XAVIER KANG YOON MOOK V. INSUN
DEVELOPMENT SDN. BHD.
HIGH COURT MALAYA, JOHOR BAHRU
DATO' HJ. ABDUL MALIK BIN HJ. ISHAK J
[ORIGINATING SUMMONS NO. 24-516 OF 1994]
25 JANUARY 1995
CONTRACT: Sale of house - Time essence of the agreement - Breach -
Options available to the innocent party - What damages plaintiff is entitled
to.
By a sale and purchase agreement dated 19 August 1986, the plaintiff
agreed to purchase from the defendant (a licensed housing developer) a piece
of land together with a single storey low cost house (said house). The
plaintiff paid 10% of the purchase price and the balance was payable on
instalment basis as envisaged in the said agreement. By clause 18(i) of the
said agreement, the defendant agreed to complete the said house and deliver
vacant possession to the plaintiff within 24 calendar months from the date
of the said agreement. Further, by clause (18) (2) the defendant agreed to
pay liquidated damages at the rate of 10% per annum of the purchase price to
be calculated on a day to day basis in the event the defendant failed to
deliver vacant possession of said house within the time stipulated. In total
disregard and in breach of the said agreement, the defendant failed to
complete and deliver vacant possession of the said house to the plaintiff
and this state of affairs prevailed until the originating summons was filed.
Pursuant to clause 7 of the agreement time was the essence of the contract.
The plaintiff terminated the agreement and claimed inter alia
liquidated damages.
Held:
[1] As time was provided to be of the essence of the sale &
purchase agreement, the stipulated time period within which the said house
had to be delivered to the plaintiff became an essential condition of the
sale & purchase agreement. The failure of the defendant to fulfill this
condition would entitle the plaintiff to have an option of treating the sale
& purchase agreement either (a) as having been repudiated and sue for
damages, or (b) as still continuing. The plaintiff rightly exercised his
option to proceed under (a).
[2] The language employed in clause 18(2) of the sale & purchase
agreement is clear and unambiguous and its natural meaning relate to the
right of the purchaser plaintiff to rescind and sue immediately for
liquidated damages if the recalcitrant developer failed to deliver the said
house within 24 months form the date of the sale & purchase agreement. In
construing clause 18(2) of the sale & purchase agreement, one must examine
the language employed therein and one must not be influenced by other
unnecessary conditions.
[Plaintiffs' claim allowed].
Cases referred to:
Linggi Plantations Ltd. v. Jagatheesan [1971] 1 LNS 66
Eng Mee Yong & Ors. v. Letchumanan [1979] 1 LNS 18
Lombard North Central plc v. Butterworth [1987] QB 527 at p. 535; [1987] 1
ALL ER 267 at pp. 271 to 272; [1987] 2 WLR 7 at p. 13 (foll)
Chye Fook & Anor. v. Teh Teng Seng Realty Sdn. Bhd. [1989] 1 MLJ 308 (foll)
Tan Yang Long & Anor. V. Newacres Sdn. Bhd [1992] 3 CLJ 666 (Rep)
Loh Wai Lian v. S.E.A. Housing Corporation Sdn. Bhd. [1987] 2 MLJ l (refd)
Azali bin Bakar v. Insun Development Sdn. Bhd. [1994] 3 AMR 51 (cit)
Malaysia National Insurance Sdn. Bhd. v. Abdul Aziz bin Mohamed Daud [1978]
1 LNS 117
Choo Yin Loo v. Visuvalingam Pillay [1930] 7 FMSLR 135 (cit)
Bank of England v. Vagliano Brothers [1891] AC 107 (foll)
Legislation referred to:
Contracts Act, 1950 (Act 136) , ss. 56, 56(1) ,
65 &
76
Housing Developers (Control and Licensing) Act, 1966 (Revised 1973) (Act
118) s. 24
Housing Developers (Control and Licensing) Regulations, 1970, cl. 17
Housing Developers (Control and Licensing) Regulations, 1982cl. 18(2)
Limitation Act, 1953, s. 6(1)(a)
Rules of the High Court 1980, O. 28 r. 4
Others referred to:
Halsbury's Laws of England, 4th Edn., Vol. 9, p. 370
For the plaintiff - Adi Radlan bin Abdul Rahman; M/s. Mak, Ng, Shao & Kee
For the defendant - S. Thomas; M/s. Rashid & Lee
[Plaintiffs' claim allowed].
|