LIMMEWAH DEVELOPMENT SDN BHD V. DR
JASBIR SINGH S/O HARBHAJAN SINGH
HIGH COURT [MUAR]
CIVIL APPEAL NO 11-1 OF 1990
RICHARD TALALLA, J
17 FEBRUARY 1993
GROUNDS OF JUDGMENT
By agreement (the contract) made on the 15th day of September 1981, the
appellant who was a housing developer (the Developer) contracted with the
respondent (the Buyer) to sell the Buyer a bungalow. The contract was
governed by the provisions of The Housing Developers (Control and Licensing)
Act, 1966 (the Act) and was in the form prescribed by the Rules thereunder.
The contract provided inter alia for the purchase price to be paid by
instalments and at times, as were set out in a schedule attached thereto, in
default the Buyer to pay interest on the sum due and unpaid, the
bungalow to be completed and ready for delivery of possession to the Buyer
within a certain time if not the Developer was to be liable to pay the Buyer
liquidated damages calculable as stipulated in the contract.
The Buyer was a government servant. He made an application to the
Government for a loan to buy the bungalow. The Developer knew about this. In
fact the Developer had executed a document addressed to the Secretary (the
Secretary), Housing Loan Division, Treasury, Malaysia, in reference to the
Buyer's application, wherein particulars of the title to the land on which
the bungalow was to be built were given together with the price of the land
and bungalow, the deposit paid and the balance purchase price payable
whereafter in the said document the Developer agreed to transfer the
ownership of the land to the Buyer immediately the cost of the land had been
settled, charge the same and deliver title thereto to the Government and
accept a schedule of progress payments stipulated by the Government (the
Government's schedule of payments).
The Buyer claimed the liquidated damages, pleading the Developer's
failure or refusal to deliver vacant possession of the bungalow within the
contracted time. The Buyer made a further claim of $6,000.00 pleading that
the Developer knowing that the Buyer was away in the United
Kingdom began harassing the Buyer to pay interest and collect the keys to
the bungalow which allegedly was far from completed, resulting in the Buyer,
as the Buyer claimed, having to return to Malaysia twice at a cost of
$6,000.00.
The Buyer also claimed damages for pain, anxiety, distress and
humiliation.
The Developer in its defence denied the Buyer's claim, alleging that on
16 January 1983 the Certificate of Practical Completion was given by the
architect and that on 5 February following the Developer had given the Buyer
notice by letter that the bungalow was ready for vacant possession. The
Developer pleaded that it was the Buyer that delayed the scheduled
instalment payments and counterclaimed interest for late payment as provided
for in the contract.
The Buyer's defence to the counterclaim was that the schedule of payments
and imposition of interest on overdue payments in the contract were varied
in writing, as evidenced by the appellant having accepted the Government's
schedule of payments, that having accepted the Government's schedule of
payments the appellant had waived payment according to and was estopped from
relying on the schedule of payments and terms governing payment of interest
provided in the contract, that if there was any delay in payment of the
purchase price it was caused by the Developer in failing to comply with the requirement of Government relating to completion of the bungalow
and transfer of the land to the Buyer.
A trial ensued before the learned Magistrate (the Magistrate) who after
hearing witnesses and considering the evidence found for the Buyer on his
claim for liquidated damages, but not on his other claims, and dismissed the
counterclaim. The Magistrate set out five issues and made express findings
in regard to each of them as follows: Firstly, the date for completion and
delivery of possession of the bungalow to the Buyer was 25 August 1981,
secondly, the date of delivery of vacant possession of the bungalow to the
Buyer was 16 January 1985, thirdly the Developer was bound by the
Government's schedule of payments as well as the schedule in the contract,
fourthly that the Buyer's claims for $6,000.00 and damages for pain,
anxiety, distress and humiliation were not allowed by reason of the decision
in S.E.A Housing Corporation Sdn. Bhd. v. Lee Poh Choo [1982] 2 M.L.J. 31,
and fifthly that the Developer was estopped from claiming interest for late
payment based on the decision in Regina Navamoney D/O D.T. Periathamby v.
Joseph Varghese [1987] 1 C.L.J. 68 and section 115 of the Evidence Act 1950.
The Magistrate also found that there was delay on the part of the Developer
in transferring the title to the Buyer and charging the land to the
Government which delay was caused by there being a caveat lodged against the
same.
Both the Developer and the Buyer were aggrieved by the decision of the
Magistrate and appealed and cross-appealed respectively to this Court. By
consent counsel filed written submissions in the appeal.
As to the first finding of the Magistrate counsel for the Developer in
his submission (the Submission) conceded that the date for completion and
delivery of vacant possession of the bungalow was 25 August 1981.
As to the Magistrate's second finding which was one of fact, the onus was
on the Developer to establish before this Court that the finding was
perverse or plainly wrong. See Mulkh Raj Sharma v. Shanti Sroop [1983] 2
M.L.J. 396 a decision of the Federal Court. The Developer could have done
so, for example, by demonstrating that there was no evidence upon which such
a finding of fact could be made. The Developer failed completely to
discharge that onus. Such being the case it was not open to this Court to
disturb the finding. In truth a perusal of the record disclosed ample
evidence upon which the Magistrate was able to make his finding. The Buyer
had testified to delay in completion of the bungalow, failure on the part of
the Developer to transfer title to the land by reason of a caveat and
failure or refusal of the Developer to give possession of the bungalow
including requests by the Buyer's solicitors for such possession and that it
was only on 16 January 1985 that possession was given. The
Buyer's testimony corroborated the evidence of an officer from the
Government who had earlier testified to delay on the part of the Developer
in completing the bungalow, transferring title and charging the land to the
Government. A third witness namely the Buyer's solicitor testified to
repeated demands in writing for delivery of possession of the bungalow which
demands were not met. The Magistrate made express reference to this witness
saying that it was on 16 January 1985 that the key was received by the
solicitor. The Magistrate properly observed that the evidence of the
solicitor was not challenged by the Developer. That being the case it is not
surprising that the Magistrate accepted the evidence of the solicitor. See
the decision of Raja Azlan Shah, C.J., now D.Y.M.M. Yang DiPertuan Agong in
Wong Swee Chin v Public Prosecutor [1981] 1 M.L.J. 212 at page 213.
Then it was argued on behalf of the Developer relying on the case of
Kanching Realty Sdn. Bhd. v. Leong Kok Chin & Anor. [1990] 1 C.L.J. 1144
that the Magistrate should have decided when the bungalow was completed and
ready to be delivered and not when vacant possession was given to the Buyer.
I do not agree. It is elementary law that every case must be decided on its
own facts. In the Kanching case the learned Judge found that the developer
should have completed the house and had it ready for delivery of vacant
possession on 1 April but only had it so ready in October
following and accordingly the Judge held the developer liable to pay
liquidated damages to the buyer for the period of delay between April and
October. That was not the case in this instance where it would appear that
the bungalow was finally ready sometime in October 1984 but the Developer
failed or refused to deliver possession till 26 January 1985. It was not
just a question of the Developer having the bungalow ready for delivery of
vacant possession. Coupled with that obligation was a requirement on the
part of the Developer to deliver vacant possession to the Buyer. There was
no question of the Buyer entering into possession of the bungalow on his own
and without reference to the Developer. Such a course would have amounted to
the Buyer taking the law into his own hands, a course of conduct which is to
be discouraged.
As to the Magistrate's third finding it was conceded in the Submission
that the Developer had agreed to the Government's schedule of payments. Yet
it was argued that the Developer's obligation was to complete the works as
stated in the contract and not as stated in the Government's schedule of
payments and a number of reasons was submitted by counsel for the Developer.
Those reasons were considered but with respect it is not necessary to refer
to them. Suffice it to say that the learned Magistrate rightly followed the
decision in Regina Nevamoney's case which I do respectfully adopt
and follow. There is ample authority to indicate that the Act was passed to
protect buyers, often individuals with limited financial resources, from
victimisation by developers who usually have far more financial resources
than the buyers. It was stated by Suffian L.P. in the S.E.A. Housing
Corporation case that a developer cannot contract out of the obligations
placed upon him by the Act and regulations made thereunder. Thus the
Developer whilst free to bind himself to terms outside the contract such as
the terms imposed by Government in this case was not free to do so in breach
of the Developer's obligations under the contract. Accordingly it seemed to
me that the Developer was duty bound either to fit whatever he undertook
outside the terms of the contract within his obligations under the contract
or alternatively, independently of such undertakings, the Developer should
have honoured his obligations under the contract and having done so then
gone ahead to seek payment or other remedy flowing from that which he so
undertook.
In any event it was conceded in the Submission that as at 25 August 1981
the date for completion and delivery of vacant possession the glass doors,
pipes and basins were not fitted and the drains were not done. That being
the case it cannot be seen how it can be argued that the bungalow was
completed and ready for delivery of vacant possession on the
completion date. The reason given for non completion was that these items
were likely to be vandalized or stolen. To my mind, that was not a legally
binding reason for not fulfilling the Developer's obligation under the
agreement. The Developer could easily have saved the situation by employing
a watchman to guard its housing development. Then it was argued that the
Developers' architect had in evidence given an undertaking to install these
fittings as soon as the Buyer moved in promising that the installation could
be done in one day. Again in my view there was no legal obligation on the
part of the Buyer to accept the undertaking and assurance.
It had to follow that the Developer's appeal against the second, third
and fifth findings of the Magistrate had to fail.
As to the Magistrate's fourth finding, it seemed to me that the
Magistrate was perfectly right in following the S.E.A. Housing Corporation
case where at page 35 it was said in regard to the contractual provision for
damages for delay by the developer in delivery of vacant possession of a
house, that such provision was intended to be comprehensive and precluded
the purchaser from recovering under any other head damages in the event of
delay in delivery as happened there. Thus in this case the Buyer was
entitled only to the liquidated damages provided for in the
contract and nothing else. It had to follow that the Buyer's claim for
$6,000.00 and damages for pain and so on was bound to fail and the
Magistrate was again right in disallowing the same.
For the reasons above stated, the appeal and the cross-appeal are both
dismissed with costs, to be taxed.
|