ONG SEOK HENG V. WEE CHEONG MOTOR &
HOUSING DEVELOPER SDN. BHD.
HIGH COURT MALAYA, PENANG
MOHAMED DZAIDDIN J
[ORIGINATING SUMMONS NO. 24-666-1985]
12 SEPTEMBER 1990
JUDGMENT
Mohamed Dzaiddin J:
This is an appeal from the decision of Penolong Kanan Pendaftar on the
question of damages in lieu of specific performance of an agreement for sale
of a flat.
Before I proceed to consider this appeal, I must remind myself of the
principle upon which an appellate Court will interfere with the award of
damages made by a single Judge. In Davies v. Powell Duffryn Associated
Collieries Ltd. [1942] AC 601 at pp. 616-617, Lord Wright stated at p.
617 as follows:
It is difficult to lay down in precise rule which will cover all cases
but a good general guide is offered by Greer LJ in Flint v. Lovell.
In effect, the Court, before it interferes with an award of damages,
should be satisfied that the Judge has acted on a wrong principle of law,
or has misapprehended the facts, or has for these or other reasons made a
wholly erroneous estimate of the damage suffered.
With this in mind, I shall now proceed to consider the grounds of appeal.
However, before doing so let me briefly state the facts of the case. By an
agreement in writing dated 10 December 1977 made between the applicant and
the respondent, the respondent agreed to sell to the applicant a unit of
flat to be constructed on Lots 56, 57 and 227,
Section 6, North East District, Pulau Pinang ("the said property") at
the purchase price of RM47,000. The applicant paid to the respondent RM1,000
as part payment towards the purchase price. The necessary plans for the
construction of the said property were duly approved. The respondent however
did not commence constructing the said flat for reason which was known later
to be due to the respondent's inability to evict the squatters from the said
property. Subsequently, some time in June 1981 the applicant lodged a
private caveat over the said property. This was followed by filing an action
against the respondent vide Civil Suit No. 1190 of 1985 on 1 October
1985 claiming for specific performance of the said agreement and damages in
addition to or in lieu of specific performance. On the hearing of the
application by the respondent under the present originating summons to
remove the private caveat, the respondent admitted that they were unable to
construct the said flat thereby breaching the agreement. In the result, on
22 September 1986 this Court ordered the respondent to pay damages to the
applicant in lieu of specific performance to be assessed by the Penolong
Kanan Pendaftar, failing which the private caveat would remain until the
disposal of the Civil Suit No. 1190 of 1985. On 27 October 1987, the learned
Penolong Kanan Pendaftar awarded the respondent damages in the sum of
RM54,000 with interest at 8% per annum and the refund of RM1,000 being the
deposit paid by the applicant to carry interest at similar rate. The
Registrar arrived at this sum by taking the difference in price between the
market value of the property as at the date of judgment (RM100,000) less the
contract price (RM47,000).
Therefore, the issue in this appeal is whether the learned Penolong Kanan
Pendaftar erred in principle in the assessment of damages.
Encik Ismadi, Counsel for the respondent submitted that the learned
Penolong Kanan Pendaftar erred on two grounds in her assessment of damages.
First, he contended that the measure of damages should be the market value
of the said property at the purported date of completion of the contract
less the contract price. Counsel relied on the judgment of Gill J in
Central Malaysia Development Co. Ltd. v. Chin Pak Chin [1967] 2 MLJ 174
(FC) followed by Shankar J in Balasubramaniam v. Venkitasan [1986] 2
MLJ 55. Counsel submitted that as the present case involved the sale of a
flat and no specified time for completion was stated in the agreement,
the Housing Developers (Control and Licensing) Rules 1970 should apply
and
under r. 12(1) the completion period must be deemed to be 18 months from
the execution of the sale agreement. In the circumstances, the amount of
damages should be the difference between the market value of the property at
the completion of 18 months from 10 December 1977 less the contract price of
RM47,000.
Secondly, Counsel submitted that the Registrar had failed to consider the
applicant's conduct in not mitigating her loss. She ought to have prosecuted
her claim much earlier and not to wait for 8 years after the signing of the
booking proforma to file her writ. In the circumstances, there was
considerable delay on the applicant's part to bring this action which
disentitled her to claim the market price to be at the date of judgment.
In the present appeal, it is not disputed that the applicant's claim
against the respondent in Civil Suit No. 1190 of 1985 was for specific
performance of the sale agreement and for damages in addition to or in lieu
of specific performance. Thus, this Court, in awarding damages in lieu of
specific performance acted
under s. 18 of the Specific Relief Act 1950 (Act 137). However, it is
quite proper, indeed this Court when assessing damages under s. 18 should
adopt the same basis of assessment of damages as under
s. 74 of the Contracts Act 1950 (Act 136). (See: Sinnadurai's Sale
and Purchase of Real Property in Malaysia p. 427.) Thus, Gill J in
Central Malaysia Development Co. Ltd. v. Chin Pak Chin (supra)
stated that in contracts for the sale of land where the contract is not
completed the normal measure of damages is the market value of the property
at the contractual time for completion less the contract price. This means
the market value is to be assessed as at the time when the breach occurred.
However, there are cases where the Courts had determined the market value of
the property on some other dates, e.g., the date of judgment. In Cheng
Chuan Development Sdn. Bhd. v. Ng Ah Hock [1982] 2 MLJ 222, the Federal
Court, affirming the decision of the trial Judge, assessed damages to be the
difference between the contract price and the price at which the shophouse
was sold to the third party. In Tan Geok Khoon & Anor. v. Paya Terubong
Est. Sdn. Bhd. (Penang High Court Civil Suit No. 831 of 1984), Datuk
Edgar Joseph Jr. J held that the relevant date for the assessment of damages
would be the date of judgment especially since there was no evidence that
they would be greater if assessed at the date of breach. In Johnson v.
Agnew [1980] AC 367, the House of Lords held that the date of assessment
of damages for a claim of specific performance should be that at the date
when the contract was lost which would be the date of the hearing of the
specific performance. In Malhotra v. Choudhury [1980] 1 Ch 52, the
Court of Appeal held that the date for assessment of damages should be the
date of the judgment and not the date of the breach.
Following the above decisions, I must reject Encik Ismadi's submission
that the market value of the flat should be assessed as at the expiry of 18
months from the date of the agreement. Here, there is no evidence that the
respondent was a licensed housing developer under
the Housing Developers (Control and Licensing) Act 1966. There was also
no proper sale agreement executed between the parties thereby not specifying
the date or time for the completion of sale. Therefore, in the absence of
these facts, in my opinion, the market value should be assessed at the date
of the breach which on the facts in this case must be the date when the
respondent admitted (at the hearing of the application for the removal of
the private caveat) that they were unable to construct the said flat i.e.,
at the date of the judgment. In the result, I hold that the assessment by
the Penolong Kanan Pendaftar is correct.
On the issue whether the applicant ought to have mitigated her loss, I am
satisfied, based on the facts, the applicant had not acted unreasonably in
prosecuting her case. From her affidavit dated 24 September 1985 filed in
support of her application for an extension of the private caveat until the
final disposal of the civil suit, I am satisfied that the applicant had
given a satisfactory explanation.
For reasons stated above, it is my finding that the Penolong Kanan
Pendaftar had not erred in principle. This appeal is dismissed with costs.
|