AW YONG WAI CHOO & ORS. V. ARIEF TRADING
SDN. BHD. & ANOR.
HIGH COURT MALAYA, IPOH
PEH SWEE CHIN J
[HIGH COURT CIVIL SUIT NO. 753 OF 1982 CONSOLIDATED WITH
93/82, 687/82, 688/82, 689/82, 692/82, 693/82, 696/82, 710/82, 711/82,
712/82, 752/82, 754/82, 756/82, 757/82, 759/82, 762/82, 763/82, 764/82,
766/82, 768/82, 769/82, 782/82, 783/82, 784/82, 786/82, 787/82, 789/82,
791/82, 793/82, 794/82, 795/82, 10/83, 20/83, 57/83 & 659/83]
21 SEPTEMBER 1991
Civil Procedure: Cost - Getting-up fee - Consolidation of
actions - Whether getting-up fee must be confined only to points raised at
hearing of consolidated action - Whether costs of getting-up should be
repeated in each individual case in the consolidated action
Civil Procedure: Action - Consolidation of actions - Common facts and
law and relief claimed - Same transaction or series of transactions -
Whether a single action including all plaintiffs would have been more
appropriate
JUDGMENT
Peh Swee Chin J:
A long wrangle among some 36 house buyers, (hereafter called the
plaintiffs); the housing developer (hereafter called the developer) and the
subsequent land owner in question (hereafter called the corporation) finally
landed in Court which heard 36 civil suits all consolidated on the very day
of hearing, all with a common cause of action, all against the developer and
the corporation giving rise to common questions of law and fact.
Before evidence viva voce commenced, the Court discussed with all
Counsels and with their commendable co-operation, made a consent order
inter alia (a) that all the 36 cases be consolidated forthwith; (c) that
one only of 36 plaintiffs need give evidence for the time being as the
evidence for all other plaintiffs, who would have given similar evidence,
and (c) that any other witness may, if necessary, be called, examined and
cross-examined. The consent order was of course to save valuable time. This
object is believed to have been achieved.
Thus plaintiff in Civil Suit No. 753/82, one Miss Aw Yong Wai Choo gave
evidence on behalf of all in all the controversial aspects of the case. The
developer, that is the same 1st defendant in all consolidated cases, was not
present neither was it represented by Counsel. The corporation, that is the
2nd defendant in all the consolidated cases, took up the cudgels for itself
in what appeared to be a mess left behind by the developer who had made
itself completely scarce leaving so many people in the lurch.
PW1, that is Miss Aw Yong, said she signed an agreement on 24 July 1979
for the purchase of her house and the agreement P1 was produced (similar
agreements for all other plaintiffs). The house was not completed, within 18
months thereafter as provided in the agreement, and in fact the construction
of it was not even started within the same period. She took up the matter
with the developer and was told that it had some problem with the local
authority. She made a complaint to the Ministry of Housing and Local
Government. Then the corporation called for a meeting with all similar
buyers in similar straits. At the meeting the corporation asked for an
increase in price for each unit of the house and further, that if such
increase was accepted, a new purchase agreement would have to be signed. The
increase in price was not agreed to and buyers of some 313 units formed a
pro tem committee to take up legal action.
In a civil suit (not one of those consolidated herein) a house buyer
obtained summary judgment against both the present developer and the
corporation and the corporation herein had appealed to the then Federal
Court but the appeal was withdrawn. After withdrawal of the appeal, the
corporation offered to settle each of the claims of the plaintiffs by
building the house with an increase of 50% of the original purchase price
over and above the original purchase price or alternatively, paying to each
RM30,000.
This evidence of offer of RM30,000 was objected to as being made without
prejudice and the Court decided that the evidence could be accepted for the
time being until there was later evidence to say that it was made without
prejudice and if such later evidence was accepted, and then in that event,
it would be totally excluded from the deliberation of the Court. In the
event that had turned out, there was no further specific evidence to
buttress this objection.
She said she had lodged a caveat against the land in question. On being
asked by the Court, learned Counsel for the corporation informed the Court
that the corporation had on its own accord built and completed building the
houses.
After conclusion of all the evidence, and on a day subsequent to it, the
Court called for all Counsels to be present in chambers where it appeared to
be agreed on all hands that all the houses had been built for all the
plaintiffs in the actions consolidated herein and that at the same time the
plaintiffs had merely each paid 10% of the purchase price in each case. All
this information, consisting of undisputed issues, not fully referred to in
evidence, was vital to the Court before it could make what was in its
opinion, a just and fair decision.
To revert to Miss Aw Yong's evidence, she also said that there was a sign
board at the work site stating that it was a joint venture between the
developer and the corporation. Before buying the house, she was given a
brochure (P7) by which she knew the corporation was the registered
proprietor of the land in question. The brochure came with a schedule of
payments given by the developer.
Under cross-examination, she agreed that the vendor in the agreement (P1)
was the developer which was the only contracting party with her. She agreed
there was nothing in the agreement to say that the developer was a partner
with anybody else. She agreed that she took the developer on reading the
agreement, as the proprietor of the land. She said that the words (in the
agreement) stated that the developer was (authorised by) the registered
proprietor. She said she knew from the brochure that the corporation was the
registered proprietor and she agreed that the corporation was not a party to
the agreement and there was nothing in it to suggest that the corporation
was a partner to the developer. She said she had paid 10% (towards the price
mentioned in the agreement).
She said, inter alia, that the date of the agreement was 24 July
1978 and the house was delivered to her on 23 January 1980. She understood
that the housing scheme (of which her house formed a part) was the
corporation's project. She highlighted the express words, to the effect,
about the joint venture being between "Perbadanan Kemajuan Negeri Perak"
(that is the corporation) as owner and "Arief Trading" (that is the
developer) as developer as printed on the brochure (P7).
She agreed further that the present house delivered to her was built by
the corporation itself and not by the developer and she agreed that the
specifications of the corporation relating to the said house were not the
same as those of the developer. She agreed that the word of "partnership"
was not printed in the brochure (P7) or the schedule of payments (P8). She
said she did not know that the withdrawal of the appeal mentioned earlier in
question from the Federal Court was the result of an amicable settlement
between the corporation and that house buyer called Mr. Hew, by way of an
ex-gratia payment without admission of liability and that the said Mr.
Hew had assigned his agreement with the developer to the corporation, but
she did not know that the appeal was withdrawn as a result of compromise.
Out of the house buyers, she agreed only 38 were still pursuing Court
action. She said the said 38 house buyers insisted on the houses being
completed at the original price.
Encik Ismail, that is DW1, a former employee and former manager of
building and housing department of corporation at the relevant period stated
that the corporation applied for the land in question (then State land). The
letter of approval (P18) dated 19 April 1977 was received by him with a
request to pay quit rent and premium totalling RM383,700. He said they had
wanted to develop the said land into a housing scheme on their own. The
corporation was incorporated by the Perak State Development Corporation
Enactment 1967 and it did not require a developer's licence. He said further
that they were directed by the State Government of Perak to allow the
developer, a Bumiputra company to develop it instead as the Government
wanted to give an opportunity to Bumiputra developers and the developer had
agreed to donate part of the profit to Arief Institute of Education; to
reserve 30% of houses built for Bumiputras and to give opportunity to
Bumiputra building contractors. DW1 then referred to and highlighted various
clauses of P4, an agreement between the corporation and the developer dated
29 December 1977 governing the relationship between the corporation and the
developer. P4 was introduced into evidence by PW1 earlier and on the basis
of it, she said she was advised to sue the corporation as well as the
developer, (vide p. 4 of the notes of evidence). He said that the
corporation was to get 50% of the profit from the developer which developed
the land and built the houses at the latter's entire own cost.
He said further that in early 1979, questions were raised in the Perak
State Legislative Assembly on the housing scheme and on the problems faced
by the house buyers and they decided to look into the problem trying "to
salvage the project" and they decided to take over the management of the
project "to protect the funds of the purchasers". They entered into a formal
agreement with the developer (to give effect to the take-over of the housing
scheme). They found that estimates of the developer were far below the price
on which they could build houses. They decided to build the houses "on their
own" and to sell them below "the market value" but higher than those prices
which the developer had intended to sell for. The developer then "assigned"
the agreements with the house buyers to the corporation. DW1 said further
that under P4, the earlier agreement of the corporation with the developer,
the developer had complete control of the management and finance of the
project and the corporation was not liable for any liabilities of the
developer. He referred to the house buyer called Mr. Hew with whom they had
settled on certain payment without admission of liability by means of D25,
that is expressly stated to be by way of an ex-gratia payment without
admission of liability whatsoever in full settlement by reference to the
relevant civil suit and the Federal Court Civil Appeal (with particulars
supplied). There were 313 purchasers, and they managed then to "solve
problem" with 201 purchasers. He had never received earlier estimates and
specifications of the developer from the developer. The gentleman called
Arief (incorporated into the name of the developer) was from Indonesia and
he did not know whether this man was a citizen. He said to the effect that
the estimates of the developer were so low that the corporation demanded an
extra increase of 50%.
DW2, that is Dato' Hamdan, said he was the general manager of the
corporation and he had executed P4 with the developer and the other
signatory of the corporation was the then Menteri Besar. He said that the
corporation was a statutory agency of the State Government formed in line
with New Economic Policy with a view to restructuring society. The
corporation had the ability and experience to develop housing schemes. The
developer was to pay 50% of its profit to the corporation.
In cross-examination, Dato' Hamdan denied that P4 was intended to be a
business arrangement; if it was, he said it would be better to sell the
whole land to the developer and further it was not a joint venture, if it
was, they would put up a joint venture company. It was simply to allow Encik
Arief to develop the land to achieve the true object of helping Bumiputras
and Arief, who even though Indonesian was still Bumiputra and was so
regarded by the corporation. He didn't know if the said Arief was carrying
an Indonesian passport.
It would not be necessary for the purpose of this case to comment on P1,
the building agreement between PW1 and the developer apart from saying that
it was a fairly standard type of sale and purchase agreement of a house with
all the usual provisions in which the developer was described as "vendor" in
possession of a developer's licence and "that ... the vendor is (authorised
by) the registered proprietor of the land ..." as these words were referred
to in the evidence of PW1.
P4, the agreement between the corporation and the developer would have to
be set out below for ease of reference as it was without doubt the bone of
contention between the plaintiffs and the corporation.
This agreement is made this 29 December 1977 Between The State
Economic Development Corporation Perak a body corporate established under
the Perak State Development Corporation Enactment 1967, of Club Road, Ipoh
(hereinafter called "the corporation") of the one part, and Arief Trading
Sendirian Berhad, a company registered in Malaysia and having its registered
office at 2100, Wisma Central, Jalan Ampang, Kuala Lumpur (hereinafter
called "the developer") of the other part.
Whereas the Government of the State of Perak is the owner of a
parcel of Land for Lot 46330 & Adjoining State Land in the Mukim of Ulu
Kinta in the District of Kinta as in the plan attached hereto and marked in
red (hereinafter called "the said land") and which consists of an
approximate area of 26 acres.
And whereas the Government of the State of Perak is desirous of
leasing the said land to the corporation for a period of 99 years for the
purpose of developing the said land into a housing scheme to which the
corporation has agreed.
And whereas the corporation has agreed to allow the developer to
develop the said land upon the terms and conditions hereinafter contained.
Now this Agreement Witnesseth and it is hereby Agreed and Declared
as follows:
1. In consideration of the developer agreeing that the corporation shall
have 50% of the profits of the development, the corporation shall, at the
cost of the developer, obtain the relevant leases to the said land in lots
to be set out in the layout plan specified in clause 3 hereinafter from the
Government of the State of Perak for a period of 99 years and to allow the
developer at the cost of the developer to develop the said land as a housing
scheme in accordance with plans and specifications to be approved by the
local authority and on the terms and conditions hereinafter contained.
2. The developer hereby undertakes to be solely responsible for the
finance and to seek the necessary financial resources for the whole of this
project.
3. Immediately upon the execution of this agreement the developer shall
provide the corporation a layout plan of the entire area for the development
of the said land as a housing scheme for the approval of the relevant
authority.
4. Upon the approval of the relevant authority of the layout plan under
clause 3 above, the developer shall immediately cause to be prepared for the
approval of the local authority plans, elevations, sections and drawings for
the erection of the said housing scheme on the said land together with an
outline specification or specifications of the approved method of
construction and of the materials to be used.
5. Upon signing of this agreement the developer shall be at liberty to
enter upon the land for the necessary levelling and other preliminary works
concerned therewith.
6. The developer shall submit to the corporation for approval the
estimates and specifications of the buildings and infrastructure and the
selling price.
7. The appointment of the contractor or contractors for the works in para.
6 above shall be done jointly by the corporation and the developer.
8. The appointment of consultants that is architects, engineers,
surveyors, etc., by the developer shall be with prior consultation of the
corporation.
9. Upon the approval of the plans and specifications by the relevant
authorities the developer shall have the authority to commence construction
upon the said land for the development of the housing scheme.
10. The developer shall from the date of this agreement be liable to
advance the payment for all premiums, rates, claims, assessments and other
out-goings now or hereafter at any time chargeable against the corporation
by statutes or otherwise in respect of the said land and shall obtain all
permissions and consents required and shall comply in all respects with the
statutory instruments, rules, orders and regulations for the time being in
force relating to planning control and with any orders, directions and
notices, made or given thereunder and in particular with the conditions
imposed by any permission for the development and also with any other Acts,
bylaws and regulations affecting the same and shall do all such works and
things as shall be lawfully required thereby and pay and indemnify and keep
indemnified the corporation against all fees, charges, penalties and
expenses to be made or incurred thereunder.
11. The developer shall at all times do all acts and things required by
and to conform in all respects with the provisions of any statutes land
building regulations applicable thereto and in accordance with the lawful
requirements of any statutory provisions in respect of electricity, water,
telephone or other public services.
12. The developer shall make good at its own expense any damage caused to
the public highways or adjoining properties and sewers, drains, cables and
other works thereon and thereunder through the construction of the said
housing scheme. Not to deposit or permit to be deposited upon the public
highways or adjacent land any building or other materials and to comply with
all instructions of the local or other authorities.
13. The developer hereby undertakes not to erect or build or permit or
suffer to be erected or built on the said land any building structure or
erection otherwise than in conformity with the approved plans and
specifications and not to make any material alterations without the previous
consent of the corporation and the local authority.
14. The developer shall during the carrying out of the development insure
and keep insured the same in a sum sufficient to cover the cost of
completely reinstating the same in the event of total destruction together
with architects' and surveyors' fees and other expenses incidental thereto
against loss by fire, lightning, flood, storm, tempest, commotion, riots,
explosion and in times of peace, aircraft and articles dropped therefrom a
reputable insurance company to be approved by the corporation and to pay all
premiums and other monies necessary for this purpose and whenever required
to produce to the corporation the policy or policies of such insurance and
the receipt for every such payment and in the event of the development or
any part of parts thereof being destroyed by fire or damage as aforesaid,
then as often as the same may happen to secure that all monies payable by
virtue of such insurance shall with all convenient speed be laid out and
applied to rebuilding, repairing or otherwise reinstating the development in
good and substantial manner in accordance with the terms of this agreement
and not to do or permit to be done upon the said land anything which may
render the policy or policies of insurance void or voidable or make any
increased premium payable in respect of such policy or policies.
15. The developer hereby undertakes to complete the development to the
reasonable satisfaction of the local authority in accordance with the plans
and specifications with all practicable speed and in any event within two
(2) years from the date of approval of plans and specifications, electricity
and water supplies. In the event of flood and riots or any matters beyond
the control of the developer, it shall be extended as recommended by the
architect to be agreed upon by both parties.
16. The corporation hereby agrees and undertakes that as soon as the said
land has been surveyed and sub-divided into housing lots, to endeavour with
all reasonable dispatch to have each and every of the said sub-lots issued
with Qualified Titles.
17. The corporation shall upon receipt of the Qualified Titles transfer
them to the purchasers at the request of the developer who shall confirm
that all arrangements for securing the necessary finances for the said land
and house has been finalised and will be secured by registration of the
transfer to the purchasers and charge to the financier at one and the same
time.
18. In the event of shortage of any building or other material for the
use of the project and on the developer so informing in writing to the
corporation of such shortage, the corporation hereby undertakes to assist
the developer in every possible way to obtain such building or other
materials from the relevant companies.
19. The corporation hereby undertakes that to expedite and facilitate the
smooth functioning and working of the development, it will assist the
developer in every possible way in obtaining from the appropriate
authorities the following:
(i) Approval of the layout plan for the project;
(ii) Individual titles for the sub-divided lots of the said land;
(iii) Approval of all building and engineering plans;
(iv) Certificate of Fitness for all completed buildings;
(v) Laying and supplying of water mains, electricity and telephone
cables.
20. The developer shall be responsible for processing, approving and
allotting the houses and/or shophouses to the successful applicants and to
stipulate the period upon which the deposit shall be paid and to collect and
receive all deposits for such sales. The list of selected applicants shall
be submitted to the corporation for approval. All preparation of sale
agreement shall be done by the developer's and the purchasers' solicitors.
21. It is hereby mutually agreed that not less than thirty per centum
(30%) of the number of houses, and/or shophouses shall be reserved for
Bumiputras to be taken within six (6) months from the date of laying the
foundation of the said houses and/or shophouses. If such allocation is not
fully taken up by Bumiputras within the prescribed time, the developer shall
be at liberty to sell the remaining houses or shophouses to any other
person.
22. The corporation through their general manager, and/or any officer of
the corporation authorised by the corporation reserve the right to enter and
inspect the said project from the date of implementation to the date of
completion to ensure that all specifications are strictly adhered to.
23. All costs relating to this agreement or anything arising therefrom or
anything connected therewith shall be advanced and paid by the developer as
part of the development costs for the project.
24. The developer shall maintain proper books of account from the
commencement to the conclusion of the housing scheme for all income and
expenditure which books shall be subject to audit before the final division
of the nett profits stated in clause (1) hereof and during which period the
corporation by its general manager or authorised officer shall at all
reasonable times be entitled to inspect the said books of account.
25. Time wherever mentioned in this agreement shall be the essence of the
contract.
26. Any notice or request to be given or made under this agreement to the
corporation or to the developer shall be in writing and in the case of the
corporation shall be under the hand of the general manager, the secretary
and/or solicitor or firm of solicitors purporting to act on their behalf and
in the case of the developer under the hand of the managing director,
secretary and/or solicitor or firm of solicitors purporting to act for the
developer to their respective addresses.
27. All notices shall be deemed to have been sufficiently given or made
if sent by registered post and addressed as aforesaid and shall be deemed to
have been served on and duly received by the other party in the ordinary
course of post.
28. This agreement shall be binding upon the respective representatives,
successors in title and assigns of the parties hereto.
In Witness Whereof the parties hereto have hereunto set their
hands and seals the day and year first above written.
The Common Seal of the )
State Economic )
Development ) Sgd.
Corporation) ) Pengerusi
Perak duly affixed in ) Perbadanan
the presence of: ) Kemajuan
Negeri, Perak,
Sgd.
Pengurus Besar,
Perbadanan Kemajuan Negeri
Perak.
The Common Seal of )
Arief Trading Sdn. Bhd. )
duly affixed in the presence of: )
Chop Arief Trading Sdn. Bhd.
Sgd.
Managing Director
Chop Arief Trading Sdn. Bhd.
Sgd.
Secretary.
In the statement of claim of PW1, she claimed that by virtue of the
agreement dated 29 December 1977 made between the corporation and the
developer, that is P4 aforesaid, the contracting parties thereto became
partners in the business of developing a housing estate and building houses
on it on the land in question. Her statement of claim further claimed that
under P4, the developer for the mutual benefit, entered into the agreement
with PW1 to build and sell to PW1 and that the house was to be built and
completed on or before 23 January 1980. The developer, it was said, failed
to fulfil its obligations when PW1 had been readily willing and able to
fulfil hers. She therefore claimed specific performance of the agreement
(P1), injunction from disposing of the land in question and alternatively
damages, etc.
The corporation in its defence by its reference to provisions of P4 and
other factors denied it was even a partner with the developer, and denied
any liability on P1, the agreement to which it was not a party at all, it
had merely sought to help the plaintiff as a social or moral duty and that
the market value of each house was over RM46,000 whereas the developer had
sold the same for RM35,300 and that the statement of claim disclosed no
cause of action against the corporation.
In the submission of the corporation, it was submitted that the
corporation was not a party to P1 while the developer was the vendor of the
land, the house to be built thereon. The owner of the land was in fact the
State Government of Perak, it was State land at the time of signing of P1
and the corporation merely became the registered proprietor in 1981. PW1
knew at the time of signing P1 that the corporation was not the landowner
and she had no dealings with the corporation until 1982 and the house was
subsequently constructed by the corporation on the same site on the
corporation's own specifications. Further it was never the intention of PW1
to enter into P1 with the corporation and the only remedy of PW1 was to sue
the developer alone. Learned Counsel cited authorities to the effect that a
party not being a party to a contract could not be sued on the contract. I
would call this the first point raised by the corporation.
The second point, if I may call it as such, raised by the corporation was
that the aforesaid "P1" was unenforceable as it was illegal because of
failure to comply with the r. 11(i) of the Housing Developers (Control and
Licensing) Rules 1970 by not making the landowner as a party to the
agreement of sale between the developer and PW1 and PW1 could have by a
search in the Registry of Titles found the landowner to be State Government
of Perak and that State Government was not made a party to the agreement.
The third point was that there was no intention by the corporation or the
developers to be partners to the project and that from the circumstances
leading to P4, and the evidence called for the defence it was clear that no
partnership of any kind was intended and in particular the share of profit
on the 50/50 basis was not a conducive test.
The 4th point was that the case of appeal in the Federal Court was
settled without any admission of liability and therefore not relevant, and
further that Mr. Hew's case there was decided on different issues and on
issues not pleaded before the Court here.
The answer of the learned Counsel for the plaintiffs was as comprehensive
as it was laconic. It was submitted that after reading P1 and P4, it was
clear that the corporation was the land owner and that the corporation was
the "silent" partner to the developer. Learned Counsel referred to various
clauses of P4 to support his contention of a partnership between the
corporation and the developer, and the corporation was therefore liable as
partner towards the plaintiffs.
Dealing with the first point raised about the corporation not being a
party to the contract that is P1, and about the plaintiffs not being
permitted to sue the corporation on P1, the reply of the plaintiffs was
crystal clear. It was that the plaintiffs were suing the corporation as a
partner of the developer to make the corporation liable as partner for the
debts and liabilities incurred by the developer.
In connection with the second point about the contract being illegal and
unenforceable for breach of the r. 11(1) of the then Housing Developers
(Control & Licensing) Rules 1970 by not making the State Government of Perak
as landowner at the time of the contract, as a party to the P1, this point I
am afraid is no longer an arguable point by virtue of the decision of the
Federal Court in Kin Nam Development Sdn. Bhd. V.
Khau Daw Yau [1984] 1 CLJ 181 in which the Federal Court inter
alia, confirmed the decision of the lower Court that such an agreement
was still enforceable by the purchaser there, to the effect that the breach
of the r. 11 did not by s. 24 of the Contracts Act 1950 render such purchase
agreement illegal. With the greatest respect, the Federal Court was
certainly right; just to give a well-known example, how chaotic it would be,
that all the agreements made by a company, would be declared void just
because the company failed to file annual accounts with the Registrar of
Companies?
I would deal with the 3rd point about the absence of a partnership later
in detail; but would deal with the fourth point here and now. The 4th point
was as regards the case of appeal in the Federal Court from a summary
judgment obtained by the said Mr. Hew in one case not consolidated herein.
In view of the Court's finding that a partnership did exist between the
corporation and developer as found from all the evidence without having to
depend at all on any evidence relating to this Mr. Hew's case, it would not
be necessary to deal with the 4th point, although it would have been
difficult to deal with this point as no submission was heard on the legal
consequences of such evidence, though the Court could hazard a guess that it
was related to issue estoppel, but was it?
Dealing with the 3rd point, in my opinion, if it had been proved that the
corporation and the developer were partners, then the principle of a partner
being liable for the debts and liabilities incurred by another partner in
the course of the partnership applied, then the action against the
corporation would succeed if the plaintiffs succeeded in proving the claims
against the developer, subject however to unfortunately an extraordinary
situation which had arisen on the facts of this case, and I would deal with
this extraordinary situation and the special treatment for it in detail
later on.
I had no doubt that the plaintiffs had proved more than enough to induce
this Court to grant specific performance as claimed in the writ against the
developer.
The burning question however remained, that is were the corporation and
the developer partners?
Partnership is first of all defined in our Partnership Act 1961 by s.
3(1) as follows:
3(1) Partnership is the relation which subsists between persons carrying
on business in common with a view of profit.
Section (4) says:
In determining whether a partnership does or does not exist, regard shall
be had to the following rules:
(a) joint tenancy, tenancy in common, joint property, common property,
or part ownership does not of itself create a partnership as to anything
so held or owned, whether the tenants or owners do or do not share any
profits made by the use thereof;
(b) the sharing of gross returns does not of itself create a
partnership, whether the persons sharing such returns have or have not a
joint or common right or interest in any property from which or from the
use of which the returns are derived;
(c) the receipt by a person of a share of the profits of business is
prima facie evidence that he is a partner in the business, but the
receipt of such a share, or of a payment contingent on or varying with the
profits of a business, does not of itself make him a partner in the
business; and in particular:
(i) the receipt by a person of a debt or other liquidated amount, by
instalments or otherwise, out of the accruing profits of a business does
not of itself make him a partner in the business or liable as such;
(ii) a contract for the remuneration of a servant or agent of a
person engaged in a business by a share of the profits of the business
does not of itself make the servant or agent a partner in the business
or liable as such;
(iii) a person being a widow or child of a deceased partner, and
receiving by way of annuity a portion of the profits made in the
business in which the deceased person was a partner, is not, by reason
only of such receipt, a partner in the business or liable as such;
(iv) the advance of money by way of loan to a person engaged or about
to engage in any business on a contract with that person that the lender
shall receive a rate of interest varying with the profits, or shall
receive a share of the profits, arising from carrying on the business,
does not of itself make the lender a partner with the person or persons
carrying on the business or liable as such;
Provided that the contract is in writing and signed by or on behalf of
all the parties thereto; and
(v) a person receiving, by way of annuity or otherwise, a portion of
the profits of a business in consideration of the sale by him of the
goodwill of the business is not, by reason only of such receipt a partner
in the business or liable as such.
From the sections quoted above, it would be apparent that in order to
find if partnership exists, it would be necessary to determine if the
relation as defined in s. 3(1) exists.
In my view to find the existence of such relation, the Court must find
the real intention of the parties involved. The real intention is not
necessarily the expressed intention of the parties so that even if the
parties express they are partners, the Court may decide to the contrary
after the Court considers all relevant factors taken together, please see
the leading case of Cox v. Hickman [1860] 8 HCL 268.
The definition section really sets out the essence of the decided cases
that is the Court is perfectly at liberty to determine from all the relevant
factors taken together, if such relation exists or does not exist, then the
Court attributes this finding as the real intention of the parties. This has
nothing to do with curbing contractual freedom but is meant for doing
justice. Sir Montague Smith said in the case of Mollwo March & Co. v. The
Court of Wards, [1872] (LR) 4 PC 419 at p. 438 said:
If cases should occur where any partnership, under the guise of such an
arrangement (that is a loan), are really trading as principals, and
putting forward as ostensible, others who are really their agents, they
must not hope by such devices to escape liability; for the law in cases of
this kind, will look at the body and substance of the arrangements and
fasten responsibility on the parties according to their true and real
character,
so much for the attributable real intention of the parties.
I will also express my view on some other matters before proceeding to my
findings. First, with reference to the rules for which the Court shall have
regard to in determining the question of the existence or non-existence of
partnership as expressly stated in s. 4 quoted above, in my view the stated
rules cannot be exhaustive at all, for the category of such similar rules is
never closed certainly; there are far more pigeon-holes than the stated
rules for factors to fit into them.
Further in my view the relevant factors to be taken together for
consideration are those happenings of the relation between the parties, that
is all the relevant incidents of the relation, including any written or
verbal agreement, conduct of the parties at all times, and all surrounding
circumstances.
Further in my view, contrary to what learned Counsel seemed to suggest to
me, conduct of the parties herein and surrounding circumstances, all
occurring not necessarily before but also after the signing of P4, that is
the so-called joint venture agreement between the corporation and the
developer could be considered and taken together with P4, for the Court's
function was not solely and only confined to the interpretation of P4 but to
the very larger question of whether the relation as defined by s. 3(1)
aforesaid existed.
First, the major incident of the relation between the parties, was P4 and
it fell to be considered. The Court was struck by the provision of 50% of
the "profits of development" for the corporation as opposed to gross returns
thus giving rise to a presumption of fact, that is prima facie
evidence of partnership but I must hasten to add that this provision did not
conclusively make the corporation a partner and all other relevant factors
have to be considered equally and they could give rise to a contrary
presumption of fact or could rebut the first mentioned presumption. The
Court considered all the provisions in particular, the clause providing for
sole financial responsibility of the developer (clause 2); the provision of
vacant land by corporation; the joint appointment of contractors for the
work (clause 7); joint appointment of architects, surveyors, etc. (clause
8); the sole responsibility of the developer for damage to third parties;
(clause 9); the sole responsibility for insurance against various risks by
the developer (clause 14); the approval in advance of estimates and
specifications (clause 6); the reserved right of the corporation to inspect
the project to ensure all compliance with all specifications (clause 22);
the right of the corporation to inspect all books of accounts which were
required to be properly kept and audited (clause 23).
The Court considered also the brochure distributed to potential house
buyers with words in bold type announcing a 50/50 joint venture between the
corporation as land owner and the developer as developer.
I considered also the evidence that the arrangement between the
corporation and the developer had the motive behind that is that of helping
Bumiputra entrepreneurs, Bumiputra companies and Bumiputra house buyers.
I also considered that questions raised in the State Legislative Assembly
on the project which prompted, if not wholly, at least partly the decision
to take over the development of the same project. to offer to complete the
houses at an increased price, increased by 50%, which the plaintiffs, out of
a very much larger number of other agreeable house buyers, refused to
accept.
The Court also considered all goings-on after the corporation took over.
The Court at the conclusion of evidence was satisfied on a balance of
probabilities that the indicia of partnership outweighed the negative
factors and that the relation as defined in s. 3(1) of the Partnership Act
was proved that is that a partnership existed between corporation and the
developer limited to the business of housing development with all its
attendant business of selling houses etc., limited also to the land, as
described in P4.
I will now deal with the extraordinary situation which I referred to
earlier and which I had subsequently taken into consideration in my brief
oral judgment as delivered in Court.
It arose in this way. At one stage, it appeared that to all intents and
purposes the developer had abandoned the housing scheme, for example, PW1,
one of the plaintiffs, had said in evidence to the effect that after the end
of 18 months from the date of the purchase agreement, (P1), when the
building she bought was under P1 supposed to be built and completed, there
was not even a brick here ..." "... there was only lallang ... At this stage
or thereabouts, the corporation decided to take over the housing scheme by
deciding to build houses there.
This was principally caused by the abandonment, and the motive according
to evidence called for the corporation was that they felt bound to do so by
a moral or social duty prompted to some extent by questions raised in Perak
State Assembly about the sorry state in which the housing scheme in question
was in.
When the corporation decided to take over the scheme, it called for some
sort of tripartite agreement called "assignment agreement" to be signed by
all the house buyers and the developer; with an increase in price over and
above the contractual price set out in each of their earlier purchase
agreements the plaintiffs had signed with the developer. Of the 313 house
buyers, a large number had responded, leaving the present plaintiffs and a
few more possibly, refusing to accept the offer and deciding to go to Court,
and hence the multiple actions before me.
The increase of 50% in price was, (according to the corporation, and this
had never been contradicted by the plaintiffs), caused by apparently
superior specifications used by the corporation for building the houses as
compared with those as set out in the purchase agreement of the developer,
that is P1. The corporation said, without any contradiction from the
plaintiffs, that in fixing the increase in price of 50%, it was below the
prevailing market value at that time, possibly with reference to the
aforesaid moral or social duty by which the corporation felt bound, though
the corporation could not suppress, at least, a minor part played by certain
unspoken reason in causing it to take over the housing scheme and fixing an
increase in price below the prevailing market value; the reason being of
course, that the abandonment of the scheme by the developer could
potentially bring the corporation into the troubled waters of litigation.
The houses all had been built and completed subsequently by employing the
new and more expensive specifications and since all the houses had been
built and completed, the Court ordered specific performance in lieu of
damages against the corporation also.
Consequent to my order of specific performance against the corporation
qua partner of the developer, it would be obvious that the plaintiffs in
the course of it, all stood to gain and enjoy a benefit, that is houses of
superior quality by virtue of superior specifications. The Court could award
a sum as the cost of additional work or expense by virtue of those
specifications of the corporation but the Court's hands were somewhat tied,
because of the lack of a pleaded counterclaim and the troubling scarcity of
evidence of the actual cost involved in those specifications of the
corporation.
However the question that kept occurring to my mind was; should the
plaintiff gain more than what they had bargained for and get away with it?
The corporation though owned by the State Government of Perak should not be
regarded, to use local parlance, as a "milking cow" but just like another
commercial company.
Law is magnanimous, for s. 71 of the Contracts Act 1950 provides:
71. When a person lawfully does anything for another person or delivers
anything to him, not intending to do so gratuitously and such other person
enjoys the benefit thereof, the latter is bound to make compensation to the
former, in respect of, or to restore the thing done or delivered.
Section 71 (hereafter this section) of our Contracts Act 1950 is the same
as s. 70 of the Indian Contract Act and numerous cases have been decided in
India under this section. I will refer to a few having bearing on this
section. Thus in Palanivelu v. Neelavathi & Anor. AIR [1937] Journal,
50, the defendants and their sister (who was married to the plaintiff), gave
a promissory note for a certain sum of money carrying interest in
consideration of plaintiff managing the estate left by the father of the
defendants. On refusal to pay, the plaintiff sued on the promissory note
which was however dismissed on the ground of undue influence, but the Privy
Council upheld the alternative claim for compensation for services rendered,
on the accepted finding that the plaintiff was under the impression that he
would receive remuneration for his services and that he did not intend to
perform such services gratuitously, and of course the defendants had enjoyed
the benefit of such services.
In another case, Gangapathi Pillai v. Budayasamy, AIR (49) [1952],
Madhya Pradesh; it was decided also under the same section. In that case, to
give effect to the lease of mill granted by the defendant to plaintiff,
defendant had to effect certain additional construction to the mill. The
defendant failed to do so on account of lack of money and time. The
plaintiff then did so and tried to recover the expense from the defendant on
the ground that the defendant had agreed to reimburse the plaintiff. The
trial Court found that the plaintiff had failed to prove the agreement to
reimburse the plaintiff. On appeal the Appellate Court found that all the
conditions under this section were fulfilled and the plaintiff was entitled
to recover under this section even if the plaintiff had failed to prove the
earlier agreement to reimburse the plaintiff. The same appellate Court held
further to the effect the failure of the plaintiff to plead an alternative
claim under this particular section did not at all debar the plaintiff from
his claim under this section relying on the effect of the decision of the
Indian Supreme Court case of Subramanyam v. Thayyappa [1961] 1 Mad.
LJ, (SN), 30/SC).
When the corporation decided to take over the housing scheme, and build
the houses according to their more expensive specifications, it did so in no
way which could be conceivably unlawful. When it did so, it did not intend
to do so gratuitously, for example the corporation attempted repeatedly to
ask for an increase of 50% of the price. The plaintiffs had all gained and
enjoyed the benefit of such specifications, thus, all the conditions in this
section of the Contracts Act 1950 were fulfilled.
The plaintiffs could and would be heard to say elsewhere that if the
corporation was liable as partner for the developer, the corporation could
not increase the purchase price any more than the developer could, but in my
view by saying so, it would be begging the question, brushing aside the
extraordinary situation crying out for the invocation of this section of the
Contracts Act set out above. Could the plaintiffs really justify it as some
sort of windfall which was not created by them, this would be neither fair
nor just.
I therefore decided not to order the payment of indemnity or "liquidated
damages" for late delivery of the houses against the corporation, using the
benefit the plaintiffs gained as a set-off against the plaintiffs' own
claims for such indemnity provided for under the purchase agreement made by
the plaintiffs with the developer. I ordered that such indemnity be awarded
however against the developer, thus making a distinction between a
defaulting trading partner and a sleeping partner who had subsequently given
more to plaintiffs than what the defaulting trading partner had given. I did
this in effect by disallowing the plaintiffs to insist on the strict
performance of the contractual rights of the claim for the said liquidated
damages for the late delivery of houses to the plaintiffs against the
sleeping partner who had so given more than what the plaintiffs were
entitled to.
I also had in mind a principle of the doctrine of equitable estoppel
which in my view should apply and did apply equally, without the need to
resort to this section above. This principle was explained in some detail in
Gan Tuck Meng & Ors. v. Ngan Yin Groundnut Factory Sdn. Bhd. & Anor.
[1990] 1 MLJ 227 and I repeat what Buckley, LJ said in Shaw v. Applegate,
[1977] 1 WLR 970, about the arising of an equity or doctrine of equitable
estoppel, that:
... the real test, I think, must be whether upon the facts of the
particular case, the situation has become such, that it would be dishonest
or unconscionable for the plaintiffs or the person having the right sought
to be enforced, to continue to seek to enforce it.
The extraordinary situation described above was such that it would be
unconscionable for the plaintiffs to insist on strictly enforcing the
obligation providing for the payment of the said liquidated damages for late
delivery of houses, and it was for this Court to decide how an equity should
be satisfied.
I therefore ordered specific performance of all the agreements against
both the developer (1st defendant) and the corporation (2nd defendant) but
with an express order to the effect that the corporation (2nd defendant)
need not pay indemnity for late delivery of houses provided by the
agreements with all the usual directions as to payment and the execution of
transfers of titles etc. and further costs against both developer and the
corporation. |