretation, it merely laid down
the responsibility of the vendor over minor defects within one year of the
delivery of vacant possession and of his subsequent liability were there to
be discovered new ones. Definitely this defect liability period provision is
silent as to the ousting of fundamental breaches. To use the words under
para 3 of the headnote in George Mitchell (Chesterhall) Ltd v Finney Lock
Seeds Ltd[1983] 1 All ER 108:
Those breaches could not have occurred without negligence on the part
of the defendants. Accordingly (Lord Denning MR dissenting), on its true
construction the limitation clause did not exempt the defendants from
liability because there was nothing in it which protected them from the
consequences of their own negligence and (per Oliver LJ) because what was
delivered was wholly different in kind from that which the plaintiffs had
ordered.
The fact that the defendant, sometime in 1990, rebuilt the building lends
credence to the court's findings that what was delivered to the plaintiffs
in 1986 was not the unit of property agreed and expected by the latter. Had
the building been built in line with all the required specifications and in
accordance with all legal requirements surely the building would not have
been torn down and rebuilt.
The next relevant point that is to be considered is whether after having
realized that a fundamental breach had occurred whether the plaintiffs had
acquiesced to the continuance of the contract or had elected to rescind it.
If the rescission was good in law then they had extricated themselves from
the agreement consequenting in the termination of the contract. Several
events were highlighted by the defendant to prop up the argument that the
plaintiffs had acquiesced in the continuance of the contract, viz:
(i) the charge and loan documents executed in 1986 (B12-24);
(ii) legal fees paid in August/September 1986 (B28);
(iii) after having taken vacant possession in June 1986 the
plaintiff had visited one Mr Ng, a representative of the defendant's
company, requesting that remedial works be carried out. In fact, in 1987,
PW1 again asked for a second remedial works be carried out. He was
promised that further remedial works would be carried out after the 1988
Chinese New Year;
(iv) the employment of an architect in April 1988;
(v) the preliminary reports prepared by PW4 in September 1988
and photos taken in April 1988;
(vi) photographs taken in February, June and December 1990
(B111–134);
(vii) a loan taken by the plaintiffs from 7 October 1986 all the
way up to 13 October 1993;
(viii) payments of quit rents from 1987 to 1991 (B29/B31);
(ix) assessments paid by the plaintiffs from July 1988 until
January 1992 (B32/B34); and
(x) PW1's continual reference to the house as his house and his
acceptance of the house as his.
The sum total of these factors, the defendant submitted, would lead to
the irresistible conclusion that the plaintiffs wanted the defendant to
rectify the defects as indicated by their conduct especially the continued
monitoring of the repairs, visits to the scene, taking of photographs and
employing of experts. The defendant's counsel submitted that surely, all
these factors support the contention that the plaintiffs had acquiesced to
the continuance of this contract. If the court were to agree with the issue
of the acquiescence, the dicta of Salleh Abbas FJ (as he then was) in Sim
Chio Huat v Wong Ted Fui [1983] 1 MLJ 151 would be relevant especially
at p 153 para G–H left which reads:
By allowing the delivery dates to pass and by acquiescing in the work
continuing under the agreement and indeed by ordering extra work to be
done for each of these houses, for which the agreement made no provision,
the appellant must be held to have waived his right to rescind the
agreement on account of repudiation and also the right to treat himself as
discharged therefrom. He must be deemed to have elected the agreement as
still continuing.
It would appear in the current case, which is at variance with Sim
Chio Huat,that the plaintiffs had elected to treat themselves as
discharged from further performance of the contract as they had sent a
letter of rescission on 28 May 1988. The plaintiffs, on the other hand, were
not reluctant to admit that they had acquiesced up to 28 May 1988 but not
thereafter. Post 28 May 1988, the plaintiffs showed no further interest in
the said building. The fact that the plaintiffs did not join the other seven
purchasers to demand that the developers carry out remedial works held
testimony to his lack of interest. It was not disputed that the plaintiffs
had not occupied nor taken the keys to the house. The subsequent photographs
taken in 1990 were merely to support the legal action when this present suit
was filed on 18 November 1988. The plaintiffs' counsel too gave reasonable
answers as to why payments had to be continued whether in the form of quit
rents, assessments or the monthly instalments as these were legal and
contractual payments to third parties. Aside from these factors which were
justified by the plaintiffs, the court was affected by these nagging
questions namely:
(i) did the defendant accept the rescission? and
(ii) if the rescission was not accepted why did the defendant
rebuild the relevant premises without obtaining prior permission from the
plaintiffs?
After considering all the evidence and the subsequent actions of the
defendant, I was satisfied that an effective rescission had been proved by
the plaintiffs and that the defendant had also accepted the repudiation of
the contract. Notwithstanding this factor of acceptance by the defendant, I
was satisfied too that the unilateral act of the plaintiffs to terminate the
agreement was sufficient and in accordance with the requirements of the law.
The subsequent activity of the defendant to literally rebuild the four rows
of houses including the said building without securing any prior permission
from the plaintiffs merely supported the correctness of the plaintiffs'
assertion.
The consequential effect of delivering a defective house unfit for human
habitation and unsafe, the defendant thus too, had breached cl 7 of the
agreement. Clause 7 clearly provided that 'time shall be the essence of the
contract' in relation to all the provisions of the agreement.
Perhaps it is quite timely to refer to the case of Chye Fook & Anor v
Teh Teng Seng Realty Sdn Bhd [1989] 1 MLJ 308 at p 309
para C–D as regards damages where Abdul Malek J (as he then was) said:
Now, it is pertinent to examine the law on this point. In Mayson v
Clouet & Anor[1924] AC 980, Lord Dunedin had said 'the law is quite
plain. If one party to a contract commits a breach then if that breach is
something that goes to the root of the contract, the other party has his
option. He may still treat the contract as existing and sue for specific
performance; or he may elect to hold the contract as at an end, that is,
no longer binding on him — while retaining the right to sue for damages in
respect of the breach committed.'
As it was in this case, the plaintiffs did not treat the contract as
subsisting entitling him the right to sue for damages in respect of the
breach but to completely repudiate the contract. For some reason or other,
the plaintiffs did not succeed in proving certain relevant claims such as
the differences in expenses for buying a new house. On the other hand, I was
satisfied that the plaintiffs did prove to the satisfaction of the court the
following prayers which had to be refunded by the defendant, viz:
(1) the purchase price of RM62,950 as illustrated in the sales and
purchase agreement (B1–B11) paid through a RM50,000 loan and the balance
from his own savings (B50);
(2) interest on loan at 10% (B14);
(3) expenses incurred for processing fee (B36);
(4) stamp duties at RM630 (B28);
(5) relevant assessments (B32–B34);
(6) all quit rents (B29–B31);
(7) proven costs of RM300 to experts (B35); and
(8) legal fees RM1,276 (B28).
For this action, I ordered cost against the defendant. The counterclaim
of the defendant was dismissed.
|